CN106649008A - Method and system for automatically executing mobile terminal physical startup and shutdown pressure test - Google Patents

Method and system for automatically executing mobile terminal physical startup and shutdown pressure test Download PDF

Info

Publication number
CN106649008A
CN106649008A CN201611022508.7A CN201611022508A CN106649008A CN 106649008 A CN106649008 A CN 106649008A CN 201611022508 A CN201611022508 A CN 201611022508A CN 106649008 A CN106649008 A CN 106649008A
Authority
CN
China
Prior art keywords
mobile terminal
pressure test
relay
shutting down
automated execution
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611022508.7A
Other languages
Chinese (zh)
Inventor
赵德明
付仁杰
牛永魁
胡鹰彦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huizhou TCL Mobile Communication Co Ltd
Original Assignee
Huizhou TCL Mobile Communication Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huizhou TCL Mobile Communication Co Ltd filed Critical Huizhou TCL Mobile Communication Co Ltd
Priority to CN201611022508.7A priority Critical patent/CN106649008A/en
Publication of CN106649008A publication Critical patent/CN106649008A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F11/00Error detection; Error correction; Monitoring
    • G06F11/22Detection or location of defective computer hardware by testing during standby operation or during idle time, e.g. start-up testing
    • G06F11/2205Detection or location of defective computer hardware by testing during standby operation or during idle time, e.g. start-up testing using arrangements specific to the hardware being tested
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F11/00Error detection; Error correction; Monitoring
    • G06F11/22Detection or location of defective computer hardware by testing during standby operation or during idle time, e.g. start-up testing
    • G06F11/2273Test methods
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04MTELEPHONIC COMMUNICATION
    • H04M1/00Substation equipment, e.g. for use by subscribers
    • H04M1/24Arrangements for testing
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F11/00Error detection; Error correction; Monitoring
    • G06F11/22Detection or location of defective computer hardware by testing during standby operation or during idle time, e.g. start-up testing
    • G06F11/2284Detection or location of defective computer hardware by testing during standby operation or during idle time, e.g. start-up testing by power-on test, e.g. power-on self test [POST]

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Quality & Reliability (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Signal Processing (AREA)
  • Telephone Function (AREA)

Abstract

The invention discloses a method and system for automatically executing a mobile terminal physical startup-shutdown pressure test. The method comprises the steps of A, stopping a relay after the relay is connected to a Power source for a fixed value; B, starting up or shutting down the mobile terminal by conveying an ADB order. Through the method and system for automatically executing the mobile terminal physical startup-shutdown pressure test, intelligent control over the physical startup and shutdown pressure test of the mobile terminal can be achieved; moreover, the automated execution sets manpower free, and improves work efficiency and accuracy.

Description

The method and system of automated execution mobile terminal physical switching on and shutting down pressure test
Technical field
The present invention relates to mobile terminal test field, more particularly to a kind of automated execution mobile terminal physical switching on and shutting down pressure The method and system of power test.
Background technology
Physical switch machine pressure test is a basic test project of the mobile terminal in development, and this test is usual Need the model machine of 5 or so, every switching on and shutting down 1000 times, if manual test, probably need the workload for expending for 12 man days;And Also there is certain error in manual test;Also, also waste of manpower stand-by period when switching on and shutting down are waited, testing efficiency compared with It is low.
Therefore, prior art has yet to be improved and developed.
The content of the invention
In view of above-mentioned the deficiencies in the prior art, it is an object of the invention to provide a kind of automated execution mobile terminal physical The method and system of switching on and shutting down pressure test, it is intended to which it is low to solve mobile terminal physical switching on and shutting down pressure test efficiency, labor intensive Big problem.
Technical scheme is as follows:
A kind of method of automated execution mobile terminal physical switching on and shutting down pressure test, wherein, including step:
A, the time of relay connection Power power supplys continue to be disconnected after a fixed value;
B, mobile terminal is booted up or shut down by conducting ADB orders.
The method of described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, step A includes:
A1, after Preset Time, control relay connection Power power supplys.
The method of described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, before step A also Including:
S, the Preset Time for pre-setting relay circulation connection Power power supplys, make relay periodically connection Power power supplys.
The method of described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, step B includes:
B1, Intelligent Recognition mobile terminal screen interface;
B2, when mobile terminal screen interface be unlock interface when, conduct ADB orders, click screen solution lock icon be unlocked;
B3, when mobile terminal screen interface for shutdown interface when, conduct ADB orders, click screen shutdown icon.
The method of described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, in step A, after The duration of electrical equipment connection Power power supplys disconnects after reaching 2 seconds.
A kind of system of automated execution mobile terminal physical switching on and shutting down pressure test, wherein, including:
Computer and mobile terminal, the relay being connected with mobile terminal, the relay connects with the Power power supplys of mobile terminal Connect, and disconnect after the time of connection Power power supplys continues a fixed value;
The computer is also connected with mobile terminal by USB line, and conducts ADB orders to mobile terminal by the USB line Boot up or shut down;
The computer is also connected with mobile terminal by Serial Port Line, and by Serial Port Line mobile terminal serial ports log is captured;
The computer is connected with relay by Cable lines, the switch of control relay.
The system of described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, the relay every It is connected with Power power supplys after Preset Time.
The system of described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, pre-set relay The Preset Time of circulation connection Power power supplys, makes relay periodically connection Power power supplys.
The system of described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, the Serial Port Line is used for Intelligent Recognition mobile terminal screen interface, when mobile terminal screen interface is unlock interface, by USB line ADB orders is conducted, The solution lock icon for clicking on screen is unlocked;
When mobile terminal screen interface is shutdown interface, ADB orders are conducted by USB line, click on the shutdown icon of screen.
The system of described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, the relay connection The duration of Power power supplys disconnects after reaching 2 seconds.
Beneficial effect:The invention discloses a kind of method of automated execution mobile terminal physical switching on and shutting down pressure test and System, wherein, methods described includes step:A, the time of relay connection Power power supplys continue to be disconnected after a fixed value;It is B, logical Cross conduction ADB orders to boot up mobile terminal or shut down, by the method for the present invention and system, can be to mobile terminal Based Intelligent Control, also, automated execution are realized in physical switch machine pressure test, and liberation is artificial, improve operating efficiency and accurately Property.
Description of the drawings
Fig. 1 is the flow chart of the method for automated execution mobile terminal physical switching on and shutting down pressure test of the present invention.
The stream of the step of Fig. 2 is the method for automated execution mobile terminal physical switching on and shutting down pressure test of the present invention S2 Cheng Tu.
Fig. 3 is the structural representation of the system of automated execution mobile terminal physical switching on and shutting down pressure test of the present invention Figure.
Specific embodiment
The present invention provides a kind of method and system of automated execution mobile terminal physical switching on and shutting down pressure test, to make this The purpose of invention, technical scheme and effect are clearer, clear and definite, and below the present invention is described in more detail.It should be appreciated that this The described specific embodiment in place is not intended to limit the present invention only to explain the present invention.
Fig. 1 is referred to, Fig. 1 is the method for automated execution mobile terminal physical switching on and shutting down pressure test of the present invention Flow chart, the invention discloses a kind of method of automated execution mobile terminal physical switching on and shutting down pressure test, wherein, including step Suddenly:
S1, the time of relay connection Power power supplys continue to be disconnected after a fixed value;
S2, mobile terminal is booted up or shut down by conducting ADB orders.The invention discloses a kind of automated execution movement The method of terminals physical switching on and shutting down pressure test, can automatically be tested mobile terminal physical switching on and shutting down pressure, by after Electrical equipment connects Power power supplys, and simulation staff pressing switch switch carrys out controlling switch machine, and relay connection Power power supplys continue one Disconnect after set time, now, mobile terminal screen interface occurs start or the icon that shuts down, and for example, start needs start solution Lock, shutdown needs to click on and confirms that shutdown icon just completes switching on and shutting down control, therefore, mobile terminal is entered by conducting ADB orders Row switching on and shutting down are controlled, and shutdown icon are unlocked or are click on by order control and completes switching on and shutting down, whole operation, it is only necessary to user Code control is pre-set, and need not manually operate machine, liberation is artificial, and circulate operation, efficiency high.
Further, the method for described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, the step Rapid S1 includes:
S101, after Preset Time, control relay connection Power power supplys.The method of the invention, in step S1, The time of relay connection Power power supplys continues to be disconnected after a fixed value, in order to realize loop control mobile terminal switching on and shutting down, because This, the control relay connection Power power supplys after Preset Time, for the first time for during start, after Preset Time, relay connects The operation of Power power supplys is as shut down, and is moved in circles, and can automatically move the physical switch machine pressure test of terminal.
Further, the method for described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, the step Also include before rapid S1:
S0, the Preset Time for pre-setting relay circulation connection Power power supplys, make relay periodically connection Power power supplys. The method of the invention, for the accuracy for ensureing to test, user can pre-set the pre- of relay circulation connection Power power supplys If the time, for example, start and unlocked time need ten seconds, predeterminable 11 seconds or other were more than ten seconds times, when reaching To 11 seconds or other Preset Times, relay connection Power power supplys were shut down, and in the same manner, shutdown is same, are arranged start and are closed The machine time, Preset Time control relay connection Power power supplys are reached, the Preset Time is generally definite value, also dependent on opening Machine time or unused time, it is separately provided Preset Time after start, or postboost Preset Time to precisely control survey Examination.
Further, the method for described automated execution mobile terminal physical switching on and shutting down pressure test, as shown in Fig. 2 For the flow chart of step S2, wherein, step S2 includes:
S201, Intelligent Recognition mobile terminal screen interface;
S202, when mobile terminal screen interface be unlock interface when, conduct ADB orders, click screen solution lock icon solved Lock;
S203, when mobile terminal screen interface for shutdown interface when, conduct ADB orders, click screen shutdown icon.The present invention Methods described, step S2 is to carry out switching on and shutting down control to mobile terminal by conducting ADB orders, specifically, first intelligently The screen interface of identification mobile terminal, the screen interface of startup and shutdown is different, and start might have start unblock, and shutdown has Shutdown icon treats that user confirms, therefore, when mobile terminal screen interface is unlock interface, the ADB orders of unblock are conducted, to moving Dynamic terminal unlocking icon is unlocked, likewise, when mobile terminal screen interface is shutdown interface, conducting ADB orders, clicks on The shutdown icon of screen, realizes the shutdown control of mobile terminal.
Further, the method for described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, the step In rapid S1, the duration of relay connection Power power supplys reach 2 seconds after disconnect.The method of the invention, step S1 In, the usual switching on and shutting down pressing switch 2 second time of switch, mobile terminal received start-up command, therefore, the present invention is preferably described The duration of relay connection Power power supplys disconnects after reaching 2 seconds.
Presently preferred embodiments of the present invention, has specifically included following component, and specific component purposes is:
Relay:The on-off of pseudo-terminal power key
USB line:Connection PC and terminal, by conducting the shutdown icon on ADB orders click screen
Serial Port Line:Connection PC and terminal serial ports, capture terminal serial ports log
Perform script:Receiving user's input parameter, control relay and terminal perform test
Realize principle:
Switching on and shutting down are controlled:Relay serves as one kind " automatic switch " that control high current running is gone with small current, and relay is connected Connect terminal(Mobile phone, flat board)The power and ground of key, then PC and relay are connected by Serial Port Line, PC ends perform The switch of Python Script controlling relays so as to the switching on and shutting down of control terminal, script perform that circulation every time includes from start to Shutdown overall process.Mainly include identification terminal and relay, connect power supply Power on, wait (Wait) start to complete, shut down, Control cycle-index etc..
Crucial script:
# relays simulation length presses Power keys
def pressPowerLong(number):
os.system(relayPath+" "+relayNumber+" open "+number)
time.sleep(2)
os.system(relayPath+" "+relayNumber+" close "+number)
# loop bodies, control repeat switch machine
for i in range(loopTime):
print "start",
print i+1,
print" loop"
print "Power on device"
pressPowerLong("1")
Time.sleep (100) # waits start
Os.system (" adb-s "+serialNumber+ " shell input swipe 240 780 240 400 ") # leads to Cross adb slip unblocks
time.sleep(2)
pressPowerLong("1")
Os.system (" adb-s "+serialNumber+ " shell input tap 235 545 ") # are clicked on by adb Power Off
time.sleep(30)
print "finished "
print ""
i=i+1
Automation unblock and click Power off controls
Terminal enters engineering mode and opens USB Debug, and connecting terminal and PC, PC section by data wire needs to install ADB drives It is dynamic.ADB (Android Debug Bridge) is institute's band instrument in Android SDK.Can be operated on PC using ADB Android device or simulator.Same PC can connect multiple Android devices.
PC ends perform script control mobile phone controls handset sliding unlocking screen and clicks on Power off by ADB
"adb -s "+serialNumber+" shell input swipe 240 780 240 400"
"adb -s "+serialNumber+" shell input tap 235 545"
MTK serial ports reads serial ports UART log
Serial ports UART log connect PC and relay by Secure CRT software grabs by Serial Port Line, open Secure Corresponding port numbers and Baud rate 921600 in computer equipment manager are selected in CRT softwares, newly-built connection(MTK).
Further, the invention also discloses a kind of automated execution mobile terminal physical switching on and shutting down pressure test is System, as shown in figure 3, for the structural representation of the system, wherein, including:
Computer 101 and mobile terminal 1 02, the relay 103 being connected with mobile terminal 1 02, the relay 103 and mobile terminal 101 Power power supplys connection, and disconnect after the time of connection Power power supplys continues a fixed value;
The computer 101 is also connected with mobile terminal 1 02 by USB line 104, and conducts ADB lives by the USB line 104 Order is booted up or shut down to mobile terminal 1 02;
The computer 101 is also connected with mobile terminal 1 02 by Serial Port Line 105, and by Serial Port Line 105 mobile terminal 1 02 is captured Serial ports log;
The computer 101 is connected with relay 103 by Cable lines 106, the switch of control relay 103.
Further, the system of described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, it is described after Electrical equipment is connected after Preset Time with Power power supplys.
Further, the system of described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, set in advance The Preset Time of relay circulation connection Power power supplys is put, relay periodically connection Power power supplys are made.
Further, the system of described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, the string Mouth line is used for Intelligent Recognition mobile terminal screen interface, when mobile terminal screen interface is unlock interface, is conducted by USB line ADB orders, the solution lock icon for clicking on screen is unlocked;
When mobile terminal screen interface is shutdown interface, ADB orders are conducted by USB line, click on the shutdown icon of screen.
Further, the system of described automated execution mobile terminal physical switching on and shutting down pressure test, wherein, it is described after The duration of electrical equipment connection Power power supplys disconnects after reaching 2 seconds.
In sum, the invention discloses a kind of method of automated execution mobile terminal physical switching on and shutting down pressure test and System, wherein, methods described includes step:A, the time of relay connection Power power supplys continue to be disconnected after a fixed value;It is B, logical Cross conduction ADB orders to boot up mobile terminal or shut down, by the method for the present invention and system, can be to mobile terminal Based Intelligent Control, also, automated execution are realized in physical switch machine pressure test, and liberation is artificial, improve operating efficiency and accurately Property.
It should be appreciated that the application of the present invention is not limited to above-mentioned citing, and for those of ordinary skills, can To be improved according to the above description or be converted, all these modifications and variations should all belong to the guarantor of claims of the present invention Shield scope.

Claims (10)

1. a kind of method of automated execution mobile terminal physical switching on and shutting down pressure test, it is characterised in that including step:
A, the time of relay connection Power power supplys continue to be disconnected after a fixed value;
B, mobile terminal is booted up or shut down by conducting ADB orders.
2. the method for automated execution mobile terminal physical switching on and shutting down pressure test according to claim 1, its feature exists In step A includes:
A1, after Preset Time, control relay connection Power power supplys.
3. the method for automated execution mobile terminal physical switching on and shutting down pressure test according to claim 2, its feature exists In also including before step A:
S, the Preset Time for pre-setting relay circulation connection Power power supplys, make relay periodically connection Power power supplys.
4. the method for automated execution mobile terminal physical switching on and shutting down pressure test according to claim 1, its feature exists In step B includes:
B1, Intelligent Recognition mobile terminal screen interface;
B2, when mobile terminal screen interface be unlock interface when, conduct ADB orders, click screen solution lock icon be unlocked;
B3, when mobile terminal screen interface for shutdown interface when, conduct ADB orders, click screen shutdown icon.
5. the method for automated execution mobile terminal physical switching on and shutting down pressure test according to claim 1, its feature exists In, in step A, relay connection Power power supplys duration reach 2 seconds after disconnect.
6. a kind of system of automated execution mobile terminal physical switching on and shutting down pressure test, it is characterised in that include:
Computer and mobile terminal, the relay being connected with mobile terminal, the relay connects with the Power power supplys of mobile terminal Connect, and disconnect after the time of connection Power power supplys continues a fixed value;
The computer is also connected with mobile terminal by USB line, and conducts ADB orders to mobile terminal by the USB line Boot up or shut down;
The computer is also connected with mobile terminal by Serial Port Line, and by Serial Port Line mobile terminal serial ports log is captured;
The computer is connected with relay by Cable lines, the switch of control relay.
7. the system of automated execution mobile terminal physical switching on and shutting down pressure test according to claim 6, its feature exists In the relay is connected after Preset Time with Power power supplys.
8. the system of automated execution mobile terminal physical switching on and shutting down pressure test according to claim 7, its feature exists In, the Preset Time of relay circulation connection Power power supplys is pre-set, make relay periodically connection Power power supplys.
9. the system of automated execution mobile terminal physical switching on and shutting down pressure test according to claim 6, its feature exists In the Serial Port Line is used for Intelligent Recognition mobile terminal screen interface, when mobile terminal screen interface is unlock interface, passes through USB line conducts ADB orders, and the solution lock icon for clicking on screen is unlocked;
When mobile terminal screen interface is shutdown interface, ADB orders are conducted by USB line, click on the shutdown icon of screen.
10. the system of automated execution mobile terminal physical switching on and shutting down pressure test according to claim 6, its feature exists Disconnect after reaching 2 seconds in, duration of relay connection Power power supplys.
CN201611022508.7A 2016-11-21 2016-11-21 Method and system for automatically executing mobile terminal physical startup and shutdown pressure test Pending CN106649008A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611022508.7A CN106649008A (en) 2016-11-21 2016-11-21 Method and system for automatically executing mobile terminal physical startup and shutdown pressure test

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611022508.7A CN106649008A (en) 2016-11-21 2016-11-21 Method and system for automatically executing mobile terminal physical startup and shutdown pressure test

Publications (1)

Publication Number Publication Date
CN106649008A true CN106649008A (en) 2017-05-10

Family

ID=58808329

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611022508.7A Pending CN106649008A (en) 2016-11-21 2016-11-21 Method and system for automatically executing mobile terminal physical startup and shutdown pressure test

Country Status (1)

Country Link
CN (1) CN106649008A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107391329A (en) * 2017-07-14 2017-11-24 惠州Tcl移动通信有限公司 A kind of method, system and storage device for testing mobile terminal Reusability
CN108111764A (en) * 2018-01-03 2018-06-01 上海传英信息技术有限公司 A kind of method and its system of Real-Time Switch PDAF
CN110417976A (en) * 2018-04-26 2019-11-05 上海晨兴希姆通电子科技有限公司 A kind of control device, on-off testing system and its method of switching on and shutting down test
CN113010360A (en) * 2021-04-22 2021-06-22 读书郎教育科技有限公司 Software and hardware combined aging test method for simulating real operation on/off

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130241584A1 (en) * 2012-03-16 2013-09-19 Hon Hai Precision Industry Co., Ltd. Power-on test apparatus and system for testing electronic device
CN104601771A (en) * 2014-12-26 2015-05-06 沈阳晨讯希姆通科技有限公司 Method and system for testing main board of mobile phone

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130241584A1 (en) * 2012-03-16 2013-09-19 Hon Hai Precision Industry Co., Ltd. Power-on test apparatus and system for testing electronic device
CN104601771A (en) * 2014-12-26 2015-05-06 沈阳晨讯希姆通科技有限公司 Method and system for testing main board of mobile phone

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
在代码下成长: "adb 命令模拟按键事件", 《CSDN博客,公开网址:HTTPS://BLOG.CSDN.NET/WO_HA/ARTICLE/DETAILS/53097600?DEPTH_1》 *
恋恋西风: "adb 命令模拟按键事件 模拟 点击 事件", 《CSDN博客 HTTPS://BLOG.CSDN.NET/Q610098308/ARTICLE/DETAILS/48781747》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107391329A (en) * 2017-07-14 2017-11-24 惠州Tcl移动通信有限公司 A kind of method, system and storage device for testing mobile terminal Reusability
CN107391329B (en) * 2017-07-14 2021-05-28 惠州Tcl移动通信有限公司 Method, system and storage device for testing repeated use of mobile terminal
CN108111764A (en) * 2018-01-03 2018-06-01 上海传英信息技术有限公司 A kind of method and its system of Real-Time Switch PDAF
CN108111764B (en) * 2018-01-03 2021-07-23 上海传英信息技术有限公司 Method and system for switching PDAF (PDAF) in real time
CN110417976A (en) * 2018-04-26 2019-11-05 上海晨兴希姆通电子科技有限公司 A kind of control device, on-off testing system and its method of switching on and shutting down test
CN113010360A (en) * 2021-04-22 2021-06-22 读书郎教育科技有限公司 Software and hardware combined aging test method for simulating real operation on/off

Similar Documents

Publication Publication Date Title
CN106649008A (en) Method and system for automatically executing mobile terminal physical startup and shutdown pressure test
CN107678949B (en) Automatic testing method for realizing different communication modes of embedded equipment
CN101175285A (en) Automatic testing method and system for mobile phone software
CN103744784A (en) Method and system for automatically testing mobile phone applications
CN105786691A (en) Automatic integration testing device, method and system of mobile terminal
CN105740139B (en) A kind of debugging embedded software method based on virtual environment
CN103544100A (en) Method, system and client side for testing APP of portable data processing equipment
CN105578238A (en) Automatic test method and system of turn-on and turn-off of electrical appliance device
CN103927256A (en) Method for controlling multiple Android devices
CN104090751A (en) Method for acquiring root authority in Android system
CN110837466A (en) Embedded software dynamic test method based on source code piling
CN102346456B (en) Programmable intelligent terminal device and programmable intelligent terminal operation method
CN100488119C (en) Anti-field software debugging method for communication apparatus
KR100794130B1 (en) Automatic Function Testing Equipment for Application Software and Additional Service of Mobile Communication Terminal
CN202693709U (en) Test tool and test system of electric equipment
CN113836505A (en) Method for rapidly acquiring shell permission of terminal equipment based on android system
CN102681861B (en) Method and device for installing software
CN106506598A (en) A kind of access BIOS setup interfaces and the method for OS
CN103927257A (en) Method and device for triggering android behavior event
CN113420189A (en) Intelligent terminal android App control method and system based on RPA
CN105224453A (en) The automatic test approach of system compatibility and device
CN103793321B (en) application program detection method and system
CN109634856B (en) IOS intelligent terminal remote real machine debugging system and method based on cloud service
CN108334426A (en) A kind of more SSD/HDD integration tests and tele-control system and its method
CN104239202A (en) Non-Root testing method and system of interactive intelligent equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170510

RJ01 Rejection of invention patent application after publication