CN106677257A - Installation process of sinking pipe for offshore water intake and discharge in power plant - Google Patents
Installation process of sinking pipe for offshore water intake and discharge in power plant Download PDFInfo
- Publication number
- CN106677257A CN106677257A CN201710135835.1A CN201710135835A CN106677257A CN 106677257 A CN106677257 A CN 106677257A CN 201710135835 A CN201710135835 A CN 201710135835A CN 106677257 A CN106677257 A CN 106677257A
- Authority
- CN
- China
- Prior art keywords
- immersed tube
- immersed
- drainage
- steel
- water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03B—INSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
- E03B3/00—Methods or installations for obtaining or collecting drinking water or tap water
- E03B3/04—Methods or installations for obtaining or collecting drinking water or tap water from surface water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/02—Caissons able to be floated on water and to be lowered into water in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/08—Lowering or sinking caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0061—Production methods for working underwater
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Health & Medical Sciences (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Earth Drilling (AREA)
Abstract
本发明公开了一种电厂海上取排水沉管的安装工艺,包括以下步骤:沉管预制、沉管上驳、半潜驳船运输、钢浮箱安装、半潜驳船下潜、沉管吊运、沉管定位、沉管下沉对接、拉合紧密、拆除钢浮箱、拆除测量塔、前节千斤顶及安装扣板。本发明的电厂海上取排水沉管的安装工艺,沉管采用钢箱助浮安装,解决了沉管自身浮力不足的问题;能确保沉管的安装精度满足设计及规范要求通过对拆除钢浮箱工艺的优化,可有效的保护下一节沉管的基床,还能减少工程造价,缩短施工工期。
The invention discloses an installation process of an immersed tube for water intake and drainage in a power plant. Immersed tube positioning, sinking and docking of immersed tubes, tight pulling, removal of steel buoyancy tanks, removal of measuring towers, front section jacks and installation of gussets. In the installation process of the immersed tube for water intake and drainage of the power plant in the present invention, the immersed tube is installed with the aid of a steel box for buoyancy, which solves the problem of insufficient buoyancy of the immersed tube itself; it can ensure that the installation accuracy of the immersed tube meets the requirements of the design and specifications by removing the steel buoyant tank The optimization of the process can effectively protect the foundation bed of the next section of the immersed tube, and can also reduce the project cost and shorten the construction period.
Description
技术领域technical field
本发明涉及一种电厂海上取排水沉管的安装工艺。The invention relates to an installation process of a submerged pipe for taking water out of the sea of a power plant.
背景技术Background technique
随着经济和社会的持续发展,用电量也飞速增长,为了满足人们生产和生活的用电需求,其主要方式是发电厂的改建、扩建和增容,其中许多是火电站和核电站。火力发电和核能发电都需要对发电设备进行冷却,这就需要大量的冷却水。因此,大型核电、火电站大多靠近海湾、河口、湖泊、水库等处选址,以便就地利用水资源实现冷却。取排水沉管工程是决定发电厂热能效率高低的重要因素之一。取排水沉管的安装施工难度大,具体体现在以下几个方面:With the continuous development of economy and society, electricity consumption is also increasing rapidly. In order to meet people's production and living electricity demand, the main way is to rebuild, expand and increase the capacity of power plants, many of which are thermal power plants and nuclear power plants. Both thermal power generation and nuclear power generation need to cool the power generation equipment, which requires a large amount of cooling water. Therefore, most large-scale nuclear power plants and thermal power plants are located close to bays, estuaries, lakes, reservoirs, etc., so as to use water resources to achieve cooling on the spot. The intake and drainage immersed tube engineering is one of the important factors that determine the thermal efficiency of power plants. The installation and construction of intake and drainage immersed pipes is difficult, which is reflected in the following aspects:
1)沉管的基础采用碎石基床的结构形式,钢浮箱在拆除过程中,易对下一节沉管的碎石基床造成破坏;1) The foundation of the immersed tube adopts the structural form of the crushed stone bed. During the dismantling of the steel buoyancy tank, it is easy to cause damage to the crushed stone bed of the next section of the immersed tube;
2)预制沉管的体积大、重量重,且沉管本身不具备封闭空间,自身提供的浮力较小;2) The prefabricated immersed tube is bulky and heavy, and the immersed tube itself does not have a closed space, and the buoyancy provided by itself is small;
3)设计要求沉管的安装精度控制在2cm之内,要求精度极高;3) The design requires that the installation accuracy of the immersed tube be controlled within 2cm, requiring extremely high accuracy;
4)沉管的节数多、安装线路长,沉管的安装平面位置精度控制要求高,若控制不到位,极易造成较大的累积误差。4) The number of immersed tubes is large, the installation line is long, and the precision control of the installation plane position of the immersed tube is high. If the control is not in place, it is easy to cause a large cumulative error.
发明内容Contents of the invention
本发明的目的在于克服现有技术的缺陷而提供一种电厂海上取排水沉管的安装工艺,它能确保沉管的安装精度满足设计及规范要求,还能减少工程造价,缩短施工工期。The purpose of the present invention is to overcome the defects of the prior art and provide an installation process of the immersed pipe for the offshore intake and drainage of the power plant, which can ensure that the installation accuracy of the immersed pipe meets the design and specification requirements, and can also reduce the project cost and shorten the construction period.
本发明的目的是这样实现的:一种电厂海上取排水沉管的安装工艺,包括以下步骤:沉管预制、沉管上驳、半潜驳船运输、钢浮箱安装、半潜驳船下潜、沉管吊运、沉管定位、沉管下沉对接、拉合紧密、拆除钢浮箱、拆除测量塔、前节千斤顶及安装扣板;其中,The object of the present invention is achieved in this way: an installation process of immersed tubes for water intake and drainage in a power plant, comprising the following steps: prefabrication of immersed tubes, barge on immersed tubes, semi-submerged barge transportation, installation of steel buoyancy tanks, submersion of semi-submersible barges, Immersed tube hoisting, immersed tube positioning, immersed tube sinking and docking, pulling tight, removing steel buoyancy tank, removing measuring tower, front section jack and installing buckle plate; among them,
进行所述沉管预制步骤时,是在预制场码头预制多节取水沉管、两座取水头沉箱、多节排水沉管和三座排水口头部沉管;预制时按由岸侧往海侧方向自小至大编制预制件号,以便由岸侧往海侧交替安装取、排水沉管;When carrying out the immersed tube prefabrication step, it is to prefabricate multi-section water intake immersed tubes, two water intake head caissons, multi-section drainage immersed tubes and three outfall head immersed tubes at the prefabrication yard wharf; The direction of the prefabricated parts is compiled from small to large, so that the intake and drainage immersed pipes can be installed alternately from the shore side to the sea side;
进行所述沉管上驳步骤时,将预制完成的沉管装在半潜驳船上,沉管置于半潜驳船的船艏位置,每次仅安装一节沉管;When carrying out the barge step of the immersed tube, the prefabricated immersed tube is installed on the semi-submersible barge, the immersed tube is placed at the bow of the semi-submersible barge, and only one section of the immersed tube is installed each time;
进行所述半潜驳船运输步骤时,由拖轮将装有一节沉管的半潜驳船由预制场码头拖带至下潜坑,半潜驳船顺沉管的安装轴线方向并且船首朝向海侧,船尾朝向岸侧,再通过四角抛八字锚就位;When carrying out the semi-submerged barge transportation step, the semi-submersible barge with one section of immersed tube is towed from the prefabricated yard wharf to the submerged pit by the tugboat. Facing the shore, and then throw the figure-of-eight anchor in place through the four corners;
进行所述钢浮箱安装步骤时,起重船先就位,接着安装测量GPS和拉合千斤顶,再通过起重船安装钢浮箱;起重船就位时,起重船与半潜驳船同轴线地停在半潜驳船的船首并通过四角抛八字锚就位;安装测量GPS时,将所述测量GPS安放到测量塔的顶端,通过无线信号与起重船的电脑连接好,再将测量塔吊放到沉管的预埋件上,通过法兰螺栓固定在预埋件上;沉管中轴线的头尾端均要安装一座测量塔;所述拉合千斤顶安装在沉管头部的吊环上;安装钢浮箱时,钢浮箱放置于平板驳船上,平板驳船停靠在就位后的半潜驳船的一侧;起重船通过横向移船将钢浮箱从平板驳船起吊至半潜驳船上,再通过前后移船并借助半潜驳船上的卷扬机牵引将钢浮箱塞入沉管的每个孔道内;When carrying out the step of installing the steel pontoon, the lifting ship is first in place, and then the measuring GPS and the pulling jack are installed, and then the steel buoy is installed by the lifting ship; when the lifting ship is in place, the lifting ship and the semi-submersible barge Coaxially stop at the bow of the semi-submersible barge and place the figure-of-eight anchors through the four corners; when installing the measurement GPS, place the measurement GPS on the top of the measurement tower, connect it to the computer of the crane ship through a wireless signal, and then Place the measuring tower on the embedded part of the immersed tube and fix it on the embedded part through flange bolts; a measuring tower should be installed at the head and tail of the central axis of the immersed tube; the pulling jack is installed at the head of the immersed tube When installing the steel buoyant box, the steel buoyant box is placed on the flat barge, and the flat barge is docked on one side of the semi-submersible barge after it is in place; the crane ship lifts the steel buoyant box from the flat barge to the On the semi-submersible barge, the steel buoyant box is inserted into each channel of the immersed tube by moving the ship forward and backward and pulling by the hoist on the semi-submersible barge;
进行所述半潜驳船下潜步骤时,是在钢浮箱安装完成后,半潜驳船注水下潜,当沉管的顶板的上表面略高于水面时,起重船先向前移动船位,使起重船的扒杆从半潜驳船的首塔楼之间伸入半潜驳船体的沉管全长的1/2处,当起重船的主钩垂线与沉管的中心重合时停止移船,放下主钩,系挂吊缆,然后半潜驳船继续下潜,直到沉管的顶部浸入水面约1m时停止下潜;When carrying out the diving step of the semi-submersible barge, after the installation of the steel buoyancy tank is completed, the semi-submersible barge dives with water injection, and when the upper surface of the top plate of the immersed tube is slightly higher than the water surface, the lifting ship moves forward first, Make the lifting bar extend from between the bow towers of the semi-submersible barge to 1/2 of the total length of the immersed tube of the semi-submersible barge, and stop when the vertical line of the main hook of the lifting ship coincides with the center of the immersed tube Move the ship, put down the main hook, hang the suspension cable, and then the semi-submersible barge continues to dive until the top of the immersed tube is immersed in the water surface for about 1m and stops diving;
进行沉管吊运步骤时,起重船向后移动船位,将沉管吊离半潜驳船,在吊运过程中,保持沉管的顶面在水面以下1m,再收紧后锚移动船位,使拔杆退出半潜驳船,随后半潜驳船排水上浮并收缆移出下潜坑,再移出航道位置,之后起重船移至安装位置,抛锚收缆就位,最后半潜驳船由拖轮拖回预制场码头,进行下节沉管上驳、运输和下潜;During the hoisting step of the immersed tube, the crane ship moves backward to lift the immersed tube away from the semi-submersible barge. During the hoisting process, keep the top surface of the immersed tube 1m below the water surface, and then tighten the anchor to move the ship position. Make the barge withdraw from the semi-submersible barge, then the semi-submersible barge floats up with water and the cable is moved out of the submerged pit, and then moved out of the channel position, then the crane ship moves to the installation position, the anchor is dropped and the cable is placed in place, and finally the semi-submersible barge is towed back by the tugboat The wharf of the prefabrication yard, carrying out barging, transportation and diving of the lower section of the immersed tube;
进行所述沉管定位步骤时,包括依次进行的起重船定位和沉管初定位;When performing the step of positioning the immersed tube, it includes the positioning of the crane ship and the initial positioning of the immersed tube in sequence;
进行起重船定位时,起重船吊着沉管进入基槽范围后停船抛锚,参照前节沉管尾部预留的测量塔为对标标准,并通过收放缆绳移动船位,当起重船吊运沉管至离前节沉管10m时,停止移船并精确调整船位准备沉管安装;When positioning the crane ship, the crane ship hangs the immersed tube into the range of the foundation groove and then stops the ship and anchors. Refer to the measurement tower reserved at the end of the immersed tube in the previous section as the benchmarking standard, and move the position of the ship by retracting and releasing the cables. When the crane ship When the immersed tube is hoisted to 10m away from the immersed tube at the front section, stop moving the ship and precisely adjust the position of the ship to prepare for the installation of the immersed tube;
进行沉管初定位时,起重船的电脑通过无线信号接收沉管顶部的测量GPS的信号,将沉管的精确位置反映在定位软件上,由测量员反馈信息给船长,并由船长指挥卷扬机操作工绞缆进行初定位,使沉管的轴线与安装轴线基本保持对齐,待沉管缓缓靠近并距离前节沉管1m时,停止移船;When performing the initial positioning of the immersed tube, the computer of the crane ship receives the GPS signal from the top of the immersed tube through wireless signals, reflects the precise position of the immersed tube on the positioning software, and the surveyor feeds back the information to the captain, who then directs the hoist The operator twisted the cable for initial positioning, so that the axis of the immersed tube was basically aligned with the installation axis, and stopped moving the ship when the immersed tube slowly approached and was 1m away from the immersed tube of the front section;
进行所述沉管下沉对接步骤时,包括排水沉管水下对接和取水沉管水下对接;When performing the sinking and docking step of the immersed tube, it includes the underwater docking of the drainage immersed tube and the underwater docking of the water intake immersed tube;
进行排水沉管水下对接时,先将待装排水沉管缓慢靠近前节排水沉管,此时保持待装排水沉管高于前节排水沉管1m,直至待装排水沉管距离前节排水沉管小于50cm时,再将待装排水沉管慢慢向左靠近导向构件直至与导向构件接触时停止向左移动,此时开始下放待装排水沉管至标高与前节排水沉管一致时停止下放,然后向前缓慢移动排水沉管直至与前节排水沉管靠紧;When carrying out the underwater docking of the drainage immersed tube, first slowly approach the drainage immersed tube to be installed to the front section of the drainage immersed tube, at this time, keep the to-be-installed drainage immersed tube 1m higher than the front section of the drainage immersed tube until the to-be-installed drainage immersed tube is 1m higher than the front section When the drainage sinking tube is less than 50cm, move the draining sinking tube to be installed slowly to the left and close to the guide member until it touches the guide member and stop moving to the left. Stop lowering at the same time, and then slowly move the drain sinking tube forward until it is close to the front drain sinking tube;
进行取水沉管水下对接时,对接水平方向及垂直方向位置均通过测量塔控制,对接时,先将待装取水沉管缓慢靠近前节取水沉管,直至距离前节取水沉管1m时,停止移动,再次调整待装取水沉管的轴线位置、标高与前节取水沉管一致,然后起重船向前移动船位,直至待装取水沉管与前节取水沉管靠紧;When carrying out the underwater docking of the water intake immersed tube, the horizontal and vertical positions of the docking are controlled by the measuring tower. Stop moving, and adjust the axis position and elevation of the immersed pipe to be installed to be consistent with the immersed pipe in the front section, and then move the crane ship forward until the immersed pipe to be installed is close to the immersed pipe in the front section;
进行所述拉合紧密步骤时,由潜水员下水进行沉管的拉合作业,拉合千斤顶通过钢丝绳、卸扣与前节沉管尾部吊点连接,连接完成后,工作船上油泵开始供油,千斤顶拉杆回收,沉管开始拉合,直至两节沉管接缝小于2cm停止拉合,最后,起重船松钩,接着由潜水员在水下拆除沉管吊点上的卸扣;When carrying out the pulling and tightening step, the divers go into the water to carry out the pulling and closing operation of the immersed tube. The pulling jack is connected to the lifting point at the tail of the immersed tube in the front section through a wire rope and a shackle. After the connection is completed, the oil pump on the working ship starts to supply oil, and the jack The pull rod is recovered, and the immersed tube starts to be pulled together until the joint between the two sections of the immersed tube is less than 2cm. Finally, the lifting boat releases the hook, and then the diver removes the shackle on the lifting point of the immersed tube underwater;
进行所述拆除钢浮箱步骤时,包括依次进行的钢浮箱注水下沉、拉出钢浮箱、钢浮箱出水和钢浮箱回收;When carrying out the step of removing the steel buoyant tank, it includes the water injection and sinking of the steel buoyant tank, the pulling out of the steel buoyant tank, the water discharge of the steel buoyant tank and the recycling of the steel buoyant tank;
进行钢浮箱注水下沉时,为精确控制钢浮箱注水量,在钢浮箱制作时已在内腔内安装了泡沫;When the steel pontoon tank is sinking with water, in order to accurately control the water injection volume of the steel pontoon tank, foam has been installed in the inner cavity when the steel pontoon tank is manufactured;
进行拉出钢浮箱时,是在钢浮箱下沉至沉管的底板后,潜水员将起重船的抽芯锚缆绳通过卸扣与钢浮箱的头部吊环连接,起重船间接性收紧缆绳试拉钢浮箱,若试拉过程中发现受阻,立即放松缆绳并后移船位,直至试拉时钢浮箱平顺移动,方可持续将钢浮箱拉出沉管;When pulling out the steel pontoon, after the steel pontoon sinks to the bottom plate of the immersed tube, the diver connects the core-pulling anchor cable of the crane ship to the head ring of the steel pontoon through a shackle, and the crane ship indirectly Tighten the cable and try to pull the steel buoy box. If you find any obstruction during the test pull, immediately loosen the cable and move the ship back until the steel buoy box moves smoothly during the test pull, then you can continue to pull the steel buoy box out of the immersed tube;
进行钢浮箱出水时,是在钢浮箱拉出沉管后,起重船下放吊钩,潜水员在水下进行换缆作业,将吊钩系挂在钢浮箱的顶部四个吊环上,并打开钢浮箱尾部的出水阀门排水,吊钩系缆完成后,起重船收紧吊缆,缓慢将钢浮箱吊出水面;When the steel pontoon is out of water, after the steel pontoon is pulled out of the immersed tube, the lifting hook is lowered by the crane, and the diver changes the cable underwater, and the hook is hung on the top four rings of the steel pontoon. And open the water outlet valve at the tail of the steel buoy to drain water. After the hook mooring is completed, the crane ship tightens the suspension cable and slowly lifts the steel buoy out of the water;
进行浮箱回收时,是在钢浮箱吊出水面并在钢浮箱排水完毕后,由起重船将钢浮箱吊至平板驳船上存放,并关闭钢浮箱上的进、出阀门,等待下一件沉管安装;When the buoyant tank is recovered, after the steel buoyant tank is hoisted out of the water and the steel buoyant tank is drained, the steel buoyant tank is hoisted by the crane to the flat barge for storage, and the inlet and outlet valves on the steel buoyant tank are closed. Waiting for the installation of the next immersed tube;
进行拆除测量塔、前节千斤顶和安装扣板步骤时,由潜水员水下拆除岸侧一端的测量塔和前节沉管上的千斤顶并吊出水面,再安装扣板,完成该节沉管的安装工作。When carrying out the steps of removing the measurement tower, the front section jack and installing the gusset plate, the divers underwater remove the measurement tower at the shore side and the jack on the front section of the immersed tube and lift them out of the water, and then install the gusset plate to complete the installation of this section of immersed tube Installation works.
上述的电厂海上取排水沉管的安装工艺,其中,安装取水管时,还包括在拆除测量塔、前节千斤顶及安装扣板步骤后进行接缝注浆步骤,即通过压力泵将水泥浆通过两节沉管的接缝处预留的注浆管注入两节取水沉管的两圈止水带之间空隙中。The installation process of the above-mentioned immersed pipe for water intake and drainage of the power plant, wherein, when installing the water intake pipe, it also includes the step of joint grouting after the steps of removing the measuring tower, the front section jack and installing the gusset plate, that is, the cement slurry is passed through the pressure pump. The grouting pipe reserved at the joint of the two immersed tubes is injected into the gap between the two rings of the water stop of the two immersed tubes for water intake.
上述的电厂海上取排水沉管的安装工艺,其中,进行所述沉管预制步骤时,所述取水沉管的预制数量为二十节,第一节取水沉管至十三节取水沉管为双孔共壁管,每孔的横截面呈矩形;第十四节取水沉管为双孔共壁管过渡至两个单孔管,每孔的横截面也呈矩形;第十五节取水沉管至第二十节取水沉管均为单孔管,并且孔的横截面均为矩形;第十七节取水沉管与第十五节取水沉管连接的一端面以及第十八节取水沉管与第十六节取水沉管连接的一端面均为直面,另一端面为斜面;第十九节取水沉管和第二十节取水沉管的两端面均为斜面;每座所述取水头沉箱呈圆筒形并沿圆周开设一圈用钢筋混凝土支柱支撑并分隔的进水窗口,每个进水窗口均设置进水格栅;每座取水头沉箱内均设置井字形横梁及并在横梁的相交处设置立柱。The installation process of the above-mentioned immersed tubes for water intake and drainage in the power plant, wherein, when performing the immersed tube prefabrication step, the prefabricated number of immersed tubes for water intake is 20 sections, and the immersed tubes for water intake of the first section to the thirteen sections of immersed tubes for water intake are Double-hole co-wall pipe, the cross-section of each hole is rectangular; the fourteenth section of the sinking pipe is a double-hole co-wall pipe transition to two single-hole pipes, and the cross-section of each hole is also rectangular; the fifteenth section of water sinking The tube to the twentieth section of the sinking tube for water intake are all single-hole tubes, and the cross-section of the hole is rectangular; One end of the connection between the pipe and the water intake immersed pipe in Section 16 is straight, and the other end is inclined; both ends of the immersed water intake pipe in Section 19 and the immersed water intake pipe in Section 20 are inclined; The head caisson is in the shape of a cylinder, and a circle of water inlet windows supported and separated by reinforced concrete pillars is opened along the circumference. Each water inlet window is equipped with a water inlet grille; Columns are set at the intersections of beams.
上述的电厂海上取排水沉管的安装工艺,其中,进行所述沉管预制步骤时,所述排水沉管的预制数量为六十四节;第一节排水沉管至第五十一节排水沉管均为三孔管,每孔的横截面呈矩形;第五十二节排水沉管为三孔共壁管过渡至三个单孔管,每孔的横截面呈矩形;第五十三节排水沉管至第六十四节排水沉管均为单孔管并且孔的横截面均呈矩形;每座所述排水口头部沉管为横截面呈正方形的单孔沉管并且孔的尺寸沿水流方向逐渐减小,排水口头部沉管的顶部设置三个矩形犀头,每个犀头的四周分别设置一个排水窗口。The installation process of the above-mentioned immersed tubes for the offshore intake and drainage of the power plant, wherein, when performing the immersed tube prefabrication step, the prefabricated number of the drain immersed tubes is 64 sections; the first section of drainage immersed tubes to the fifty-first section of drainage The immersed tubes are all three-hole tubes, and the cross-section of each hole is rectangular; the fifty-second drainage immersed tube is a transition from three-hole co-wall tubes to three single-hole tubes, and the cross-section of each hole is rectangular; The immersed pipes from Section 64 to Section 64 are all single-hole pipes with a rectangular cross-section; Decrease gradually along the direction of water flow, three rectangular rhinoceros heads are arranged on the top of the immersed pipe at the head of the drain, and a drainage window is respectively arranged around each rhinoceros head.
上述的电厂海上取排水沉管的安装工艺,其中,进行所述半潜驳船运输步骤时,取水沉管的下潜坑设在取水沉管的安装轴线的延长线上并距离第一节取水沉管的安装位置为466m;排水沉管的下潜坑有两个,第一个排水沉管的下潜坑设在排水沉管的安装轴线的延长线上并距离第一节排水沉管的安装位置为774m,第二个排水沉管的下潜坑设在排水口头部沉管的基槽位置。The installation process of the above-mentioned immersed pipe for water intake and drainage at sea in a power plant, wherein, during the transportation step of the semi-submersible barge, the submerged pit for the immersed pipe for water intake is set on the extension line of the installation axis of the immersed pipe for water intake and is at a distance from the first section of the immersed tube for water intake. The installation position of the pipe is 466m; there are two submerged pits for the drainage immersed pipe. The location is 774m, and the submerged pit of the second drainage immersed pipe is set at the foundation groove of the immersed pipe at the head of the outfall.
上述的电厂海上取排水沉管的安装工艺,其中,进行所述钢浮箱安装步骤时,除了将钢浮箱塞在沉管的孔道内,还采用外绑钢浮箱,即由起重船将钢浮箱吊放至沉管的两侧或顶部并系好捆绑钢丝绳,捆绑钢丝绳在沉管的两侧拉环及钢浮箱的外侧定位环中为松弛设置,当沉管下潜入水中后,钢浮箱上浮,捆绑钢丝绳自然拉紧,当钢浮箱上浮至顶面与沉管的顶面齐平后,半潜驳船暂停下潜,由操作人员将系于钢浮箱的吊环上的细钢丝绳拉紧并将钢丝绳端部系于沉管的顶板中部预埋的拉环上,让钢箱紧靠于沉管的侧壁上,之后半潜驳船继续下潜直至沉管的顶面没入水面1m。The installation process of the above-mentioned immersed tube for water intake and drainage of the power plant, wherein, when performing the installation step of the steel buoyant tank, in addition to plugging the steel buoyant tank into the channel of the immersed tube, an externally bound steel buoyant tank is also used, that is, the steel buoyant tank is installed by the crane ship. Hang the steel pontoon to the two sides or the top of the immersed tube and tie the bundled steel wire rope. The bundled steel wire rope is set loosely in the pull rings on both sides of the immersed tube and the outer positioning ring of the steel pontoon. When the immersed tube dives into the water , the steel buoyant tank floats up, and the bundled steel wire rope is naturally tightened. When the steel buoyant tank floats up to the top surface and is flush with the top surface of the immersed tube, the semi-submersible barge suspends diving. The thin wire rope is tightened and the end of the wire rope is tied to the pre-buried pull ring in the middle of the roof of the immersed tube, so that the steel box is close to the side wall of the immersed tube, and then the semi-submersible barge continues to dive until the top surface of the immersed tube is submerged. The water surface is 1m.
上述的电厂海上取排水沉管的安装工艺,其中,进行所述半潜驳船下潜步骤时,先要进行下潜前的准备,包括扫海、选择下潜和吊运安装的时段。In the installation process of the above-mentioned immersed pipe for the offshore intake and drainage of the power plant, when performing the step of diving the semi-submersible barge, preparations before diving must first be carried out, including the periods of sea sweeping, selection of diving and hoisting and installation.
本发明的电厂海上取排水沉管的安装工艺具有以下特点:The installation process of the sinking pipe for the offshore intake and drainage of the power plant of the present invention has the following characteristics:
1)加强沉管预制质量控制及沉管基础施工质量控制,确保沉管的安装精度满足设计及规范要求;1) Strengthen the quality control of immersed tube prefabrication and immersed tube foundation construction quality control to ensure that the installation accuracy of immersed tube meets the design and specification requirements;
2)严格控制取水沉管接头的预制质量,在下水安装前,对场内所有取水沉管的阴阳榫接头进行配对测量,对不满足尺寸要求的阴阳榫接头进行打磨调整,同时,在水下安装时,严格按设计要求控制接缝宽度,在接头注浆过程中严格控制注浆压力,确保接头注浆密实;2) Strictly control the prefabrication quality of the joints of the water intake immersed pipes. Before the installation in the water, carry out matching measurements on the male and female joints of all the water intake immersed pipes on the site, and grind and adjust the male and female joints that do not meet the size requirements. During installation, the joint width is strictly controlled according to the design requirements, and the grouting pressure is strictly controlled during the joint grouting process to ensure that the joints are densely grouted;
3)安装开始时,严格控制首件沉管的安装平面位置,后续施工中,对每件沉管安装平面位置进行记录分析,若累积误差较大,则及时对下节沉管的安装位置进行调整,以确保沉管的整体轴线位置符合设计要求;3) At the beginning of the installation, strictly control the installation plane position of the first immersed tube. During the subsequent construction, record and analyze the installation plane position of each immersed tube. Adjust to ensure that the overall axis position of the immersed tube meets the design requirements;
4)沉管采用钢箱助浮安装,解决了沉管自身浮力不足的问题;4) The immersed tube is installed with a steel box for buoyancy, which solves the problem of insufficient buoyancy of the immersed tube itself;
5)优化钢浮箱的拆除工艺,即在钢浮箱前部的上部吊耳露出沉管时,用起重船吊住钢浮箱前部的上部吊耳继续拉出钢浮箱,在钢浮箱后部的上部吊耳露出沉管时,将钢浮箱放置在基床上并系挂钢浮箱后部的上部吊耳,起重船起吊钢浮箱并继续拉出钢浮箱,直至将钢浮箱全部拉出沉管。通过对钢箱助拆除工艺的优化,可有效的保护下一节沉管的基床。5) Optimize the dismantling process of the steel pontoon, that is, when the upper lug at the front of the steel pontoon exposes the immersed tube, use a crane to hang the upper lug at the front of the steel pontoon and continue to pull out the steel pontoon. When the upper lugs at the rear of the buoyant box are exposed to the immersed tube, place the steel buoyant box on the foundation bed and hang the upper lugs at the rear of the steel buoyant box. The lifting ship lifts the steel buoyant box and continues to pull out the steel buoyant box until Pull the steel pontoon all the way out of the immersed tube. Through the optimization of the aided demolition process of the steel box, the foundation bed of the next immersed tube can be effectively protected.
附图说明Description of drawings
图1是本发明的电厂海上取排水沉管的安装工艺的流程图;Fig. 1 is the flow chart of the installation process of the power plant sea intake and drainage sinking pipe of the present invention;
图2是采用本发明的电厂海上取排水沉管的安装工艺安装的取水沉管的安装顺序示意图;Fig. 2 is a schematic diagram of the installation sequence of the water intake immersed tube installed by adopting the installation process of the power plant offshore intake and drain immersed tube of the present invention;
图3是采用本发明的电厂海上取排水沉管的安装工艺安装的排水沉管的安装顺序示意图;Fig. 3 is a schematic diagram of the installation sequence of the drainage immersed pipe installed by adopting the installation process of the offshore water intake and drainage immersed pipe of the power plant of the present invention;
图4是本发明的电厂海上取排水沉管的安装工艺采用的钢浮箱的前视图;Fig. 4 is the front view of the steel pontoon used in the installation process of the power plant's offshore intake and drainage sinking pipe of the present invention;
图5是本发明的电厂海上取排水沉管的安装工艺采用的钢浮箱的后视图;Fig. 5 is the rear view of the steel pontoon used in the installation process of the offshore water intake and sinking pipe of the power plant of the present invention;
图6是本发明的电厂海上取排水沉管的安装工艺采用的钢浮箱的俯视图;Fig. 6 is the plan view of the steel pontoon used in the installation process of the power plant's sea intake and drainage immersed pipe of the present invention;
图7是本发明的电厂海上取排水沉管的安装工艺采用的钢浮箱的轴向剖面图;Fig. 7 is the axial sectional view of the steel buoyancy tank adopted in the installation process of the offshore intake and drainage sinking pipe of the power plant of the present invention;
图8a是本发明的电厂海上取排水沉管的安装工艺采用的钢浮箱外绑在第二节和第三节取水沉管上的结构示意图;Fig. 8a is a schematic structural view of the steel buoy box used in the installation process of the offshore water intake immersed pipe of the power plant of the present invention and tied to the second and third water intake immersed pipes;
图8b是图8a的侧视图;Figure 8b is a side view of Figure 8a;
图9a是本发明的电厂海上取排水沉管的安装工艺采用的钢浮箱外绑在第十四节取水沉管上的结构示意图;Fig. 9a is a schematic structural view of the steel buoy box used in the installation process of the offshore water intake immersed tube of the power plant of the present invention and tied to the water intake immersed tube of the fourteenth section;
图9b是图9a的侧视图;Figure 9b is a side view of Figure 9a;
图10a是本发明的电厂海上取排水沉管的安装工艺采用的钢浮箱外绑在第一节和第三节排水沉管上的结构示意图;Fig. 10a is a schematic structural view of the steel buoy box used in the installation process of the offshore water intake and drainage immersed pipe of the power plant of the present invention and tied to the first and third section of the drainage immersed pipe;
图10b是图10a的侧视图;Figure 10b is a side view of Figure 10a;
图11是本发明的电厂海上取排水沉管的安装工艺采用的钢浮箱外绑在第五十二节排水沉管上的俯视图;Fig. 11 is a top view of the steel buoy box used in the installation process of the power plant's offshore intake and drainage immersed pipe of the present invention and tied to the fifty-second section of the drainage immersed pipe;
图12是本发明的电厂海上取排水沉管的安装工艺采用的钢浮箱外绑在第五十九节和六十一节排水沉管上的俯视图;Fig. 12 is a top view of the steel buoy box used in the installation process of the offshore water intake and drainage immersed pipe of the power plant of the present invention tied to the fifty-ninth section and the sixty-first section drainage immersed pipe;
图13是本发明的电厂海上取排水沉管的安装工艺采用的钢浮箱外绑在排水口头部沉管上的俯视图。Fig. 13 is a top view of the steel buoy box used in the installation process of the immersed pipe for the offshore intake and drainage of the power plant of the present invention and tied to the immersed pipe at the head of the outlet.
具体实施方式detailed description
下面将结合附图对本发明作进一步说明。The present invention will be further described below in conjunction with accompanying drawing.
请参阅图1至图13,本发明一种电厂海上取排水沉管的安装工艺,包括以下步骤:沉管预制、沉管上驳、半潜驳船运输、钢浮箱安装、半潜驳船下潜、沉管吊运、沉管定位、沉管下沉对接、拉合紧密、拆除钢浮箱、拆除测量塔、前节千斤顶及安装扣板。Please refer to Fig. 1 to Fig. 13, the installation process of an immersed tube for water intake and drainage of a power plant in the present invention includes the following steps: prefabrication of the immersed tube, barge on the immersed tube, transportation by semi-submersible barge, installation of steel buoyancy tank, and submersion of the semi-submersible barge , Immersed tube hoisting, Immersed tube positioning, Immersed tube sinking butt joint, pull tight, remove steel buoyancy tank, remove measuring tower, front section jack and install gusset plate.
进行沉管预制步骤时,是在预制场码头预制二十节取水沉管、两座取水头沉箱、六十四节排水沉管和三座排水口头部沉管;预制时按由岸侧往海侧方向自小至大编制预制件号,以便由岸侧往海侧交替安装取、排水沉管;第一节取水沉管至十三节取水沉管为双孔共壁管,每孔的横截面呈矩形;第十四节取水沉管为双孔共壁管过渡至两个单孔管而呈“Y”形,每孔的横截面也呈矩形;第十五节取水沉管至第二十节取水沉管均为单孔管,并且孔的横截面均为矩形;第十七节取水沉管与第十五节取水沉管连接的一端面以及第十八节取水沉管与第十六节取水沉管连接的一端面均为直面,另一端面为15°的斜面;第十九节取水沉管和第二十节取水沉管的两端面均为15°的斜面;每座取水头沉箱呈具有顶板和底板的圆筒形并沿圆周开设一圈用钢筋混凝土支柱支撑并分隔的进水窗口,每个进水窗口均设置铜合金的进水格栅;每座取水头沉箱内均设置井字形横梁并在横梁的相交处设置;排水沉管的预制数量为六十四节;第一节排水沉管至第五十一节排水沉管均为三孔管,每孔的横截面呈矩形;第五十二节排水沉管为三孔共壁管过渡至三个单孔管,每孔的横截面呈矩形;第五十三节排水沉管至第六十四节排水沉管均为单孔管并且孔的横截面均呈矩形;每座排水口头部沉管为横截面呈正方形的单孔沉管并且孔的尺寸沿水流方向逐渐减小,排水口头部沉管的顶部设置三个矩形犀头,每个犀头的四周分别设置一个排水窗口;During the prefabrication steps of immersed tubes, 20 sections of water intake immersed tubes, two water intake head caissons, 64 sections of drainage immersed tubes and three outfall head immersed tubes are prefabricated at the prefabrication yard wharf; The number of prefabricated parts is compiled from small to large in the side direction, so that the intake and drainage immersed pipes can be installed alternately from the shore side to the sea side; The cross-section is rectangular; the fourteenth section of the immersed tube is a double-hole co-walled tube transitioning to two single-hole tubes in a "Y" shape, and the cross-section of each hole is also rectangular; the fifteenth section of the water-immersed tube to the second The water intake and immersed tubes of the tenth section are all single-hole tubes, and the cross-sections of the holes are all rectangular; One end of the six-section water intake and immersed tube connection is a straight face, and the other end is a 15° slope; both ends of the nineteenth and twentieth water intake and immersed tubes are both 15° slopes; each water intake The head caisson has a cylindrical shape with a top plate and a bottom plate, and a circle of water inlet windows supported and separated by reinforced concrete pillars is opened along the circumference. Each water inlet window is equipped with a copper alloy water inlet grille; Well-shaped beams are set at the intersections of the beams; the prefabricated number of immersed drainage pipes is 64 sections; the immersed drainage pipes from the first section to the fifty-first section are all three-hole pipes, and the horizontal section of each hole The cross-section is rectangular; the fifty-second section of the drainage sinking pipe is a three-hole co-wall pipe transitioning to three single-hole pipes, and the cross-section of each hole is rectangular; the fifty-third section of the drainage sinking pipe to the sixty-fourth section of the drainage sinking The pipes are all single-hole pipes and the cross-section of the hole is rectangular; the immersed tube at the head of each drain is a single-hole immersed tube with a square cross-section and the size of the hole gradually decreases along the direction of water flow. The top of the immersed tube at the head of the drain Set three rectangular rhinoceros heads, and set a drainage window around each rhinoceros head;
进行沉管上驳步骤时,采用气囊移运工艺将预制完成的沉管装在半潜驳船上,沉管置于半潜驳船的船艏位置,每次仅安装一节沉管;When carrying out the barge step of the immersed tube, the prefabricated immersed tube is installed on the semi-submersible barge using the air bag transfer process, and the immersed tube is placed at the bow of the semi-submersible barge, and only one section of immersed tube is installed each time;
进行半潜驳船运输步骤时,由拖轮将装有一节沉管的半潜驳船由预制场码头沿设定航道拖带至下潜坑,半潜驳船顺沉管的安装轴线方向并且船首朝向海侧,船尾朝向岸侧,再通过四角抛八字锚就位;取水沉管的下潜坑设在取水沉管的安装轴线的延长线上并距离第一节取水沉管的安装位置为466m;排水沉管的下潜坑有两个,第一个排水沉管的下潜坑设在排水沉管的安装轴线的延长线上并距离第一节排水沉管的安装位置为774m,第二个排水沉管的下潜坑设在排水口头部沉管的基槽位置;When carrying out the semi-submersible barge transportation step, the semi-submersible barge equipped with a section of immersed tube is towed by the tugboat from the wharf of the precast yard to the submerged pit along the set channel. The semi-submersible barge follows the installation axis of the immersed tube and the bow faces the sea side , the stern of the ship faces the shore side, and then throws the figure-of-eight anchors in place through the four corners; the submerged pit of the water intake immersed tube is set on the extension line of the installation axis of the water intake immersed tube and is 466m away from the installation position of the first section of the water intake immersed tube; There are two submerged pits for the drainage immersed pipe. The first submerged pit for the drainage immersed pipe is set on the extension line of the installation axis of the drainage immersed pipe and is 774m away from the installation position of the first section of the drainage immersed pipe. The submerged pit of the pipe is set at the foundation groove of the immersed pipe at the head of the drain;
进行钢浮箱安装步骤时,起重船先就位,接着安装测量GPS和拉合千斤顶,再通过起重船安装钢浮箱;起重船就位时,起重船与半潜驳船同轴线地停在半潜驳船的船首并通过四角抛八字锚就位;安装测量GPS时,将测量GPS安放到测量塔的顶端,通过无线信号与起重船的电脑连接好,再利用起重船的小吊钩将测量塔吊放到沉管的预埋件上,通过法兰螺栓固定在预埋件上;沉管的中轴线的头尾端均要安装一座测量塔;通过两点成直线进行定位控制;拉合千斤顶安装在沉管头部的吊环上;安装钢浮箱时,钢浮箱放置于平板驳船上,平板驳船停靠在就位后的半潜驳船的一侧;起重船通过横向移船将钢浮箱从平板驳船起吊至半潜驳船上,再通过前后移船并借助半潜驳船上的卷扬机牵引将钢浮箱塞入沉管的每个孔道内;除了将钢浮箱塞在沉管的孔道内,还在第十四节取水沉管和第五十二节排水沉管的顶部加挂钢浮箱助浮,以解决吊装过程中的平衡问题,另外在第二节和第三节取水沉管、第一节至第四节、第八节、第十三节、第十八节、第二十二节、第二十七节、第三十二节、第三十七节、第四十二节、第五十九节和第六十节排水沉管的两侧外绑钢浮箱助浮,由于这些构件自重大,内塞钢浮箱助浮能力有限;即在半潜驳船及起重船在下潜坑就位后,由起重船将钢浮箱200吊放至沉管100的两侧并系好捆绑钢丝绳300(直径43mm),捆绑钢丝绳300在沉管100的两侧拉环101及钢浮箱200的外侧定位环201中为松弛设置;当沉管100下潜入水中后,钢浮箱200上浮,捆绑钢丝绳300自然拉紧,当钢浮箱200上浮至顶面与沉管100的顶面齐平后,半潜驳船暂停下潜,由操作人员将系于钢浮箱200的上部吊耳22上的细钢丝绳400(直径15mm)拉紧并将钢丝绳400端部系于沉管100的顶板中部预埋的拉环102上,让钢浮箱200紧靠于沉管100的侧壁上,防止钢浮箱200往两侧漂移(见图8a至图10b);之后半驳船继续下潜直至沉管的顶面没入水面1m;When installing the steel pontoon, the crane ship is in place first, then the measuring GPS and the pulling jack are installed, and then the steel pontoon is installed through the crane ship; when the crane ship is in place, the crane ship is coaxial with the semi-submersible barge Stop at the bow of the semi-submersible barge in line and place it in place through the four corners; when installing the measurement GPS, place the measurement GPS on the top of the measurement tower, connect it to the computer of the crane ship through wireless signals, and then use the crane ship to Lift the measuring tower onto the embedded part of the immersed tube with a small hook, and fix it on the embedded part through flange bolts; a measuring tower should be installed at the head and tail of the central axis of the immersed tube; Positioning control; the pulling jack is installed on the lifting ring at the head of the immersed tube; when the steel buoyancy box is installed, the steel buoyancy box is placed on the flat barge, and the flat barge is docked on the side of the semi-submersible barge after it is in place; the crane ship passes Move the ship horizontally to lift the steel buoy box from the flat barge to the semi-submersible barge, and then insert the steel buoy box into each channel of the immersed tube by moving the ship back and forth and pulling the hoist on the semi-submersible barge; It is plugged in the channel of the immersed tube, and steel buoyancy tanks are added to the top of the water intake immersed tube in the fourteenth section and the drainage immersed tube in the fifty-second section to help float to solve the balance problem during the hoisting process. In addition, in the second section And the third section of water intake pipe, the first section to the fourth section, the eighth section, the thirteenth section, the eighteenth section, the twenty-second section, the twenty-seventh section, the thirty-second section, the third section The two sides of the drainage immersed pipes in the seventeenth, forty-second, fifty-ninth and sixtieth sections are bound with steel buoyancy tanks to aid buoyancy. Due to the weight of these components, the inner buoyancy of the steel buoyancy tanks is limited; That is, after the semi-submersible barge and the crane ship are in place in the diving pit, the steel buoy box 200 is hoisted to both sides of the immersed tube 100 by the crane ship and the tied steel wire rope 300 (diameter 43 mm) is fastened. The pull rings 101 on both sides of the tube 100 and the outer positioning ring 201 of the steel buoyancy tank 200 are set loosely; when the immersed tube 100 dives into the water, the steel buoyancy tank 200 floats up, and the binding steel wire rope 300 is naturally tightened. When the steel buoyancy tank 200 After floating up until the top surface is flush with the top surface of the immersed tube 100, the semi-submersible barge suspends the dive, and the thin steel wire rope 400 (diameter 15mm) tied to the upper lug 22 of the steel buoyancy tank 200 is tightened by the operator and The end of the steel wire rope 400 is tied to the pull ring 102 pre-buried in the middle of the top plate of the immersed tube 100, so that the steel buoyant tank 200 is close to the side wall of the immersed tube 100, preventing the steel buoyant tank 200 from drifting to both sides (see Figure 8a to Fig. 10b); After that, the semi-barge continues to dive until the top surface of the immersed tube is submerged into the water surface by 1m;
进行半潜驳船下潜步骤时,是在钢浮箱安装完成后进行,先要进行下潜前的准备,包括扫海、选择下潜和吊运安装的时段;扫海即为在首节沉管安装前,安排测量船配置多波束测深仪对下潜坑区域及吊运路线进行扫海,绘制精确的等深线图;选择下潜和吊运安装时段即为收集历年潮位、气象资料,结合沉管吃水,下潜坑、吊运路线上水深,找出满足下潜、吊运水深要求的潮位时间段,以选择下潜、吊运、安装作业时间;半潜驳船注水下潜,当沉管的顶板的上表面略高于水面时,由起重船先向前移动船位,使起重船的扒杆从半潜驳船的首塔楼之间伸入半潜驳船体的沉管全长的1/2处,当起重船的主钩垂线与沉管的中心重合时停止移船,放下主钩,系挂吊缆,然后半潜驳船继续下潜,直到沉管的顶部浸入水面约1m时停止;When the semi-submersible barge dives, it is carried out after the installation of the steel buoyancy tank is completed, and the preparations before the dive must be carried out first, including sea sweeping, selection of diving and hoisting and installation periods; sea sweeping means sinking in the first section. Before the pipe installation, arrange the survey ship to be equipped with a multi-beam echo sounder to sweep the sea in the diving pit area and the lifting route, and draw an accurate contour map; the selection of the diving and lifting installation time is to collect the tidal level and meteorological data over the years , combined with the draft of the immersed tube, the water depth of the diving pit and the lifting route, find out the tide level time period that meets the requirements of the diving and lifting water depth, so as to select the time for diving, lifting, and installation operations; the semi-submersible barge dives with water, When the upper surface of the top plate of the immersed tube is slightly higher than the water surface, the lifting ship moves the position forward first, so that the lifting bar extends from between the bow towers of the semi-submerged barge into the entire immersed tube of the semi-submersible barge. At 1/2 of the length, when the vertical line of the main hook of the crane ship coincides with the center of the immersed tube, stop moving the ship, put down the main hook, hang the suspension cable, and then the semi-submersible barge continues to dive until the top of the immersed tube is immersed Stop when the water surface is about 1m;
进行沉管吊运步骤时,起重船将沉管吊离半潜驳船,在吊运过程中,保持沉管的顶面在水面以下1m,再收紧后锚移动船位,使拔杆退出半潜驳船,起重船移至安装位置时,抛锚收缆就位;随后半潜驳船排水上浮并收缆移出下潜坑,再移出航道位置,然后由拖轮拖回预制场码头,进行下节沉管上驳、运输和下潜;During the hoisting step of the immersed tube, the crane ship lifts the immersed tube away from the semi-submersible barge. During the hoisting process, keep the top surface of the immersed tube 1m below the water surface, and then tighten the anchor to move the ship position, so that the pulling rod is withdrawn from the semi-submersible barge. When the submersible barge and the crane ship move to the installation position, they drop the anchor and take up the cable in place; then the semi-submersible barge floats up with water, takes up the cable and moves out of the submerged pit, and then moves out of the channel position, and then is towed back to the prefabricated yard wharf by the tugboat for the lower section sinking tube loading, transport and submersion;
进行沉管定位步骤时,包括依次进行的起重船定位和沉管初定位;When carrying out the steps of positioning the immersed tube, it includes the positioning of the crane ship and the initial positioning of the immersed tube in sequence;
进行起重船定位时,起重船吊着沉管进入基槽范围后停船抛锚,参照前节沉管尾部预留的测量塔为对标标准,并通过收放缆绳移动船位,当起重船吊运沉管至离已安装的前节沉管10m时,停止移船并精确调整船位准备沉管安装;When positioning the crane ship, the crane ship hangs the immersed tube into the range of the foundation groove and then stops the ship and anchors. Refer to the measurement tower reserved at the end of the immersed tube in the previous section as the benchmarking standard, and move the position of the ship by retracting and releasing the cables. When the crane ship When the immersed tube is hoisted to 10m away from the installed front section immersed tube, stop moving the ship and precisely adjust the position of the ship to prepare for the installation of the immersed tube;
进行沉管初定位时,起重船的电脑通过无线信号接收沉管顶部的测量GPS的信号,将沉管的精确位置反映在定位软件上,由测量员指挥卷扬机操作工绞缆进行初定位,使沉管的轴线与安装轴线基本保持对齐,待沉管缓缓靠近并距离前节沉管约1m时,停止移船;When conducting the initial positioning of the immersed tube, the computer of the crane ship receives the GPS signal from the top of the immersed tube through wireless signals, and reflects the precise position of the immersed tube on the positioning software. The surveyor directs the winch operator to perform the initial positioning. Keep the axis of the immersed tube basically aligned with the installation axis, and stop moving the ship when the immersed tube is slowly approaching and about 1m away from the immersed tube of the front section;
进行沉管下沉对接步骤时,包括排水沉管水下对接和取水沉管水下对接;When performing the sinking and docking steps of the immersed tube, it includes the underwater docking of the drainage immersed tube and the underwater sinking tube of the water intake;
进行排水沉管水下对接时,先将待装排水沉管缓慢靠近前节排水沉管,此时保持待装排水沉管高于前节排水沉管1m,由于导向构件位于前节排水沉管左侧,在待装排水沉管前移过程中应稍偏于前节排水沉管的右侧,直至待装排水沉管距离前节排水沉管小于50cm时,再将待装排水沉管慢慢向左靠近导向构件直至与导向构件接触时停止向左移动,此时开始下放待装排水沉管至标高与前节排水沉管一致时停止下放,然后向前缓慢移动排水沉管直至与前节排水沉管靠紧,完成对接;When carrying out the underwater docking of the immersed drainage tube, the immersed drainage tube to be installed is slowly approached to the immersed drainage tube of the front section. On the left side, during the forward movement of the immersed drainage pipe to be installed, it should be slightly on the right side of the immersed drainage pipe of the front section. Slowly approach the guide member to the left until it touches the guide member and stop moving to the left. At this time, start to lower the drain sinking pipe to be installed until the elevation is the same as that of the front drain sinking pipe. The water-saving sinking pipe is close to complete the docking;
进行取水沉管水下对接时,对接水平方向及垂直方向位置均通过测量塔控制,若对接出现困难时,可通过潜水员水下观察、探摸,完成对接;对接时,先将待装取水沉管缓慢靠近前节取水沉管,直至距离前节取水沉管1m时,停止移动,再次调整待装取水沉管的轴线位置、标高与前节取水沉管一致,然后起重船向前移动船位,直至待装取水沉管与前节取水沉管靠紧,完成对接;When carrying out the underwater docking of the water intake immersed tube, the horizontal and vertical positions of the docking are controlled by the measuring tower. If the docking is difficult, the docking can be completed through underwater observation and exploration by divers; The pipe slowly approaches the immersed pipe for water intake at the front section until it is 1m away from the immersed pipe for water intake at the front section, then stops moving, adjusts the axis position and elevation of the immersed pipe to be installed to be consistent with the immersed pipe for water intake at the front section, and then moves the crane ship forward , until the water intake immersed tube to be installed is close to the water intake immersed tube of the front section, and the docking is completed;
进行拉合紧密步骤时,由潜水员下水进行沉管的拉合作业,拉合千斤顶通过钢丝绳、卸扣与前节沉管尾部吊点连接,连接完成后,工作船上油泵开始供油,千斤顶拉杆回收,沉管开始拉合,直至两节沉管接缝小于2cm停止拉合,由潜水员水下摄影取证,两节沉管拉合完成,最后,起重船松钩,接着由潜水员在水下拆除沉管吊点上的卸扣;When performing the pulling and tightening steps, divers are launched into the water to carry out the pulling and closing operation of the immersed tube. The pulling jack is connected to the lifting point at the tail of the immersed tube in the front section through a wire rope and a shackle. After the connection is completed, the oil pump on the workboat starts to supply oil, and the jack rod is recovered. , the immersed tube starts to pull together, and stops until the joint of the two immersed tubes is less than 2cm. The diver takes underwater photography to obtain evidence. The shackle on the lifting point of the immersed tube;
进行拆除钢浮箱步骤时,包括依次进行的钢浮箱注水下沉、拉出钢浮箱、钢浮箱出水和钢浮箱回收;When carrying out the step of removing the steel buoyant tank, it includes the water injection sinking of the steel buoyant tank, the pulling out of the steel buoyant tank, the water discharge of the steel buoyant tank and the recovery of the steel buoyant tank;
进行钢浮箱注水下沉时,为精确控制钢浮箱注水量,在钢浮箱制作时已在内腔内安装了泡沫,以确保钢浮箱在注满水后,其重力略大于其浮力即可。When sinking the steel pontoon with water injection, in order to accurately control the water injection volume of the steel pontoon, foam has been installed in the inner cavity during the manufacture of the steel pontoon to ensure that the gravity of the steel pontoon is slightly greater than its buoyancy after it is filled with water That's it.
进行拉出钢浮箱时,是在钢浮箱下沉至沉管的底板后,潜水员将起重船的抽芯锚缆绳通过卸扣与钢浮箱前部的上部吊耳连接,在水位较深段可在船头安装导向架,减小缆绳仰角,起重船间接性收紧缆绳试拉钢浮箱,若试拉过程中发现受阻,立即放松缆绳并后移船位,直至试拉时钢浮箱平顺移动,方可持续将钢浮箱拉出沉管;在钢浮箱前部的上部吊耳露出沉管时,用起重船吊住钢浮箱前部的上部吊耳继续拉出钢浮箱,在钢浮箱后部的上部吊耳露出沉管时,将钢浮箱放置在基床上并系挂钢浮箱后部的上部吊耳,起重船起吊钢浮箱并继续拉出钢浮箱,直至将钢浮箱全部拉出沉管。When pulling out the steel pontoon, after the steel pontoon sinks to the bottom plate of the immersed tube, the diver connects the core-pulling anchor cable of the crane ship to the upper lug at the front of the steel pontoon through a shackle. In the deep section, a guide frame can be installed at the bow to reduce the elevation angle of the cable. The crane ship indirectly tightens the cable to try to pull the steel buoy. Only when the buoyant tank moves smoothly can the steel buoyant tank be pulled out of the immersed tube; when the upper lugs at the front of the steel buoyant tank are exposed to the immersed tube, use a crane to hang the upper lugs at the front of the steel buoyant tank and continue to pull out Steel pontoon, when the upper lug at the rear of the steel pontoon exposes the immersed tube, place the steel pontoon on the foundation bed and tie the upper lug at the rear of the steel pontoon, the crane lifts the steel pontoon and continues to pull The steel buoyancy box is tapped until all the steel buoyancy boxes are pulled out of the immersed tube.
进行钢浮箱出水时,是在钢浮箱拉出沉管后,起重船下放吊钩,潜水员在水下进行换缆作业,将吊钩系挂在钢浮箱的四个上部吊耳上,并打开钢浮箱尾部的出水阀门排水,吊钩系缆完成后,起重船收紧吊缆,缓慢将钢浮箱吊出水面,由于此时钢浮箱处于重力略大于浮力的状态,因此在吊出水面时不会出现上跳情况;When the steel pontoon is out of the water, after the steel pontoon pulls out the immersed tube, the lifting hook is lowered by the crane, and the divers change the cable underwater, and the hook is hung on the four upper lugs of the steel pontoon. , and open the water outlet valve at the tail of the steel buoy to drain water. After the hook mooring is completed, the crane ship tightens the suspension cable and slowly lifts the steel buoy out of the water. Since the gravity of the steel buoy is slightly greater than the buoyancy at this time, Therefore, there will be no upward jump when lifting out of the water;
进行浮箱回收时,是在钢浮箱吊出水面并在钢浮箱排水完毕后,由起重船将钢浮箱放回水面,并关闭钢浮箱上的进、出水阀门,再将钢浮箱吊至平板驳船上存放,等待下一件沉管安装;When the buoyant tank is recovered, after the steel buoyant tank is hoisted out of the water and the steel buoyant tank is drained, the steel buoyant tank is put back to the water surface by the crane ship, and the water inlet and outlet valves on the steel buoyant tank are closed, and then the steel buoyant tank is put back into the water surface. The pontoon is hoisted to the flat barge for storage, waiting for the installation of the next immersed tube;
进行拆除测量塔、前节千斤顶和安装扣板步骤时,潜水员水下拆除岸侧一端的测量塔和前节沉管上的千斤顶并吊出水面,然后钢浮箱注水下沉并由起重船逐件拉出沉管,完成该节沉管的安装工作。该件沉管安装完成后,为保证沉管接缝不发生松动,不能立即拆除对拉装置,应待下一节沉管安装完成后再拆除,最后进行扣板安装。During the steps of dismantling the measuring tower, the front section jack and installing the buckle plate, the divers underwater remove the measuring tower at the shore side and the jack on the front section immersed tube and lift them out of the water, then the steel buoyancy tank is filled with water and sank by the lifting ship Pull out the immersed tube piece by piece to complete the installation of this section of immersed tube. After the installation of the immersed tube is completed, in order to ensure that the joints of the immersed tube do not loosen, the counter-tensioning device cannot be removed immediately. It should be removed after the installation of the next section of immersed tube is completed, and finally the gusset plate is installed.
安装取水管时,还要进行接缝注浆步骤,即通过压力泵将水泥浆通过两节沉管的接缝处预留的注浆管注入两节取水沉管的两圈止水带之间空隙中。When installing the water intake pipe, a joint grouting step is also required, that is, the cement slurry is injected through the grouting pipe reserved at the joint of the two immersed pipes through the pressure pump and injected between the two rings of water stops of the two immersed pipes in the void.
本发明的电厂海上取排水沉管的安装工艺采用的钢浮箱包括由前封板1、后封板2、顶板3、底板4和两侧板5、5’构成的横截面为矩形的封闭仓,其中,The steel buoyant tank adopted in the installation process of the offshore water intake and drainage sinking pipe of the power plant of the present invention includes a closed box with a rectangular cross section consisting of a front sealing plate 1, a rear sealing plate 2, a top plate 3, a bottom plate 4, and two side plates 5, 5′. warehouse, of which,
封闭仓的中部通过一块隔板20分为前仓10和后仓30;前仓10和后仓30的长度相同;封闭仓的总长度与单节取排水管的长度适配;封闭仓的横截面的长度和宽度分别小于单节取排水管的内孔的横截面的长度和宽度;The middle part of the closed warehouse is divided into the front warehouse 10 and the rear warehouse 30 by a partition plate 20; the length of the front warehouse 10 and the rear warehouse 30 is the same; The length and width of the section are respectively less than the length and width of the cross-section of the inner hole of the single-section intake and drainage pipe;
前封板1的上部并排地设有一个前仓通气阀11、两个前仓进水阀12一个后仓通气阀13和两个后仓进水阀14,该前封板1的下部并排地设置一个前仓出水阀15和一个后仓出水阀16;The top of the front cover plate 1 is provided with a front storehouse ventilation valve 11, two front storehouse water inlet valves 12, a rear storehouse breather valve 13 and two rear storehouse water inlet valves 14 side by side, and the lower part of the front cover plate 1 is arranged side by side. A front warehouse outlet valve 15 and a rear warehouse outlet valve 16 are provided;
后仓通气阀13通过一根后仓通气管130与后仓30连通;该后仓通气管130沿前仓10的长度方向水平设置并且它的内端头均穿过隔板20伸入后仓30;Rear storehouse ventilation valve 13 communicates with rear storehouse 30 through a back storehouse vent pipe 130; 30;
两个后仓进水阀14一一对应地通过两根后仓进水管140与后仓30连通;该两根后仓进水管140沿前仓10的长度方向水平设置并且它们的内端头均穿过隔板20伸入后仓30;The two rear warehouse water inlet valves 14 are communicated with the rear warehouse 30 through two rear warehouse water inlet pipes 140 in one-to-one correspondence; the two rear warehouse water inlet pipes 140 are horizontally arranged along the length direction of the front warehouse 10 and their inner ends are all Extend through the partition 20 into the rear compartment 30;
后仓出水阀16通过一根后仓出水管160与后仓30连通;该后仓出水管160沿前仓10的长度方向水平设置并且它们的内端头均穿过隔板20伸入后仓30;The rear warehouse outlet valve 16 communicates with the rear warehouse 30 through a rear warehouse outlet pipe 160; the rear warehouse outlet pipe 160 is horizontally arranged along the length direction of the front warehouse 10 and their inner ends all pass through the partition plate 20 and stretch into the rear warehouse 30;
为了便于吊装,在前封板1的上下端分别相对地设置一对端部吊耳21;并在顶板3上对应前仓10的中部两侧和后仓30的中部两侧分别相对地设置一个上部吊耳22;In order to facilitate hoisting, a pair of end lugs 21 are respectively arranged oppositely at the upper and lower ends of the front cover plate 1; upper lug 22;
为了便于运输,在底板4的前后部分别设置一对滚轮40。In order to facilitate transportation, a pair of rollers 40 are respectively provided at the front and rear of the bottom plate 4 .
以上实施例仅供说明本发明之用,而非对本发明的限制,有关技术领域的技术人员,在不脱离本发明的精神和范围的情况下,还可以作出各种变换或变型,因此所有等同的技术方案也应该属于本发明的范畴,应由各权利要求所限定。The above embodiments are only for the purpose of illustrating the present invention, rather than limiting the present invention. Those skilled in the relevant technical fields can also make various changes or modifications without departing from the spirit and scope of the present invention. Therefore, all equivalent The technical solutions should also belong to the category of the present invention and should be defined by each claim.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710135835.1A CN106677257B (en) | 2017-03-09 | 2017-03-09 | A kind of mounting process of power plant sea taking and discharging immersed tube |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710135835.1A CN106677257B (en) | 2017-03-09 | 2017-03-09 | A kind of mounting process of power plant sea taking and discharging immersed tube |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106677257A true CN106677257A (en) | 2017-05-17 |
| CN106677257B CN106677257B (en) | 2018-10-19 |
Family
ID=58828426
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710135835.1A Active CN106677257B (en) | 2017-03-09 | 2017-03-09 | A kind of mounting process of power plant sea taking and discharging immersed tube |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106677257B (en) |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107642106A (en) * | 2017-09-01 | 2018-01-30 | 中交第航务工程局有限公司 | A kind of ship method for arranging for immersed tube installation |
| CN113374935A (en) * | 2021-06-09 | 2021-09-10 | 安徽鲁班建设投资集团有限公司 | Construction method for underwater installation of water intake head of water plant by using ship-borne method |
| CN113700017A (en) * | 2021-08-31 | 2021-11-26 | 中交第四航务工程局有限公司 | Underwater stay cord positioning method and measuring and positioning method for underwater installation of immersed tube |
| CN113879487A (en) * | 2021-10-12 | 2022-01-04 | 中交第四航务工程局有限公司 | Non-self-floating immersed tube discharging method |
| CN114370230A (en) * | 2021-12-07 | 2022-04-19 | 上海市基础工程集团有限公司 | Pretreatment method for vertical jacking water taking and discharging pipe in rock stratum |
| CN115434368A (en) * | 2022-05-13 | 2022-12-06 | 华侨大学 | A cross-sea immersed tube construction technology |
| CN116290106A (en) * | 2023-02-16 | 2023-06-23 | 江苏省水利建设工程有限公司 | Underwater immersed tube system and construction method thereof |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU1656085A2 (en) * | 1989-02-15 | 1991-06-15 | Южный Государственный Проектно-Изыскательский Институт По Проектированию Объектов Сельскохозяйственного Водоснабжения И Обводнения Пастбищ | Floating water intake and clarifying apparatus |
| US20100065508A1 (en) * | 2008-09-17 | 2010-03-18 | Mark Hayes Bolan | Method and apparatus of submersible intake equipment |
| CN201512384U (en) * | 2009-10-27 | 2010-06-23 | 钟爱民 | Dedicated air bag for carrying heavy objects |
| CN201915442U (en) * | 2011-01-07 | 2011-08-03 | 广东省电力设计研究院 | Marine underwater assembled water intake |
| CN202403938U (en) * | 2011-07-20 | 2012-08-29 | 北京尚洋东方环境科技股份有限公司 | Multifunctional automatic floating-sinking water taking device |
| CN103806409A (en) * | 2014-02-13 | 2014-05-21 | 中交第四航务工程局有限公司 | Milling forming system of gravity wharf foundation bed and construction method for gravity wharf structure |
| CN205076011U (en) * | 2015-10-30 | 2016-03-09 | 青岛海西重机有限责任公司 | Combination flotation tank formula sea worker's platform launching gear |
-
2017
- 2017-03-09 CN CN201710135835.1A patent/CN106677257B/en active Active
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU1656085A2 (en) * | 1989-02-15 | 1991-06-15 | Южный Государственный Проектно-Изыскательский Институт По Проектированию Объектов Сельскохозяйственного Водоснабжения И Обводнения Пастбищ | Floating water intake and clarifying apparatus |
| US20100065508A1 (en) * | 2008-09-17 | 2010-03-18 | Mark Hayes Bolan | Method and apparatus of submersible intake equipment |
| CN201512384U (en) * | 2009-10-27 | 2010-06-23 | 钟爱民 | Dedicated air bag for carrying heavy objects |
| CN201915442U (en) * | 2011-01-07 | 2011-08-03 | 广东省电力设计研究院 | Marine underwater assembled water intake |
| CN202403938U (en) * | 2011-07-20 | 2012-08-29 | 北京尚洋东方环境科技股份有限公司 | Multifunctional automatic floating-sinking water taking device |
| CN103806409A (en) * | 2014-02-13 | 2014-05-21 | 中交第四航务工程局有限公司 | Milling forming system of gravity wharf foundation bed and construction method for gravity wharf structure |
| CN205076011U (en) * | 2015-10-30 | 2016-03-09 | 青岛海西重机有限责任公司 | Combination flotation tank formula sea worker's platform launching gear |
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107642106A (en) * | 2017-09-01 | 2018-01-30 | 中交第航务工程局有限公司 | A kind of ship method for arranging for immersed tube installation |
| CN113374935A (en) * | 2021-06-09 | 2021-09-10 | 安徽鲁班建设投资集团有限公司 | Construction method for underwater installation of water intake head of water plant by using ship-borne method |
| CN113700017A (en) * | 2021-08-31 | 2021-11-26 | 中交第四航务工程局有限公司 | Underwater stay cord positioning method and measuring and positioning method for underwater installation of immersed tube |
| CN113700017B (en) * | 2021-08-31 | 2023-02-03 | 中交第四航务工程局有限公司 | Underwater stay cord positioning method and measuring and positioning method for underwater installation of immersed tube |
| CN113879487A (en) * | 2021-10-12 | 2022-01-04 | 中交第四航务工程局有限公司 | Non-self-floating immersed tube discharging method |
| CN113879487B (en) * | 2021-10-12 | 2023-02-24 | 中交第四航务工程局有限公司 | Unloading method of non-self-floating sinking tube |
| CN114370230A (en) * | 2021-12-07 | 2022-04-19 | 上海市基础工程集团有限公司 | Pretreatment method for vertical jacking water taking and discharging pipe in rock stratum |
| CN115434368A (en) * | 2022-05-13 | 2022-12-06 | 华侨大学 | A cross-sea immersed tube construction technology |
| CN116290106A (en) * | 2023-02-16 | 2023-06-23 | 江苏省水利建设工程有限公司 | Underwater immersed tube system and construction method thereof |
Also Published As
| Publication number | Publication date |
|---|---|
| CN106677257B (en) | 2018-10-19 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106677257B (en) | A kind of mounting process of power plant sea taking and discharging immersed tube | |
| US6244785B1 (en) | Precast, modular spar system | |
| CN106677258B (en) | A kind of installation technology of offshore water intake caisson in power plant | |
| CN103046553B (en) | Method for carrying out deepwater laying on large-volume reinforced mud-filling tubular bags by using geotextiles-laying vessels | |
| WO1998021415A9 (en) | Precast, modular spar system | |
| CN110295648B (en) | A facility for taking water from a rapid riverbed and its overall installation and construction method | |
| CN112728212B (en) | Offshore immersed pipe of sewage sea area discharge pipe and underwater installation construction method | |
| CN102837804A (en) | Installation equipment and installation method for suction anchor in deep water | |
| CN110607797A (en) | Underwater construction method for water taking head | |
| CN109024525B (en) | An artificial island structure considering the development and utilization of underground space and its construction method | |
| CN103803036B (en) | Large ship utilizes the technique of water under air bag | |
| CN103603364A (en) | Deepwater suction-type gravity foundation and deepwater mounting device and deepwater mounting method thereof | |
| JP4570592B2 (en) | Towing self-sinking anchor block and method of collecting mooring lines attached to it | |
| CN106522275A (en) | Construction process for shipping large sinking pipes by self-propelled semi-submerged ship | |
| JP3551180B2 (en) | Method and apparatus for dissolving water-soluble gas in the sea and isolating it in the deep sea, and laying method | |
| CN111350208A (en) | A method for prefabricating pipe sections of immersed tunnels | |
| CN115434368A (en) | A cross-sea immersed tube construction technology | |
| CN112779967B (en) | Construction method for sea-land connecting section of sewage sea area discharge pipe | |
| CN104164885A (en) | Caisson towing method | |
| CN115929990B (en) | Method for installing submarine pipeline in deep sea section | |
| CN203583509U (en) | Deepwater suction type gravity foundation and deepwater mounting device thereof | |
| CN102704502A (en) | Offshore submerged box type foundation structure and construction method thereof | |
| CN217272346U (en) | Cross river canal and lift by crane launching gear | |
| CN214776446U (en) | Tension leg type shallow sea rock-soil exploration mobile platform | |
| CN111005400A (en) | Equipment and method capable of performing migration and prefabrication of offshore wind power barrel type foundation |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CP01 | Change in the name or title of a patent holder | ||
| CP01 | Change in the name or title of a patent holder |
Address after: 200032 No. 139, Xuhui District, Shanghai, Pingjiang Road Patentee after: CCCC THIRD HARBOR ENGINEERING Co.,Ltd. Patentee after: CCCC Third Aviation Bureau Sixth Engineering (Xiamen) Co.,Ltd. Patentee after: XIAMEN BRANCH OF CCCC THIRD HARBOR ENGINEERING Co.,Ltd. Address before: 200032 No. 139, Xuhui District, Shanghai, Pingjiang Road Patentee before: CCCC THIRD HARBOR ENGINEERING Co.,Ltd. Patentee before: CCCC Sanya (Xiamen) Engineering Co.,Ltd. Patentee before: XIAMEN BRANCH OF CCCC THIRD HARBOR ENGINEERING Co.,Ltd. |