CN106703410A - 双向大柱网钢网架分块悬挑提升施工方法 - Google Patents
双向大柱网钢网架分块悬挑提升施工方法 Download PDFInfo
- Publication number
- CN106703410A CN106703410A CN201510793219.6A CN201510793219A CN106703410A CN 106703410 A CN106703410 A CN 106703410A CN 201510793219 A CN201510793219 A CN 201510793219A CN 106703410 A CN106703410 A CN 106703410A
- Authority
- CN
- China
- Prior art keywords
- stress
- rod
- deformation
- construction
- analysis
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Abstract
本发明涉及钢结构网架。一种双向大柱网钢网架分块悬挑提升施工方法,它包括:通过结构设计软件分析原结构在自重荷载下整体一次成形时的受力和变形状态,找出结构变形形状的反弯点位置和受拉杆、受压杆的范围;以变形形状的反弯点或受拉、受压杆分界点,初步确定分块位置;结合现场施工条件以及补档处杆件拼装精度要求,对初步分块位置进行局部调整,使最终分块后结构的受力状态与原设计一次成形的尽可能接近;按确定的施工方案,进行结构的施工全过程分析,对其它次要施工阶段个别超指标的杆件进行截面替换,保证整个施工过程结构的安全性。本发明施工成形后结构的变形和受力状态与原设计一次成形后的状态比较接近,减少了受力性质发生根本性改变的杆件数量,消除了结构安全隐患,保证网架分块连接处挠度变形的一致性,降低了合拢难度。
Description
技术领域
本发明涉及钢结构网架,尤其涉及双向大柱网钢网架悬挑提升施工方法。
背景技术
长期以来,对于超大面积网架的整体提升,人们都是从方便施工的角度考虑,网架的分块往往是以轴线为界限,从而使得网架在拼装的时候容易控制连接位置处的挠度,便于网架拼装。但是这种以轴线为界限的分块方法,从结构设计合理性的角度考虑,会存在以下三个方面不利的影响:
一、改变了大部分杆件的受力性质,原来设计成受压杆的可能变成受拉杆或原来设计成受拉杆的可能变成受压杆,存在较大的结构安全隐患;
二、结构成形后跨中挠度偏大,影响建筑的外观效果;
三、造成大面积的杆件替换,提高工程施工成本。
发明内容
本发明旨在解决现有技术的缺陷,提供一种双向大柱网钢网架分块悬挑提升施工方法。本发明施工成形后结构的变形和受力状态与原设计一次成形后的状态比较接近,尽可能减少了受力性质发生根本性改变的杆件数量,消除了结构安全隐患,保证网架分块连接处挠度变形的一致性,降低了合拢难度。
本发明一种双向大柱网钢网架分块悬挑提升施工方法,它包括:
步骤一、通过结构设计软件分析原结构在自重荷载下整体一次成形时的受力和变形状态,找出结构变形形状的反弯点位置和受拉杆受压杆的范围;
步骤二、以变形形状的反弯点或受拉和受压杆分界点,初步确定分块位置;
步骤三、对初步分块位置进行局部调整;局部调整按以下步骤进行:
按提升时的边界条件和初步分块分析网架的受力和变形,并与整体分析时的结果相比较,分析杆件补档处两边的相对变形以及现场场地条件;对初步分块位置进行局部调整,确保最终分块后结构的受力状态与原设计一次成形的尽可能接近,杆件补档处两边杆件的相对变形在安装允许的误差范围内;
步骤四、为保证施工阶段和使用阶段的安全,分别确定施工阶段和使用阶段的杆件应力比控制范围;
步骤五、以上一条应力比控制指标为依据,重新运行结构分析,对超过应力比指标范围的杆件进行截面替换;
步骤六、按确定的施工方案,进行结构的施工全过程分析,对其它次要施工阶段个别超指标的杆件进行截面替换,保证整个施工过程结构的安全性。
本发明施工成形后结构的变形和受力状态与原设计一次成形后的状态比较接近,尽可能减少了受力性质发生根本性改变的杆件数量,消除了结构安全隐患。保证网架分块连接处挠度变形的一致性,降低了合拢难度。避免人为增大跨中挠度,保证建筑外观效果。减少杆件截面替换的数量,降低工程造价。
具体实施方式
本发明一种双向大柱网钢网架分块悬挑提升施工方法,它包括:
步骤一、通过结构设计软件分析原结构在自重荷载下整体一次成形时的受力和变形状态,找出结构变形形状的反弯点位置和受拉杆受压杆的范围;
步骤二、以变形形状的反弯点或受拉和受压杆分界点,初步确定分块位置;
步骤三、对初步分块位置进行局部调整;局部调整按以下步骤进行:
按提升时的边界条件和初步分块分析网架的受力和变形,并与整体分析时的结果相比较,分析杆件补档处两边的相对变形以及现场场地条件;对初步分块位置进行局部调整,确保最终分块后结构的受力状态与原设计一次成形的尽可能接近,杆件补档处两边杆件的相对变形在安装允许的误差范围内;
步骤四、为保证施工阶段和使用阶段的安全,分别确定施工阶段和使用阶段的杆件应力比控制范围;
步骤五、以上一条应力比控制指标为依据,重新运行结构分析,对超过应力比指标范围的杆件进行截面替换;
步骤六、按确定的施工方案,进行结构的施工全过程分析,对其它次要施工阶段个别超指标的杆件进行截面替换,保证整个施工过程结构的安全性。
Claims (1)
1.一种双向大柱网钢网架分块悬挑提升施工方法,其具体实施办法如下:
步骤一、通过结构设计软件分析原结构在自重荷载下整体一次成形时的受力和变形状态,找出结构变形形状的反弯点位置和受拉杆受压杆的范围;
步骤二、以变形形状的反弯点或受拉和受压杆分界点,初步确定分块位置;
步骤三、对初步分块位置进行局部调整;局部调整按以下步骤进行:
按提升时的边界条件和初步分块分析网架的受力和变形,并与整体分析时的结果相比较,分析杆件补档处两边的相对变形以及现场场地条件,对初步分块位置进行局部调整,确保最终分块后结构的受力状态与原设计一次成形的尽可能接近,杆件补档处两边杆件的相对变形在安装允许的误差范围内;
步骤四、为保证施工阶段和使用阶段的安全,分别确定施工阶段和使用阶段的杆件应力比控制范围;
步骤五、以上一条应力比控制指标为依据,重新运行结构分析,对超过应力比指标范围的杆件进行截面替换;
步骤六、按确定的施工方案,进行结构的施工全过程分析,对其它次要施工阶段个别超指标的杆件进行截面替换,保证整个施工过程结构的安全性。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510793219.6A CN106703410A (zh) | 2015-11-18 | 2015-11-18 | 双向大柱网钢网架分块悬挑提升施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510793219.6A CN106703410A (zh) | 2015-11-18 | 2015-11-18 | 双向大柱网钢网架分块悬挑提升施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106703410A true CN106703410A (zh) | 2017-05-24 |
Family
ID=58932623
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510793219.6A Pending CN106703410A (zh) | 2015-11-18 | 2015-11-18 | 双向大柱网钢网架分块悬挑提升施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106703410A (zh) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102102445A (zh) * | 2011-03-09 | 2011-06-22 | 中国建筑第八工程局有限公司 | 超大焊接球网架的分块吊装施工方法 |
CN102168490A (zh) * | 2011-03-09 | 2011-08-31 | 中国建筑第八工程局有限公司 | 双曲面焊接球网架分块直接吊装施工方法 |
CN103866986A (zh) * | 2014-03-09 | 2014-06-18 | 山西四建集团有限公司 | 大跨度变截面螺栓球节点网壳安装方法 |
CN104032966A (zh) * | 2014-06-27 | 2014-09-10 | 中国十九冶集团(防城港)设备结构有限公司 | 弧形双层网架分块吊装高空合拢安装方法 |
CN104947942A (zh) * | 2015-05-06 | 2015-09-30 | 浙江东南网架股份有限公司 | 超高度拱形网架结构计算机控制外扩累积提升的安装方法 |
-
2015
- 2015-11-18 CN CN201510793219.6A patent/CN106703410A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102102445A (zh) * | 2011-03-09 | 2011-06-22 | 中国建筑第八工程局有限公司 | 超大焊接球网架的分块吊装施工方法 |
CN102168490A (zh) * | 2011-03-09 | 2011-08-31 | 中国建筑第八工程局有限公司 | 双曲面焊接球网架分块直接吊装施工方法 |
CN103866986A (zh) * | 2014-03-09 | 2014-06-18 | 山西四建集团有限公司 | 大跨度变截面螺栓球节点网壳安装方法 |
CN104032966A (zh) * | 2014-06-27 | 2014-09-10 | 中国十九冶集团(防城港)设备结构有限公司 | 弧形双层网架分块吊装高空合拢安装方法 |
CN104947942A (zh) * | 2015-05-06 | 2015-09-30 | 浙江东南网架股份有限公司 | 超高度拱形网架结构计算机控制外扩累积提升的安装方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107476581B (zh) | 一种钢结构双层悬挑结构吊装安装方法 | |
US8180588B2 (en) | Compensation method for structural deformation occurring during construction of super tall building | |
Wang et al. | Progressive collapse simulation of the steel-concrete composite floor system considering ductile fracture of steel | |
CN106703410A (zh) | 双向大柱网钢网架分块悬挑提升施工方法 | |
CN103352567A (zh) | 超高层门型建筑的施工方法 | |
Lelli et al. | Advanced analyses of the membrane action of composite slabs under natural fire scenarios: A case study of the JTI headquarters | |
Gaur et al. | A parametric study of multy-storey R/C buildings with horizontal irregularity | |
JP6333528B2 (ja) | 構造設計支援システム | |
KR101399679B1 (ko) | 대규모 구조물의 성능 기반 구조 해석 방법 | |
JP6572332B2 (ja) | 構造設計支援システム | |
CN204531100U (zh) | 可调式幕墙龙骨系统 | |
CN206328951U (zh) | 一种大跨度变截面的钢筋混凝土梁 | |
Fiore et al. | The influence of uncertainties of infill panels relative to the seismic response of RC existing buildings | |
Ivanov et al. | Seismic design optimization considering base-isolation system | |
CN206554263U (zh) | 一种薄壁组合钢结构的房屋 | |
CN206581390U (zh) | 一种大跨度钢框架结构 | |
CN206346427U (zh) | 一种楼屋面外露钢梁包裹节点 | |
JP7326118B2 (ja) | 設計支援装置 | |
Umnova et al. | Design of low-rise buildings from thin-walled steel frame structures | |
Henry et al. | Experimental testing and modelling to address the performance of RC walls during the 2010/2011 Canterbury earthquakes | |
CN104805902A (zh) | 一种改善机库受力性能的结构 | |
Mosquera et al. | A sequential algorithm for minimum weight design of 2-D steel portal frames using Eurocode 3 | |
CN114150894B (zh) | 一种超高层建筑结构拆改施工方法及校核方法 | |
Goud et al. | Design Amplification Factor for Open Ground Storey RC Structure with Infill Openings in Upper Storeys | |
CN106759867A (zh) | 一种大跨度钢框架结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170524 |