CN106759168A - A kind of generating water diverting structure arrangement for taking into account environmental protection and sand discharge demand - Google Patents
A kind of generating water diverting structure arrangement for taking into account environmental protection and sand discharge demand Download PDFInfo
- Publication number
- CN106759168A CN106759168A CN201710037944.XA CN201710037944A CN106759168A CN 106759168 A CN106759168 A CN 106759168A CN 201710037944 A CN201710037944 A CN 201710037944A CN 106759168 A CN106759168 A CN 106759168A
- Authority
- CN
- China
- Prior art keywords
- power station
- environmental protection
- flow
- demand
- arrangement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B9/00—Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B8/00—Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
- E02B8/02—Sediment base gates; Sand sluices; Structures for retaining arresting waterborne material
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B8/00—Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
- E02B8/08—Fish passes or other means providing for migration of fish; Passages for rafts or boats
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B9/00—Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
- E02B9/02—Water-ways
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A40/00—Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
- Y02A40/60—Ecological corridors or buffer zones
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Sewage (AREA)
Abstract
The power station generating water diverting structure arrangement of environmental protection and sand discharge demand is taken into account the invention discloses a kind of, including the diversion system that side of pulling in shore is arranged, and the blocking dam short, by riverbed main flow position future insufficiency in river course.Blocking dam two sides crest elevation is high, future insufficiency is arranged in just to channel thread position on dam body;Dash and sand prevention bank are set before the diversion system intake gate of bank arrangement.The present invention had both met the major function requirement of power station generating water diversion and sand control using simple arrangement;Release ecological flow and the mistake fish demand of environmental protection requirement can be taken into account again;It is not required to set special sand discharge and ecology is released facility, be also not required to set special fish pass, structural facilities arrangement is simple, smaller on the fish movement influence in former river course, simplifies the difficulty of artificial control scheduling, reduces quantities.Due to not blocking river, the influence to environment is reduced.It is particularly suited for the power station generating water diverting structure arrangement of fragile, higher to the environmental requirement middle-size and small-size Hydraulic and Hydro-Power Engineering of fully-loaded stream, affiliated area surroundings.
Description
Technical field
The present invention relates to a kind of water diverting structure arrangement, more particularly, to a kind of affiliated area surroundings fragility, to ring
Border requires the generating water diverting structure arrangement in the middle-size and small-size Hydraulic and Hydro-Power Engineering built on higher, fully-loaded stream.
Background technology
Hydraulic and Hydro-Power Engineering when hinge dash, generating water diverting structure is built, in order to ensure generating diversion efficiency and fortune
Row stabilization, is both needed to arrange water retaining structure in river course, typically river need to all be blocked disconnected, in will necessarily so influenceing former river course
The normal activity of aquatile, thus consideration of generally still needing sets fish pass structure, conventional way is on water retaining structure
Or bank sets the fish pass structures such as special fish pass;It is to keep Ecological Stabilization in basin, it is also contemplated that for downstream is released certain life
State flow, also needs the special ecology of arrangement to release facility;Additionally, when natural sediment yield is larger in river course, it is also contemplated that setting
Desilting works.Above-mentioned facility is built, and not only engineering structure pattern is various, and engineering operation scheduling is complicated, and construction investment increases, weight
What is wanted is the expansion due to project scale, result in the aggravation to surrounding environment influence, and the influence to vulnerable environment area will
It is bigger.Environmental protection concept how is implemented in project playout, the influence to environment is reduced as far as possible, must cautiously examined when being conceptual design
The problem of worry.
The content of the invention
The technical problem to be solved in the present invention is to provide a kind of major function for both having met power station generating water diversion and sand control will
Ask, ecological flow can be taken into account again and is released and meet fish normal existence demand, be not required to be respectively provided with special facilities, fortune can be simplified
OK, river is not blocked, the less generating water diverting structure arrangement for taking into account environmental protection and sand discharge demand of the influence to environment.
The technical solution adopted in the present invention is:A kind of power station generating water diverting structure cloth for taking into account environmental protection and sand discharge demand
Structure, including the diversion system that side of pulling in shore is arranged are put, blocking dam, blocking dam is located in river course, and riverbed main flow portion is leaned on blocking dam
Position is reserved jagged, sets dash and sand prevention bank before the intake gate of the diversion system of side arrangement of pulling in shore, and the dam body of blocking dam can be from
By overflow, the two sides crest elevation of blocking dam meets to be generated electricity when flood season power station is completely sent out quotes water level requirement needed for flow, while full
Flow rate of water flow is more than required water level requirement during bed load sediment median particle diameter start velocity in sufficient flood season storehouse.
The blocking dam is arranged close to intake gate.
The gradient is more than bed load sediment median particle diameter critical grade scope during the blocking dam is arranged in river course, that is, be chosen at
In river course in the maximum scope of the gradient.
The blocking dam dam body is highly 2~5 meters.
The position of breach is located in the range of channel thread on the blocking dam, logical as fish pass, ecological flow, silt conveying
Road;The Yokogawa of breach is 1~4m to width, requirement of the fish migration to upstream and downstream head and flow velocity is met, while taking into account sand discharge
And dry season releases ecological flow demand.
There is certain slope the upstream and downstream of the blocking dam, are 1:0.3~1:0.7, a width of 2~4m of dam crest.
The dash and the length and bank crest level of sand prevention bank set before the intake gate, meet the maximum introduced needed for power station
Generating flow and the excessively requirement of bank flow velocity, cross bank flow velocity and do not cause that river bed load sediment median particle diameter starts, and crossing bank flow velocity is
0.6~1.8m/s;Also meet dry season riverbed ecological flow to release demand, ecological flow of the elevation higher than dry season riverbed demand
The water level of corresponding natural river course, sand prevention bank is highly 1~2m.
It is middle-size and small-size Hydraulic and Hydro-Power Engineering that the arrangement is used for fully-loaded stream, scale.
The arrangement is used for the facility of fragile, high to the environmental protection requirement Hydraulic and Hydro-Power Engineering of affiliated area surroundings
Arrangement.
The beneficial effects of the invention are as follows:Using simple arrangement, the major function of power station generating water diversion and sand control had both been met
It is required that;Release ecological flow and the fish migration demand of environmental protection requirement can be taken into account again;It is not required to set special desilting works,
It is not required to set special fish pass, structural facilities arrangement is simple, smaller on the fish movement influence in former river course.When blocking dam highly
Often dam safety evaluation ability when relatively low, to meet generating diversion and ecological flow requirement of releasing, power station intake gate gate need to be with
Water amount situation of change is frequently dispatched.Using arrangement of the invention, gate manual dispatching, the difficulty of control are simplified.Together
When, because structural shape is simple, reduce quantities;Due to not blocking river, the influence to environment is reduced as far as possible.It is this kind of
Power station generating diversion arrangement, be particularly suited for fully-loaded stream, affiliated area surroundings it is fragile, it is higher to environmental requirement in
The power station generating water diverting structure arrangement of small water conservancy hydroelectric project.
Brief description of the drawings
Fig. 1 is that the horizontal layout of the generating water diverting structure arrangement that the present invention takes into account environmental protection and sand discharge demand is illustrated
Figure.
Fig. 2 is gap position schematic diagram on blocking dam in Fig. 1.
Fig. 3 is A-A profiles in Fig. 1.
Fig. 4 is B-B profiles in Fig. 1.
In figure:
1-blocking dam;
2-breach;
3-diversion system intake gate;
4-dash and sand prevention bank.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and detailed description:
As shown in figures 1-4, the power station generating water diverting structure arrangement for taking into account environmental protection and sand discharge demand of the invention,
Diversion system including side arrangement of pulling in shore, blocking dam, blocking dam 1 is located in river course, reserved by riverbed main flow position on blocking dam 1
Jagged 2, dash and sand prevention bank 4 are set before the intake gate 3 of the diversion system of side arrangement of pulling in shore, the dam body of blocking dam 1 can be freely
Overflow, the two sides crest elevation of blocking dam 1 meets to be generated electricity when flood season power station is completely sent out quotes water level requirement needed for flow, while meeting
Flow rate of water flow is more than required water level requirement during bed load sediment median particle diameter start velocity in flood season storehouse.
Specifically, be arranged in river course, the highly relatively low two sides crest elevation of blocking dam 1 is high, just to channel thread portion
The position elevation of breach 2 is low.
The blocking dam 1 should be close proximity to arrangement with the distance of intake gate 3.
The dam location of blocking, answers choice arrangement gradient in river course to be more than bed load sediment median particle diameter critical grade
Scope, is typically chosen in the scope of gradient maximum in river course.
The blocking dam two sides crest elevation being arranged in river course is high, just low to main stem position breach elevation.
The blocking dam dam body maximum height is relatively low, is 2~5 meters, and the influence to environment is small.Dam body is highly determined along river
It is small to dam body maximum bottom width, it is not required to set fish rest pond.The setting of its two sides crest elevation, when should meet flood season power station and completely sending out
Generate electricity and quote water level requirement needed for flow, should also meet in flood season storehouse flow rate of water flow and start stream more than bed load sediment median particle diameter
Required water level requirement when fast.
The position of breach should be located in the range of channel thread on the blocking dam, as fish pass, ecological flow, silt conveying
Deng passage;The Yokogawa of breach should meet requirement of the fish migration to upstream and downstream head and flow velocity to width, and width is generally 1
~4m, breach should take into account sand discharge simultaneously and dry season releases ecological flow demand.
The dam body of the blocking dam can free overflow, the ecological flow generate electricity and quote flow superfluous water amount, released from and river
Come under husky dam body spilling and breach by blocking dam to let out in water.Its section need to meet steady demand and upstream and downstream are arranged as
Answer the gradient, generally 1:0.3~1:0.7, dam crest is wide to take into account construction demand but should not be too big, preferably 2~4m;
The length and bank crest level of the sand prevention bank set before described intake gate, should meet the maximum hair introduced needed for power station
The magnitude of current and the requirement of bank flow velocity is crossed, cross bank flow velocity by not causing that river bed load sediment median particle diameter starts control, cross bank stream
Speed is generally 0.6~1.8m/s;Dry season riverbed ecological flow should also be met to release demand, its elevation should be higher than that dry season riverbed
The water level of the natural river course corresponding to the ecological flow of demand, sand prevention bank is highly preferably 1~2m.
Described arrangement, it is adaptable on fully-loaded stream, scale be medium and small Hydraulic and Hydro-Power Engineering.Especially fit
For the facility arrangement of fragile, very high to the environmental protection requirement Hydraulic and Hydro-Power Engineering of affiliated area surroundings.
The present invention had both met generating water diversion and sand control requirement;The demand of ecological flow and fish migration can be taken into account again;It is not required to set
Put special fish pass and ecology is released facility, reduce quantities;River is not blocked, the influence to environment is reduced as far as possible, while
Also simplify intake gate gate traffic control, the difficulty of control.
It is described in detail with reference to specific embodiment:
Certain medium hydropower station engineering, Project Areas vulnerable environment, affiliated basin is fully-loaded stream, and head pivot area riverbed is right
Bank side is protection zone.According to environmental requirement, must not build for engineering influences right bank protection zone environment;Engineering needs to ensure former after building
The normal migration passage of raw fish;River course domestic demand is released ecological flow at least 4.37m3/s。
Engineering affiliated river flood season and dry season carry out water and differ larger, to ensure normal power generation diversion and the effect in power station
Benefit, need to stop up intake gate water level before gates high;But for take into account dry season release ecological flow and fish normal migration and need not be again
Special facility being respectively provided with, therefore, river should not all be blocked.Scale, development task demand and environmental protection according to engineering
It is required that, to ensure power station normal power generation diversion and benefit, while considering to reduce the influence to environment as far as possible, arranged in riverbed
Blocking dam being highly only 4m, not blocking river all.To avoid building for power station from influenceing right bank protection zone, generating diversion
Building is arranged in left bank.
Requirement, the engineering that the scale of incorporation engineering, consideration diversion and power are released to water level, sand discharge and ecological flow are to right bank
The factor such as the influence of protection zone and fish species, carry out comprehensive analysis determine this engineering can meet water diversion engineering generating
Major function requirement, can take into account again environmental protection and sand discharge demand generating water diverting structure arrangement.
As shown in figures 1-4, blocking dam 1 is arranged in riverbed, plays a part of banked-up water level, meet power station diversion
The requirement of generating.But the heap soil or fertilizer over and around the roots height of water level necessarily causes the decline of flow rate of water flow in river course, also necessarily causes lower sluicing stream to take husky energy
The decline of power, such as takes no action to necessarily cause the alluvial of silt in storehouse, so as to influence the generating diversion quality in power station and normal
On-road efficiency;Simultaneously because this engineering reservoir is substantially without storage capacity, the depth of water is shallower in storehouse, before the intake gate lock of power station inlet velocity compared with
Greatly, when intake gate opens a sluice gate diversion, the silt of greater particle size in river bed load is easily made to carry in channel, so as to cause to generate electricity
Diversion silt content increases and the Sediment Siltation in flume channel.Such as routinely mentality of designing, it is considered to power station diversion and power demand,
River should be blocked disconnected by blocking dam 1, still there is the demand of fish migration and ecological flow of releasing due to this engineering, such as all cut river course
It is disconnected, then the specialized facilities that fish pass and ecological flow are released must be set in addition, so then building species it is more, from now on power station adjust
Degree operation is complicated, periphery protection zone ambient influnence is increased and construction investment is larger.Through analysis and research, to simplify structure and work
Cheng Yunhang difficulty, and the influence to environment is reduced as far as possible, take following aggregate measures and solve:
1st, by blocking dam 1 and power station intake gate 3 close proximity to arrangement, to cause not dropped into the flow rate of water flow in storehouse as far as possible
It is low excessive, it is considered to the influence of the factor such as orographic condition, stream gradient, determine blocking dam 1 with power station intake gate 3 at a distance of about 80m.
2nd, for the benefit of silt discharge in storehouse, in the maximum scope of the position choice arrangement of blocking dam 1 gradient in the river course, should
Section mean inclination is about 1%, more than bed load sediment median particle diameter critical grade 4 ‰.
3rd, consider project scale, earial drainage to the washing away of downstream, to factors, the dam body dam of blocking dam 1 such as the influence degrees of environment
Crest level is no more than main stem elevation.If the height of blocking dam 1 obtains larger, although beneficial to the matter for improving power station generating diversion
Amount, but the increasing of its caused depth rise, the depth of water, will cause that flow rate of water flow lowers row that is more and being unfavorable for silt in storehouse in storehouse
Go out, thus blocking dam 1 height set it is smaller.Consideration carrys out in beach volleyball outbound major part, water level needed for analysis generating diversion
And flow rate of water flow is more than water level requirement needed for bed load sediment median particle diameter start velocity in storehouse, through comprehensive analysis, the dam of blocking dam 1
Body maximum height is defined as 4m.
4th, the demand of fish migration etc. is considered, river is not blocked disconnected all for blocking dam 1, and blocking dam is in the left and right bank two in river course
Side is arranged, in the main flow position future insufficiency 2 in river course, as the passage of fish pass, ecological flow, silt conveying etc..
5th, body according to this engineering fish is long, Burden-Swimming Ability of KM, migration characteristic the features such as, while mud when taking into account non-flood period water
Husky start velocity needs and should meet dry season to release the requirement of ecological flow, determines the width of breach 2.Breach primary section is
Trapezoidal, bottom width is 2.0m, and two side slope ratios are 1:1, the depth of water is 0.6~4.1m, indentation, there max-flow in migration season breach
Speed is about 1.2m/s, and breach is 5.2m to maximum bottom width along river.The sectional dimension of indentation, there, meets wanting for the normal migration of fish
Ask;Meanwhile, when dry season, natural water amount was smaller, Water Requirement passes through breach 2 to be essentially identical to the state in former river course
Under let out, when flood season natural water amount is larger, Water Requirement is let out under being combined by breach 2 and blocking dam both sides elevations dam body 1.
6th, it is highly relatively low due to blocking dam 1, come under husky dam body and breach 2 by blocking dam 1 to let out in river.Dry season
Runoff and sediment load amount hour, can by being let out under breach 2, flood season runoff and sediment load amount it is larger when, under being combined by dam body and breach 2
Let out.Dam body by can free overflow build is set, it is considered to dam stabilization and spend being connected for dam current and downstream, its section is upper and lower
Trip has been arranged as one and has answered the gradient, is taken as 1:0.4.Dam crest is wide to take into account construction demand but should not be too big, and this engineering is taken as 2m.
7th, the dash and the length and bank crest level of sand prevention bank 4 for being set before intake gate 3, introducing needed for should meeting power station is most
Big generating flow and the requirement of bank flow velocity is crossed, cross bank flow velocity by not causing that river bed load sediment median particle diameter starts control, root
According to river course inlet flow rate and sediment charge, particle composition situation, it is 0.6~1.8m/s to cross bank flow rates;
The length and bank crest level of dash and sand prevention bank 4, should also meet dry season riverbed ecological flow and release demand, and it is high
Journey should be higher than that the water level of the natural river course corresponding to the ecological flow of dry season riverbed demand.According to environmental requirement, engineering need to let out
Put ecological flow and at least should be 4.37m3/ s, according to the natural stage-discharge relation line in river course, river course naturally carrys out flow for 4.37m3/s
When, corresponding water level is 2157.14m, as ensures ecological flow Minimum requirements, and water-blocking bank elevation should be higher than that before intake gate
2157.14m.The fraction of the ecological flow let out under consideration, water-blocking bank elevation is 2157.50m before determining power station intake gate, and bank is high
It is 1m to spend, and length is 40m.So ensure that when natural water amount is less than 4.37m in river course3During/s, manual dispatching is not required to
Control, all natural water can not enter in the intake gate of power station and fully enter former river course.The setting of water-blocking bank both gave
Ecological flow is released the absolute guarantee of demand, in turn simplify frequent scheduling and the operation difficulty of intake gate gate.Due to not again
Set special ecological flow to release facility, save construction investment, also reduce the influence to environment.
Embodiment described above is merely to illustrate technological thought of the invention and feature, in the art its object is to make
Technical staff it will be appreciated that present disclosure and implementing according to this, it is impossible to patent model of the invention is only limited with the present embodiment
Enclose, i.e., equal change or modification that all disclosed spirit is made still can be in the scope of the claims of the invention.
Claims (9)
1. it is a kind of to take into account the power station generating water diverting structure arrangement of environmental protection and sand discharge demand, including the diversion that side of pulling in shore is arranged
System, blocking dam, it is characterised in that blocking dam (1) is reserved with by riverbed main flow position scarce in river course, on blocking dam (1)
Mouth (2), dash and sand prevention bank (4), the dam body energy of blocking dam (1) are set before the intake gate (3) of the diversion system of side arrangement of pulling in shore
Free overflow, the two sides crest elevation of blocking dam (1) meets to be generated electricity when flood season power station is completely sent out quotes water level requirement needed for flow, together
When meet in flood season storehouse required water level requirement when flow rate of water flow is more than bed load sediment median particle diameter start velocity.
2. the power station generating water diverting structure arrangement of environmental protection and sand discharge demand, its feature are taken into account according to claim 1
It is that the blocking dam (1) is arranged close to intake gate (3).
3. the power station generating water diverting structure arrangement of environmental protection and sand discharge demand, its feature are taken into account according to claim 1
It is that the gradient is more than bed load sediment median particle diameter critical grade scope during the blocking dam (1) is arranged in river course, that is, be chosen at
In river course in the maximum scope of the gradient.
4. the power station generating water diverting structure arrangement of environmental protection and sand discharge demand, its feature are taken into account according to claim 1
It is that blocking dam (1) dam body is highly 2~5 meters.
5. the power station generating water diverting structure arrangement of environmental protection and sand discharge demand, its feature are taken into account according to claim 1
It is that the position of breach (2) is located in the range of channel thread on the blocking dam (1), defeated as fish pass, ecological flow, silt
Send passage;The Yokogawa of breach (2) is 1~4m to width, meets requirement of the fish migration to upstream and downstream head and flow velocity, while and
Turning round and look at sand discharge and dry season releases ecological flow demand.
6. the power station generating water diverting structure arrangement of environmental protection and sand discharge demand, its feature are taken into account according to claim 1
It is that there is certain slope the upstream and downstream of the blocking dam (1), are 1:0.3~1:0.7, a width of 2~4m of dam crest.
7. the power station generating water diverting structure arrangement of environmental protection and sand discharge demand, its feature are taken into account according to claim 1
It is the dash and the length and bank crest level of sand prevention bank (4) set before the intake gate (3), meets introducing needed for power station
Maximum generation flow and the excessively requirement of bank flow velocity, cross bank flow velocity and do not cause that river bed load sediment median particle diameter starts, cross bank stream
Speed is 0.6~1.8m/s;Also meet dry season riverbed ecological flow to release demand, ecology of the elevation higher than dry season riverbed demand
The water level of the natural river course corresponding to flow, sand prevention bank is highly 1~2m.
8. the power station generating water diverting structure arrangement of environmental protection and sand discharge demand, its feature are taken into account according to claim 1
It is that it is middle-size and small-size Hydraulic and Hydro-Power Engineering that the arrangement is used for fully-loaded stream, scale.
9. the power station generating water diverting structure arrangement of environmental protection and sand discharge demand, its feature are taken into account according to claim 8
It is that the arrangement is used for the facility cloth of fragile, high to the environmental protection requirement Hydraulic and Hydro-Power Engineering of affiliated area surroundings
Put.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710037944.XA CN106759168A (en) | 2017-01-18 | 2017-01-18 | A kind of generating water diverting structure arrangement for taking into account environmental protection and sand discharge demand |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710037944.XA CN106759168A (en) | 2017-01-18 | 2017-01-18 | A kind of generating water diverting structure arrangement for taking into account environmental protection and sand discharge demand |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106759168A true CN106759168A (en) | 2017-05-31 |
Family
ID=58945248
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710037944.XA Pending CN106759168A (en) | 2017-01-18 | 2017-01-18 | A kind of generating water diverting structure arrangement for taking into account environmental protection and sand discharge demand |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106759168A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107268519A (en) * | 2017-06-16 | 2017-10-20 | 水利部交通运输部国家能源局南京水利科学研究院 | A kind of tidal reach tributary inlet door dike header structure |
CN109680659A (en) * | 2018-12-28 | 2019-04-26 | 中国水利水电科学研究院 | A kind of water channeling type power station Overflow Section ecological reconstruction structure and method |
CN110258478A (en) * | 2019-07-03 | 2019-09-20 | 中国电建集团成都勘测设计研究院有限公司 | Ecological power station and head pivot building set arragement construction |
CN115434290A (en) * | 2022-07-22 | 2022-12-06 | 中国电建集团贵阳勘测设计研究院有限公司 | Hydropower station rectification and river connectivity restoration structure |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU3562702A (en) * | 1999-11-03 | 2003-06-12 | Lauriston Enterprises Pty Ltd | Gutter protector & guttering incorporating same |
CN103510493A (en) * | 2013-10-23 | 2014-01-15 | 罗富强 | Low overflow dam cave depot type hydropower station |
CN104863101A (en) * | 2015-05-27 | 2015-08-26 | 中国电建集团贵阳勘测设计研究院有限公司 | Hydropower station water-reducing river reach fish habitat protection system |
CN205000309U (en) * | 2015-09-30 | 2016-01-27 | 中国电建集团贵阳勘测设计研究院有限公司 | Fish passing device suitable for low-water-head overflow dam |
CN206529749U (en) * | 2017-01-18 | 2017-09-29 | 中国电建集团北京勘测设计研究院有限公司 | A kind of power station generating water diverting structure arrangement for taking into account environmental protection and sand discharge demand |
-
2017
- 2017-01-18 CN CN201710037944.XA patent/CN106759168A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU3562702A (en) * | 1999-11-03 | 2003-06-12 | Lauriston Enterprises Pty Ltd | Gutter protector & guttering incorporating same |
CN103510493A (en) * | 2013-10-23 | 2014-01-15 | 罗富强 | Low overflow dam cave depot type hydropower station |
CN104863101A (en) * | 2015-05-27 | 2015-08-26 | 中国电建集团贵阳勘测设计研究院有限公司 | Hydropower station water-reducing river reach fish habitat protection system |
CN205000309U (en) * | 2015-09-30 | 2016-01-27 | 中国电建集团贵阳勘测设计研究院有限公司 | Fish passing device suitable for low-water-head overflow dam |
CN206529749U (en) * | 2017-01-18 | 2017-09-29 | 中国电建集团北京勘测设计研究院有限公司 | A kind of power station generating water diverting structure arrangement for taking into account environmental protection and sand discharge demand |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107268519A (en) * | 2017-06-16 | 2017-10-20 | 水利部交通运输部国家能源局南京水利科学研究院 | A kind of tidal reach tributary inlet door dike header structure |
CN109680659A (en) * | 2018-12-28 | 2019-04-26 | 中国水利水电科学研究院 | A kind of water channeling type power station Overflow Section ecological reconstruction structure and method |
CN110258478A (en) * | 2019-07-03 | 2019-09-20 | 中国电建集团成都勘测设计研究院有限公司 | Ecological power station and head pivot building set arragement construction |
CN115434290A (en) * | 2022-07-22 | 2022-12-06 | 中国电建集团贵阳勘测设计研究院有限公司 | Hydropower station rectification and river connectivity restoration structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103266583B (en) | Bent slope underflow energy dissipation structure of water conservancy and hydropower engineering | |
CN106759168A (en) | A kind of generating water diverting structure arrangement for taking into account environmental protection and sand discharge demand | |
CN203256706U (en) | Underflow energy dissipation structure of broken slope in hydraulic and hydroelectric projects | |
CN206529749U (en) | A kind of power station generating water diverting structure arrangement for taking into account environmental protection and sand discharge demand | |
CN203188185U (en) | United energy dissipation structure under ultralow Froude number | |
CN105951689B (en) | A kind of reservoir let out in advance and ecological flow under let out structure | |
CN105257454B (en) | A kind of water channeling type swirling water current electricity generation system | |
CN114108575B (en) | Stepped grading spillway with energy dissipation effect | |
CN107386220A (en) | The dam structure of breach shunting two | |
CN202214710U (en) | Overflowing-drainage integrated brake weir | |
CN106702968B (en) | It is a kind of can automatic sand washing subtract the arc line type overflow dam and its operation method of silt | |
CN103290804A (en) | Method and structure for providing downstream ecological flow after gate locking of stream guidance water release structure | |
CN206752427U (en) | A kind of power station ground power house tailrace outlet structure and its power station | |
CN102383401A (en) | Overflow water drainage integral type sluice weir | |
CN202718071U (en) | Barrage structure capable of lowering silt of reservoir area | |
CN105019414B (en) | Composite lock chamber structure for narrow water intake of mountain hydropower project | |
CN209493909U (en) | A kind of aqueduct is across reservoir point water intaking structure | |
CN206554031U (en) | It is a kind of sand washing to subtract the arc line type overflow dam of silt automatically | |
CN207143879U (en) | The dam structure of breach shunting two | |
CN221030007U (en) | Energy dissipation structure of flood discharge tunnel water outlet | |
CN102251498A (en) | New method for reducing silt of large and medium tidal range river mouth bar sand section channel | |
CN209429079U (en) | A kind of powerhouse of hydropower station tailwater channel structure | |
CN206204891U (en) | Prevent the drainage structure for debris flow of diversion tunnel outlet obstruction | |
CN201933471U (en) | Double-layer separation flood discharge structure of side spillway | |
CN104099908A (en) | Gravity type sand obstructing and guiding structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||