CN106677141B - 西域砾岩ⅴ类围岩导流兼泄洪冲砂洞全断面开挖施工方法 - Google Patents
西域砾岩ⅴ类围岩导流兼泄洪冲砂洞全断面开挖施工方法 Download PDFInfo
- Publication number
- CN106677141B CN106677141B CN201611221948.5A CN201611221948A CN106677141B CN 106677141 B CN106677141 B CN 106677141B CN 201611221948 A CN201611221948 A CN 201611221948A CN 106677141 B CN106677141 B CN 106677141B
- Authority
- CN
- China
- Prior art keywords
- full
- surrounding rock
- excavation
- section
- conglomerate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B8/00—Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
- E02B8/06—Spillways; Devices for dissipation of energy, e.g. for reducing eddies also for lock or dry-dock gates
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
一种西域砾岩Ⅴ类围岩导流兼泄洪冲砂洞全断面开挖施工方法,根据设计图纸中开挖断面尺寸,采用激光导向仪指向,用全站仪对掌子面进行放样;采用机械式短进尺全断面开挖法对西域砾岩Ⅴ类围岩隧洞进行开挖,开挖一个循环进尺之后,进行初期支护。本发明针对西域砾岩Ⅴ类围岩采用免爆全断面开挖或反铲全断面开挖,具有挖进度快,效率高,适用性强,投入人力资源较少,安全系数高,综合成本低。
Description
技术领域
本发明属于隧洞掘进的方法技术领域,具体涉及到一种西域砾岩Ⅴ类围岩导流兼泄洪冲砂洞全断面开挖施工方法。
背景技术
新疆奴尔水利枢纽工程由碾压式沥青混凝土心墙坝、左岸导流兼泄洪冲沙洞、左岸表孔溢洪洞、左岸发电引水洞、及发电厂房等主要建筑物组成。
其中,导流兼泄洪冲砂洞采用龙抬头与导流洞结合的方式,布置于河床左岸,由进口引渠段、闸井段、渐变段和洞身段组成,全长848m。洞身段主要开挖尺寸为导流洞3.5m×4.0m的城门洞,纵坡i=0.0084;泄洪洞为直径4m的圆洞,纵坡i=0.0174,其中有2个转弯段分别为0+75~0+108m,转弯半径30m,角度63°;洞身段位于西域砾岩微风化-新鲜岩体内,岩体较完整、结构面不发育,隧洞围岩类别属Ⅳ类,洞顶上覆西域砾岩,厚度为24~87m;洞身段大部分位于中更新统冲积砂卵砾石,成洞条件差,存在塌方和掉块,隧洞围岩类别属Ⅴ类,少部分位于基岩强弱风化层内,隧洞围岩类别属Ⅴ类。
按照常规施工办法Ⅴ类围岩不宜采用全断面法开挖,主要采用台阶法、预留核心土法、中隔壁法,全断面开挖主要采用盾构法、TBM法。
根据现场开挖跟踪检查发现,人工开挖进度严重滞后,并存在一定的安全风险;分台阶开挖因开挖断面尺寸较小,实施难度较大;反铲开挖只适合胶结极松散洞段,胶结稍密洞段实施难度较大。
发明内容
本发明所要解决的技术问题在于提供一种效率高、进度快、成本低、安全系数 高的Ⅴ类围岩导流兼泄洪冲砂洞全断面开挖施工方法。
解决上述技术问题所采用的技术方案是:一种西域砾岩Ⅴ类围岩导流兼泄洪冲砂洞全断面开挖施工方法,包括以下步骤:
(1)根据设计图纸中开挖断面尺寸,采用激光导向仪指向,用全站仪对掌子面进行放样;
(2)采用机械式短进尺全断面开挖法对西域砾岩Ⅴ类围岩隧洞进行开挖,开挖一个循环进尺之后,进行初期支护。
作为一种优选的技术方案,所述的步骤(2)中初期支护包括:a、安装钢拱架;b、挂网;c、喷射混凝土。
作为一种优选的技术方案,所述的钢拱架榀间距0.6~1.5m。
作为一种优选的技术方案,所述的喷射混凝土采用干喷法,自下而上分层喷射,每层厚度为0.04~0.07m,各层喷射间隔时间为30min~60min。
作为一种优选的技术方案,所述的步骤(2)中Ⅴ类围岩是微胶结密实砂砾石层,采用免爆全断面开挖,预留0.2m厚保护层,人工风镐开挖,循环进尺1.0~1.5m,钢拱架榀间距为1~1.5m。
作为一种优选的技术方案,所述的步骤(2)中Ⅴ类围岩是微胶结、稍密实砂砾石层,采用反铲全断面开挖,预留0.5m厚保护层,人工撬杠开挖,循环进尺0.5~1.0m,钢拱架榀间距为0.6~1m。
本发明的有益效果如下:
本发明针对西域砾岩Ⅴ类围岩采用免爆全断面开挖或反铲全断面开挖,具有挖进度快,效率高,适用性强,投入人力资源较少,安全系数高,综合成本低。
具体实施方式
下面结合实施例对本发明进一步详细说明,但本发明不限于下述的实施方式。
实施例1
一种西域砾岩Ⅴ类围岩导流兼泄洪冲砂洞全断面开挖施工方法,包括以下步骤:
(1)根据设计图纸中开挖断面尺寸,采用激光导向仪指向,用全站仪对掌子面进行放样;
(2)本实施例的西域砾岩Ⅴ类围岩是微胶结密实砂砾石层,采用免爆全断面开挖,预留0.2m厚保护层,人工风镐开挖,循环进尺1.2m,开挖一个循环进尺之后,进行初期支护;
初期支护包括:a、安装钢拱架;b、挂网;c、喷射混凝土。
a、安装钢拱架包括以下步骤:
1)测量定位
首先测定出线路中线,确定高程,然后再测定其横向位置;钢拱架设于曲线上时,安设方向为该点的法线方向;安设于直线上时,安设方向与线路中线垂直;每榀的位置定位准确,上下、左右偏差小于0.05m,斜度<2°;
2)在隧洞初喷混凝土后,钢拱架按照先侧墙后顶拱的顺序安装,钢拱架通过锁脚锚杆固定在隧洞壁上,相邻两钢拱架榀间距为1.2m,相邻两榀钢拱架采用Φ22钢筋相连,形成纵向连接系;
b、挂网
钢拱架安装完成之后,人工绑扎钢筋网片并与钢拱架连接,安装成型后网片距喷射面不小于0.05m。
c、喷射混凝土
喷射混凝土采用干喷法,自下而上分层喷射,每层厚度为0.055m,前一层喷射完毕,间隔时间为50min后,用钢制刷将表面乳皮清除,并用风水将喷层面清洗干净,进行下一层喷射,直至喷射混凝土表面平整,不出现干斑、疏松、脱空、裂缝、 露筋等现象,停止喷射,等待混凝土表层凝固后,开始喷水养护。
实施例2
在本实施例中,西域砾岩Ⅴ类围岩是微胶结密实砂砾石层,采用免爆全断面开挖,预留0.2m厚保护层,人工风镐开挖,循环进尺1m,开挖一个循环进尺之后,进行初期支护,相邻两钢拱架榀间距为1m。其他施工步骤与实施例1相同。
实施例3
在本实施例中,西域砾岩Ⅴ类围岩是微胶结密实砂砾石层,采用免爆全断面开挖,预留0.2m厚保护层,人工风镐开挖,循环进尺1.5m,开挖一个循环进尺之后,进行初期支护,相邻两钢拱架榀间距为1.5m。其他施工步骤与实施例1相同。
实施例4
在本实施例中,西域砾岩Ⅴ类围岩是微胶结、稍密实砂砾石层,采用反铲全断面开挖,预留0.5m厚保护层,人工撬杠开挖,循环进尺0.8m,开挖一个循环进尺之后,进行初期支护,相邻两钢拱架榀间距为0.8m。其他施工步骤与实施例1相同。
实施例5
在本实施例中,西域砾岩Ⅴ类围岩是微胶结、稍密实砂砾石层,采用反铲全断面开挖,预留0.5m厚保护层,人工撬杠开挖,循环进尺0.5m,开挖一个循环进尺之后,进行初期支护,相邻两钢拱架榀间距为0.6m。其他施工步骤与实施例1相同。
实施例6
在本实施例中,西域砾岩Ⅴ类围岩是微胶结、稍密实砂砾石层,采用反铲全断面开挖,预留0.5m厚保护层,人工撬杠开挖,循环进尺1m,开挖一个循环进尺之后,进行初期支护,相邻两钢拱架榀间距为1m。其他施工步骤与实施例1相同。
Claims (3)
1.一种西域砾岩Ⅴ类围岩导流兼泄洪冲砂洞全断面开挖施工方法,其特征在于包括以下步骤:
(1)根据设计图纸中开挖断面尺寸,采用激光导向仪指向,用全站仪对掌子面进行放样;
(2)采用机械式短进尺全断面开挖法对西域砾岩Ⅴ类围岩隧洞进行开挖,开挖一个循环进尺之后,进行初期支护;
所述的Ⅴ类围岩是微胶结密实砂砾石层,采用免爆全断面开挖,预留0.2m厚保护层,人工风镐开挖,循环进尺1.0~1.5m,钢拱架榀间距为1~1.5m;
所述的Ⅴ类围岩是微胶结、稍密实砂砾石层,采用反铲全断面开挖,预留0.5m厚保护层,人工撬杠开挖,循环进尺0.5~1.0m,钢拱架榀间距为0.6~1m。
2.根据权利要求1所述的西域砾岩Ⅴ类围岩导流兼泄洪冲砂洞全断面开挖施工方法,其特征在于所述的步骤(2)中初期支护包括:a、安装钢拱架;b、挂网;c、喷射混凝土。
3.根据权利要求2所述的西域砾岩Ⅴ类围岩导流兼泄洪冲砂洞全断面开挖施工方法,其特征在于:所述的喷射混凝土采用干喷法,自下而上分层喷射,每层厚度为0.04~0.07m,各层喷射间隔时间为30min~60min。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611221948.5A CN106677141B (zh) | 2016-12-27 | 2016-12-27 | 西域砾岩ⅴ类围岩导流兼泄洪冲砂洞全断面开挖施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611221948.5A CN106677141B (zh) | 2016-12-27 | 2016-12-27 | 西域砾岩ⅴ类围岩导流兼泄洪冲砂洞全断面开挖施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106677141A CN106677141A (zh) | 2017-05-17 |
CN106677141B true CN106677141B (zh) | 2021-05-04 |
Family
ID=58870486
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611221948.5A Active CN106677141B (zh) | 2016-12-27 | 2016-12-27 | 西域砾岩ⅴ类围岩导流兼泄洪冲砂洞全断面开挖施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106677141B (zh) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3920277A (en) * | 1974-06-07 | 1975-11-18 | Dresser Ind | Tunnel boring machine roll correction |
CN104141500A (zh) * | 2014-04-11 | 2014-11-12 | 中国水利水电第十一工程局有限公司 | 一种板结砂砾石地层洞室施工方法 |
CN104453921A (zh) * | 2014-12-15 | 2015-03-25 | 中铁二十局集团有限公司 | 一种软岩隧道开挖施工工艺 |
CN105863651A (zh) * | 2016-05-30 | 2016-08-17 | 中铁工程装备集团有限公司 | 一种盾构与新奥法相结合的隧道施工方法 |
-
2016
- 2016-12-27 CN CN201611221948.5A patent/CN106677141B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3920277A (en) * | 1974-06-07 | 1975-11-18 | Dresser Ind | Tunnel boring machine roll correction |
CN104141500A (zh) * | 2014-04-11 | 2014-11-12 | 中国水利水电第十一工程局有限公司 | 一种板结砂砾石地层洞室施工方法 |
CN104453921A (zh) * | 2014-12-15 | 2015-03-25 | 中铁二十局集团有限公司 | 一种软岩隧道开挖施工工艺 |
CN105863651A (zh) * | 2016-05-30 | 2016-08-17 | 中铁工程装备集团有限公司 | 一种盾构与新奥法相结合的隧道施工方法 |
Non-Patent Citations (1)
Title |
---|
三峡右岸地下电站尾水系统开挖施工测量;张勇;《中国三峡建设》;20070731;第41-42页 * |
Also Published As
Publication number | Publication date |
---|---|
CN106677141A (zh) | 2017-05-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US12025008B2 (en) | Vertical orthogonal top exhausting air duct structure of deeply-buried subway station and construction method therefor | |
CN110700841B (zh) | 用于隧道开挖的双侧壁导坑式开挖方法 | |
CN105041349A (zh) | 一种在地铁区间盾构隧道基础上扩挖车站的暗挖施工方法 | |
CN101769154A (zh) | 一种隧道施工的开挖支护方法 | |
CN104612698A (zh) | 一种浅埋暗挖隧道上台阶中隔壁施工方法 | |
CN105064397A (zh) | 一种在地铁区间盾构隧道基础上扩挖车站的明挖施工方法 | |
CN106703828A (zh) | 采用预制装配式衬砌结合pba建造地铁车站的施工方法 | |
CN103806464B (zh) | 大型高铁车站与地铁上下交汇逆作法施工方法 | |
CN102373930A (zh) | 一种软弱围岩大断面连拱隧道的快速施工方法 | |
CN103938634B (zh) | 一种深基坑支护结构及施工方法 | |
CN111997624A (zh) | 一种浅埋大断面暗挖矩形隧道施工方法 | |
CN103362513A (zh) | 暗挖区间既有洞体改造施工工法 | |
CN110566223B (zh) | 一种深埋pba地铁车站断面设计方法 | |
CN110230495B (zh) | 一种地铁车站双侧壁导坑施工核心土开挖工法 | |
CN104632227A (zh) | 单层梁拱结构的地铁车站开挖工艺 | |
WO2021237912A1 (zh) | 一种岩矸配合成形的伪采空层支护限沉回采方法 | |
RU2485318C1 (ru) | Способ строительства станционных тоннелей с малыми осадками земной поверхности | |
CN104131566A (zh) | 一种地下室无水平支撑基坑的施工方法 | |
CN204282399U (zh) | 一种地铁围护结构 | |
CN106193120A (zh) | 地下室悬挑底板逆作结构及施工方法 | |
CN106677141B (zh) | 西域砾岩ⅴ类围岩导流兼泄洪冲砂洞全断面开挖施工方法 | |
CN211038701U (zh) | 一种“先盾后井”的矿山法地铁区间风井 | |
US11821316B1 (en) | System and construction method of single-layer lining tunnel structure based on mine-tunnelling method | |
CN115030556A (zh) | 一种清水砖外墙老建筑修缮加固方法 | |
CN203947557U (zh) | 围墙排水结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |