CN106677209A - Intelligent comprehensive pre-fabricating pipe gallery and construction technique thereof - Google Patents

Intelligent comprehensive pre-fabricating pipe gallery and construction technique thereof Download PDF

Info

Publication number
CN106677209A
CN106677209A CN201710034738.3A CN201710034738A CN106677209A CN 106677209 A CN106677209 A CN 106677209A CN 201710034738 A CN201710034738 A CN 201710034738A CN 106677209 A CN106677209 A CN 106677209A
Authority
CN
China
Prior art keywords
construction
prefabricating square
piping lane
intelligent comprehensive
culverts
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710034738.3A
Other languages
Chinese (zh)
Inventor
杨新梅
王卫灯
李玉玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Guolong Industrial Co Ltd
Original Assignee
Henan Guolong Industrial Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Guolong Industrial Co Ltd filed Critical Henan Guolong Industrial Co Ltd
Priority to CN201710034738.3A priority Critical patent/CN106677209A/en
Publication of CN106677209A publication Critical patent/CN106677209A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

The invention provides an intelligent comprehensive pre-fabricating pipe gallery and a construction technique thereof and relates to the technical field of municipal infrastructure building. The intelligent comprehensive pre-fabricating pipe gallery comprises a plurality of pipe-shaped pre-fabricating square culverts; connecting holes are formed in the inner walls of the pre-fabricating square culverts in the axial directions of the pre-fabricating square culverts, the multiple pre-fabricating square culverts are sequentially connected and correspond to the connecting holes one to one; and connecting pieces are installed in the connecting holes in a penetrating mode, and the multiple pre-fabricating square culverts are tightly attached in sequence through the connecting pieces. The technical problem that through a cast-in-place type pipe gallery, the construction quality is difficult to control due to limiting of the conditions such as the construction on-site environment and climate is solved, and the technical effects that rainwater leakage is effectively avoided, the construction quality is guaranteed, the construction environment is improved, the construction period is shortened, the influences of construction on city transportation and surrounding resident lives are reduced are achieved.

Description

The prefabricated piping lane of intelligent comprehensive and its construction technology
Technical field
The present invention relates to civilian infrastructure construction technique field, more particularly, to a kind of prefabricated piping lane of intelligent comprehensive and its Construction technology.
Background technology
City Buried Pipeline is the important infrastructure and " life line " for ensureing city operations.In recent years, as city is fast Speed development, underground utilities are increasingly complicated or even deep-rooted, formed " underground noodles problem ", and pipe network facilities increase or keep in repair, The pipe first-aids such as communication, water supply, coal gas cause urban pavement constantly to excavate and fill as slide fastener, have had a strong impact on the people The daily life and city operations order of the masses.
Now someone have developed cast-type underground pipe gallery, by municipal administration, electric power, communication, combustion gas, water supply, middle water, draining, heat The various pipelines such as power are integrated in one, and solve the situation that the old pipe of maintenance, the row of applying newly manage continuous excavated pavement, but cast-type underground Piping lane is limited by conditions such as job site natural environment and climates, and construction quality is difficult to control to.
In view of this, it is special to propose the present invention.
The content of the invention
An object of the present invention is to provide a kind of intelligent comprehensive prefabricated piping lane, to solve prior art in using cast-in-place Formula underground pipe gallery, is limited by conditions such as job site natural environment and climates, the unmanageable technical problem of construction quality.
The prefabricated piping lane of intelligent comprehensive that the present invention is provided, it is characterised in that described including multiple prefabricating square culverts in a tubular form The inwall of prefabricating square culvert is provided with connecting hole, and the connecting hole is axially arranged along the prefabricating square culvert, multiple prefabricated sides Culvert is sequentially connected, and the connecting hole is corresponded, and connector is equipped with the connecting hole, and the connector makes multiple described Prefabricating square culvert is brought into close contact successively.
Further, it is provided with sealing rod between the adjacent prefabricating square culvert.
Further, the end of one end of the prefabricating square culvert is provided with positioning convex, the other end of the prefabricating square culvert End be provided with detent, the positioning convex matches with the detent.
Further, installing hole is provided with the inwall of the prefabricating square culvert, on the installing hole cable bearer is provided with.
Further, the connector is PC rods.
The second object of the present invention there are provided a kind of construction technology of the prefabricated piping lane of intelligent comprehensive, to solve existing skill Cast-type underground pipe gallery is adopted in art, is limited by conditions such as job site natural environment and climates, the unmanageable skill of construction quality Art problem.
The construction technology of the prefabricated piping lane of intelligent comprehensive that the present invention is provided comprises the steps:By multiple prefabricating square culverts successively Connection, and the connecting hole of multiple prefabricating square culverts is corresponded, connector is arranged in successively the connecting hole of multiple prefabricating square culverts In, tensioning connector makes multiple prefabricating square culverts be brought into close contact successively, that is, make the prefabricated piping lane of intelligent comprehensive.
Further, the construction technology of the prefabricated piping lane of the intelligent comprehensive also includes water-proof treatment technology, at the waterproof Science and engineering skill is arranged at before multiple prefabricating square culverts are sequentially connected, and the water-proof treatment technology is to arrange sealing in the end of prefabricating square culvert Bar.
Further, the construction technology of the prefabricated piping lane of the intelligent comprehensive also includes construction pre-treating technology, the construction Pre-treating technology is to carry out sanding process at the construction field (site).
Further, the construction technology of the prefabricated piping lane of the intelligent comprehensive also includes joint filling handling process, at the joint filling Science and engineering skill is arranged at after being brought into close contact successively between the prefabricating square culvert, to prevent the seam crossing between contiguous prefabricated Fang Han from oozing Water.
Further, the construction technology of the prefabricated piping lane of the intelligent comprehensive also includes joint treatment technique, the seam crossing Science and engineering skill is arranged at after joint treatment technique, so that construction road surface recovers current.
The prefabricated piping lane of intelligent comprehensive that the present invention is provided, by being sequentially connected using prefabricating square culvert in a tubular form, by electricity Various municipal pipelines such as power, communication, water supply, combustion gas are concentrated in together, and accomplish the comprehensive utilization and resource-sharing of the underground space, are kept away Exempt from urban pavement constantly to excavate and fill;Connecting hole is respectively provided with by the inwall in multiple prefabricating square culverts, and it is multiple prefabricated The connecting hole of Fang Han is corresponded so that connector can sequentially pass through the connecting hole of multiple prefabricating square culverts, to be connected by tensioning Multiple prefabricating square culverts that make of fitting are brought into close contact successively, effectively prevent the seepage of rainwater, it is ensured that construction quality, improve and apply The construction environment of workman person, shortens the construction period, reduces the impact to construct road pavement traffic and nearby residents life.
The construction technology of the prefabricated piping lane of intelligent comprehensive that the present invention is provided, at the construction field (site), only need to be by multiple prefabricating square culverts It is sequentially connected, and is tensioned successively to be brought into close contact multiple prefabricating square culverts by connector, you can complete construction, saves a large amount of Engineering time and expense, and effectively reduce construction noise, the impact to nearby residents life is reduced, simultaneously because prefabricated Fang Han is completed in factory, without the need for cast in situs, for the weather and environment of job site is without particular/special requirement, and its construction Quality is more reliable.In addition, the construction technology of the prefabricated piping lane of intelligent comprehensive of present invention offer, improves the work of workmen Environment, its difficulty of construction is lower, and safety coefficient is higher, can be prevented effectively from the generation of construction safety accident.
Description of the drawings
In order to be illustrated more clearly that the specific embodiment of the invention or technical scheme of the prior art, below will be to concrete The accompanying drawing to be used needed for embodiment or description of the prior art is briefly described, it should be apparent that, in describing below Accompanying drawing is some embodiments of the present invention, for those of ordinary skill in the art, before creative work is not paid Put, can be with according to these other accompanying drawings of accompanying drawings acquisition.
Fig. 1 is the structural representation of the prefabricated piping lane of intelligent comprehensive that the embodiment of the present invention 1 is provided;
Fig. 2 is the structural representation of the single storehouse prefabricating square culvert shown in Fig. 1;
Fig. 3 is the structural representation of another angle in single storehouse prefabricating square culvert shown in Fig. 1;
The structure of double storehouse prefabricating square culverts that Fig. 4 is adopted by the prefabricated piping lane of intelligent comprehensive that the embodiment of the present invention 2 is provided is shown It is intended to;
Fig. 5 is the structural representation of double storehouse prefabricating square culverts another angle shown in Fig. 4;
Fig. 6 is the flow chart of the construction method of the prefabricated piping lane of intelligent comprehensive that the embodiment of the present invention 3 is provided.
Icon:The mono- storehouse prefabricating square culverts of 100-;The mono- storehouse connecting holes of 101-;The mono- storehouse positioning convex of 102-;The mono- storehouse positioning of 103- is recessed Groove;The mono- storehouse cable beareves of 104-;The double storehouse prefabricating square culverts of 200-;The double storehouse connecting holes of 201-;The double storehouse positioning convex of 202-;The double storehouses of 203- Detent;The double storehouse cable beareves of 204-.
Specific embodiment
Technical scheme is clearly and completely described below in conjunction with accompanying drawing, it is clear that described enforcement Example is a part of embodiment of the invention, rather than the embodiment of whole.Based on the embodiment in the present invention, ordinary skill The every other embodiment that personnel are obtained under the premise of creative work is not made, belongs to the scope of protection of the invention.
In describing the invention, it should be noted that term " " center ", " on ", D score, "left", "right", " vertical ", The orientation or position relationship of the instruction such as " level ", " interior ", " outward " be based on orientation shown in the drawings or position relationship, merely to Be easy to description the present invention and simplify description, rather than indicate or imply indication device or element must have specific orientation, With specific azimuth configuration and operation, therefore it is not considered as limiting the invention.Additionally, term " first ", " second ", " the 3rd " is only used for describing purpose, and it is not intended that indicating or implying relative importance.
In describing the invention, it should be noted that unless otherwise clearly defined and limited, term " installation ", " phase Company ", " connection " should be interpreted broadly, for example, it may be being fixedly connected, or being detachably connected, or be integrally connected;Can Being to be mechanically connected, or electrically connect;Can be joined directly together, it is also possible to be indirectly connected to by intermediary, Ke Yishi The connection of two element internals.For the ordinary skill in the art, with concrete condition above-mentioned term can be understood at this Concrete meaning in invention.
City Buried Pipeline is the important infrastructure and " life line " for ensureing city operations, with rapid urban, Underground pipeline construction scale is not enough, highlights the problems such as management level are not high, and some cities occur heavy rain waterlogging, pipeline leakage in succession Blast, road surface such as are subsided at the event, life property safety of people and city operations order have been had a strong impact on, for this reason, it may be necessary to unite Underground pipeline construction is raised, under urban pavement pipe gallery is built, to ensure life property safety of people, safeguard city Running order.
Cast-type being adopted the pipe gallery under urban pavement now, i.e. one-time cast-forming at the construction field (site), due to existing more The restriction of construction environment and weather so that vibrating for pouring type pipe gallery or conserves not good at leakiness, causes to seep water and leaks Water phenomenon is serious.In addition, cast-type pipe gallery also needs to formwork cast at the construction field (site), fluting area is big, and required operation is more, Construction period is long, and field management difficulty is big, has had a strong impact on the orthobiosiss of urban transportation and surrounding resident.
Therefore, the technology that developing a kind of prefabricated piping lane of novel intelligent composite becomes those skilled in the art's urgent need to resolve is asked Topic.
The prefabricated piping lane of intelligent comprehensive provided by the present invention is described further with reference to embodiment.
Embodiment 1
Fig. 1 is the structural representation of the prefabricated piping lane of intelligent comprehensive that the embodiment of the present invention 1 is provided;Fig. 2 is the list shown in Fig. 1 The structural representation of storehouse prefabricating square culvert;Fig. 3 is the structural representation of another angle in single storehouse prefabricating square culvert shown in Fig. 1;As schemed Shown in 1-3, the prefabricated piping lane of intelligent comprehensive that the embodiment of the present invention 1 is provided, including multiple single storehouse prefabricating square culverts 100 in a tubular form, Single storehouse connecting hole 101, axle of single storehouse connecting hole 101 along single storehouse prefabricating square culvert 100 are provided with the inwall of single storehouse prefabricating square culvert 100 To setting, multiple single storehouse prefabricating square culverts 100 are sequentially connected, and single storehouse connecting hole 101 is corresponded, and is worn in single storehouse connecting hole 101 Connector (not shown) is provided with, connector makes multiple single storehouse prefabricating square culverts 100 be brought into close contact successively.
The prefabricated piping lane of intelligent comprehensive that the present invention is provided, by being sequentially connected using single storehouse prefabricating square culvert 100 in a tubular form, So that various municipal pipelines such as electric power, communication, water supply, combustion gas to be concentrated in together, accomplish comprehensive utilization and the resource of the underground space It is shared, it is to avoid urban pavement is constantly excavated and filled;Single storehouse connection is arranged by the inwall in multiple single storehouse prefabricating square culverts 100 Hole 101, and single storehouse connecting hole 101 of multiple single storehouse prefabricating square culverts 100 corresponds so that connector can be arranged in successively many In single storehouse connecting hole 101 of individual single storehouse prefabricating square culvert 100, it is logical can cross tensioning connector make multiple single storehouse prefabricating square culverts 100 according to It is secondary to be brought into close contact, effectively prevent the seepage of rainwater, it is ensured that construction quality, the construction environment of workmen is improved, shorten Construction period, reduce the impact to construct road pavement traffic and nearby residents life.
It should be noted that the single storehouse prefabricating square culvert 100 provided in the present invention can respectively set in the diverse location of inwall Multiple single storehouse connecting holes 101 are put, so that the inwall of single storehouse prefabricating square culvert 100 can wear multiple connectors, to increase connection The tensile force of part so that the connection between multiple single storehouse prefabricating square culverts 100 is more closely more stable.
In order to further enhance the percolation-proof effect of the prefabricated piping lane of intelligent comprehensive provided in an embodiment of the present invention, in the present invention A kind of preferred implementation in, be provided with sealing rod between adjacent single storehouse prefabricating square culvert 100.
In embodiments of the present invention, sealing rod is a kind of adhesive tape of water-swellable, and it can utilize the viscosity of itself, directly It is pasted onto the end of single storehouse prefabricating square culvert 100, meets after water volumetric expansion to block the sky between adjacent single storehouse prefabricating square culvert 100 Gap, so as to Seepage occurs in the seam crossing for avoiding the quality inspection of adjacent single storehouse prefabricating square culvert 100, so that the embodiment of the present invention is provided The prefabricated piping lane of intelligent comprehensive antiseep it is better.
As shown in Figures 2 and 3, the end of one end of single storehouse prefabricating square culvert 100 provided in an embodiment of the present invention is provided with list Storehouse positioning convex 102, the end of the other end is provided with single storehouse detent 103, single storehouse positioning convex 102 and single storehouse detent 103 match.
In order that the even closer laminating of adjacent single storehouse prefabricating square culvert 100 connection, the embodiment of the present invention is prefabricated in single storehouse Contain 100 two ends and be respectively provided with single storehouse positioning convex 102 (bellmouth) and single storehouse detent 103 (interface) in side so that be adjacent What is connected between single storehouse prefabricating square culvert 100 more consolidates, it is to avoid event of subsiding, and affects traffic and the running order in city.
As Figure 1-3, the inwall of single storehouse prefabricating square culvert 100 provided in an embodiment of the present invention is provided with single storehouse installing hole (not shown), is provided with single storehouse cable bearer 104 on single storehouse installing hole.
The prefabricated piping lane of intelligent comprehensive provided in an embodiment of the present invention is used to accommodating various underground utilities, including electric power, communication, Water supply, combustion gas etc., various pipelines are concentrated in together and are easily caused maintenance difficulty, and the embodiment of the present invention is in single storehouse prefabricating square culvert 100 Inwall single storehouse installing hole is set, single storehouse cable bearer 104 is provided with single storehouse installing hole, so that different pipelines can By different single held separates of storehouse cable bearer 104, it is easy to engineering staff to overhaul, in the side of being preferable to carry out of the embodiment of the present invention In formula, the quantity of single storehouse installing hole and single storehouse cable bearer 104 is multiple, still there is corresponding after increasing in order to later stage pipeline Single storehouse cable bearer 104 carries out the erection of newly-increased pipeline.
In embodiments of the present invention, connector is PC rods.
PC rods are that, with Merlon as main component, the one kind being prepared from using coextrusion techniques CO-EXTRUSION is high Quality bar.Because its surface covers a floor height concentration UV absorbent, in addition to having anti-ultraviolet characteristic and can keep It is permanent weather-proof, it is will never fade.PC rods can effectively prevent water seepage;PC rods also have good mechanical performance, shock resistance And weather resistance, it can keep physical properties index to stablize in the range of -40 DEG C to 120 DEG C, and when being heated Remain dimensionally-stable.
The embodiment of the present invention using PC rods by being used as connector so that the antiseep effect of the prefabricated piping lane of intelligent comprehensive is more It is good.
Embodiment 2
The embodiment of the present invention is the improvement on the basis of embodiment 1, and the technical scheme of the description of embodiment 1 falls within this enforcement Example, will not be described here.The present embodiment is with the difference of embodiment 1, the prefabricated piping lane of intelligent comprehensive that embodiment 1 is provided It is made up of single storehouse prefabricating square culvert, the prefabricated piping lane of intelligent comprehensive that the present embodiment is provided is made up of double storehouse prefabricating square culverts, and Fig. 4 is this The structural representation of double storehouse prefabricating square culverts that the prefabricated piping lane of intelligent comprehensive that bright embodiment 2 is provided is adopted;Fig. 5 is Fig. 4 The structural representation of shown pair of storehouse prefabricating square culvert another angle;As shown in Figure 4 and Figure 5, double storehouse prefabricating square culverts 200 are by two lists Storehouse prefabricating square culvert 100 is formed by connecting side by side, in order to save construction technology, contains the double storehouses of mould preparation by double storehouse sides in factory prefabricated Side contains 200, to reduce the difficulty of construction of job site.
By arranging double storehouses prefabricating square culverts 200 so that the prefabricated piping lane of intelligent comprehensive provided in an embodiment of the present invention can hold Receive more underground utilities, make the layout of underground utilities more reasonable.
As shown in Figure 4 and Figure 5, the embodiment of the present invention provides intelligent comprehensive double storehouse prefabricating square culverts that prefabricated piping lane is adopted The diverse location of 200 inwall is evenly equipped with multiple pairs of storehouse connecting holes 201, in order to multiple connectors are arranged in respectively into multiple setting In being placed in double storehouse connecting holes 201 of diverse location, to cause multiple pairs of storehouse prefabricating square culverts 200 tight successively by being tensioned connector Laminating.
As shown in Figure 4 and Figure 5, the end of one end of double storehouse prefabricating square culverts 200 is provided with double storehouses positioning convex 202, another The end at end is provided with double storehouses detent 203, and double storehouse positioning convex 202 match with double storehouse detents 203, in order to phase The even closer laminating of connection between adjacent double storehouses prefabricating square culvert 200.
In embodiments of the present invention, double storehouses installing hole is provided with the inwall of double storehouse prefabricating square culverts 200, on double storehouse installing holes Double storehouses cable bearer 204 is provided with, the effect of double storehouse cable beareves 204 will not be described here with list storehouse cable bearer 104.
In embodiments of the present invention, double storehouse prefabricating square culverts 200 are when being sequentially connected, between adjacent pair of storehouse prefabricating square culvert 200 Sealing rod is also equipped with, to avoid rain leakage from entering inside prefabricating square culvert, underground utilities is caused to damage.In the present embodiment The sealing rod that sealing rod is provided with embodiment 1, will not be described here.
It should be noted that for the ease of transport and hoisting large-size prefabricating square culvert, can also be by prefabricating square culvert prepared composition The first prefabricating square culvert body and the second prefabricating square culvert body of body formula structure, it is again that the first prefabricating square culvert body and second is pre- at the construction field (site) Fang Hanti assemblings processed are made after prefabricating square culvert, then prepare the prefabricated piping lane of intelligent comprehensive by being sequentially connected large scale prefabricated Fang Han. In addition, according to the requirement of job site environment and underground utilities, can also be many using three storehouse prefabricating square culverts, four storehouse prefabricating square culverts etc. Storehouse prefabricating square culvert prepares the prefabricated piping lane of intelligent comprehensive, to meet the needs of urban transportation and running order.
Embodiment 3
Fig. 6 is the flow chart of the construction method of the prefabricated piping lane of intelligent comprehensive that the embodiment of the present invention 3 is provided, as shown in fig. 6, The construction technology of the prefabricated anti-piping lane of Urban Underground that above-described embodiment 1 and embodiment 2 are provided is present embodiments provided, including it is as follows Step:Multiple prefabricating square culverts are sequentially connected, and correspond the connecting hole of multiple prefabricating square culverts, connector is worn successively In multiple connecting holes, tensioning connector makes multiple prefabricating square culverts be brought into close contact successively, that is, make the prefabricated piping lane of intelligent comprehensive.
The construction technology of the prefabricated piping lane of intelligent comprehensive that the present invention is provided, at the construction field (site), only need to be by multiple prefabricating square culverts It is sequentially connected, and multiple prefabricating square culverts is brought into close contact successively by being tensioned connector, you can completes construction, save substantial amounts of Engineering time and expense, and construction noise is effectively reduced, the impact to nearby residents life is reduced, simultaneously because prefabricated side Culvert is completed in factory, without the need for cast in situs, for the weather and environment of job site is without particular/special requirement, and its construction matter Amount is more reliable.In addition, the construction technology of the prefabricated piping lane of intelligent comprehensive of present invention offer, improves the building ring of workmen Border, its difficulty of construction is lower, and safety coefficient is higher, can be prevented effectively from the generation of construction safety accident.
In the construction technology of the prefabricated piping lane of intelligent comprehensive provided in an embodiment of the present invention, prefabricating square culvert is being put into into construction Before scene, scene needs to carry out sanding process, so that construction site is more smooth clean and tidy, it is to avoid collapse phenomenon occur, protect The construction quality of the prefabricated piping lane of card intelligent comprehensive.
After sanding, after by hoisting machine are placed on construction ground multiple prefabricating square culverts, paste in the end of prefabricating square culvert If sealing rod, then the end of multiple prefabricating square culverts is sequentially connected, and is tensioned connector so that be tight successively to individual prefabricating square culvert Closely connected conjunction, to avoid the occurrence of water-impervious phenomenon.
After again multiple prefabricating square culverts are closely connected, in addition it is also necessary to carry out joint filling handling process, will be adjacent by grouting method Seam crossing between prefabricating square culvert is filled and led up, to further enhance percolation-proof effect.
After joint treatment, also need to carry out backfill handling process, the state to construction is recovered in job site, it is ensured that road What face traffic and nearby residents were lived is normally carried out.
The construction technology of the prefabricated piping lane of intelligent comprehensive provided in an embodiment of the present invention, construction quality is more reliable, construction method It is more simple and convenient, can shorten construction period, reduce the impact to nearby residents life of constructing, recover faster urban transportation and Running order.
Finally it should be noted that:Various embodiments above only to illustrate technical scheme, rather than a limitation;To the greatest extent Pipe has been described in detail with reference to foregoing embodiments to the present invention, it will be understood by those within the art that:Its according to So the technical scheme described in foregoing embodiments can be modified, either which part or all technical characteristic are entered Row equivalent;And these modifications or replacement, do not make the essence disengaging various embodiments of the present invention technology of appropriate technical solution The scope of scheme.

Claims (10)

1. the prefabricated piping lane of a kind of intelligent comprehensive, it is characterised in that including multiple prefabricating square culverts in a tubular form, the prefabricating square culvert Inwall is provided with connecting hole, and the connecting hole is axially arranged along the prefabricating square culvert, and multiple prefabricating square culverts are sequentially connected, And the connecting hole is corresponded, be equipped with connector in the connecting hole, the connector make multiple prefabricating square culverts according to It is secondary to be brought into close contact.
2. the prefabricated piping lane of intelligent comprehensive according to claim 1, it is characterised in that arrange between the adjacent prefabricating square culvert There is sealing rod.
3. the prefabricated piping lane of intelligent comprehensive according to claim 1, it is characterised in that the end of one end of the prefabricating square culvert Positioning convex is provided with, the end of the other end of the prefabricating square culvert is provided with detent, and the positioning convex is fixed with described Position groove match.
4. the prefabricated piping lane of intelligent comprehensive according to claim 1, it is characterised in that arrange on the inwall of the prefabricating square culvert There is installing hole, on the installing hole cable bearer is provided with.
5. the prefabricated piping lane of intelligent comprehensive according to claim 1, it is characterised in that the connector is PC rods.
6. the construction technology of the prefabricated piping lane of intelligent comprehensive according to any one of claim 1-5, it is characterised in that include as Lower step:Multiple prefabricating square culverts are sequentially connected, and correspond the connecting hole of multiple prefabricating square culverts, connector is worn successively In the connecting hole of multiple prefabricating square culverts, tensioning connector makes multiple prefabricating square culverts be brought into close contact successively, that is, make intelligence comprehensive Close prefabricated piping lane.
7. the construction technology of the prefabricated piping lane of intelligent comprehensive according to claim 6, it is characterised in that also including water-proofing treatment Technique, the water-proof treatment technology is arranged at before multiple prefabricating square culverts are sequentially connected, and the water-proof treatment technology is in prefabricated side The end of culvert arranges sealing rod.
8. the construction technology of the prefabricated piping lane of intelligent comprehensive according to claim 6, it is characterised in that also including place before construction Science and engineering skill, the construction pre-treating technology is to carry out sanding process at the construction field (site).
9. the construction technology of the prefabricated piping lane of intelligent comprehensive according to claim 6, it is characterised in that also process including joint filling Technique, the joint filling handling process is arranged at after being brought into close contact successively between the prefabricating square culvert, to prevent contiguous prefabricated side Seam crossing infiltration between culvert.
10. the construction technology of the prefabricated piping lane of intelligent comprehensive according to claim 9, it is characterised in that at also including backfill Science and engineering skill, the backfill handling process is arranged at after joint treatment technique, so that construction road surface recovers current.
CN201710034738.3A 2017-01-18 2017-01-18 Intelligent comprehensive pre-fabricating pipe gallery and construction technique thereof Pending CN106677209A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710034738.3A CN106677209A (en) 2017-01-18 2017-01-18 Intelligent comprehensive pre-fabricating pipe gallery and construction technique thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710034738.3A CN106677209A (en) 2017-01-18 2017-01-18 Intelligent comprehensive pre-fabricating pipe gallery and construction technique thereof

Publications (1)

Publication Number Publication Date
CN106677209A true CN106677209A (en) 2017-05-17

Family

ID=58859243

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710034738.3A Pending CN106677209A (en) 2017-01-18 2017-01-18 Intelligent comprehensive pre-fabricating pipe gallery and construction technique thereof

Country Status (1)

Country Link
CN (1) CN106677209A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108457302A (en) * 2018-03-16 2018-08-28 中国电建集团福建省电力勘测设计院有限公司 Bolt splices axis bendable full precast assembly open cut cable tunnel
CN109403378A (en) * 2018-12-12 2019-03-01 中国建筑土木建设有限公司 A kind of piping lane interface structure and its construction method
CN109555157A (en) * 2018-12-25 2019-04-02 中铁十七局集团有限公司 It is a kind of list cabin and more cabin steel pipes corridor and concrete pipe gallery connection structure
CN110374137A (en) * 2019-05-28 2019-10-25 江苏金贸科技发展有限公司 A kind of assembled pipe gallery push type construction technology
CN113404091A (en) * 2021-05-28 2021-09-17 内蒙古送变电有限责任公司 Construction method for encapsulating and splicing prefabricated square culvert foundation and cable trench foundation
CN114530797A (en) * 2022-02-16 2022-05-24 北京市海实电气安装工程有限公司 Construction method of cable

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060092552A (en) * 2005-02-18 2006-08-23 (주)한국건설공법 The non-strut down framework construction method of having used cast in place concrete pile
CN104947709A (en) * 2015-04-15 2015-09-30 上海市政工程设计研究总院(集团)有限公司 Pre-assembled single-compartment municipal tunnel and construction method thereof
CN105350572A (en) * 2015-10-29 2016-02-24 周兆弟 Assembled type underground pipe gallery
CN105507346A (en) * 2016-02-02 2016-04-20 济南汇富住宅工业有限公司 Prefabricated underground pipe gallery
CN105544605A (en) * 2016-01-29 2016-05-04 中铁第四勘察设计院集团有限公司 Modular assembly type comprehensive pipe gallery

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060092552A (en) * 2005-02-18 2006-08-23 (주)한국건설공법 The non-strut down framework construction method of having used cast in place concrete pile
CN104947709A (en) * 2015-04-15 2015-09-30 上海市政工程设计研究总院(集团)有限公司 Pre-assembled single-compartment municipal tunnel and construction method thereof
CN105350572A (en) * 2015-10-29 2016-02-24 周兆弟 Assembled type underground pipe gallery
CN105544605A (en) * 2016-01-29 2016-05-04 中铁第四勘察设计院集团有限公司 Modular assembly type comprehensive pipe gallery
CN105507346A (en) * 2016-02-02 2016-04-20 济南汇富住宅工业有限公司 Prefabricated underground pipe gallery

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108457302A (en) * 2018-03-16 2018-08-28 中国电建集团福建省电力勘测设计院有限公司 Bolt splices axis bendable full precast assembly open cut cable tunnel
CN109403378A (en) * 2018-12-12 2019-03-01 中国建筑土木建设有限公司 A kind of piping lane interface structure and its construction method
CN109555157A (en) * 2018-12-25 2019-04-02 中铁十七局集团有限公司 It is a kind of list cabin and more cabin steel pipes corridor and concrete pipe gallery connection structure
CN109555157B (en) * 2018-12-25 2023-10-03 中铁十七局集团有限公司 Connection structure of single-cabin and multi-cabin steel pipe gallery and concrete pipe gallery
CN110374137A (en) * 2019-05-28 2019-10-25 江苏金贸科技发展有限公司 A kind of assembled pipe gallery push type construction technology
CN113404091A (en) * 2021-05-28 2021-09-17 内蒙古送变电有限责任公司 Construction method for encapsulating and splicing prefabricated square culvert foundation and cable trench foundation
CN114530797A (en) * 2022-02-16 2022-05-24 北京市海实电气安装工程有限公司 Construction method of cable
CN114530797B (en) * 2022-02-16 2024-01-30 北京市海实电气安装工程有限公司 Construction method of cable

Similar Documents

Publication Publication Date Title
CN106677209A (en) Intelligent comprehensive pre-fabricating pipe gallery and construction technique thereof
CN202969415U (en) Multifunctional assembled comprehensive pipe gallery
CN103256052B (en) Construction method for integral straight middle wall type double-arch tunnel
WO2017071110A1 (en) Assembled-type underground pipe gallery
CN106638681B (en) A kind of pipe gallery
WO2017071113A1 (en) Cement-soil mixing pile protected underground pipe gallery
CN106337436A (en) Rectangular concrete comprehensive pipe gallery prefabricated pipe sections and machining method
CN105401593A (en) Assembly type square underground pipe gallery
CN108396778A (en) A kind of construction method in precast assembly tunnel
CN204040062U (en) Prefabricated wedge shape flexible interface assembling piping lane
CN207498985U (en) A kind of partial precast assembly steel concrete combination underground pipe gallery for exempting from template
CN108193707A (en) A kind of comprehensive pipe gallery structure
WO2017071111A1 (en) Underground pipe gallery protection structure
CN205894103U (en) Prefabricated parabola type utility tunnel
CN109372558A (en) A kind of construction method of subway large section tunnel tunneling support replacement and main structure
CN206128117U (en) Prefabricated section of jurisdiction of rectangle concrete utility tunnel
CN210315654U (en) Urban tunnel, rail transit interval tunnel and utility tunnel co-construction structure
CN208136954U (en) Precast splice type Pipe rack
CN203284814U (en) Transformer substation prefabricated concrete water-scattering device
CN204098066U (en) The square underground pipe gallery of assembling
CN108360567A (en) The reversed construction method in precast assembly tunnel
CN204098067U (en) Side's culvert formula underground pipe gallery
CN208830353U (en) Underground pedestrian passageway prefabricated components, standard knot and two-part underground pedestrian passageway
CN106592635A (en) Integrated inspection shaft and installation method thereof
CN109695256A (en) Three circular shields build pipe gallery

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 454150 Jiefang Road, Macun District, Jiaozuo, Henan Province, No. 3698

Applicant after: Guo long Polytron Technologies Inc

Address before: 454150 Jiefang Road, Macun District, Jiaozuo, Henan Province, No. 3698

Applicant before: HENAN GUOLONG INDUSTRIAL CO., LTD.

CB02 Change of applicant information
CB02 Change of applicant information

Address after: 454150 3968 Jiefang East Road, Macun District, Jiaozuo, Henan

Applicant after: Guo long Polytron Technologies Inc

Address before: 454150 3698 Jiefang East Road, Macun District, Jiaozuo, Henan

Applicant before: Guo long Polytron Technologies Inc

CB02 Change of applicant information
RJ01 Rejection of invention patent application after publication

Application publication date: 20170517

RJ01 Rejection of invention patent application after publication