CN106685088A - Anti-misoperation system for secondary plate pressing of electric protection device - Google Patents

Anti-misoperation system for secondary plate pressing of electric protection device Download PDF

Info

Publication number
CN106685088A
CN106685088A CN201710072763.0A CN201710072763A CN106685088A CN 106685088 A CN106685088 A CN 106685088A CN 201710072763 A CN201710072763 A CN 201710072763A CN 106685088 A CN106685088 A CN 106685088A
Authority
CN
China
Prior art keywords
pressure plate
secondary pressure
preview
misoperation
storehouse
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710072763.0A
Other languages
Chinese (zh)
Other versions
CN106685088B (en
Inventor
孙建人
刘亚栋
陶旭嫣
杨涛
于慎航
李现忠
刘志洋
胡国洋
王亮亮
李元飞
王天
王天一
田立伟
廖峰然
程秀娟
梁欢
杨重艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Yantai Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Yantai Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Yantai Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710072763.0A priority Critical patent/CN106685088B/en
Publication of CN106685088A publication Critical patent/CN106685088A/en
Application granted granted Critical
Publication of CN106685088B publication Critical patent/CN106685088B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • H02J13/0006
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/242Home appliances

Abstract

The invention discloses an anti-misoperation system for secondary plate pressing of an electric protection device. The anti-misoperation system is characterized in that an anti-misoperation system platform for secondary plate pressing of the electric protection device is constructed by establishing a basic database of the anti-misoperation system for secondary plate pressing of the electric protection device, formulating a logical checking process for anti-misoperation rehearsal of secondary plate pressing of the electric protection device and setting up an anti-misoperation rehearsal interface for secondary plate pressing of the electric protection device. In order to reduce the complexity of system implementation and simplify the software structure of the system, the anti-misoperation system adopts a modular design idea so as to divide the system into a data service module, an anti-misoperation process module and a user interface module from bottom to top. The anti-misoperation system disclosed by the invention has the advantages that the checking anti-misoperation rehearsal for the content of on-off operation of secondary plate pressing of the electric protection device in a switching-operation order can be realized, and simultaneously information services are provided for being convenient to intercept the on-off state of secondary plate pressing of the electric protection device and rechecking the correctness of the on-off state.

Description

A kind of electric protective device secondary pressure plate anti-misoperation system
Technical field:
The present invention relates to a kind of electric protective device secondary pressure plate anti-misoperation system, belong to power system power transformation O&M field.
Background technology:
1. the correctness of electric switching operation is concerning power network safety operation.Currently, using the microcomputer based on " five prevent " logic Anti-misoperation system is highly developed to the way that electrical primary equipment carries out anti-misoperation preview, and achieves expected anti- Miss effect.In contrast, because the anti-error modular design standard for electric protective device secondary pressure plate is not yet written, at this stage It is main that the anti-of electric protective device secondary pressure plate is realized by way of power network operation maintenance personnel before operation manual review operation order Maloperation is checked.Ticket people is filled out due to operation order and (examines ticket people)Difference in terms of technical merit and sense of responsibility, it is in addition electric in transformer station Gas shielded device secondary pressure plate substantial amounts, operation rules is complicated, every year due to electric protective device two that human factor causes Secondary pressing plate leakage is thrown, miscarrying, and then triggers the phenomenon of serious power grid accident to emerge in an endless stream, and power network safety operation is constituted very big Threaten.
2. the correctness that periodically state was thrown/stopped to verification electric protective device secondary pressure plate be in power transformation maintenance work extremely Important content.The live artificial mode checked one by one is gone due to fully relying on power network operation maintenance personnel at present, with electric network protection Increasingly perfect and new electric protective device constantly the putting into operation in power system of configuration, the above-mentioned secondary pressure of electric protective device Plate is thrown/is stopped consumption of the regular checking work of state to human and material resources and shows abnormal surprising situation.
The content of the invention:
It can be that electric protective device is secondary to develop one kind it is an object of the invention to overcome the shortcomings of above-mentioned background technology Pressing plate is thrown/is stopped operation and provides the analog platform of verification property anti-misoperation preview, while knowing for power network operation maintenance personnel is convenient secondary Pressing plate throws/stop state, check the electric protective device secondary pressure plate anti-misoperation system that its correctness provides information service.
The present invention can be achieved by the following measures compared with the prior art:A kind of electric protective device secondary pressure plate is anti-error Operating system, it is characterised in that it includes data service module, anti-error procedure module and subscriber interface module;Wherein:
It is system-based database in described data service module, wherein being configured with secondary pressure plate anti-misoperation preview rule Storehouse, electric switching operation task library, electrical primary equipment library, electric protective device screen cabinet storehouse, secondary pressure plate storehouse and secondary pressure plate Anti-misoperation preview logout storehouse;
Secondary pressure plate anti-misoperation preview rule is stored in described secondary pressure plate anti-misoperation preview rule base, secondary pressure plate is prevented Maloperation preview rule includes the mission number of rule base electric switching operation, rule base electrical primary device numbering, rule base Electric protective device screen cabinet numbering, rule base secondary pressure plate numbering, rule base secondary pressure plate throwing/stop instruction and the secondary pressure of rule base Plate anti-misoperation constraints totally 6 attributes, cover in transformer station electrical primary equipment in every electric switching operation task Electric protective device screen cabinet on related secondary pressure plate throwing/stop instruction and secondary pressure plate anti-misoperation constraints content;
Described rule base secondary pressure plate anti-misoperation constraints is based on related electric protection device operation management regulation system It is fixed;
It is associated with rule base electric switching operation mission number in secondary pressure plate anti-misoperation preview rule base, electrically falls The mission number of task library electric switching operation and task library electric switching operation task names two defined in lock operation task storehouse Item attribute, for recording every electric switching operation mission bit stream;
It is associated with rule base electrical primary device numbering in secondary pressure plate anti-misoperation preview rule base, electrical primary sets Equipment library electrical primary device numbering and equipment library electrical primary device name attribute defined in standby storehouse, for recording transformer station Interior electrical primary facility information;
It is associated with rule base electric protective device screen cabinet numbering in secondary pressure plate anti-misoperation preview rule base, electrically protects Screen cabinet storehouse electric protective device screen cabinet numbering, screen cabinet storehouse electric protective device screen cabinet title and screen defined in protection unit screen cabinet storehouse Cabinet storehouse electrical primary device numbering, is used to record the secondary protector screen cabinet information of electrical primary equipment in transformer station;
It is associated with rule base secondary pressure plate numbering in secondary pressure plate anti-misoperation preview rule base, it is fixed in secondary pressure plate storehouse Justice pressing plate storehouse secondary pressure plate numbering, pressing plate storehouse secondary pressure plate title and pressing plate storehouse electric protective device screen cabinet numbering, are used to remember Secondary pressure plate information in record transformer station on each electric protective device screen cabinet;
Described secondary pressure plate anti-misoperation preview logout storehouse is used to store secondary pressure plate anti-misoperation preview logout, Secondary pressure plate anti-misoperation preview logout includes that preview time, record storehouse electric switching are thrown/stopped to record storehouse secondary pressure plate Operation task title, record storehouse electrical primary device name, record storehouse electric protective device screen cabinet title, record storehouse secondary pressure plate Preview command content is thrown/stopped to title and record storehouse secondary pressure plate;
Secondary pressure plate to being performed in described subscriber interface module is thrown/is stopped preview instruction and carries out instruction parsing, obtains preview and refers to Make electric switching operation mission number, preview instruct electrical primary device numbering, preview instruction electric protective device screen cabinet to number, This 5 preview command contents of preview instruction are thrown/stopped to preview instruction secondary pressure plate numbering, preview instruction secondary pressure plate;
It is right according to the secondary pressure plate anti-misoperation preview rule provided in data service module in described anti-error procedure module The secondary pressure plate after instructing parsing performed in described subscriber interface module is thrown/is stopped preview instruction and carries out item by item anti-error core It is right;By successively by parsing after the preview that obtains instruct electric switching operation mission number and rule base electric switching operation task Numbering, preview instruction electrical primary device numbering and rule base electrical primary device numbering, preview instruction electric protective device screen Cabinet is numbered and rule base electric protective device screen cabinet is numbered, preview instructs secondary pressure plate numbering and rule base secondary pressure plate to number, Whether preview instruction secondary pressure plate is thrown/is stopped preview instruction and checked with rule base secondary pressure plate throwing/stop instruction, checks its content Unanimously;If occurring in audit process, content is inconsistent, and the anti-error verification flow of the anti-error procedure module stops, while touching Send out subscriber interface module described and send maloperation information to operation maintenance personnel and warn;If checked result is consistent, further basis Whether the electrical primary of anti-error preview operation, secondary device state check-up rules storehouse secondary pressure plate anti-misoperation constraints are full Foot, if meeting rule base secondary pressure plate anti-misoperation constraints, operation of secondary pressure plate preview is denoted as by present system time Time, while instructing the electric switching operation task that electric switching operation mission number is denoted as operation preview to compile the preview Number, by it is described preview instruct electrical primary device numbering be denoted as operation preview electrical primary device numbering, by it is described preview refer to Make electric protective device screen cabinet number be denoted as the electric protective device screen cabinet numbering of operation preview, the preview is instructed into secondary pressure Plate numbering be denoted as operation preview secondary pressure plate numbering, by it is described preview instruct secondary pressure plate throw/stop preview instruction be denoted as operation Preview command content is thrown/stopped to the secondary pressure plate of preview, so that secondary pressure plate anti-misoperation preview logout information is generated, while The described subscriber interface module of triggering update correspondence electric protective device secondary pressure plate simulation throw/stop state;If being unsatisfactory for institute Rule base secondary pressure plate anti-misoperation constraints is stated, is then triggered described subscriber interface module and is sent secondary pressure to operation maintenance personnel The unmet information warning of plate anti-misoperation constraints;
Described secondary pressure plate anti-misoperation preview logout information carries out data parsing in described data service module; Described secondary pressure plate anti-misoperation is obtained by data parsing and preview logout, and then construct secondary pressure plate anti-misoperation Preview logout storehouse;Wherein, the record storehouse secondary pressure plate defined in the secondary pressure plate anti-misoperation preview logout storehouse Preview time is thrown/stopped for recording described operation of secondary pressure plate preview time;The secondary pressure plate anti-misoperation previews event Record storehouse electric switching operation task names defined in record storehouse are used to record the electric switching of the operation preview according to What operation task numbering was parsed from described secondary pressure plate anti-misoperation preview rule base and electric switching operation task library Record storehouse operation task title;Record storehouse electrical primary defined in the secondary pressure plate anti-misoperation preview logout storehouse sets The electrical primary device numbering that standby title is used to record the operation preview according to is pre- from described secondary pressure plate anti-misoperation Drill the electrical primary device name parsed in rule base and electrical primary equipment library;The secondary pressure plate anti-misoperation previews thing Record storehouse electric protective device screen cabinet title defined in part record storehouse is used to record the electric guarantor of the operation preview according to Protection unit screen cabinet numbering is parsed from described secondary pressure plate anti-misoperation preview rule base and electric protective device screen cabinet storehouse Electric protective device screen cabinet title;The secondary pressure of record storehouse defined in the secondary pressure plate anti-misoperation preview logout storehouse The secondary pressure plate numbering that board name is used to record the operation preview according to previews rule from described secondary pressure plate anti-misoperation The secondary pressure plate title for then being parsed in storehouse and secondary pressure plate storehouse;It is fixed in the secondary pressure plate anti-misoperation preview logout storehouse The record storehouse secondary pressure plate of justice is thrown/is stopped preview instruction and throws/stop preview command content for recording the secondary pressure plate of operation preview;By This obtains secondary pressure plate anti-misoperation preview logout;Secondary pressure plate anti-misoperation among the data service module is pre- Drill and described secondary pressure plate anti-misoperation preview logout is stored in logout storehouse;
Described subscriber interface module provides access related electric protection device secondary pressure plate anti-misoperation for power network operation maintenance personnel Preview the human-machine interactive information interface of logout;Secondary pressure plate anti-misoperation among described system-based database is pre- The anti-misoperation preview logout power supply network operation maintenance personnel for drilling reading secondary pressure plate in logout storehouse understands and grasp correlation The throwing of electric protective device secondary pressure plate/stop cause and event information.
In order to further realize the purpose of the present invention, it is directed in described rule base secondary pressure plate anti-misoperation constraints The protection device of transformer, bus, 220kV and above circuit and 110kV and following voltage class circuit is formulated Rule base secondary pressure plate anti-misoperation constraints be:
(1)Input transformer " gap protection input " secondary pressure plate, answers before disabling transformer " zero sequence excessively stream input " secondary pressure plate Check transformer neutral point grounding switch in a point position;Conversely, should be disabled before the transformer neutral point grounding switch that closes transformer " Gap protection input " secondary pressure plate, puts into transformer " zero sequence excessively stream input " secondary pressure plate;
(2)Bus should put into " charge protection " and " mother excessively stream " secondary pressure plate before being charged by bus connection switch, charging is finished should Disable above-mentioned two secondary pressure plate;In bus grid switching operation, answered first before disconnecting " bus connection switch operation power " small air switch Input " mother interconnection " secondary pressure plate;Conversely, " the bus connection switch operation electricity that should first be closed before disabling " mother interconnection " secondary pressure plate Source " small air switch;
(3)Any a set of " reclosing outlet " secondary pressure plate in two sets of protection devices of 220kV and above circuit " reclosing outlet " secondary pressure plate during another set of protection device should be checked before the input is in rest position;Input " links up three to jump " reclosing outlet " secondary pressure plate should be first disabled before lock-reclosing lock " secondary pressure plate, " actuating breaker failure protection " secondary pressure plate is disabled Before first line switching should be disconnected;
(4)" tripping operation outlet " should be simultaneously disabled when out of service for the route protection of 110kV and following voltage class and " reclosing goes out Mouthful " secondary pressure plate;Conversely, above-mentioned two secondary pressure plate should put into during protection input simultaneously.
The present invention can produce following good effect compared with the prior art:
The anti-misoperation preview function that the present invention is provided can realize the secondary pressure of electric protective device to being filled in grid switching operation bill The anti-error inspection of verification of operation content is thrown/stopped to plate, and the mistake to being wherein unsatisfactory for secondary pressure plate anti-misoperation constraints is entered Row effectively warning;The secondary pressure plate anti-misoperation preview logout that the present invention is provided can be known for power network operation maintenance personnel is convenient And verification electric protective device secondary pressure plate is thrown/is stopped state and provides information service, effectively save man power and material.
1)The anti-error audit function of verification of operation content is thrown/stopped to secondary pressure plate
By taking the grid switching operation that certain 220kV bus has a power failure as an example, before practical operation, power network operation maintenance personnel is logged in and is integrated with this hair The microcomputer anti-error operation simulation system of bright system, by operating preview to electric protective device in the grid switching operation bill that is pre-filled with Secondary pressure plate is thrown/is stopped operation content and carries out the anti-error inspection of verification property item by item.
The anti-error audit function example of verification of operation content is thrown/stopped to secondary pressure plate as shown in Figure 7, is pulled open in preview Present system warning power network operation maintenance personnel " ' 1LP2 interconnections input ' during " circuitbreaker control power supply of mother 2200 " small air switch Secondary pressure plate does not put into, it is impossible to pull open ' circuitbreaker control power supply of mother 2200 ' small air switch!”.On inspection, due to filling out ticket people Carelessness, input " 1LP2 interconnection input " secondary pressure plate and " circuitbreaker control power supply of mother 2200 " small air switch will be pulled open Operation order fills in reverse, is unsatisfactory for being set in the preview rule base of the secondary pressure plate anti-misoperation among data service module of the present invention The anti-misoperation constraints of fixed " 1LP2 interconnections input " secondary pressure plate.As seen from Figure 7, the present invention is used as a kind of effective anti- Delay work tool, can throw/stop operation content to the electric protective device secondary pressure plate filled in electric switching operation ticket and check The anti-error inspection of property, the content to being wherein unsatisfactory for secondary pressure plate anti-misoperation constraints warns, realizes and effectively evade The purpose of maloperation risk in electric switching operation.
2)Function serving information
By taking two main transformers of 220kV transformer stations as an example, arranged according to power network normal operating mode, #1 main transformers high-pressure side Neutral ground runs, the operation of #2 main transformers high-pressure side isolated neutral, corresponding #1 main transformers high-pressure side " zero sequence mistake Stream input " secondary pressure plate should be put into operation, and " gap protection input " secondary pressure plate should be disabled, #2 main transformers high-pressure side " zero sequence Excessively stream input " secondary pressure plate should be disabled, and " gap protection input " secondary pressure plate should put into operation.When #1 main transformers are turned by operation After maintenance, to ensure whole station 220kV at least 1 earth point of system, it is necessary to two main transformer high-pressure side neutral grounds Mode is switched;Accordingly, main transformer high-pressure side " zero sequence excessively stream input ", the throwing of " gap protection input " secondary pressure plate, The mode of stopping should switch therewith.As shown in figure 8, power network operation maintenance personnel is by " the #2 main transformer protection screens into present system A " secondary pressure plates anti-misoperation preview interface can easily consult the anti-of " 1LP4 220kV gap protections input " secondary pressure plate Maloperation previews logout, from the record:On " the #2 main transformer protection screens A " of " 220kV#2 main transformers " " 1LP4 220kV gap protections input " secondary pressure plate in " 220kV #1 main transformers by operation turn maintenance " operation task in “2015/5/16 10:36:05 " " deactivation ".Power network operation maintenance personnel can be easily using the function serving information that the present invention is provided Throw secondary pressure plate/stop state and its correctness is checked, it is to avoid go substation field to check or browse associative operation and remember The inconvenience of record, is effectively saved man power and material.
Brief description of the drawings:
Fig. 1 is modular construction schematic diagram of the invention;
Fig. 2 is the database structure schematic diagram of data service module of the invention;
Fig. 2-1 is the secondary pressure plate anti-misoperation preview rule base data structure component of Fig. 2;
Fig. 2-2 is the electric switching operation task library data structure component of Fig. 2;
Fig. 2-3 is the electrical primary equipment library data structure component of Fig. 2;
Fig. 2-4 is the electric protective device screen cabinet database data structure component of Fig. 2;
Fig. 2-5 is the secondary pressure plate database data structure component of Fig. 2;
Fig. 2-6 is the secondary pressure plate anti-misoperation preview logout database data structure component of Fig. 2;
Fig. 3 be subscriber interface module of the invention in secondary pressure plate throw/stop preview instruction analytic structure figure;
Fig. 4 is the anti-error verification flow chart of anti-error procedure module of the invention;
Fig. 5 is the secondary pressure plate anti-misoperation preview logout information data structure of generation in anti-error verification flow of the invention Figure;
Fig. 6 is the data genaration figure of secondary pressure plate anti-misoperation preview logout in data service module of the invention;
Fig. 7 is the anti-error audit function example schematic diagram of verification that operation content was thrown/stopped to secondary pressure plate of the invention;
Fig. 8 is function serving information schematic diagram of the invention.
Specific embodiment:Specific embodiment of the invention is elaborated below in conjunction with the accompanying drawings:
Embodiment:A kind of electric protective device secondary pressure plate anti-misoperation system(Referring to Fig. 1), in its modular construction from lower and On be followed successively by data service module, anti-error procedure module and subscriber interface module.
It is system-based database in described data service module(Referring to Fig. 2), wherein it is anti-error to be configured with secondary pressure plate Operation preview rule base, electric switching operation task library, electrical primary equipment library, electric protective device screen cabinet storehouse, secondary pressure plate Storehouse and secondary pressure plate anti-misoperation preview logout storehouse.
Described secondary pressure plate anti-misoperation preview rule base(Referring to Fig. 2-1)Middle storage secondary pressure plate anti-misoperation preview Rule, secondary pressure plate anti-misoperation previews the mission number of regular storehouse electric switching operation, rule base electric defined in rule Secondary device numbering, rule base electric protective device screen cabinet numbering, rule base secondary pressure plate numbering, rule base secondary pressure plate are thrown/are stopped Instruction and rule base secondary pressure plate anti-misoperation constraints totally 6 attributes, cover every electric switching operation in transformer station Throwing/the stop instruction of related secondary pressure plate and the anti-error behaviour of secondary pressure plate on the electric protective device screen cabinet of electrical primary equipment in task Make constraints content.
Described rule base secondary pressure plate anti-misoperation constraints content is based on related electric protection device O&M pipe Reason regulation is formulated.In the present invention is implemented, for transformer, bus, 220kV and above circuit and 110kV And the protection device of following voltage class circuit has formulated specific rule base secondary pressure plate anti-misoperation constraints respectively:
(1):Input transformer " gap protection input " secondary pressure plate, answers before disabling transformer " zero sequence excessively stream input " secondary pressure plate Check transformer neutral point grounding switch in a point position;Conversely, should be disabled before the transformer neutral point grounding switch that closes transformer " Gap protection input " secondary pressure plate, puts into transformer " zero sequence excessively stream input " secondary pressure plate.
(2):Bus should put into " charge protection " and " mother excessively stream " secondary pressure plate before being charged by bus connection switch, charge Finishing should disable above-mentioned two secondary pressure plate.In bus grid switching operation, before disconnecting " bus connection switch operation power " small air switch " mother interconnection " secondary pressure plate should first be put into;Conversely, should first being closed before disabling " mother interconnection " secondary pressure plate, " bus connection switch is operated Power supply " small air switch.
(3):Any a set of " reclosing outlet " is secondary in two sets of protection devices of 220kV and above circuit Pressing plate should check another set of protection device before the input in " reclosing outlet " secondary pressure plate in rest position.Input " is linked up " reclosing outlet " secondary pressure plate should be first disabled before three jump lock-reclosing locks " secondary pressure plate, " actuating breaker failure protection " is disabled secondary First line switching should be disconnected before pressing plate.
(4):The route protection of 110kV and following voltage class should simultaneously disable " tripping operation outlet " and " weight when out of service Close a floodgate and export " secondary pressure plate;Conversely, above-mentioned two secondary pressure plate should put into during protection input simultaneously.
It is associated with rule base electric switching operation mission number in secondary pressure plate anti-misoperation preview rule base, electricity The mission number of task library electric switching operation and task library electric switching operation task name defined in gas grid switching operation task library Claim two attributes, for recording every electric switching operation mission bit stream.Its data structure is as shown in Fig. 2-2.
It is associated with rule base electrical primary device numbering in secondary pressure plate anti-misoperation preview rule base, electric one Equipment library electrical primary device numbering and equipment library electrical primary device name attribute defined in secondary device storehouse, are used to record change Electrical primary facility information in power station.Its data structure is as Figure 2-3.
It is associated with rule base electric protective device screen cabinet numbering in secondary pressure plate anti-misoperation preview rule base, electricity Screen cabinet storehouse electric protective device screen cabinet numbering, screen cabinet storehouse electric protective device screen cabinet title defined in gas shielded device screen cabinet storehouse And screen cabinet storehouse electrical primary device numbering, it is used to record the secondary protector screen cabinet information of electrical primary equipment in transformer station. Its data structure is as in Figure 2-4.
It is associated with rule base secondary pressure plate numbering in secondary pressure plate anti-misoperation preview rule base, secondary pressure plate storehouse Defined in pressing plate storehouse secondary pressure plate numbering, pressing plate storehouse secondary pressure plate title and pressing plate storehouse electric protective device screen cabinet numbering, use To record the secondary pressure plate information in transformer station on each electric protective device screen cabinet.Its data structure is as shown in Figure 2-5.
As shown in figures 2-6, described secondary pressure plate anti-misoperation preview logout storehouse is anti-error for storing secondary pressure plate Operation preview logout, when secondary pressure plate anti-misoperation preview logout includes that preview is thrown/stopped to record storehouse secondary pressure plate Between, record storehouse electric switching operation task names, record storehouse electrical primary device name, record storehouse electric protective device screen cabinet name Claim, preview command content is thrown/stopped to record storehouse secondary pressure plate title and record storehouse secondary pressure plate.
As shown in figure 3, preview instruction is thrown/stopped to the secondary pressure plate to being performed in described subscriber interface module carries out instruction solution Analysis, obtains the mission number of preview instruction electric switching operation, preview instruction electrical primary device numbering, preview instruction electic protection This 5 preview instructions of preview instruction are thrown/stopped to device screen cabinet numbering, preview instruction secondary pressure plate numbering, preview instruction secondary pressure plate Content.
As shown in figure 1, in described anti-error procedure module, it is anti-error according to the secondary pressure plate provided in data service module Preview instruction is thrown/stopped to operation preview rule to the secondary pressure plate after instructing parsing performed in described subscriber interface module The anti-error inspection of verification property is carried out item by item.Its anti-error verification flow as shown in figure 4, by successively by parsing after the preview that obtains instruct Electric switching operation mission number and the mission number of rule base electric switching operation, preview instruction electrical primary device numbering and rule Then storehouse electrical primary device numbering, preview instruction electric protective device screen cabinet numbering are compiled with rule base electric protective device screen cabinet Number, preview instruction secondary pressure plate numbering with rule base secondary pressure plate numbering, preview instruction secondary pressure plate throw/stop preview instruction with rule Then secondary pressure plate throwing/stop instruction in storehouse is checked, and checks whether its content is consistent.If occurring content in audit process to differ Cause, then the anti-error verification flow of the anti-error procedure module stops, while triggering the subscriber interface module to power network O&M people Member sends the warning of maloperation information;If checked result is consistent, further according to the electrical primary, secondary of anti-error preview operation Equipment state checks whether rule base secondary pressure plate anti-misoperation constraints meets, if meeting the anti-error behaviour of rule base secondary pressure plate Make constraints, then present system time of the invention is denoted as secondary pressure plate anti-misoperation preview time, while will be described pre- Instruction electric switching operation mission number is drilled to be denoted as the electric switching operation mission number of operation preview, the preview is instructed into electricity Gas primary equipment numbering is denoted as the electrical primary device numbering of operation preview, instructs electric protective device screen cabinet to compile the preview Number it is denoted as the electric protective device screen cabinet numbering of operation preview, instructs the preview secondary pressure plate numbering to be denoted as operation preview Secondary pressure plate numbering, by it is described preview instruct secondary pressure plate throw/stop preview instruction be denoted as operation preview secondary pressure plate throw/stop it is pre- Command content is drilled, so that a secondary pressure plate anti-misoperation preview logout information for data structure as shown in Figure 5 is generated, together When the described subscriber interface module of triggering update secondary pressure plate in correspondence electric protective device screen cabinet simulation throw/stop state.If The rule base secondary pressure plate anti-misoperation constraints is unsatisfactory for, is then triggered described subscriber interface module and is sent out to operation maintenance personnel Go out the unmet information warning of secondary pressure plate anti-misoperation constraints.
As shown in figure 1, described secondary pressure plate anti-misoperation previews logout information in described data service module In carry out data parsing.Described secondary pressure plate anti-misoperation is obtained by data parsing and preview logout, and then construct The process in secondary pressure plate anti-misoperation preview logout storehouse is as shown in Figure 6.Wherein, the secondary pressure plate anti-misoperation preview thing Record storehouse secondary pressure plate defined in part record storehouse is thrown and stops preview time for recording described operation of secondary pressure plate preview time; Record storehouse electric switching operation task names defined in the secondary pressure plate anti-misoperation preview logout storehouse are used to record Electric switching operation mission number according to described operation preview from described secondary pressure plate anti-misoperation preview rule base and The record storehouse operation task title parsed in electric switching operation task library.The secondary pressure plate anti-misoperation preview event note The electrical primary equipment that record storehouse electrical primary device name defined in record storehouse is used to record the operation preview according to is compiled Number electrical primary implementor name parsed from described secondary pressure plate anti-misoperation preview rule base and electrical primary equipment library Claim.Record storehouse electric protective device screen cabinet title defined in the secondary pressure plate anti-misoperation preview logout storehouse is used to remember The electric protective device screen cabinet numbering for recording the operation preview according to previews rule base from described secondary pressure plate anti-misoperation And the electric protective device screen cabinet title parsed in electric protective device screen cabinet storehouse.The secondary pressure plate anti-misoperation previews thing Record storehouse secondary pressure plate title defined in part record storehouse be used to record the secondary pressure plate numbering of the operation preview according to from The secondary pressure plate title parsed in described secondary pressure plate anti-misoperation preview rule base and secondary pressure plate storehouse.The secondary pressure Preview instruction is thrown/stopped to record storehouse secondary pressure plate defined in plate anti-misoperation preview logout storehouse for recording operation preview Preview command content is thrown/stopped to secondary pressure plate.Thus the secondary pressure plate anti-misoperation preview event note of structure as shown in figures 2-6 is obtained Record.Described secondary pressure plate is stored in secondary pressure plate anti-misoperation preview logout storehouse among the data service module Anti-misoperation previews logout.
Prevent for power network operation maintenance personnel provides access related electric protection device secondary pressure plate in described subscriber interface module Maloperation previews the human-machine interactive information interface of logout.As shown in figure 1, i.e. among described system-based database The anti-misoperation preview logout power supply network O&M of secondary pressure plate is read in secondary pressure plate anti-misoperation preview logout storehouse Personnel understand and grasp the throwing of related electric protection device secondary pressure plate/stop cause and event information, to check and checking correlation The correctness that state was thrown/stopped to electric protective device secondary pressure plate provides information service, it is to avoid arrangement power network operation maintenance personnel goes to become The inconvenience of operation note is browsed in power station on-site verification, has effectively saved man power and material.

Claims (2)

1. a kind of electric protective device secondary pressure plate anti-misoperation system, it is characterised in that it includes data service module, anti-error Procedure module and subscriber interface module;Wherein:
It is system-based database in described data service module, wherein being configured with secondary pressure plate anti-misoperation preview rule Storehouse, electric switching operation task library, electrical primary equipment library, electric protective device screen cabinet storehouse, secondary pressure plate storehouse and secondary pressure plate Anti-misoperation preview logout storehouse;
Secondary pressure plate anti-misoperation preview rule is stored in described secondary pressure plate anti-misoperation preview rule base, secondary pressure plate is prevented Maloperation preview rule includes the mission number of rule base electric switching operation, rule base electrical primary device numbering, rule base Electric protective device screen cabinet numbering, rule base secondary pressure plate numbering, rule base secondary pressure plate throwing/stop instruction and the secondary pressure of rule base Plate anti-misoperation constraints totally 6 attributes, cover in transformer station electrical primary equipment in every electric switching operation task Electric protective device screen cabinet on related secondary pressure plate throwing/stop instruction and secondary pressure plate anti-misoperation constraints content;
Described rule base secondary pressure plate anti-misoperation constraints is based on related electric protection device operation management regulation system It is fixed;
It is associated with rule base electric switching operation mission number in secondary pressure plate anti-misoperation preview rule base, electrically falls The mission number of task library electric switching operation and task library electric switching operation task names two defined in lock operation task storehouse Item attribute, for recording every electric switching operation mission bit stream;
It is associated with rule base electrical primary device numbering in secondary pressure plate anti-misoperation preview rule base, electrical primary sets Equipment library electrical primary device numbering and equipment library electrical primary device name attribute defined in standby storehouse, for recording transformer station Interior electrical primary facility information;
It is associated with rule base electric protective device screen cabinet numbering in secondary pressure plate anti-misoperation preview rule base, electrically protects Screen cabinet storehouse electric protective device screen cabinet numbering, screen cabinet storehouse electric protective device screen cabinet title and screen defined in protection unit screen cabinet storehouse Cabinet storehouse electrical primary device numbering, is used to record the secondary protector screen cabinet information of electrical primary equipment in transformer station;
It is associated with rule base secondary pressure plate numbering in secondary pressure plate anti-misoperation preview rule base, it is fixed in secondary pressure plate storehouse Justice pressing plate storehouse secondary pressure plate numbering, pressing plate storehouse secondary pressure plate title and pressing plate storehouse electric protective device screen cabinet numbering, are used to remember Secondary pressure plate information in record transformer station on each electric protective device screen cabinet;
Described secondary pressure plate anti-misoperation preview logout storehouse is used to store secondary pressure plate anti-misoperation preview logout, Secondary pressure plate anti-misoperation preview logout includes that preview time, record storehouse electric switching are thrown/stopped to record storehouse secondary pressure plate Operation task title, record storehouse electrical primary device name, record storehouse electric protective device screen cabinet title, record storehouse secondary pressure plate Preview command content is thrown/stopped to title and record storehouse secondary pressure plate;
Secondary pressure plate to being performed in described subscriber interface module is thrown/is stopped preview instruction and carries out instruction parsing, obtains preview and refers to Make electric switching operation mission number, preview instruct electrical primary device numbering, preview instruction electric protective device screen cabinet to number, This 5 preview command contents of preview instruction are thrown/stopped to preview instruction secondary pressure plate numbering, preview instruction secondary pressure plate;
It is right according to the secondary pressure plate anti-misoperation preview rule provided in data service module in described anti-error procedure module The secondary pressure plate after instructing parsing performed in described subscriber interface module is thrown/is stopped preview instruction and carries out item by item anti-error core It is right;By successively by parsing after the preview that obtains instruct electric switching operation mission number and rule base electric switching operation task Numbering, preview instruction electrical primary device numbering and rule base electrical primary device numbering, preview instruction electric protective device screen Cabinet is numbered and rule base electric protective device screen cabinet is numbered, preview instructs secondary pressure plate numbering and rule base secondary pressure plate to number, Whether preview instruction secondary pressure plate is thrown/is stopped preview instruction and checked with rule base secondary pressure plate throwing/stop instruction, checks its content Unanimously;If occurring in audit process, content is inconsistent, and the anti-error verification flow of the anti-error procedure module stops, while touching Send out subscriber interface module described and send maloperation information to operation maintenance personnel and warn;If checked result is consistent, further basis Whether the electrical primary of anti-error preview operation, secondary device state check-up rules storehouse secondary pressure plate anti-misoperation constraints are full Foot, if meeting rule base secondary pressure plate anti-misoperation constraints, operation of secondary pressure plate preview is denoted as by present system time Time, while instructing the electric switching operation task that electric switching operation mission number is denoted as operation preview to compile the preview Number, by it is described preview instruct electrical primary device numbering be denoted as operation preview electrical primary device numbering, by it is described preview refer to Make electric protective device screen cabinet number be denoted as the electric protective device screen cabinet numbering of operation preview, the preview is instructed into secondary pressure Plate numbering be denoted as operation preview secondary pressure plate numbering, by it is described preview instruct secondary pressure plate throw/stop preview instruction be denoted as operation Preview command content is thrown/stopped to the secondary pressure plate of preview, so that secondary pressure plate anti-misoperation preview logout information is generated, while The described subscriber interface module of triggering update correspondence electric protective device secondary pressure plate simulation throw/stop state;If being unsatisfactory for institute Rule base secondary pressure plate anti-misoperation constraints is stated, is then triggered described subscriber interface module and is sent secondary pressure to operation maintenance personnel The unmet information warning of plate anti-misoperation constraints;
Described secondary pressure plate anti-misoperation preview logout information carries out data parsing in described data service module; Described secondary pressure plate anti-misoperation is obtained by data parsing and preview logout, and then construct secondary pressure plate anti-misoperation Preview logout storehouse;Wherein, the record storehouse secondary pressure plate defined in the secondary pressure plate anti-misoperation preview logout storehouse Preview time is thrown/stopped for recording described operation of secondary pressure plate preview time;The secondary pressure plate anti-misoperation previews event Record storehouse electric switching operation task names defined in record storehouse are used to record the electric switching of the operation preview according to What operation task numbering was parsed from described secondary pressure plate anti-misoperation preview rule base and electric switching operation task library Record storehouse operation task title;Record storehouse electrical primary defined in the secondary pressure plate anti-misoperation preview logout storehouse sets The electrical primary device numbering that standby title is used to record the operation preview according to is pre- from described secondary pressure plate anti-misoperation Drill the electrical primary device name parsed in rule base and electrical primary equipment library;The secondary pressure plate anti-misoperation previews thing Record storehouse electric protective device screen cabinet title defined in part record storehouse is used to record the electric guarantor of the operation preview according to Protection unit screen cabinet numbering is parsed from described secondary pressure plate anti-misoperation preview rule base and electric protective device screen cabinet storehouse Electric protective device screen cabinet title;The secondary pressure of record storehouse defined in the secondary pressure plate anti-misoperation preview logout storehouse The secondary pressure plate numbering that board name is used to record the operation preview according to previews rule from described secondary pressure plate anti-misoperation The secondary pressure plate title for then being parsed in storehouse and secondary pressure plate storehouse;It is fixed in the secondary pressure plate anti-misoperation preview logout storehouse The record storehouse secondary pressure plate of justice is thrown/is stopped preview instruction and throws/stop preview command content for recording the secondary pressure plate of operation preview;By This obtains secondary pressure plate anti-misoperation preview logout;Secondary pressure plate anti-misoperation among the data service module is pre- Drill and described secondary pressure plate anti-misoperation preview logout is stored in logout storehouse;
Described subscriber interface module provides access related electric protection device secondary pressure plate anti-misoperation for power network operation maintenance personnel Preview the human-machine interactive information interface of logout;Secondary pressure plate anti-misoperation among described system-based database is pre- The anti-misoperation preview logout power supply network operation maintenance personnel for drilling reading secondary pressure plate in logout storehouse understands and grasp correlation The throwing of electric protective device secondary pressure plate/stop cause and event information.
2. a kind of electric protective device secondary pressure plate anti-misoperation system according to claim 1, it is characterised in that described Rule base secondary pressure plate anti-misoperation constraints in for transformer, bus, 220kV and above circuit and The rule base secondary pressure plate anti-misoperation constraints that the protection device of 110kV and following voltage class circuit is formulated is:
(1)Input transformer " gap protection input " secondary pressure plate, answers before disabling transformer " zero sequence excessively stream input " secondary pressure plate Check transformer neutral point grounding switch in a point position;Conversely, should be disabled before the transformer neutral point grounding switch that closes transformer " Gap protection input " secondary pressure plate, puts into transformer " zero sequence excessively stream input " secondary pressure plate;
(2)Bus should put into " charge protection " and " mother excessively stream " secondary pressure plate before being charged by bus connection switch, charging is finished should Disable above-mentioned two secondary pressure plate;In bus grid switching operation, answered first before disconnecting " bus connection switch operation power " small air switch Input " mother interconnection " secondary pressure plate;Conversely, " the bus connection switch operation electricity that should first be closed before disabling " mother interconnection " secondary pressure plate Source " small air switch;
(3)Any a set of " reclosing outlet " secondary pressure plate in two sets of protection devices of 220kV and above circuit " reclosing outlet " secondary pressure plate during another set of protection device should be checked before the input is in rest position;Input " links up three to jump " reclosing outlet " secondary pressure plate should be first disabled before lock-reclosing lock " secondary pressure plate, " actuating breaker failure protection " secondary pressure plate is disabled Before first line switching should be disconnected;
(4)" tripping operation outlet " should be simultaneously disabled when out of service for the route protection of 110kV and following voltage class and " reclosing goes out Mouthful " secondary pressure plate;Conversely, above-mentioned two secondary pressure plate should put into during protection input simultaneously.
CN201710072763.0A 2017-02-10 2017-02-10 A kind of electric protective device secondary pressure plate anti-misoperation system Expired - Fee Related CN106685088B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710072763.0A CN106685088B (en) 2017-02-10 2017-02-10 A kind of electric protective device secondary pressure plate anti-misoperation system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710072763.0A CN106685088B (en) 2017-02-10 2017-02-10 A kind of electric protective device secondary pressure plate anti-misoperation system

Publications (2)

Publication Number Publication Date
CN106685088A true CN106685088A (en) 2017-05-17
CN106685088B CN106685088B (en) 2019-03-12

Family

ID=58860874

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710072763.0A Expired - Fee Related CN106685088B (en) 2017-02-10 2017-02-10 A kind of electric protective device secondary pressure plate anti-misoperation system

Country Status (1)

Country Link
CN (1) CN106685088B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108471106A (en) * 2018-04-17 2018-08-31 国网河南省电力公司电力科学研究院 One kind is based on single mother partition mode of connection busbar interval secondary anti-misoperation method and device
CN108512198A (en) * 2018-04-17 2018-09-07 国网河南省电力公司电力科学研究院 One kind being used for supervisory control of substation plane line interval secondary anti-misoperation method and device
CN113972738A (en) * 2021-10-18 2022-01-25 国网辽宁省电力有限公司丹东供电公司 Power system relay protection operation anti-misoperation device and method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103389705A (en) * 2013-07-19 2013-11-13 国家电网公司 Operation monitoring system and method
CN105226816A (en) * 2015-09-23 2016-01-06 国家电网公司 Pressing plate Stateful Inspection and anti-error management system
CN105302121A (en) * 2015-11-24 2016-02-03 积成电子股份有限公司 Sequential control operation order automatic anti-error check method based on simulation IED device

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103389705A (en) * 2013-07-19 2013-11-13 国家电网公司 Operation monitoring system and method
CN105226816A (en) * 2015-09-23 2016-01-06 国家电网公司 Pressing plate Stateful Inspection and anti-error management system
CN105302121A (en) * 2015-11-24 2016-02-03 积成电子股份有限公司 Sequential control operation order automatic anti-error check method based on simulation IED device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
王建兵: ""变电站二次压板防误管理系统的应用"", 《电工技术》 *
黄东方,孙亚辉: ""保护压板投退全过程防误措施的研究与实现"", 《福建电力与电工》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108471106A (en) * 2018-04-17 2018-08-31 国网河南省电力公司电力科学研究院 One kind is based on single mother partition mode of connection busbar interval secondary anti-misoperation method and device
CN108512198A (en) * 2018-04-17 2018-09-07 国网河南省电力公司电力科学研究院 One kind being used for supervisory control of substation plane line interval secondary anti-misoperation method and device
CN108471106B (en) * 2018-04-17 2019-11-12 国网河南省电力公司电力科学研究院 One kind is based on single mother partition mode of connection bus interval secondary anti-misoperation method and device
CN113972738A (en) * 2021-10-18 2022-01-25 国网辽宁省电力有限公司丹东供电公司 Power system relay protection operation anti-misoperation device and method

Also Published As

Publication number Publication date
CN106685088B (en) 2019-03-12

Similar Documents

Publication Publication Date Title
Wang et al. Electrical safety considerations in large-scale electric vehicle charging stations
Sarangi et al. Distributed generation hybrid AC/DC microgrid protection: A critical review on issues, strategies, and future directions
CN103401226B (en) Substation area differential protection method for intelligent substation
CN202940643U (en) Comprehensive anti-misoperation system for power distribution network
CN103401170A (en) Box type transformer station
Li et al. Assessment method and indexes of operating states classification for distribution system with distributed generations
CN106685088A (en) Anti-misoperation system for secondary plate pressing of electric protection device
CN107945608A (en) Almightiness type power supply station Training in Comprehensive Skills device
CN105305365A (en) Power grid relay protection emergency management system
CN104821662A (en) Multidimensional intelligent anti-misoperation system and method
CN102957203A (en) Electrical equipment anti-misoperation method, device and system
CN107067081A (en) Substation secondary maintenance safety measure generation method based on many object models
CN206074794U (en) The portable power storage load box checked by false wiring of electric energy metering equipment
Pordanjani et al. Single-phase ferroresonance in an ungrounded system during system energization
CN108964259A (en) A kind of power grid intelligence control system
CN209543688U (en) A kind of substation's experience system
CN109921516A (en) A kind of topology based on electrical principle and prevent maloperation method
CN106058893A (en) High-voltage and high-capacity chain-type STATCOM device protection system
CN103077631B (en) Training device for three-phase circuit breaker spring operation mechanism
CN106026047A (en) Optimized control method of high-reliability distribution automation based on multi-source coordination and cooperation
CN208271415U (en) Almightiness type power supply station Training in Comprehensive Skills device
Hesami et al. Fault Current Protection in distribution system connected EVCH: A Review
CN105449853B (en) Method for building digital substation
CN103840553B (en) Failure starting circuit and method for starting failure circuit
Fan et al. Control and protection strategy design of ITER toroidal field coil power supply system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190312

Termination date: 20200210

CF01 Termination of patent right due to non-payment of annual fee