CN106758865A - A kind of steel sand barrel for being applied to real-time display bearing capacity in bridge rotating - Google Patents

A kind of steel sand barrel for being applied to real-time display bearing capacity in bridge rotating Download PDF

Info

Publication number
CN106758865A
CN106758865A CN201611203739.8A CN201611203739A CN106758865A CN 106758865 A CN106758865 A CN 106758865A CN 201611203739 A CN201611203739 A CN 201611203739A CN 106758865 A CN106758865 A CN 106758865A
Authority
CN
China
Prior art keywords
sand barrel
barrel
sand
steel
lower sand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611203739.8A
Other languages
Chinese (zh)
Inventor
梁旭
王福华
王良
赵福
周春
姚志安
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Hi-Run Engineering & Equipment Co Ltd
Original Assignee
Wuhan Hi-Run Engineering & Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Hi-Run Engineering & Equipment Co Ltd filed Critical Wuhan Hi-Run Engineering & Equipment Co Ltd
Priority to CN201611203739.8A priority Critical patent/CN106758865A/en
Publication of CN106758865A publication Critical patent/CN106758865A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/08Methods or apparatus specially adapted for erecting or assembling bridges by rotational movement of the bridge or bridge sections

Abstract

A kind of steel sand barrel for being applied to real-time display bearing capacity in bridge rotating, including steel sand bucket and data synthetical collection instrument(13), steel sand bucket include upper sand barrel(1), lower sand barrel(7)And cover plate(8), upper sand barrel(1)It is interior filled with concrete(19), lower sand barrel(7)It is under-filled to have quartz sand(12), lower sand barrel wallboard(21)Outer surface is provided with hanger(24), upper sand barrel(1)Staving be placed on lower sand barrel(7)Quartz sand(12)On, upper sand barrel(1)Built-in type concrete strain gauge is inside installed(2), upper sand barrel(1)And lower sand barrel(7)Between along bucket wall circumferentially four guy type displacement meters are uniformly installed(3), built-in type concrete strain gauge(2)And guy type displacement meter(3)Respectively with aggregation of data Acquisition Instrument(13)It is connected.Show the size of its bearing capacity in real time in bridge casting process.

Description

A kind of steel sand barrel for being applied to real-time display bearing capacity in bridge rotating
Technical field
The present invention relates to a kind of steel sand bucket, more specifically to one kind is applied to show bearing capacity in real time in bridge rotating Steel sand barrel, belong to technical field of bridge construction.
Background technology
In recent years, with high-speed railway, the construction of highway, large quantities of leap existing railways and highway are emerged in succession Large bridge.Such large bridge due to being restricted by construction environment and traffic factor, using conventional construction method difficulty very Greatly, influence of the erection by swing construction can preferably avoid transporting All other routes is usually taken.
At present, swivel, the core during swivel are generally realized using the method for flat turn in the construction of bridge rotating method Part is Rotary ball hinge;Rotary ball hinge is typically mounted at the theoretical position of centre of gravity of swivel bridge, and it is mainly by ball pivot main part, auxiliary Support system and trailer system three parts are helped to constitute.Swivel bridge during construction, due to construction error, its reality Center of gravity can not possibly be always held at the center of Rotary ball hinge;The deviation of center of gravity can produce tilting moment, the work of auxiliary shoring system With being to carry the scope inner equilibrium tilting moment at it, it is ensured that the smooth construction of bridge.
Steel sand bucket belongs to the part in auxiliary shoring system, undertakes whole together with ball pivot main part when bridge is poured The weight of bridge.But steel sand bucket is temporary support, bridge can be weighed and counterweight before swivel after the completion of pouring to the bridge, Now steel sand bucket will be removed;By weighing and counterweight for bridge so that the actual center gravity of bridge is at Rotary ball hinge center In certain deviation range, meet swivel and require.
At present, existing steel sand bucket, the function with vertical one-way movement simultaneously can bear certain vertical load, but can not Show the size of its vertical load born so that bridge its center of gravity deflection during pouring is unable to real-time monitoring, finally Bridge pours and completes its position of centre of gravity and may farther out, before swivel be unfavorable for the stabilization of whole bridge from theoretical position of centre of gravity deviation Property.
The content of the invention
It is vertical that steel sand bucket it is an object of the invention to be directed in the construction of existing highway bridge erection by swing can not show that it bears The size of load so that bridge is the problems such as its center of gravity deflection is unable to real-time monitoring during pouring, there is provided one kind is applied to The steel sand barrel of bearing capacity is shown in bridge rotating in real time.
To achieve the above object, institute is the present invention using technical solution:One kind is applied to show in real time in bridge rotating Show the steel sand barrel of bearing capacity, it is characterised in that:Including steel sand bucket and data synthetical collection instrument, described steel sand bucket includes upper Sand bucket, lower sand barrel and cover plate, the upper sand barrel are be made up of upper sand barrel panel, upper sand barrel base plate and upper sand barrel wallboard barrel-shaped Concrete is filled with body, upper sand barrel, the lower sand barrel is made up of lower sand barrel panel, lower sand barrel wallboard and lower sand barrel base plate Barrel-shaped body, two lower sand barrel flange connecting plates are provided with lower sand barrel along bucket wall circumferencial direction, and lower sand barrel is under-filled quartz Sand, described lower sand barrel wallboard outer surface is provided with hanger, and the staving of upper sand barrel is placed on the quartz sand of lower sand barrel, described It is connected by screw bolt and nut between upper sand barrel panel and lower sand barrel panel, described cover plate is arranged on by screw and packing ring On lower sand barrel wallboard, built-in type concrete strain gauge is installed in described upper sand barrel, along bucket wall between upper sand barrel and lower sand barrel It is circumferential that four guy type displacement meters are uniformly installed, described built-in type concrete strain gauge and guy type displacement meter respectively with number It is connected according to synthetical collection instrument.
Upper sand barrel shrouding is provided with described upper sand barrel panel.
Described upper sand barrel is internally provided with upper sand barrel gusset.
Described lower sand barrel inner bottom surface is evenly distributed four pressure cells, described pressure cell and aggregation of data Acquisition Instrument phase Connection.
Described lower sand barrel wallboard outer surface is evenly distributed and is provided with four external labeling type strain gauges, and described external labeling type should Become meter to be connected with aggregation of data Acquisition Instrument.
Compared with prior art, the beneficial effects of the invention are as follows:
Built-in type concrete strain gauge is installed in the present invention in upper sand barrel, installation is evenly distributed between upper sand barrel and lower sand barrel There are four guy type displacement meters, lower sand barrel inner bottom surface is evenly distributed four pressure cells, and lower sand barrel wallboard outer surface is circumferentially equal Cloth is provided with four external labeling type strain gauges, and the strain of built-in type concrete strain gauge, guy type displacement meter, pressure cell and external labeling type Meter is connected with aggregation of data Acquisition Instrument respectively.Therefore the size of its bearing capacity can be in real time shown in bridge casting process, So that bridge can pour density in casting process according to the pressure value real-time control of each steel sand bucket, it is ensured that center of gravity is being wanted In the range of asking, solving existing steel sand bucket can not in real time show bearing capacity, cause bridge to pour completion its position of centre of gravity possibility From theoretical position of centre of gravity deviation farther out the problems such as, it is ensured that position of centre of gravity in error range, improve bridge construction process in it is steady It is qualitative.
Brief description of the drawings
Fig. 1 is schematic structural view of the invention.
Fig. 2 is top view of the present invention.
Fig. 3 is steel sand barrel side view in the present invention.
Fig. 4 is upper sand barrel structural representation in the present invention.
Fig. 5 is the A-A sectional views of Fig. 4.
Fig. 6 is lower sand barrel structural representation in the present invention.
Fig. 7 is the B-B sectional views of Fig. 6.
In figure, upper sand barrel 1, built-in type concrete strain gauge 2, guy type displacement meter 3, bolt 4, nut 5, external labeling type strain Meter 6, lower sand barrel 7, cover plate 8, screw 9, packing ring 10, pressure cell 11, quartz sand 12, aggregation of data Acquisition Instrument 13, upper sand barrel panel 14, upper sand barrel shrouding 15, upper sand barrel base plate 16, upper sand barrel wallboard 17, upper sand barrel gusset 18, concrete 19, lower sand barrel panel 20, Lower sand barrel wallboard 21, lower sand barrel flange connecting plate 22, lower sand barrel base plate 23, hanger 24.
Specific embodiment
Below in conjunction with brief description of the drawings, the present invention is described in further detail with specific embodiment.
Referring to Fig. 1 to Fig. 3, a kind of steel sand barrel for being applied to real-time display bearing capacity in bridge rotating, it is a kind of Temporary support in Bridge Rotation Construction Technique, can in bridge concreting process is turned real-time monitoring its position of centre of gravity, protect The stability of bridge, including steel sand bucket and data synthetical collection instrument 13 are demonstrate,proved, described steel sand bucket includes upper sand barrel 1, the and of lower sand barrel 7 Cover plate 8.
Referring to Fig. 1 to Fig. 5, the upper sand barrel 1 is by upper sand barrel panel 14, upper sand barrel base plate 16 and the structure of upper sand barrel wallboard 17 Into barrel-shaped body, concrete 19 is filled with upper sand barrel 1.Built-in type concrete strain gauge 2 is installed in described upper sand barrel 1, The built-in type concrete strain gauge 2 is connected by data wire with aggregation of data Acquisition Instrument 13;Built-in type concrete strain gauge 2 is pre- It is embedded in inside concrete 19, for the strain measurement inside concrete 19.Upper sand barrel is provided with described upper sand barrel panel 14 Shrouding 15, upper sand barrel shrouding 15 is located in the middle of upper sand barrel panel 14, and the size of upper sand barrel shrouding 15 is smaller than upper sand barrel panel 14;On Sand bucket shrouding 15 is welded on upper sand barrel panel 14 after the completion of concrete 19 is poured, and it is used to seal whole upper sand barrel 1.It is described Upper sand barrel 1 be internally provided with upper sand barrel gusset 18, upper sand barrel gusset 18 is used to strengthen the intensity of upper sand barrel 1.
Referring to Fig. 1 to Fig. 3, Fig. 6 to Fig. 7, the lower sand barrel 7 is by lower sand barrel panel 20, lower sand barrel wallboard 21 and lower sand The barrel-shaped body that barrel soleplate 23 is constituted, lower sand barrel 7 is under-filled quartz sand 12.It is provided with along bucket wall circumferencial direction on lower sand barrel 7 Two lower sand barrel flange connecting plates 22, sand is unloaded for steel sand bucket.The described outer surface of lower sand barrel wallboard 21 is provided with hanger 24, For the lifting of steel sand bucket.Described cover plate 8 is arranged on lower sand barrel wallboard 21 by screw 9 and packing ring 10.Described lower sand 7 inner bottom surfaces of bucket are evenly distributed four pressure cells 11, and described pressure cell 11 is connected with aggregation of data Acquisition Instrument 13;Steel sand bucket Pressure cell 11 is also subjected to certain pressure when bearing the pressure of vertical direction, and the size of the pressure can be shown by pressure cell 11 Out.The described outer surface of lower sand barrel wallboard 21 is evenly distributed and is provided with four external labeling type strain gauges 6, and described external labeling type should Become meter 6 to be connected with aggregation of data Acquisition Instrument 13;Its lower sand barrel wallboard 21 can occur when steel sand bucket bears the pressure of vertical direction Deformation, produces certain strain, the strain to be measured by external labeling type strain gauge 6.
Referring to Fig. 1 to Fig. 3, the staving of upper sand barrel 1 is placed on the quartz sand 12 of lower sand barrel 7, described upper sand barrel panel It is connected with nut 5 by bolt 4 between 14 and lower sand barrel panel 20.During specific making, upper sand barrel 1 is placed on quartz sand 12 Afterwards, upper sand barrel 1 need to be pressed under the forcing press of corresponding tonnage according to specific requirement, makes total height of steel sand bucket after pressure need to meet Specific requirement;Clamping screw 4 and nut 5 again are highly transferred to after predetermined value, upper sand barrel 1 and lower sand barrel 7 are coupled together.Upper sand barrel It is evenly distributed between 1 and lower sand barrel 7 and four guy type displacement meters 3 is installed, described guy type displacement meter 3 passes through data wire It is connected with aggregation of data Acquisition Instrument 13;Guy type displacement meter 3 mechanical movement can be converted into one kind can measure, record Or the electric signal of transmission, the change for measuring displacement.
Referring to Fig. 1 to Fig. 3, after steel sand bucket manufacture is completed, pressure calibration test need to be carried out.During test on upper sand barrel 1 Apply different normal pressures, so as to obtain the built-in type concrete strain gauge 2, stay-supported being connected with aggregation of data Acquisition Instrument 13 The test data of displacement meter 3, external labeling type strain gauge 6 and pressure cell 11 meter;Again by calculating and plotting go out pressure with it is each strain and The loading and unloading calibration curve of displacement.During steel sand bucket works at the scene, by the number on aggregation of data Acquisition Instrument 13 According to the calibration curve drawn out, you can with show now steel sand bucket carrying pressure size.
Referring to Fig. 1 to Fig. 3, this steel sand barrel belongs to the parts in Rotary ball hinge auxiliary shoring system, is poured in bridge Build construction period and play interim fixed support.Start to turn pouring for bridge, in-site installation after Rotary ball hinge installation When, this steel sand barrel is respectively arranged to direction across bridge both direction along bridge along swivel bridge, remaining position uses ordinary steel sand bucket. By along bridge to two pressure values of steel sand barrel can calculate bridge along bridge to gravity center eccentric, by direction across bridge two The pressure value of steel sand barrel can calculate the gravity center eccentric of bridge direction across bridge, and then phase is used during bridge is poured The measure answered is adjusted so that the eccentricity value of bridge center of gravity within the specific limits, improves the stability of bridge.
Above content is to combine specific preferred embodiment further description made for the present invention, it is impossible to assert Specific implementation of the invention is confined to these explanations.For general technical staff of the technical field of the invention, On the premise of not departing from present inventive concept, some simple deduction or replace can also be made, said structure should all be considered as belonging to Protection scope of the present invention.

Claims (5)

  1. It is 1. a kind of to be applied to the real-time steel sand barrel for showing bearing capacity in bridge rotating, it is characterised in that:Including steel sand bucket and Aggregation of data Acquisition Instrument(13), described steel sand bucket includes upper sand barrel(1), lower sand barrel(7)And cover plate(8), the upper sand barrel(1) It is by upper sand barrel panel(14), upper sand barrel base plate(16)With upper sand barrel wallboard(17)The barrel-shaped body for constituting, upper sand barrel(1)Interior filling There is concrete(19), the lower sand barrel(7)It is by lower sand barrel panel(20), lower sand barrel wallboard(21)With lower sand barrel base plate(23)Structure Into barrel-shaped body, lower sand barrel(7)On bucket wall circumferencial direction is provided with two lower sand barrel flange connecting plates(22), lower sand barrel(7) It is under-filled to have quartz sand(12), described lower sand barrel wallboard(21)Outer surface is provided with hanger(24), upper sand barrel(1)Staving It is placed on lower sand barrel(7)Quartz sand(12)On, described upper sand barrel panel(14)With lower sand barrel panel(20)Between pass through spiral shell Bolt(4)And nut(5)It is connected, described cover plate(8)By screw(9)And packing ring(10)Installed in lower sand barrel wallboard(21) On, described upper sand barrel(1)Built-in type concrete strain gauge is inside installed(2), upper sand barrel(1)And lower sand barrel(7)Between along bucket Wall is circumferentially uniformly provided with four guy type displacement meters(3), described built-in type concrete strain gauge(2)And guy type displacement meter (3)Respectively with aggregation of data Acquisition Instrument(13)It is connected.
  2. 2. it is according to claim 1 it is a kind of be applied in bridge rotating the steel sand barrel of display bearing capacity in real time, it is special Levy and be:Described upper sand barrel panel(14)On be provided with upper sand barrel shrouding(15).
  3. 3. it is according to claim 1 it is a kind of be applied in bridge rotating the steel sand barrel of display bearing capacity in real time, it is special Levy and be:Described upper sand barrel(1)It is internally provided with upper sand barrel gusset(18).
  4. 4. it is according to claim 1 it is a kind of be applied in bridge rotating the steel sand barrel of display bearing capacity in real time, it is special Levy and be:Described lower sand barrel(7)Inner bottom surface is evenly distributed four pressure cells(11), described pressure cell(11)It is comprehensive with data Close Acquisition Instrument(13)It is connected.
  5. 5. it is according to claim 1 it is a kind of be applied in bridge rotating the steel sand barrel of display bearing capacity in real time, it is special Levy and be:Described lower sand barrel wallboard(21)Outer surface is evenly distributed and is provided with four external labeling type strain gauges(6), described is outer Mounted strain gauge(6)With aggregation of data Acquisition Instrument(13)It is connected.
CN201611203739.8A 2016-12-23 2016-12-23 A kind of steel sand barrel for being applied to real-time display bearing capacity in bridge rotating Pending CN106758865A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611203739.8A CN106758865A (en) 2016-12-23 2016-12-23 A kind of steel sand barrel for being applied to real-time display bearing capacity in bridge rotating

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611203739.8A CN106758865A (en) 2016-12-23 2016-12-23 A kind of steel sand barrel for being applied to real-time display bearing capacity in bridge rotating

Publications (1)

Publication Number Publication Date
CN106758865A true CN106758865A (en) 2017-05-31

Family

ID=58897689

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611203739.8A Pending CN106758865A (en) 2016-12-23 2016-12-23 A kind of steel sand barrel for being applied to real-time display bearing capacity in bridge rotating

Country Status (1)

Country Link
CN (1) CN106758865A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114991025A (en) * 2022-05-31 2022-09-02 宁波市政工程建设集团股份有限公司 Intelligent sand bucket device and using method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1193105A (en) * 1997-09-24 1999-04-06 Masashige Inaba Continuous paving structure of bridge face
CN101424128A (en) * 2008-12-12 2009-05-06 中建三局建设工程股份有限公司 Civil engineering construction flask device
CN101476298A (en) * 2009-01-24 2009-07-08 中国建筑第二工程局有限公司 Integral bridge descending construction method and construction equipment
CN201358441Y (en) * 2009-01-24 2009-12-09 中国建筑第二工程局有限公司 Sand barrel used for whole descending of bridge
CN105507163A (en) * 2015-11-26 2016-04-20 中铁四局集团建筑工程有限公司 Device for discriminating swivel bridge weighing test critical point and detection method
CN205329548U (en) * 2015-12-10 2016-06-22 中国二冶集团有限公司 Sand section of thick bamboo temporary support
CN205676781U (en) * 2016-05-31 2016-11-09 成都亚佳工程新技术开发有限公司 One exempts from Rotary ball hinge system of weighing
CN206457732U (en) * 2016-12-23 2017-09-01 武汉海润工程设备有限公司 It is a kind of to be applied in bridge rotating the steel sand barrel of display bearing capacity in real time

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1193105A (en) * 1997-09-24 1999-04-06 Masashige Inaba Continuous paving structure of bridge face
CN101424128A (en) * 2008-12-12 2009-05-06 中建三局建设工程股份有限公司 Civil engineering construction flask device
CN101476298A (en) * 2009-01-24 2009-07-08 中国建筑第二工程局有限公司 Integral bridge descending construction method and construction equipment
CN201358441Y (en) * 2009-01-24 2009-12-09 中国建筑第二工程局有限公司 Sand barrel used for whole descending of bridge
CN105507163A (en) * 2015-11-26 2016-04-20 中铁四局集团建筑工程有限公司 Device for discriminating swivel bridge weighing test critical point and detection method
CN205329548U (en) * 2015-12-10 2016-06-22 中国二冶集团有限公司 Sand section of thick bamboo temporary support
CN205676781U (en) * 2016-05-31 2016-11-09 成都亚佳工程新技术开发有限公司 One exempts from Rotary ball hinge system of weighing
CN206457732U (en) * 2016-12-23 2017-09-01 武汉海润工程设备有限公司 It is a kind of to be applied in bridge rotating the steel sand barrel of display bearing capacity in real time

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114991025A (en) * 2022-05-31 2022-09-02 宁波市政工程建设集团股份有限公司 Intelligent sand bucket device and using method
CN114991025B (en) * 2022-05-31 2023-12-08 宁波市政工程建设集团股份有限公司 Intelligent sand barrel device and use method

Similar Documents

Publication Publication Date Title
CN104843582B (en) A kind of steel containment vessel of nuclear power station bottom (head) hanging method and Special-purpose hanger rigging thereof
CN105369738A (en) Prepressing method of flushing type bridge rubber raft
CN101949729B (en) Weighting device and calibrating method of large weighting apparatus
CN102564549A (en) Array piezoelectric sensor for dynamic weight measurement of vehicle
CN206457732U (en) It is a kind of to be applied in bridge rotating the steel sand barrel of display bearing capacity in real time
CN106758865A (en) A kind of steel sand barrel for being applied to real-time display bearing capacity in bridge rotating
CN113186839B (en) Balance weight method for unequal-span rotary cable-stayed bridge
CN105970835B (en) A kind of cable-stayed bridge rotator construction weighing structure and Weighing method
CN108910674A (en) A kind of nuclear power station CR10 and reinforcing bar composite module integral hoisting system
CN111593772B (en) Swivel bridge weighing method based on pile foundation stress measurement
CN111719602B (en) Pile foundation model loading device under complex load effect
CN202886203U (en) Small-tonnage low-speed loading device for beam bending resistance test
CN207751572U (en) A kind of steel structure concrete truck scale
CN112665783A (en) Force measuring sand box for swivel bridge and application of force measuring sand box in swivel bridge construction
CN215366842U (en) Horizontal rotation bridge tension and compression temporary locking structure
CN208009502U (en) Strip footing model test apparatus by the side slope of integrated micro stake supporting
CN106065575A (en) A kind of Bridge Rotation Construction Technique overturn-preventing system
CN113863165B (en) Large-section wide-span rigid frame bridge swivel weighing system and method
CN106989998B (en) Loading device for detecting interlocking performance of concrete interlocking block and application method
CN213579913U (en) Force measuring sand box for swivel bridge
CN110745718B (en) Deviation rectifying method for tower crane
CN208219623U (en) A kind of reusable foundation pile pile cover
CN205046487U (en) Pre -compaction device of bath formula bridge rubber raft
CN106081871B (en) A kind of nuclear power station steel dome balances hanging apparatus
CN203310500U (en) Novel flexible cup support structure with large-displacement for weighing large-scale object

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531