CN106703198A - Ultra-high-steel-structured core tube structure system with supporting frame - Google Patents

Ultra-high-steel-structured core tube structure system with supporting frame Download PDF

Info

Publication number
CN106703198A
CN106703198A CN201611035914.7A CN201611035914A CN106703198A CN 106703198 A CN106703198 A CN 106703198A CN 201611035914 A CN201611035914 A CN 201611035914A CN 106703198 A CN106703198 A CN 106703198A
Authority
CN
China
Prior art keywords
gravity
core
core walls
support
walls structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611035914.7A
Other languages
Chinese (zh)
Inventor
赵昕
丁鲲
马壮
方葆益
何荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Architecture Design and Research Institute of Tongji University Group Co Ltd
Original Assignee
Architecture Design and Research Institute of Tongji University Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Architecture Design and Research Institute of Tongji University Group Co Ltd filed Critical Architecture Design and Research Institute of Tongji University Group Co Ltd
Priority to CN201611035914.7A priority Critical patent/CN106703198A/en
Publication of CN106703198A publication Critical patent/CN106703198A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/34Extraordinary structures, e.g. with suspended or cantilever parts supported by masts or tower-like structures enclosing elevators or stairs; Features relating to the elastic stability
    • E04B1/3404Extraordinary structures, e.g. with suspended or cantilever parts supported by masts or tower-like structures enclosing elevators or stairs; Features relating to the elastic stability supported by masts or tower-like structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The invention relates to an ultra-high-steel-structured core tube structure system with a supporting frame. The ultra-high-steel-structured core tube structure system with the supporting frame comprises a plurality of gravity columns, gravity beams and a support, wherein the gravity beams are arranged on the gravity columns and are combined with the gravity columns to form a plurality of cylindrical structures; the gravity columns are steel columns or steel tube concrete columns; the gravity beams are steel beams; and the support is a steel support. Compared with the prior art, the steel structure system has the advantages of light structural dead weight, good wind resistance and anti-seismic property, flexible building arrangement, high construction speed, high construction industrial degree, less field wet operation and the like.

Description

Superelevation steel construction band support frame core wall structure system
Technical field
The invention belongs to technical field of structural engineering, and in particular to a kind of superelevation steel construction band support frame core wall structure System.
Background technology
At present, it is Frame-Shear wall to be applicable relatively more extensive super high rise structure system, and Core Walls Structure is in building Middle body, central core is formed by being gone along with sb. to guard him between elevator hoistways, stair, ventilation shaft, cable shaft, communal bathroom, equipment component Cylinder, an outter frame inner cylinder structure is formed with peripheral frame, is that the widely used main flow structure type of high-rise building exists in the world In more than 500 meters of structure, its Core Walls Structure material is the mixing of armored concrete or steel and armored concrete and combined member.This Plant dead load big, and want to improve structural behaviour, it is necessary to increase dead load, a large amount of due to concrete use so that Situ wet operation is more, and construction speed is slow.
The content of the invention
The purpose of the present invention is exactly to provide a kind of with dead load for the defect for overcoming above-mentioned prior art to exist Gently, speed of application is fast, construction industries degree high and superelevation steel construction band support frame core the advantages of few situ wet operation Barrel structure system.
The purpose of the present invention can be achieved through the following technical solutions:
A kind of superelevation steel construction band support frame core wall structure system, including multiple gravity posts, gravity beam and support, institute The gravity beam stated is arranged on gravity post, and forms multiple tubular structures with gravity column combination, and described support is arranged on tubular On the side wall of structure, described gravity post is steel column or steel core concrete column, and described gravity beam is girder steel, and described support is Bracing members.
Used as preferred technical scheme, the arrangement of described gravity post is adjusted according to building requirements, and distribution is in nine palaces Lattice is three-back-shaped, and described core wall structure system is taken in successively from bottom to up, forms low area's Core Walls Structure, middle area's core Tong Hegao areas Core Walls Structure;
When the distribution of gravity post is in nine grids type, the tubular structure of described low area's Core Walls Structure is distributed in 3 × 3 in the plane Square formation, described middle area's Core Walls Structure takes in be formed on the basis of low area's Core Walls Structure, and the tubular structure of middle area's Core Walls Structure is provided with 5 Individual, distribution in the plane is in cross, and described area's Core Walls Structure high continues to take on the basis of middle area's Core Walls Structure, area's core high The tubular structure of cylinder is provided with one;
When the distribution of gravity post is in three-back-shaped, the tubular structure distribution of described low area's Core Walls Structure is in 4 × 4 matrix, institute Shu Zhong areas Core Walls Structure takes in be formed, described height on the basis of low area's Core Walls Structure by four angles to low area's Core Walls Structure Area's Core Walls Structure takes on the basis of middle area's Core Walls Structure, and the tubular structure of area's Core Walls Structure high is provided with four, and distribution in the plane is in 2 × 2 square formation.
Used as preferred technical scheme, the form of described support uses central supported or accentric support.
Used as preferred technical scheme, the arrangement of described support punches with building or rigidity requirement is adjusted, be across The small diagonal brace of individual layer or the big diagonal brace across multilayer.
Used as preferred technical scheme, described support is type steel support, and section is box or I-shaped.
Used as preferred technical scheme, described core wall structure system also passes through semi-girder and is arranged on core wall structure body The huge post connection in outside outside system.
Used as preferred technical scheme, described semi-girder buries semi-girder and overhanging arm including Inner, and described Inner buries semi-girder by position Gravity beam in enhancement layer or refuge story position is formed, and described Inner is buried arm and is connected by overhanging arm with outside huge post.
The present invention is steel structure system, is arranged as required to bracing members, and the arrangement of support can punch or rigidity with building It is required that being adjusted.The selection of gravity post can be carried out than choosing according to rigidity requirement.Main its load-bearing effect of gravity beam.Core Walls Structure Outside huge post can be connected by semi-girder, by the weight transfer subregion on Core Walls Structure top to huge post, make Core Walls Structure internal gravity post Size reduces.
Compared with prior art, the invention has the advantages that:
(1) there is light dead load using steel structure system, wind resistance and anti-seismic performance are good, building arrangements are flexible, construction speed The advantages of degree is fast, construction industries degree is high and situ wet operation is few.
(2) due to using steel structure system and can be connected by semi-girder between outside huge post so that gravity column section chi Very little reduction, structural construction flexible arrangement, structural elements influences small to building function.
Brief description of the drawings
Fig. 1 is the structural representation of low area's Core Walls Structure of embodiment 1;
Fig. 2 is the elevation of the core wall structure system of embodiment 1;
Fig. 3 is the plan of low area's Core Walls Structure (a), middle area's Core Walls Structure (b) and area's Core Walls Structure (c) high of embodiment 1;
Fig. 4 is the gravity post arrangement using central supported form in three-back-shaped low area's Core Walls Structure elevation;
Fig. 5 is the gravity post arrangement using accentric support form in three-back-shaped low area's Core Walls Structure elevation;
Fig. 6 is the elevation of the core wall structure system of embodiment 2;
Fig. 7 is the plan of low area's Core Walls Structure (a), middle area's Core Walls Structure (b) and area's Core Walls Structure (c) high of embodiment 2;
Fig. 8 is the gravity post arrangement using central supported form in nine grids Xing Di areas Core Walls Structure elevation;
Fig. 9 is the gravity post arrangement using accentric support form in nine grids Xing Di areas Core Walls Structure elevation.
In figure, 1 is gravity post, and 2 is gravity beam, and 3 is support, and 4 is tubular structure, and 5 is low area's Core Walls Structure, and 6 is middle area's core Heart cylinder, 7 is area's Core Walls Structure high.
Specific embodiment
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.
Embodiment 1
A kind of superelevation steel construction band support frame core wall structure system, as shown in Fig. 1~2, including multiple gravity posts 1, Gravity beam 2 and support 3, gravity beam 2 is arranged on gravity post 1, and the multiple tubular structures 4 of formation are combined with gravity post 1, described Support 3 is arranged on the side wall of tubular structure 4, and gravity post 1 is steel column or steel core concrete column, and gravity beam 2 is girder steel, support 3 It is bracing members.The arrangement of gravity post 1 is adjusted according to building requirements, distribution in three-back-shaped, and core wall structure system from Under it is supreme take in successively, form low area's Core Walls Structure 5, middle area's Core Walls Structure 6 and area's Core Walls Structure 7 high, the number of gravity post 1 also subregion according to Secondary reduction;
The distribution of tubular structure 4 of low area's Core Walls Structure 5 is in 4 × 4 matrix, and middle area's Core Walls Structure 6 is on the basis of low area's Core Walls Structure 5 On, takeing in be formed by four angles to low area's Core Walls Structure 5, area's Core Walls Structure 7 high takes on the basis of middle area's Core Walls Structure 6, high The tubular structure 4 of area's Core Walls Structure 7 is provided with four, and distribution in the plane is in 2 × 2 square formation, as shown in Figure 3.
Support 3 is type steel support, and section is box or I-shaped.The form of support 3 uses central supported or accentric support, As shown in figure 4, by the way of cross support, accentric support is as shown in figure 5, during accentric support for structural representation during central supported By the way of the support of K shapes.The arrangement of support 3 punches or rigidity requirement is adjusted with building, be across individual layer small diagonal brace or Across the big diagonal brace of multilayer.
This implementation has that dead load is light, wind resistance and anti-seismic performance are good, building arrangements are flexible, speed of application is fast, work of constructing The advantages of industry degree is high and situ wet operation is few.
Embodiment 2
A kind of superelevation steel construction band support frame core wall structure system, as shown in fig. 6, including multiple gravity posts 1, gravity Beam 2 and support 3, gravity beam 2 is arranged on gravity post 1, and the multiple tubular structures 4 of formation are combined with gravity post 1, and gravity post 1 is Steel column or steel core concrete column, gravity beam 2 are girder steel, and support 3 is bracing members.The arrangement of gravity post 1 is carried out according to building requirements Regulation, distribution is taken in successively from bottom to up in nine grids type, and core wall structure system, forms low area's Core Walls Structure 5, middle area's core Heart cylinder 6 and area's Core Walls Structure 7 high, also subregion is reduced the number of gravity post 1 successively;
The distribution of gravity post 1 is in nine grids type, and the tubular structure 4 of low area's Core Walls Structure 5 is distributed in 3 × 3 square formation in the plane, Middle area's Core Walls Structure 6 takes in be formed on the basis of low area's Core Walls Structure 5, and the tubular structure 4 of middle area's Core Walls Structure 6 is provided with 5, in plane Upper distribution is in cross, and area's Core Walls Structure 7 high continues to take on the basis of middle area's Core Walls Structure 6, the tubular structure of area's Core Walls Structure 7 high 4 are provided with one, as shown in Figure 7.
Support 3 is type steel support, and section is box or I-shaped.The form of support 3 uses central supported or accentric support, Structural representation during central supported is as shown in figure 8, by the way of the support of K shapes, accentric support is as shown in figure 9, during accentric support By the way of the support of K shapes.The arrangement of support 3 punches or rigidity requirement is adjusted with building, be across individual layer small diagonal brace or Across the big diagonal brace of multilayer.
This implementation has that dead load is light, wind resistance and anti-seismic performance are good, building arrangements are flexible, speed of application is fast, work of constructing The advantages of industry degree is high and situ wet operation is few.
Embodiment 3
The present embodiment is substantially the same manner as Example 1, and difference is that the core wall structure system of the present embodiment also passes through Semi-girder is connected with the huge post in the outside being arranged on outside core wall structure system.Wherein semi-girder buries semi-girder and overhanging arm including Inner, and Inner is buried Semi-girder is formed by the gravity beam 2 positioned at enhancement layer or refuge story position, and Inner is buried arm and is connected by overhanging arm with outside huge post.
This implementation has that dead load is light, wind resistance and anti-seismic performance are good, building arrangements are flexible, speed of application is fast, work of constructing The advantages of industry degree is high and situ wet operation is few, is connected so that gravity post between outside huge post by by it by semi-girder Sectional dimension reduces, structural construction flexible arrangement, and structural elements influences small to building function.

Claims (7)

1. a kind of superelevation steel construction is with support frame core wall structure system, it is characterised in that including multiple gravity posts, gravity beam And support, described gravity beam is arranged on gravity post, and forms multiple tubular structures with gravity column combination, and described support sets Put on the side wall of tubular structure, described gravity post is steel column or steel core concrete column, and described gravity beam is girder steel, described Support be bracing members.
2. a kind of superelevation steel construction according to claim 1 is with support frame core wall structure system, it is characterised in that institute The arrangement of the gravity post stated is adjusted according to building requirements, and distribution is in nine grids type or three-back-shaped, and described Core Walls Structure Structural system is taken in successively from bottom to up, forms low area's Core Walls Structure, middle area's Core Walls Structure and area's Core Walls Structure high;
When the distribution of gravity post is in nine grids type, the tubular structure of described low area's Core Walls Structure is distributed in 3 × 3 side in the plane Battle array, described middle area's Core Walls Structure takes in be formed on the basis of low area's Core Walls Structure, and the tubular structure of middle area's Core Walls Structure is provided with 5, Distribution in the plane is in cross, and described area's Core Walls Structure high continues to take on the basis of middle area's Core Walls Structure, area's Core Walls Structure high Tubular structure be provided with one;
When the distribution of gravity post is in three-back-shaped, the tubular structure distribution of described low area's Core Walls Structure is in 4 × 4 matrix, described Middle area's Core Walls Structure takes in be formed on the basis of low area's Core Walls Structure by four angles to low area's Core Walls Structure, described area's core high Taken on the basis of Xin Tongzhong areas Core Walls Structure, the tubular structure of area's Core Walls Structure high is provided with four, distribution in the plane is in 2 × 2 Square formation.
3. with support frame core wall structure system, its feature exists a kind of superelevation steel construction according to claim 1 and 2 In support or accentric support centered on described support.
4. a kind of superelevation steel construction according to claim 3 is with support frame core wall structure system, it is characterised in that institute The arrangement of the support stated punches with building or rigidity requirement is adjusted, and is the small diagonal brace across individual layer or the big diagonal brace across multilayer.
5. a kind of superelevation steel construction according to claim 1 is with support frame core wall structure system, it is characterised in that institute The support stated is type steel support, and section is box or I-shaped.
6. a kind of superelevation steel construction according to claim 1 is with support frame core wall structure system, it is characterised in that institute The core wall structure system stated also is connected by semi-girder with the huge post in the outside being arranged on outside core wall structure system.
7. a kind of superelevation steel construction according to claim 6 is with support frame core wall structure system, it is characterised in that institute The semi-girder stated buries semi-girder and overhanging arm including Inner, and described Inner buries semi-girder by the gravity beam shape positioned at enhancement layer or refuge story position Into described Inner is buried arm and is connected by overhanging arm with outside huge post.
CN201611035914.7A 2016-11-23 2016-11-23 Ultra-high-steel-structured core tube structure system with supporting frame Pending CN106703198A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611035914.7A CN106703198A (en) 2016-11-23 2016-11-23 Ultra-high-steel-structured core tube structure system with supporting frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611035914.7A CN106703198A (en) 2016-11-23 2016-11-23 Ultra-high-steel-structured core tube structure system with supporting frame

Publications (1)

Publication Number Publication Date
CN106703198A true CN106703198A (en) 2017-05-24

Family

ID=58941267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611035914.7A Pending CN106703198A (en) 2016-11-23 2016-11-23 Ultra-high-steel-structured core tube structure system with supporting frame

Country Status (1)

Country Link
CN (1) CN106703198A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1737279A (en) * 2005-09-09 2006-02-22 北京工业大学 Method for making built-in eccentric supporting steel truss concrete combined barrel and the barrel
WO2011056897A2 (en) * 2009-11-04 2011-05-12 Framemax International Limited, A Hong Kong Limited Liability Company Building system and method
CN102535672A (en) * 2012-02-15 2012-07-04 姚攀峰 Novel hybrid huge anti-seismic structure and construction method thereof
CN203654513U (en) * 2014-01-03 2014-06-18 湖州职业技术学院 Frame-core tube combined earthquake-dissipating structure
CN203977572U (en) * 2014-04-30 2014-12-03 王本淼 A kind of high-rise building that adopts cast-in-situ hollow building roof
CN204551731U (en) * 2015-01-19 2015-08-12 江苏沪宁钢机股份有限公司 A kind of full steel structure building
CN105672481A (en) * 2016-01-20 2016-06-15 陕西省建筑科学研究院 Delay connection installation method for outrigger of super high-rise building in steel frame-core tube structure
CN206245483U (en) * 2016-11-23 2017-06-13 同济大学建筑设计研究院(集团)有限公司 Superelevation steel construction band support frame core wall structure system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1737279A (en) * 2005-09-09 2006-02-22 北京工业大学 Method for making built-in eccentric supporting steel truss concrete combined barrel and the barrel
WO2011056897A2 (en) * 2009-11-04 2011-05-12 Framemax International Limited, A Hong Kong Limited Liability Company Building system and method
CN102535672A (en) * 2012-02-15 2012-07-04 姚攀峰 Novel hybrid huge anti-seismic structure and construction method thereof
CN203654513U (en) * 2014-01-03 2014-06-18 湖州职业技术学院 Frame-core tube combined earthquake-dissipating structure
CN203977572U (en) * 2014-04-30 2014-12-03 王本淼 A kind of high-rise building that adopts cast-in-situ hollow building roof
CN204551731U (en) * 2015-01-19 2015-08-12 江苏沪宁钢机股份有限公司 A kind of full steel structure building
CN105672481A (en) * 2016-01-20 2016-06-15 陕西省建筑科学研究院 Delay connection installation method for outrigger of super high-rise building in steel frame-core tube structure
CN206245483U (en) * 2016-11-23 2017-06-13 同济大学建筑设计研究院(集团)有限公司 Superelevation steel construction band support frame core wall structure system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
原长庆主编: "《高等学校"十一五"规划教材 高层建筑混凝土结构设计》", 31 January 2008, 哈尔滨工业大学出版社 *
胡恩、施法科: "某超限高层结构性能设计与分析", 《四川建筑》 *

Similar Documents

Publication Publication Date Title
CN106522419B (en) Adjacent beam-supporting column conversion beam that strides and set up steel sheet concrete shear force wall
Shivacharan et al. Optimum position of outrigger system for tall vertical irregularity structures
CN109162437B (en) Integral steel platform for multi-cylinder steel plate shear wall and construction method thereof
CN106836495A (en) A kind of super high steel structure mega-frame building structure
CN203808094U (en) Adjustable tower crane steel platform foundation
CN206245483U (en) Superelevation steel construction band support frame core wall structure system
CN104358328B (en) All-steel four-steel pipe multistage mountable overlong buckling-restrained brace
CN102828616B (en) High-formwork support system for roof
CN204959795U (en) Self -supporting does not have row no mould basement flat slab floor
CN204663099U (en) Deck, Novel helicopter apron
CN210947266U (en) Combined oblique corrugated steel plate shear wall
Shah et al. Review on behavior of outrigger system in high rise building
CN106703198A (en) Ultra-high-steel-structured core tube structure system with supporting frame
CN105113541A (en) Self-supporting bent-frame-free and template-free basement beam-free floor and inverse construction method of same
CN104233948A (en) Bridge tower or bridge pier with multi-compartment combined structure
CN213572379U (en) Assembled double eccentric support dual lateral force resisting unit
CN208965579U (en) A kind of non-console mode lattice tower crane platform
CN103397638A (en) Tie bar for supporting system in high-rigidity integral prestressed fabricated foundation pit support
CN106013868A (en) Hyperbolic cross truss type steel structure cooling tower
CN202081639U (en) Steel truss tool type supporting structure for concrete framework industrial building templates
CN203238806U (en) Reinforced layer of variable damper
CN206245482U (en) A kind of super high steel structure mega-frame building structure
CN105003074A (en) Commercial building construction system and construction method thereof
CN204080617U (en) The bridge tower of many lattice room combining structure or bridge pier
US20200095759A1 (en) Super high-rise building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170524

RJ01 Rejection of invention patent application after publication