CN106639969B - Plugging method for perforating well section of slim hole sidetracked well - Google Patents

Plugging method for perforating well section of slim hole sidetracked well Download PDF

Info

Publication number
CN106639969B
CN106639969B CN201611075931.3A CN201611075931A CN106639969B CN 106639969 B CN106639969 B CN 106639969B CN 201611075931 A CN201611075931 A CN 201611075931A CN 106639969 B CN106639969 B CN 106639969B
Authority
CN
China
Prior art keywords
perforated interval
cement
well
cement plug
interim
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611075931.3A
Other languages
Chinese (zh)
Other versions
CN106639969A (en
Inventor
付玉红
杨平阁
肖素梅
林丽娜
何定海
谢昕
杨凯
邢璐薪
张春堂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Petrochina Co Ltd
Original Assignee
Petrochina Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Petrochina Co Ltd filed Critical Petrochina Co Ltd
Priority to CN201611075931.3A priority Critical patent/CN106639969B/en
Publication of CN106639969A publication Critical patent/CN106639969A/en
Application granted granted Critical
Publication of CN106639969B publication Critical patent/CN106639969B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices or the like
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B37/00Methods or apparatus for cleaning boreholes or wells
    • E21B37/02Scrapers specially adapted therefor

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention provides a plugging method of a perforating well section of a slim hole sidetracked well, wherein the plugging method comprises the following steps of S100, opening a wellhead blowout preventer, injecting workover fluid into a sleeve and dredging a well; s200, putting an operation tubular column, and sequentially plugging each perforation well section from top to bottom until the bottommost perforation well section completes plugging operation; step S300, cleaning the sleeve to the bottom of the artificial well by the scraper bit, wherein the plugging operation is as follows: the operation pipe column is used for drilling a suspended cement plug below the perforation well section; carrying out cement squeezing and plugging operation to form a temporary cement plug above the suspended cement plug; closing the wellhead blowout preventer, and waiting for setting under pressure; and opening the wellhead blowout preventer, and sequentially drilling the temporary cement plug and the suspended cement plug by the downward-entering scraper drill bit from top to bottom to finish plugging operation. The invention also provides another plugging method for the perforating well section of the slim hole sidetracked well. The invention does not need a packer, completes plugging from top to bottom, and can be used for permanent well sealing or major repair of small well bores.

Description

The method for blocking of Slim Hole perforated interval
Technical field
The present invention relates to the technical field of petroleum gas underground operation, in particular to a kind of Slim Hole perforated hole The method for blocking of section.
Background technique
With the continuous increase of oilfield exploitation difficulty and the development and application of new drilling technology, Slim Hole (internal diameter of casing is less than or equal to 86 millimeters) is more and more in the quantity of Oil Field, as these special wells are put into Produce and use, because caused by various factors the phenomenon that its overhaul it is also more and more, such as: due to adjusting layer or other production requirements, need Its original perforated interval is blocked.Conventional method for blocking is usually that tripping in packer carries out squeeze method closure from the bottom to top, But the internal diameter of Slim Hole Sidetracking Technology well section is too small, is difficult to find suitable small size packer, and construction risk is larger, is easy to appear The problem of packer plays envelope, sets unsuccessfully.
Summary of the invention
It is proposed by the present invention to solve inconvenient the technical issues of being blocked using conventional packer in Slim Hole The method for blocking of Slim Hole perforated interval, does not need packer, completes to block according to closure principle from top to bottom.No It is applicable only to permanently shunt in a well, applies also for the overhaul of Slim Hole.
The present invention proposes a kind of method for blocking of Slim Hole perforated interval, the Slim Hole perforated interval Method for blocking include the following steps:
Step S100 opens Wellhead packer, workover fluid is injected into casing, using the first gauguste cutter drifting to hanger Top, then using the second gauguste cutter drifting to the artificial bottom of a well of sidetracking well section;
Step S200, tripping in working string successively carry out closure operation to each perforated interval from top to bottom, until leaning on The perforated interval of the nearly artificial bottom of a well completes the closure operation;
Step S300, drag bit clears up described sleeve pipe until the artificial bottom of a well;
Wherein, the closure operation in the step S200 includes the following steps:
Step S210 plays cement cap to the perforated interval by the working string in the lower section of the perforated interval, Time, which is coagulated to the cement cap, to be formed;
Step S220 carries out squeeze method to the perforated interval and blocks operation, and in described sleeve pipe and in the hanging water The top of the bod forms the interim cement plug of the perforated interval;The Wellhead packer is closed, time with pressure is coagulated to the interim water Bod molding;
Step S230, opens the Wellhead packer, tripping in drag bit, and the drag bit touches the interim water The bod, the drag bit successively drill the interim cement plug and the cement cap from top to bottom, complete the perforated hole The closure operation of section.
Further, in the step S210, the bottom end of the working string is made to be located at the lower section of the perforated interval;
Further include step S215 between the step S210 and the step S220, above mention the working string, makes described The bottom end of working string is located at the top in the upper bound of the perforated interval, or the bottom end of the working string is made to be located at the perforated hole Section lower bound lower section and in the top of the cement cap.
Further, in the step S230, after the drag bit touches the interim cement plug, and in institute Stating before drag bit successively drills the interim cement plug and the cement cap from top to bottom further includes step S231, institute Drag bit cleaning described sleeve pipe is stated, exposes the eyelet at the perforated interval, closes the Wellhead packer, it is described this Perforated interval pressure testing;
If pressure testing is qualified, the Wellhead packer is opened, the drag bit in execution step S230 is from top to bottom Successively drill the interim cement plug and the cement cap;If pressure testing is unqualified, the step S220 is executed.
Further, in the step S220, it is to squeeze superfine cement to block operation or squeeze general that the squeeze method, which blocks operation, Logical grout off operation.
Further, in the step S215, the bottom end of the working string is located at the upper of the upper bound of the perforated interval Just, and at a distance from the upper bound of the perforated interval it is greater than or equal to 5 meters or the bottom end of the working string is located at the perforated hole Section lower bound lower section and in the top of the cement cap, and at a distance from the lower bound of the perforated interval be greater than or equal to 3 Rice, and it is less than or equal to 5 meters.
Further, in the step S215, the distance for above mentioning the working string is greater than or equal to 10 meters.
Further, in the step S210, the cement cap with a thickness of 10 meters.
Further, in the step S231, when pressure testing, test pressure is 25 megapascal, is kept for 30 minutes, works as pressure drop When less than or equal to 0.5 megapascal, pressure testing is qualified;When pressure drop is greater than 0.5 megapascal, pressure testing is unqualified.
It further, further include step S400, Xiang Suoshu after the step S300 if carrying out permanent capping operation Segmentation note integral cement plug, makes the top surface of the integral cement plug be located at the top of the hanger in casing;Then to well head Sprue bushing protects liquid in the well section of the top surface of the integral cement plug.
Further, with pressure 48 hours a length of when waiting solidifying in the step S220.
The present invention also proposes a kind of method for blocking of Slim Hole perforated interval, the Slim Hole perforated hole The method for blocking of section includes the following steps:
Step S10 opens Wellhead packer, workover fluid is injected into casing, using the first gauguste cutter drifting to hanger Top, then using the second gauguste cutter drifting to the artificial bottom of a well of sidetracking well section;
Step S20, tripping in working string, and its bottom end is made to be located at first perforation in the sidetracking well section from top to bottom Then the first cement cap is played by the working string in the lower section of well section, time, which is coagulated to first cement cap, to be formed;
Step S30 carries out squeeze method to first perforated interval and blocks operation, and in described sleeve pipe and described The top of first cement cap forms the first interim cement plug;Wellhead packer is closed, time with pressure is coagulated to described first temporarily Cement plug molding;
Step S40, opens the Wellhead packer, tripping in drag bit, and the drag bit touches described first and faces When cement plug, the drag bit successively drills the described first interim cement plug and first cement cap from top to bottom;
Step S50, the working string sequentially pass through the described first interim cement plug and described first vacantly from top to bottom After cement plug, continue working string described in downward tripping in, and make its bottom end be located in the sidetracking well section from top to bottom second Then the second cement cap is played by the working string in the lower section of a perforated interval;
Step S60 carries out squeeze method to second perforated interval and blocks operation, and in described sleeve pipe and described The top of second cement cap forms the second interim cement plug;The Wellhead packer is closed, time with pressure is coagulated to described second Interim cement plug molding;
Step S70 opens the Wellhead packer, and the drag bit cleaning described sleeve pipe is until the artificial bottom of a well.
Further, further include step S65 between the step S60 and step S70, have extremely in the sidetracking well section Few three perforated intervals, from top to bottom successively execute the perforated interval being located at below second perforated interval Step S40 ', step S50 ' and step S60 ' are blocked until the perforated interval close to the artificial bottom of a well completes squeeze method Operation;
The step S40 ' is to open the Wellhead packer, and drag bit described in tripping in, the drag bit touches Adjacent interim cement plug above the perforated interval, the drag bit successively drill adjacent above the perforated interval from top to bottom Interim cement plug and the perforated interval above adjacent cement cap;
The step S50 ' is that the working string sequentially passes through interim water adjacent above the perforated interval from top to bottom Above the bod and the perforated interval after adjacent cement cap, continue working string described in downward tripping in, and makes its bottom end position In the lower section of the perforated interval, the corresponding cement cap of the perforated interval is then beaten by the working string;
The step S60 ' is, carries out squeeze method the perforated interval and blocks operation, and in described sleeve pipe and The top of the corresponding cement cap of the perforated interval forms the corresponding interim cement plug of the perforated interval;Close the well head envelope Well device, time with pressure coagulate interim cement plug molding corresponding to the perforated interval.
The beneficial effect of the present invention compared with the prior art is: the closure of Slim Hole perforated interval of the invention Method does not need packer, completes to block according to closure principle from top to bottom, can be applied not only to permanently shunt in a well, may be used also Applied to the overhaul of Slim Hole, it is made to resume production again.Matching packer is avoided, is also avoided in slim-hole side The accident that packer construction is easy to cause is carried out in drilling well.
During carrying out closure operation to each perforated interval from top to bottom, operation is blocked in squeeze method each time Later, to the perforated interval pressure testing, to detect closure quality, pressure testing inspection is unqualified to be continued to block operation, ensure that Each perforated interval can be blocked completely, it is ensured that be blocked successfully.
Detailed description of the invention
Fig. 1 is structural representation of the wellbore before construction in the method for blocking of Slim Hole perforated interval of the invention Figure;
Fig. 2 is structure of the wellbore when constructing completion in the method for blocking of Slim Hole perforated interval of the invention Schematic diagram.
Appended drawing reference:
10- hanger;20- casing;The artificial bottom of a well 30-;
The upper bound of first perforated interval of 42-;
The lower bound of first perforated interval of 44-;
The upper bound of second perforated interval of 52-;
The lower bound of second perforated interval of 54-;
The top surface of 62- integral cement plug.
Specific embodiment
Below in conjunction with attached drawing, the technical characteristic and advantage above-mentioned to the present invention are clearly and completely described, it is clear that institute The embodiment of description is only section Example of the invention, rather than whole embodiments.
It please refers to shown in Fig. 1 and Fig. 2, there are at least two perforated intervals in sidetracking well section, each perforated interval distinguishes position The eyelet being connected with place stratum is respectively provided on casing 20 at the different depth of sidetracking well section, each perforated interval (in figure It is not shown).In Fig. 1 and embodiment shown in Fig. 2, in sidetracking well section tool there are two perforated interval, first perforated interval it is upper Be first perforated interval from top to bottom between boundary 42 and the lower bound 44 of first perforated interval, second perforated interval it is upper It is second perforated interval from top to bottom between boundary 52 and the lower bound 54 of second perforated interval.
A kind of method for blocking of Slim Hole perforated interval of the invention includes the following steps:
Step S100 opens Wellhead packer, injects workover fluid into casing 20, using the first gauguste cutter drifting to suspension The top of device 10, then using the second gauguste cutter drifting to the artificial bottom of a well of sidetracking well section 30;
Step S200, tripping in working string successively carry out closure operation to each perforated interval from top to bottom, until leaning on The perforated interval of nearly artificial bottom of a well 30 (most beneath) is completed to block operation;In the present embodiment, working string is light pipe;
Step S300, drag bit clears up casing 20 until artificial bottom of a well 30;
Wherein, the closure operation in step S200 includes the following steps:
Step S210 beats cement cap, Hou Ning to the perforated interval by working string in the lower section of the perforated interval It is formed to cement cap;
Step S220 carries out squeeze method to the perforated interval and blocks operation, and in casing 20 and in cement cap Top forms the interim cement plug of the perforated interval;Wellhead packer is closed, time with pressure, which is coagulated to interim cement plug, to be formed;
Step S230 opens Wellhead packer, tripping in drag bit, and drag bit touches interim cement plug, and scraper bores Head successively drills interim cement plug and cement cap from top to bottom, completes the closure operation of the perforated interval.
In step S210, cement cap plays the role of similar packer, by cement cap by the perforated hole Lower bound to the lower bound of well section and the perforated interval between well head to the well section between artificial bottom of a well 30 of section separates, subsequent Step S220 in, blocking of the cement by cement cap of working string injection could pass through the eyelet of the perforated interval Into corresponding stratum.
In step S230, when drilling interim cement plug and cement cap, the channel that can only drill out a perforation is supplied Drag bit tripping in can also clean out interim cement plug and cement cap completely.Can according to different needs and The drag bit of casing size selection different size in sidetracked hole.
It, will be remaining interim in each perforated interval during drag bit clears up casing 20 in step S300 Cement plug and cement cap are cleaned out.
Since in the prior art, slim-hole matching packer is more difficult, and the cement that also can be lowered into slim-hole holds stream Device.In addition, tripping in packer is easy to by card in sidetracked hole, construction is easier that thing occurs especially in Slim Hole Therefore.Such risk is then avoided using the method for blocking of Slim Hole perforated interval of the invention, does not need packer, It completes to block according to closure principle from top to bottom, can be applied not only to permanently shunt in a well, apply also for Slim Hole Overhaul, so that it is resumed production again.
If permanently shunt in a well, also need to be segmented note integral cement plug into casing 20 (below after step S300 It will be described in detail).It, can be in sidetracking well section after completing to block operation to each perforated interval if carrying out large repairs operation The other positions of casing 20 perforation again carries out mining operations;It can also continue to dig a well downwards from artificial bottom of a well 30, deeper Stratum in exploit.
Conventional operation mode from bottom to up, after carrying out closure operation to the perforated interval of lower section, at this time due to top Perforated interval do not blocked, if to examine the closure quality of the perforated interval of lower section, need using packer, by lower section Perforated interval and the perforated interval of top separate, form confined space, then can the pressure testing in this confined space.If Not by tools such as packers, then pressure testing operation can not be carried out, the closure quality of the perforated interval of lower section cannot be examined.
The method for blocking of Slim Hole perforated interval of the invention first blocks the perforated interval of top layer, at this time most The perforated interval on upper layer is blocked, and is not missed on the casing 20 above it, therefore, in the perforation of well head and top layer Confined space is formed between well section, then can the pressure testing in this confined space, to examine the sealing matter of top layer's perforated interval Amount.It gradually blocks from top to bottom, pressure testing inspection can be carried out immediately later by blocking operation every time;Pressure testing is unqualified, repeats to squeeze Grout off operation does not need matching and tripping in packer, saves the activity duration, improve operating efficiency.
The present invention proposes top-down closure principle, to each according to the casing programme feature of Slim Hole Cement cap is respectively adopted in perforated interval, the method with pressure for waiting the closure operation of solidifying and squeeze method is completed to the effective of perforated interval It blocks.Blocking perforated interval is to guarantee that casing is not missed to block the preforation tunnel on casing.
Further, in step S210, the bottom end of working string is made to be located at the lower section of the perforated interval;
Further include step S215 between step S210 and step S220, above mention working string, makes the bottom end position of working string In the top in the upper bound of the perforated interval, or make the bottom end of working string be located at the perforated interval lower bound lower section, and The top of cement cap.Working string is above suitably mentioned, the lower end of working string can be made to depart slightly from cement cap, thus When subsequent squeeze method being facilitated to block operation, cement is exported from working string, and then swimmingly from the eyelet of the perforated interval, from And block the perforated interval.
Further, in step S230, after drag bit touches interim cement plug, and drag bit from up to Under successively drill interim cement plug and cement cap before further include step S231, drag bit clears up casing 20, and exposing should Eyelet at perforated interval closes Wellhead packer, to the perforated interval pressure testing;
If pressure testing is qualified, Wellhead packer is opened, the drag bit executed in step S230 successively drills from top to bottom Interim cement plug and cement cap;If pressure testing is unqualified, step S220 is executed.
During carrying out closure operation to each perforated interval from top to bottom, operation is blocked in squeeze method each time Later, to the perforated interval pressure testing, to detect closure quality, pressure testing inspection is unqualified to be continued to block operation, ensure that Each perforated interval can be blocked completely, it is ensured that be blocked successfully.
Further, in step S220, it is to squeeze superfine cement to block operation or crowded light water mudding that squeeze method, which blocks operation, Stifled operation.If stratum is gas-bearing formation, squeezes superfine cement and block operation with preferable plugging effect;If stratum is oil reservoir, squeeze Superfine cement blocks operation and crowded ordinary cement blocks operation and all has preferable plugging effect.In most cases stratum is Oil reservoir, requirement can be met by blocking operation using crowded ordinary cement.
The average grain diameter of superfine cement, hereinafter, the slurry fluidity of superfine cement is good, has stability and can fill at 5 microns The high advantage of property.Domestic-developed go out only 7 microns of the superfine cement average grain diameter for oil well, be seven points of conventional G class g cement One of or so, since particle is small, make sealing agent that there is good mobility and penetrability, the radius that can squeeze into processing is also relatively common Cement is much bigger.
Further, in step S215, the bottom end of working string is located at the top in the upper bound of the perforated interval, and with this The distance in the upper bound of perforated interval is greater than or equal to 5 meters or the bottom end of working string is located under the lower bound of the perforated interval Just and in the top of cement cap, and at a distance from the lower bound of the perforated interval it is greater than or equal to 3 meters, and is less than or equal to 5 Rice.
Further, in step S215, the distance for above mentioning working string is greater than or equal to 10 meters.
Further, in step S210, cement cap with a thickness of 10 meters.
Further, in step S231, when pressure testing, test pressure is 25 megapascal, is kept for 30 minutes, when pressure drop is less than Or when being equal to 0.5 megapascal, pressure testing is qualified;When pressure drop is greater than 0.5 megapascal, pressure testing is unqualified.
Further, if permanently shunt in a well, further include step S400 after step S300, be segmented into casing 20 Integral cement plug is infused, the top surface 62 of integral cement plug is made to be located at the top of hanger 10;Then to well head to integral cement plug Sprue bushing protects liquid in the well section of top surface 62, and more preferably, the density of casing protection liquid is 1.0g/cm3~1.1g/cm3
Further, with pressure 48 hours a length of when waiting solidifying in step S220.
The present invention also proposes a kind of method for blocking of Slim Hole perforated interval, includes the following steps:
Step S10 opens Wellhead packer, injects workover fluid into casing 20, using the first gauguste cutter drifting to suspension The top of device 10, then using the second gauguste cutter drifting to the artificial bottom of a well of sidetracking well section 30;
Step S20, tripping in working string, and its bottom end is made to be located at first perforated interval in sidetracking well section from top to bottom Lower section, the first cement cap is then made a call to by working string, the first cement cap of Hou Ningzhi forms;
Step S30 carries out squeeze method to first perforated interval and blocks operation, and in casing 20 and in the first hanging water The top of the bod forms the first interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the first interim cement plug molding;
Step S40, opens Wellhead packer, tripping in drag bit, and drag bit touches the first interim cement plug, scraper Drill bit successively drills the first interim cement plug and the first cement cap from top to bottom;
Step S50 after working string sequentially passes through the first interim cement plug and the first cement cap from top to bottom, continues Downward tripping in working string, and the lower section for second perforated interval for being located at its bottom end in sidetracking well section from top to bottom, Then the second cement cap is made a call to by working string;
Step S60 carries out squeeze method to second perforated interval and blocks operation, and in casing 20 and in the second hanging water The top of the bod forms the second interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the second interim cement plug molding;
Step S70 opens Wellhead packer, and drag bit clears up casing 20 until artificial bottom of a well 30.
In step S70, during drag bit clears up casing 20, by interim cement remaining in each perforated interval Plug and cement cap are cleaned out.
Further include following steps after the step s 70 if necessary to permanent shut-in well: into casing 20, segmentation note is whole Cement plug makes the top surface 62 of integral cement plug be located at the top of hanger 10;Then to well head to the top surface of integral cement plug 62 Well section in sprue bushing protect liquid.
Further, further include step S65 between step S60 and step S70, have at least three to penetrate in sidetracking well section Hole well section, from top to bottom successively to the perforated interval being located at below second perforated interval execute step S40 ', step S50 ' and Step S60 ', until the perforated interval close to artificial bottom of a well 30, which completes squeeze method, blocks operation;
Step S40 ' is to open Wellhead packer, tripping in drag bit, and drag bit touches phase above the perforated interval Adjacent interim cement plug, drag bit successively drill interim cement plug and the perforation adjacent above the perforated interval from top to bottom Adjacent cement cap above well section;
Step S50 ' is that working string sequentially passes through interim cement plug adjacent above the perforated interval from top to bottom and should Above perforated interval after adjacent cement cap, continue downward tripping in working string, and its bottom end is made to be located at the perforated interval Lower section, the corresponding cement cap of the perforated interval is then beaten by working string;
Step S60 ' is to carry out squeeze method the perforated interval and block operation, and in casing 20 and in the perforation The top of the corresponding cement cap of well section forms the corresponding interim cement plug of the perforated interval;Wellhead packer is closed, it is with pressure Time coagulates interim cement plug molding corresponding to the perforated interval.
If there are three perforated intervals for tool in sidetracking well section, a step is executed between step S60 and step S70 S40 ', step S50 ' and step S60 ';
At this point, step S40 ' is specifically, open Wellhead packer, tripping in drag bit, drag bit touches second and faces When cement plug, drag bit successively drills the second interim cement plug and the second cement cap from top to bottom;
Step S50 ' is specifically, working string sequentially passes through the second interim cement plug and the second cement cap from top to bottom Afterwards, continue downward tripping in working string, and be located at its bottom end under the third perforated interval in sidetracking well section from top to bottom Then third cement cap is played by working string by side;
Step S60 ' blocks operation specifically, carrying out squeeze method to third perforated interval, and in casing 20 and the The top of three cement caps forms the interim cement plug of third;Wellhead packer is closed, time with pressure is coagulated to the interim cement plug of third Molding.
That is, if there are three perforated intervals, another Slim Hole of the invention to penetrate for tool in sidetracking well section The method for blocking of hole well section, includes the following steps:
Step S10 opens Wellhead packer, injects workover fluid into casing 20, using the first gauguste cutter drifting to suspension The top of device 10, then using the second gauguste cutter drifting to the artificial bottom of a well of sidetracking well section 30;
Step S20, tripping in working string, and its bottom end is made to be located at first perforated interval in sidetracking well section from top to bottom Lower section, the first cement cap is then made a call to by working string, the first cement cap of Hou Ningzhi forms;
Step S30 carries out squeeze method to first perforated interval and blocks operation, and in casing 20 and in the first hanging water The top of the bod forms the first interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the first interim cement plug molding;
Step S40, opens Wellhead packer, tripping in drag bit, and drag bit touches the first interim cement plug, scraper Drill bit successively drills the first interim cement plug and the first cement cap from top to bottom;
Step S50 after working string sequentially passes through the first interim cement plug and the first cement cap from top to bottom, continues Downward tripping in working string, and the lower section for second perforated interval for being located at its bottom end in sidetracking well section from top to bottom, then The second cement cap is played by working string;
Step S60 carries out squeeze method to second perforated interval and blocks operation, and in casing 20 and in the second hanging water The top of the bod forms the second interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the second interim cement plug molding;
Step S40 ', opens Wellhead packer, tripping in drag bit, and drag bit touches the second interim cement plug, scrapes Knife drill bit successively drills the second interim cement plug and the second cement cap from top to bottom;
Step S50 ', after working string sequentially passes through the second interim cement plug and the second cement cap from top to bottom, after The lower section for the third perforated interval for continuing downward tripping in working string, and being located at its bottom end in sidetracking well section from top to bottom, so Third cement cap is beaten by working string afterwards;
Step S60 ' carries out squeeze method to third perforated interval and blocks operation, and in casing 20 and hanging in third The top of cement plug forms the interim cement plug of third;Wellhead packer is closed, time with pressure is coagulated to the interim cement plug molding of third;
Step S70 opens Wellhead packer, and drag bit clears up casing 20 until artificial bottom of a well 30;In step S70, During drag bit clears up casing 20, interim cement plug remaining in each perforated interval and cement cap are cleared up dry Only, the interim cement plug of third and third cement cap are also cleaned at this time.
Further include following steps after the step s 70 if necessary to permanent shut-in well: into casing 20, segmentation note is whole Cement plug makes the top surface 62 of integral cement plug be located at the top of hanger 10;Then to well head to the top surface of integral cement plug 62 Well section in sprue bushing protect liquid.
In this way, the closure operation of three perforated intervals can be realized smoothly.
If there are four perforated intervals for tool in sidetracking well section, step twice is executed between step S60 and step S70 S40 ', step S50 ' and step S60 ', in this not go into detail.
By taking Fig. 1 and embodiment shown in Fig. 2 as an example, there are two perforated interval, first perforated intervals for tool in sidetracking well section The upper bound 42 and first perforated interval lower bound 44 between for first perforated interval from top to bottom, second perforated interval The upper bound 52 and second perforated interval lower bound 54 between for second perforated interval from top to bottom, Slim Hole is penetrated The step of method for blocking of hole well section, enumerates as follows:
Wellhead packer is opened, workover fluid is injected into casing 20, using the first gauguste cutter drifting to the top of hanger 10 Portion, then using the second gauguste cutter drifting to the artificial bottom of a well of sidetracking well section 30;The main borehole of straight well section has been before sidetracking Using wedge deflection tool and grout off;
Tripping in working string, and the lower section for first perforated interval for being located at its bottom end in sidetracking well section from top to bottom, Then the first cement cap, the molding of the first cement cap of Hou Ningzhi are made a call to by working string;
Squeeze method is carried out to first perforated interval and blocks operation, and in casing 20 and in the upper of the first cement cap It is rectangular at the first interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the first interim cement plug molding;At this point, first faces When cement plug can be condensed with the first cement cap it is integral;
More preferably, before blocking operation to first perforated interval squeeze method, working string is above mentioned, working string is made Bottom end is located at the top in the upper bound 42 of first perforated interval, and is greater than or waits at a distance from the upper bound of first perforated interval 42 It is located at the lower section of the lower bound 44 of first perforated interval in the bottom end of 5 meters or working string and in the top of cement cap, And it is greater than or equal to 3 meters at a distance from the lower bound of the first perforated interval 44, and be less than or equal to 5 meters;
Wellhead packer, tripping in drag bit are opened, drag bit touches the first interim cement plug, and drag bit is successively Drill the first interim cement plug and the first cement cap;
More preferably, after " drag bit touches the first interim cement plug ", and " drag bit is from top to bottom successively Drill the first interim cement plug and the first cement cap " before, drag bit clears up casing 20, and it is interim not drill first temporarily Cement plug and the first cement cap expose the eyelet at first perforated interval, Wellhead packer are closed, to the perforation Well section pressure testing;If pressure testing is qualified, Wellhead packer is opened, continues to execute that " drag bit successively drills first from top to bottom and faces When cement plug and the first cement cap ";If pressure testing is unqualified, squeeze method is carried out to first perforated interval again and blocks work Industry, until first perforated interval blocks completely;
After working string passes through the first interim cement plug and the first cement cap, continue downward tripping in, and make its bottom end Then the second hanging cement is broken by working string in the lower section of second perforated interval in sidetracking well section from top to bottom Plug, the molding of the second cement cap of Hou Ningzhi;
Squeeze method is carried out to second perforated interval and blocks operation, and in casing 20 and in the upper of the second cement cap It is rectangular at the second interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the second interim cement plug molding;At this point, second faces When cement plug can be condensed with the second cement cap it is integral;
More preferably, before blocking operation to second perforated interval squeeze method, working string is above mentioned, working string is made Bottom end is located at the top in the upper bound 52 of second perforated interval, and is greater than or waits at a distance from the upper bound of second perforated interval 52 It is located at the lower section of the lower bound 54 of second perforated interval in the bottom end of 5 meters or working string and in the top of cement cap, And it is greater than or equal to 3 meters at a distance from the lower bound of the second perforated interval 54, and be less than or equal to 5 meters;
Wellhead packer is opened, drag bit clears up casing 20 to artificial bottom of a well 30, and then segmentation note is whole into casing 20 Body cement plug makes the top surface 62 of integral cement plug be located at the top of hanger 10;
More preferably, tripping in drag bit, after drag bit touches the second interim cement plug, drag bit cleaning set Pipe 20 does not drill the second interim cement plug and the second cement cap temporarily, exposes the eyelet at second perforated interval , the Wellhead packer is closed, to second perforated interval pressure testing;If pressure testing is qualified, Wellhead packer is opened, Drag bit continuation successively drills the second interim cement plug and the second cement cap from top to bottom, and clears up casing gradually downward 20 to artificial bottom of a well 30;If pressure testing is unqualified, squeeze method is carried out to second perforated interval again and blocks operation, until second A perforated interval blocks completely.
It is respectively 2445.7 meters~2469.8 meters of well depth and well depth with first perforated interval and second perforated interval 2652.8 meters~2680.0 meters, for carrying out permanent capping operation, pass through following methods, it is ensured that sidetracked hole slim-hole is strong Under the service condition that note is adopted by force, pressure alternately changes, reach effective closure in 50 years.
1, using workover fluid kill-job;Gauguste cutter (i.e. the first gauguste cutter) drifting that 118 millimeters of diameter is to the top of hanger 10 Portion (well depth × 2353.00 meter), gauguste cutter (i.e. the second gauguste cutter) drifting that 75 millimeters of diameter to artificial bottom of a well 30 (well depth × 2766.0 rice);
2, first 2445.7 meters~2469.8 meters of perforated interval are blocked;
(1) 60 millimeters of diameter of working string × 2485.0 meter under, play cement cap, and the cement surface of cement cap × 2472.0 rice;
(2) after Hou Ning 24 hours, cement surface × 2472.0 meter of cement cap are visited;
(3) working string × 2435.0 meter are above mentioned, superfine cement is squeezed and blocks 2445.7 meters~2469.8 meters of perforated interval;This In embodiment, 20 meters of working string are above mentioned;
(4) Wellhead packer is closed, after time with pressure is 48 hours solidifying, the drag bit of 75 millimeters of lower diameter visits the water in casing 20 The bod (the first interim cement plug) and drilling out are to × 2472.0 meters, pressure testing: P=25MPa, 30min, △ P≤0.5MPa are Qualification, pressure testing is unqualified squeeze seal to block up again;
(5) after confirmation pressure testing is qualified, continue drilling out drifting to × 2766.0 meters;
3, first 2652.8 meters~2680.0 meters of perforated interval are blocked;Specific steps are similar with first perforated interval, Details are not described herein;
4, segmentation note integral cement plug, 1500.0 meters~2766.0 meters of well section;
5, top surface × 1500.0 meter of integral cement plug to well head fills casing protection liquid, and the density of casing protection liquid is 1.0g/cm3~1.1g/cm3
6, installing can the antitheft well head of kill-job and pressure gauge.
Particular embodiments described above has carried out further the purpose of the present invention, technical scheme and beneficial effects It is described in detail, it should be understood that the above is only a specific embodiment of the present invention, the protection being not intended to limit the present invention Range.It particularly points out, to those skilled in the art, all within the spirits and principles of the present invention, that is done any repairs Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (12)

1. a kind of method for blocking of Slim Hole perforated interval, which is characterized in that the Slim Hole perforated interval Method for blocking include the following steps:
Step S100 opens Wellhead packer, workover fluid is injected into casing, using the first gauguste cutter drifting to the top of hanger Portion, then using the second gauguste cutter drifting to the artificial bottom of a well of sidetracking well section;
Step S200, tripping in working string successively carry out closure operation to each perforated interval from top to bottom, until close to institute The perforated interval for stating artificial bottom of a well completes the closure operation;
Step S300, drag bit clears up described sleeve pipe until the artificial bottom of a well;
Wherein, the closure operation in the step S200 includes the following steps:
Step S210 successively passes through the working string to the perforated hole the lower section of each perforated interval from top to bottom Section plays cement cap, and time, which is coagulated to the cement cap, to be formed;
Step S220 successively carries out squeeze method each described perforated interval from top to bottom and blocks operation, and in described sleeve pipe It is interior and form the interim cement plug of the perforated interval in the top of the cement cap;The Wellhead packer is closed, it is with pressure Time, which is coagulated to the interim cement plug, to be formed;
Step S230, opens the Wellhead packer, tripping in drag bit, and the drag bit touches the interim cement Plug, the drag bit successively drill the interim cement plug and the cement cap from top to bottom, complete the perforated interval Closure operation.
2. the method for blocking of Slim Hole perforated interval according to claim 1, which is characterized in that in the step In S210, the bottom end of the working string is made to be located at the lower section of the perforated interval;
Further include step S215 between the step S210 and the step S220, above mention the working string, makes the operation The bottom end of tubing string is located at the top in the upper bound of the perforated interval, or the bottom end of the working string is made to be located at the perforated interval The lower section of lower bound and in the top of the cement cap.
3. the method for blocking of Slim Hole perforated interval according to claim 1, which is characterized in that the step In S230, successively bored from top to bottom after the drag bit touches the interim cement plug, and in the drag bit Wearing the interim cement plug and the cement cap further includes before step S231, clears up the set using the drag bit Pipe, exposes the eyelet at the perforated interval, closes the Wellhead packer, the perforated interval pressure testing;
If pressure testing is qualified, the Wellhead packer is opened, execute the drag bit in step S230 from top to bottom successively Drill the interim cement plug and the cement cap;If pressure testing is unqualified, the step S220 is executed.
4. the method for blocking of Slim Hole perforated interval according to any one of claims 1 to 3, which is characterized in that In the step S220, it is to squeeze superfine cement to block operation or the closure operation of crowded ordinary cement that the squeeze method, which blocks operation,.
5. the method for blocking of Slim Hole perforated interval according to claim 2, which is characterized in that the step In S215, the bottom end of the working string is located at the top in the upper bound of the perforated interval, and with the upper bound of the perforated interval away from Lower section from the lower bound that the bottom end for being greater than or equal to 5 meters or the working string is located at the perforated interval and it is described vacantly The top of cement plug, and it is greater than or equal to 3 meters at a distance from the lower bound of the perforated interval, and be less than or equal to 5 meters.
6. the method for blocking of Slim Hole perforated interval according to claim 2, which is characterized in that the step In S215, the distance for above mentioning the working string is greater than or equal to 10 meters.
7. the method for blocking of Slim Hole perforated interval according to claim 1, which is characterized in that the step In S210, the cement cap with a thickness of 10 meters.
8. the method for blocking of Slim Hole perforated interval according to claim 3, which is characterized in that the step In S231, when pressure testing, test pressure is 25 megapascal, is kept for 30 minutes, and when pressure drop is less than or equal to 0.5 megapascal, pressure testing is closed Lattice;When pressure drop is greater than 0.5 megapascal, pressure testing is unqualified.
9. the method for blocking of Slim Hole perforated interval according to claim 1, which is characterized in that if carried out forever Long property capping operation, the step S300 further include later step S400, and into described sleeve pipe, segmentation note integral cement plug, makes institute The top surface for stating integral cement plug is located at the top of the hanger;Then to well head to the well section of the top surface of the integral cement plug Interior sprue bushing protects liquid.
10. the method for blocking of Slim Hole perforated interval according to claim 1, which is characterized in that the step It is with pressure 48 hours a length of when waiting solidifying in S220.
11. a kind of method for blocking of Slim Hole perforated interval, which is characterized in that the Slim Hole perforated interval Method for blocking include the following steps:
Step S10 opens Wellhead packer, workover fluid is injected into casing, using the first gauguste cutter drifting to the top of hanger Portion, then using the second gauguste cutter drifting to the artificial bottom of a well of sidetracking well section;
Step S20, tripping in working string, and its bottom end is made to be located at first perforated interval in the sidetracking well section from top to bottom Lower section, the first cement cap is then made a call to by the working string, time is coagulated to first cement cap molding;
Step S30 carries out squeeze method to first perforated interval and blocks operation, and in described sleeve pipe and described first The top of cement cap forms the first interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the described first interim cement Plug molding;
Step S40, opens the Wellhead packer, tripping in drag bit, and the drag bit touches the described first interim water The bod, the drag bit successively drill the described first interim cement plug and first cement cap from top to bottom;
Step S50, the working string sequentially pass through the described first interim cement plug and the first hanging cement from top to bottom After plug, continue working string described in downward tripping in, and its bottom end is made to be located at second institute in the sidetracking well section from top to bottom The lower section of perforated interval is stated, the second cement cap is then made a call to by the working string;
Step S60 carries out squeeze method to second perforated interval and blocks operation, and in described sleeve pipe and described second The top of cement cap forms the second interim cement plug;The Wellhead packer is closed, time with pressure is coagulated to described second temporarily Cement plug molding;
Step S70 opens the Wellhead packer, and the drag bit cleaning described sleeve pipe is until the artificial bottom of a well.
12. the method for blocking of Slim Hole perforated interval according to claim 11, which is characterized in that in the step Further include step S65 between rapid S60 and step S70, there are at least three perforated intervals in the sidetracking well section, from up to Under step S40 ', step S50 ' and step successively are executed to the perforated interval being located at below second perforated interval S60 ', until the perforated interval close to the artificial bottom of a well, which completes squeeze method, blocks operation;
The step S40 ' is to open the Wellhead packer, and drag bit described in tripping in, the drag bit touches this and penetrates Adjacent interim cement plug above the well section of hole, the drag bit successively drill adjacent above the perforated interval face from top to bottom When cement plug and the perforated interval above adjacent cement cap;
The step S50 ' is that the working string sequentially passes through interim cement plug adjacent above the perforated interval from top to bottom With above the perforated interval after adjacent cement cap, continue working string described in downward tripping in, and being located at its bottom end should Then the corresponding cement cap of the perforated interval is played by the working string in the lower section of perforated interval;
The step S60 ' is, carries out squeeze method the perforated interval and blocks operation, and penetrates in described sleeve pipe and at this The top of the corresponding cement cap of hole well section forms the corresponding interim cement plug of the perforated interval;Close the well head shut-in well Device, time with pressure coagulate interim cement plug molding corresponding to the perforated interval.
CN201611075931.3A 2016-11-29 2016-11-29 Plugging method for perforating well section of slim hole sidetracked well Active CN106639969B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611075931.3A CN106639969B (en) 2016-11-29 2016-11-29 Plugging method for perforating well section of slim hole sidetracked well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611075931.3A CN106639969B (en) 2016-11-29 2016-11-29 Plugging method for perforating well section of slim hole sidetracked well

Publications (2)

Publication Number Publication Date
CN106639969A CN106639969A (en) 2017-05-10
CN106639969B true CN106639969B (en) 2019-03-15

Family

ID=58813112

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611075931.3A Active CN106639969B (en) 2016-11-29 2016-11-29 Plugging method for perforating well section of slim hole sidetracked well

Country Status (1)

Country Link
CN (1) CN106639969B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403912B (en) * 2018-02-27 2020-10-27 中石化石油工程技术服务有限公司 Method for horizontal well cementing plug and construction method
CN108547590B (en) * 2018-03-30 2020-07-31 重庆大学 Method for carrying out long-term well sealing on salt cavern storage by utilizing self-healing characteristic of salt rock damage

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1621658A (en) * 2003-11-28 2005-06-01 大港油田集团有限责任公司 Well cementing technology by center tube replacing elutriation method
CN101718171A (en) * 2009-11-17 2010-06-02 中国石油集团长城钻探工程有限公司 Drilling completion matching method for sidetracking horizontal well
CN101818619A (en) * 2010-03-24 2010-09-01 中国石油集团川庆钻探工程有限公司 Temporary sealing open hole casing branch well cementing and completion structure and process
CN103184851A (en) * 2011-12-28 2013-07-03 陈美玲 Plugging technology for highly-deviated well with big casing pipe

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2003273309A1 (en) * 2002-09-09 2004-03-29 Tomahawk Wellhead And Services, Inc. Top drive swivel apparatus and method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1621658A (en) * 2003-11-28 2005-06-01 大港油田集团有限责任公司 Well cementing technology by center tube replacing elutriation method
CN101718171A (en) * 2009-11-17 2010-06-02 中国石油集团长城钻探工程有限公司 Drilling completion matching method for sidetracking horizontal well
CN101818619A (en) * 2010-03-24 2010-09-01 中国石油集团川庆钻探工程有限公司 Temporary sealing open hole casing branch well cementing and completion structure and process
CN103184851A (en) * 2011-12-28 2013-07-03 陈美玲 Plugging technology for highly-deviated well with big casing pipe

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
小井眼开窗侧钻井固井工艺技术;蒋海涛;《石油钻采工艺》;20030430;第29-33页
开窗侧钻小井眼、小间隙井固井应用技术;张文泽 等;《化学工程师》;20160930;第50-53页

Also Published As

Publication number Publication date
CN106639969A (en) 2017-05-10

Similar Documents

Publication Publication Date Title
US7234546B2 (en) Drilling and cementing casing system
CN100412312C (en) Method and device for repairing oil/gas drilling bushing
CA2589891C (en) Hydrocarbon sweep into horizontal transverse fractured wells
CN105756650B (en) Method for realizing staged fracturing of horizontal well by adopting mixed temporary plugging agent to block tubular channeling
CN104514513B (en) Horizontal well horizontal segment exempts from cementing method
WO2011020998A2 (en) Method for improving waterflood performance using barrier fractures and inflow control devices
US4529036A (en) Method of determining subterranean formation fracture orientation
CN106639969B (en) Plugging method for perforating well section of slim hole sidetracked well
CN106223898B (en) Two horizontal well cementing and completion integrated pipe column devices that open
US9074470B2 (en) Methods for drilling and stimulating subterranean formations for recovering hydrocarbon and natural gas resources
CN105756591A (en) Coal bed gas well completion method
RU2391491C1 (en) Method of completing auxiliary wellbore shaft construction and rig to this end
CN114109298A (en) Method for cementing lost-circulation zone well section
RU2285794C1 (en) Well bottom zone treatment method
CN200943459Y (en) Device for repairing oil-gas drilling casing
RU2196880C1 (en) Method of well two-stage cementing
CN112431583A (en) Supporting device for drilling and completion of fishbone horizontal multilateral well in unconsolidated sandstone reservoir and supporting drilling method thereof
CN110939412A (en) Development method for realizing advanced water injection and early water injection by utilizing horizontal well
CN118065856B (en) Fine fracturing process
CN108729859A (en) A kind of injection self-advancing type multiple-limb slim hole completion tool and operating method
RU2509875C2 (en) Well construction finishing method
US11629578B2 (en) Procedures for selective water shut off of passive ICD compartments
CN114198051B (en) High-sulfur-content abandoned well sealing method
CN104453773B (en) Branch borehole plugging tool and plugging method
RU2109128C1 (en) Method of injecting into wells

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant