CN106639969A - Plugging method for perforating well section of slim hole sidetracked well - Google Patents
Plugging method for perforating well section of slim hole sidetracked well Download PDFInfo
- Publication number
- CN106639969A CN106639969A CN201611075931.3A CN201611075931A CN106639969A CN 106639969 A CN106639969 A CN 106639969A CN 201611075931 A CN201611075931 A CN 201611075931A CN 106639969 A CN106639969 A CN 106639969A
- Authority
- CN
- China
- Prior art keywords
- perforated interval
- cement
- well
- cement plug
- interim
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 70
- 239000004568 cement Substances 0.000 claims abstract description 240
- 238000004140 cleaning Methods 0.000 claims abstract description 16
- 239000012530 fluid Substances 0.000 claims abstract description 10
- 238000012360 testing method Methods 0.000 claims description 39
- 230000000903 blocking effect Effects 0.000 claims description 31
- 238000007493 shaping process Methods 0.000 claims description 24
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 11
- 239000007788 liquid Substances 0.000 claims description 8
- 230000011218 segmentation Effects 0.000 claims description 7
- 238000005553 drilling Methods 0.000 abstract description 7
- 230000008439 repair process Effects 0.000 abstract description 3
- 238000007789 sealing Methods 0.000 abstract description 2
- 238000010276 construction Methods 0.000 description 5
- 241000209094 Oryza Species 0.000 description 4
- 235000007164 Oryza sativa Nutrition 0.000 description 4
- 238000007689 inspection Methods 0.000 description 4
- 238000004519 manufacturing process Methods 0.000 description 4
- 235000009566 rice Nutrition 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 3
- 239000011440 grout Substances 0.000 description 3
- 239000000725 suspension Substances 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 2
- 230000008901 benefit Effects 0.000 description 2
- 235000013339 cereals Nutrition 0.000 description 2
- 230000008859 change Effects 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000018109 developmental process Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 239000003129 oil well Substances 0.000 description 1
- 239000002245 particle Substances 0.000 description 1
- 239000003209 petroleum derivative Substances 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/10—Sealing or packing boreholes or wells in the borehole
- E21B33/13—Methods or devices for cementing, for plugging holes, crevices or the like
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B37/00—Methods or apparatus for cleaning boreholes or wells
- E21B37/02—Scrapers specially adapted therefor
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
The invention provides a plugging method of a perforating well section of a slim hole sidetracked well, wherein the plugging method comprises the following steps of S100, opening a wellhead blowout preventer, injecting workover fluid into a sleeve and dredging a well; s200, putting an operation tubular column, and sequentially plugging each perforation well section from top to bottom until the bottommost perforation well section completes plugging operation; step S300, cleaning the sleeve to the bottom of the artificial well by the scraper bit, wherein the plugging operation is as follows: the operation pipe column is used for drilling a suspended cement plug below the perforation well section; carrying out cement squeezing and plugging operation to form a temporary cement plug above the suspended cement plug; closing the wellhead blowout preventer, and waiting for setting under pressure; and opening the wellhead blowout preventer, and sequentially drilling the temporary cement plug and the suspended cement plug by the downward-entering scraper drill bit from top to bottom to finish plugging operation. The invention also provides another plugging method for the perforating well section of the slim hole sidetracked well. The invention does not need a packer, completes plugging from top to bottom, and can be used for permanent well sealing or major repair of small well bores.
Description
Technical field
The present invention relates to the technical field of petroleum gas down-hole operation, more particularly to a kind of Slim Hole perforated hole
The method for blocking of section.
Background technology
With the continuous increase of oilfield exploitation difficulty, and the development and application of new drilling technology, Slim Hole
(internal diameter of sleeve pipe is less than or equal to 86 millimeters) is more and more in the quantity of Oil Field, with these special wells inputs
Production and application, because various factors causes the phenomenon of its overhaul also more and more, such as:Due to adjusting layer or other production requirements, need
Its former perforated interval is blocked.Conventional method for blocking enters packer under being usually carries out from the bottom to top squeeze method closure,
But the internal diameter of Slim Hole Sidetracking Technology well section is too little, it is difficult to suitable small size packer is found, and construction risk is larger, easily occurs
Packer plays envelope, sets the problem of failure.
The content of the invention
The technical problem that inconvenience is blocked using conventional packer in solve Slim Hole, it is proposed by the present invention
The method for blocking of Slim Hole perforated interval, it is not necessary to packer, according to closure principle from top to bottom closure is completed.No
Permanent shut-in well is applicable only to, the overhaul of Slim Hole is applied also for.
The present invention proposes a kind of method for blocking of Slim Hole perforated interval, the Slim Hole perforated interval
Method for blocking comprise the steps:
Step S100, opens Wellhead packer, workover fluid is injected into sleeve pipe, using the first drift size gauge tool drifting to hanger
Top, then using the artificial bottom of a well of the second drift size gauge tool drifting to sidetracking well section;
Step S200, under enter working string, successively closure operation is carried out to each perforated interval from top to bottom, until leaning on
The perforated interval of the nearly artificial bottom of a well completes the closure operation;
Step S300, drag bit cleaning described sleeve pipe is until the artificial bottom of a well;
Wherein, the closure operation in step S200 comprises the steps:
Step S210, cement cap is played in the lower section of the perforated interval by the working string to the perforated interval,
Time is coagulated to cement cap shaping;
Step S220, squeeze method closure operation is carried out to the perforated interval, and in described sleeve pipe and in the hanging water
The top of the bod forms the interim cement plug of the perforated interval;The Wellhead packer is closed, time with pressure is coagulated to the interim water
The bod is molded;
Step S230, opens the Wellhead packer, under enter drag bit, the drag bit touches the interim water
The bod, the drag bit drills successively from top to bottom the interim cement plug and the cement cap, completes the perforated hole
The closure operation of section.
Further, in step S210, the bottom of the working string is made positioned at the lower section of the perforated interval;
Also include step S215 between step S210 and step S220, above carry the working string, make described
The bottom of working string is located at the top in the upper bound of the perforated interval, or makes the bottom of the working string be located at the perforated hole
Section lower bound lower section and in the top of the cement cap.
Further, in step S230, after the drag bit touches the interim cement plug, and in institute
State drag bit to drill successively from top to bottom before the interim cement plug and the cement cap also including step S231, institute
Drag bit cleaning described sleeve pipe is stated, exposes the eyelet at the perforated interval, the Wellhead packer is closed, to this described
Perforated interval pressure testing;
If pressure testing is qualified, the Wellhead packer is opened, the drag bit in execution step S230 is from top to bottom
The interim cement plug and the cement cap are drilled successively;If pressure testing is unqualified, step S220 is performed.
Further, in step S220, the squeeze method closure operation blocks operation or crowded general to squeeze superfine cement
Logical grout off operation.
Further, in step S215, the bottom of the working string is located at the upper of the upper bound of the perforated interval
Side, and it is more than or equal to 5 meters with the distance in the upper bound of the perforated interval, or the bottom of the working string is located at the perforated hole
The lower section of the lower bound of section and in the top of the cement cap, and it is more than or equal to 3 with the distance of the lower bound of the perforated interval
Rice, and less than or equal to 5 meters.
Further, in step S215, the distance for above carrying the working string is more than or equal to 10 meters.
Further, in step S210, the thickness of the cement cap is 10 meters.
Further, in step S231, during pressure testing, test pressure is 25 MPas, is kept for 30 minutes, works as pressure drop
During less than or equal to 0.5 MPa, pressure testing is qualified;When pressure drop is more than 0.5 MPa, pressure testing is unqualified.
Further, if carrying out permanent capping operation, step S400 is also included after step S300, to described
Segmentation note integral cement plug in sleeve pipe, makes the top surface of the integral cement plug positioned at the top of the hanger;Then to well head
The sprue bushing protection liquid to the well section of the top surface of the integral cement plug.
Further, it is with pressure a length of 48 hours when waiting solidifying in step S220.
The present invention also proposes a kind of method for blocking of Slim Hole perforated interval, the Slim Hole perforated hole
The method for blocking of section comprises the steps:
Step S10, opens Wellhead packer, workover fluid is injected into sleeve pipe, using the first drift size gauge tool drifting to hanger
Top, then using the artificial bottom of a well of the second drift size gauge tool drifting to sidetracking well section;
Step S20, under enter working string, and make its bottom be located at first perforation in the sidetracking well section from top to bottom
The lower section of well section, then plays the first cement cap by the working string, and time is coagulated to first cement cap shaping;
Step S30, squeeze method closure operation is carried out to first perforated interval, and in described sleeve pipe and described
The top of the first cement cap forms the first interim cement plug;Close Wellhead packer, time with pressure is coagulated to described first interim
Cement plug is molded;
Step S40, opens the Wellhead packer, under enter drag bit, the drag bit touches described first and faces
When cement plug, the drag bit drills successively from top to bottom the described first interim cement plug and first cement cap;
Step S50, the working string sequentially passes through from top to bottom the described first interim cement plug and described first hanging
After cement plug, the working string is entered under continuing downwards, and make second in the sidetracking well section from top to bottom of its bottom
The lower section of the individual perforated interval, then plays the second cement cap by the working string;
Step S60, squeeze method closure operation is carried out to second perforated interval, and in described sleeve pipe and described
The top of the second cement cap forms the second interim cement plug;The Wellhead packer is closed, time with pressure is coagulated to described second
Interim cement plug shaping;
Step S70, opens the Wellhead packer, and the drag bit cleaning described sleeve pipe is until the artificial bottom of a well.
Further, also include having extremely in step S65, the sidetracking well section between step S60 and step S70
Few three perforated intervals, are pointed to successively from top to bottom the perforated interval below second perforated interval and perform
Step S40 ', step S50 ' and step S60 ', until the perforated interval near the artificial bottom of a well completes squeeze method closure
Operation;
Step S40 ' be to open the Wellhead packer, under enter the drag bit, the drag bit is touched
The adjacent interim cement plug in the perforated interval top, it is adjacent that the drag bit drills successively from top to bottom the perforated interval top
The adjacent cement cap of interim cement plug and perforated interval top;
Step S50 ' it is that the working string sequentially passes through from top to bottom the adjacent interim water in the perforated interval top
After the adjacent cement cap in the bod and the perforated interval top, under continuing downwards the working string is entered, and make its bottom position
In the lower section of the perforated interval, then the corresponding cement cap of the perforated interval is beaten by the working string;
Step S60 ' be perforated interval this described is carried out squeeze method closure operation, and in described sleeve pipe and
The top of the corresponding cement cap of the perforated interval forms the corresponding interim cement plug of the perforated interval;Close the well head envelope
Well device, time with pressure coagulates interim cement plug shaping corresponding to the perforated interval.
The present invention is compared to the beneficial effect of prior art:The closure of the Slim Hole perforated interval of the present invention
Method, it is not necessary to packer, according to closure principle from top to bottom closure is completed, and can be applied not only to permanent shut-in well, may be used also
It is applied to the overhaul of Slim Hole so as to resume production again.Matching packer is avoided, be it also avoid in slim-hole side
The accident that packer construction is easily caused is carried out in drilling well.
During closure operation is carried out to each perforated interval from top to bottom, in squeeze method each time operation is blocked
Afterwards, to the perforated interval pressure testing, to detect closure quality, pressure testing inspection is unqualified to be proceeded to block operation, it is ensured that
Each perforated interval can be blocked completely, it is ensured that be blocked successfully.
Description of the drawings
Fig. 1 is structural representation of the well before construction in the method for blocking of the Slim Hole perforated interval of the present invention
Figure;
Fig. 2 be the present invention Slim Hole perforated interval method for blocking in well construction complete when structure
Schematic diagram.
Reference:
10- hangers;20- sleeve pipes;30- artificials bottom of a well;
The upper bound of first perforated interval of 42-;
The lower bound of first perforated interval of 44-;
The upper bound of second perforated interval of 52-;
The lower bound of second perforated interval of 54-;
The top surface of 62- integral cement plugs.
Specific embodiment
Below in conjunction with accompanying drawing, the technical characteristic and advantage above-mentioned to the present invention is clearly and completely described, it is clear that institute
The embodiment of description section Example only of the invention, rather than whole embodiments.
Refer to shown in Fig. 1 and Fig. 2, there are at least two perforated intervals in sidetracking well section, each perforated interval distinguishes position
The eyelet being connected with place stratum is respectively provided with sleeve pipe 20 at the different depth of sidetracking well section, each perforated interval (in figure
It is not shown).In embodiment shown in Fig. 1 and Fig. 2, there are two perforated intervals in sidetracking well section, first perforated interval it is upper
Be first perforated interval from top to bottom between the lower bound 44 of boundary 42 and first perforated interval, second perforated interval it is upper
It is second perforated interval from top to bottom between the lower bound 54 of boundary 52 and second perforated interval.
A kind of method for blocking of Slim Hole perforated interval of the present invention comprises the steps:
Step S100, opens Wellhead packer, and into sleeve pipe 20 workover fluid is injected, using the first drift size gauge tool drifting to suspension
The top of device 10, then using the artificial bottom of a well 30 of the second drift size gauge tool drifting to sidetracking well section;
Step S200, under enter working string, successively closure operation is carried out to each perforated interval from top to bottom, until leaning on
The perforated interval of nearly artificial bottom of a well 30 (most beneath) completes to block operation;In the present embodiment, working string is light pipe;
Step S300, drag bit cleaning sleeve pipe 20 is until artificial bottom of a well 30;
Wherein, the closure operation in step S200 comprises the steps:
Step S210, cement cap, Hou Ning are beaten in the lower section of the perforated interval by working string to the perforated interval
To cement cap shaping;
Step S220, squeeze method closure operation is carried out to the perforated interval, and in sleeve pipe 20 and in cement cap
Top forms the interim cement plug of the perforated interval;Wellhead packer is closed, time with pressure is coagulated to the shaping of interim cement plug;
Step S230, opens Wellhead packer, under enter drag bit, drag bit touches interim cement plug, and scraper is bored
Head drills successively from top to bottom interim cement plug and cement cap, completes the closure operation of the perforated interval.
In step S210, cement cap plays a part of similar packer, by cement cap by the perforated hole
The lower bound of the lower bound to the well section between well head and the perforated interval of section is separated to the well section between artificial bottom of a well 30, follow-up
The step of S220 in, working string injection cement stopped by cement cap, the eyelet of the perforated interval could be passed through
Into corresponding stratum.
In step S230, when drilling interim cement plug and cement cap, the passage that can only get out an insertion is supplied
Enter under drag bit, it is also possible to completely clean out interim cement plug and cement cap.Can according to different demands and
Casing size in sidetracked hole selects the drag bit of different size.
It is interim by what is remained in each perforated interval during drag bit cleaning sleeve pipe 20 in step S300
Cement plug and cement cap are cleaned out.
Because in prior art, slim-hole matching packer is more difficult, also holds stream without the cement that can be lowered into The Small Well intraocular
Device.In addition, enter packer under in sidetracked hole being easy to by card, easily there is thing in the construction particularly in Slim Hole
Therefore.Such risk is then avoided using the method for blocking of the Slim Hole perforated interval of the present invention, it is not necessary to packer,
Closure is completed according to closure principle from top to bottom, permanent shut-in well is can be applied not only to, Slim Hole is applied also for
Overhaul so as to resume production again.
If permanently shunt in a well, the segmentation into sleeve pipe 20 is also needed to after step S300 and notes integral cement plug (below
Will be described in detail).If carrying out large repairs operation, after closure operation is completed to each perforated interval, can be in sidetracking well section
The other positions of sleeve pipe 20 perforation again, carries out mining operations;Can be to continue well-digging downwards from artificial bottom of a well 30, deeper
Stratum in exploit.
Conventional operating type from bottom to up, is carried out after closure operation, now due to top to the perforated interval of lower section
Perforated interval do not blocked, if to check lower section perforated interval closure quality, need to adopt packer, by lower section
Perforated interval separate with the perforated interval of top, formed confined space, then can be with pressure testing in here confined space.If
Not by instruments such as packers, then pressure testing operation cannot be carried out, it is impossible to the closure quality of the perforated interval below inspection.
The method for blocking of the Slim Hole perforated interval of the present invention, first blocks the perforated interval of the superiors, now most
The perforated interval on upper strata is blocked, and without leakage on the sleeve pipe 20 above it, therefore, in well head and the perforation of the superiors
Confined space is formed between well section, then can be with pressure testing in here confined space, to check the closure matter of the superiors' perforated interval
Amount.Gradually block from top to bottom, can immediately carry out pressure testing inspection after closure operation every time;Pressure testing is unqualified, repeats to squeeze
Grout off operation, it is not necessary to matching and under enter packer, save the activity duration, improve operating efficiency.
The present invention proposes top-down closure principle, to each according to the casing programme feature of Slim Hole
Perforated interval is respectively adopted solidifying and squeeze method closure operation the method for cement cap, time with pressure and completes to the effective of perforated interval
Closure.Blocking perforated interval is to block the preforation tunnel on sleeve pipe, it is ensured that sleeve pipe is not missed.
Further, in step S210, the bottom of working string is made positioned at the lower section of the perforated interval;
Also include step S215 between step S210 and step S220, above carry working string, make the bottom position of working string
In the top in the upper bound of the perforated interval, or the bottom of working string is made positioned at the lower section of the lower bound of the perforated interval, and
The top of cement cap.Suitably working string is above carried, the lower end that can make working string departs slightly from cement cap, so as to
When facilitating the closure operation of follow-up squeeze method, cement is exported from working string, and then swimmingly from the eyelet of the perforated interval, from
And block the perforated interval.
Further, in step S230, after drag bit touches interim cement plug, and in drag bit from up to
Under to drill successively before interim cement plug and cement cap and also include step S231, drag bit cleaning sleeve pipe 20 exposes this
Eyelet at perforated interval, closes Wellhead packer, to the perforated interval pressure testing;
If pressure testing is qualified, Wellhead packer is opened, the drag bit in execution step S230 is drilled successively from top to bottom
Interim cement plug and cement cap;If pressure testing is unqualified, execution step S220.
During closure operation is carried out to each perforated interval from top to bottom, in squeeze method each time operation is blocked
Afterwards, to the perforated interval pressure testing, to detect closure quality, pressure testing inspection is unqualified to be proceeded to block operation, it is ensured that
Each perforated interval can be blocked completely, it is ensured that be blocked successfully.
Further, in step S220, squeeze method closure operation blocks operation or crowded light water mudding to squeeze superfine cement
Stifled operation.If stratum is gas-bearing formation, squeezes superfine cement closure operation and there is preferable plugging effect;If stratum is oil reservoir, squeeze
Superfine cement blocks operation and the closure operation of crowded ordinary cement is respectively provided with preferable plugging effect.In most cases stratum is
Oil reservoir, use requirement can be met using the closure operation of crowded ordinary cement.
The average grain diameter of superfine cement is below 5 microns, and the slurry fluidity of superfine cement is good, with stability and can filling
The high advantage of property.Only 7 microns of the superfine cement average grain diameter for oil well that domestic-developed goes out, is seven points of conventional G class g cements
One of left and right, because particle is little, make sealing agent that there is good mobility and penetrability, the radius that can clamp-on process is also more common
Cement is much bigger.
Further, in step S215, the bottom of working string is located at the top in the upper bound of the perforated interval, and with this
The distance in the upper bound of perforated interval is more than or equal to 5 meters, or the bottom of working string is located under the lower bound of the perforated interval
Just and in the top of cement cap, and with the distance of the lower bound of the perforated interval it is more than or equal to 3 meters, and less than or equal to 5
Rice.
Further, in step S215, the distance for above carrying working string is more than or equal to 10 meters.
Further, in step S210, the thickness of cement cap is 10 meters.
Further, in step S231, during pressure testing, test pressure is 25 MPas, is kept for 30 minutes, when pressure drop is less than
Or during equal to 0.5 MPa, pressure testing is qualified;When pressure drop is more than 0.5 MPa, pressure testing is unqualified.
Further, if permanently shunt in a well, step S400 is also included after step S300, is segmented into sleeve pipe 20
Note integral cement plug, makes the top surface 62 of integral cement plug positioned at the top of hanger 10;Then to well head to integral cement plug
Sprue bushing protection liquid in the well section of top surface 62, more preferably, the density of casing protection liquid is 1.0g/cm3~1.1g/cm3。
Further, it is with pressure a length of 48 hours when waiting solidifying in step S220.
The present invention also proposes a kind of method for blocking of Slim Hole perforated interval, comprises the steps:
Step S10, opens Wellhead packer, and into sleeve pipe 20 workover fluid is injected, using the first drift size gauge tool drifting to suspension
The top of device 10, then using the artificial bottom of a well 30 of the second drift size gauge tool drifting to sidetracking well section;
Step S20, under enter working string, and make its bottom be located at first perforated interval in sidetracking well section from top to bottom
Lower section, then the first cement cap is made a call to by working string, time is coagulated to the shaping of the first cement cap;
Step S30, squeeze method closure operation is carried out to first perforated interval, and in sleeve pipe 20 and in the first hanging water
The top of the bod forms the first interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the first interim cement plug shaping;
Step S40, open Wellhead packer, under enter drag bit, drag bit touches the first interim cement plug, scraper
Drill bit drills successively from top to bottom the first interim cement plug and the first cement cap;
Step S50, working string is sequentially passed through from top to bottom after the first interim cement plug and the first cement cap, is continued
Enter working string under downwards, and make its bottom be located at the lower section of second perforated interval in sidetracking well section from top to bottom,
Then the second cement cap is made a call to by working string;
Step S60, squeeze method closure operation is carried out to second perforated interval, and in sleeve pipe 20 and in the second hanging water
The top of the bod forms the second interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the second interim cement plug shaping;
Step S70, opens Wellhead packer, and drag bit cleaning sleeve pipe 20 is until artificial bottom of a well 30.
In step S70, during drag bit cleaning sleeve pipe 20, the interim cement that will be remained in each perforated interval
Plug and cement cap are cleaned out.
If necessary to permanent shut-in well, after the step s 70, also comprise the steps:Segmentation note is overall into sleeve pipe 20
Cement plug, makes the top surface 62 of integral cement plug positioned at the top of hanger 10;Then to the top surface 62 of well head to integral cement plug
Well section in sprue bushing protection liquid.
Further, also include having at least three to penetrate in step S65, sidetracking well section between step S60 and step S70
Hole well section, perforated interval execution step S40 being pointed to successively from top to bottom below second perforated interval ', step S50 ' and
Step S60 ', until the perforated interval near artificial bottom of a well 30 completes squeeze method closure operation;
Step S40 ' be to open Wellhead packer, under enter drag bit, drag bit touches perforated interval top phase
Adjacent interim cement plug, drag bit drills successively from top to bottom the adjacent interim cement plug in the perforated interval top and the perforation
The adjacent cement cap in well section top;
Step S50 ' it is that working string sequentially passes through from top to bottom the adjacent interim cement plug in the perforated interval top and is somebody's turn to do
After the adjacent cement cap in perforated interval top, working string is entered under continuing downwards, and make its bottom be located at the perforated interval
Lower section, then the corresponding cement cap of the perforated interval is beaten by working string;
Step S60 ' it is that squeeze method closure operation is carried out to perforated interval this described, and in sleeve pipe 20 and in the perforation
The top of the corresponding cement cap of well section forms the corresponding interim cement plug of the perforated interval;Wellhead packer is closed, it is with pressure
Time coagulates interim cement plug shaping corresponding to the perforated interval.
If having three perforated intervals in sidetracking well section, a step is performed between step S60 and step S70
S40 ', step S50 ' and step S60 ';
Now, step S40 ' specifically, open Wellhead packer, under enter drag bit, drag bit touches second and faces
When cement plug, drag bit drills successively from top to bottom the second interim cement plug and the second cement cap;
Step S50 ' specifically, working string sequentially passes through from top to bottom the second interim cement plug and the second cement cap
Afterwards, working string is entered under continuing downwards, and its bottom is located under the 3rd perforated interval in sidetracking well section from top to bottom
Side, then plays the 3rd cement cap by working string;
Step S60 ' specifically, carry out squeeze method closure operation to the 3rd perforated interval, and in the sleeve pipe 20 and the
The top of three cement caps forms the 3rd interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the 3rd interim cement plug
Shaping.
If that is, another kind of Slim Hole for having three perforated intervals, the present invention in sidetracking well section is penetrated
The method for blocking of hole well section, comprises the steps:
Step S10, opens Wellhead packer, and into sleeve pipe 20 workover fluid is injected, using the first drift size gauge tool drifting to suspension
The top of device 10, then using the artificial bottom of a well 30 of the second drift size gauge tool drifting to sidetracking well section;
Step S20, under enter working string, and make its bottom be located at first perforated interval in sidetracking well section from top to bottom
Lower section, then the first cement cap is made a call to by working string, time is coagulated to the shaping of the first cement cap;
Step S30, squeeze method closure operation is carried out to first perforated interval, and in sleeve pipe 20 and in the first hanging water
The top of the bod forms the first interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the first interim cement plug shaping;
Step S40, open Wellhead packer, under enter drag bit, drag bit touches the first interim cement plug, scraper
Drill bit drills successively from top to bottom the first interim cement plug and the first cement cap;
Step S50, working string is sequentially passed through from top to bottom after the first interim cement plug and the first cement cap, is continued
Enter working string under downwards, and make its bottom be located at the lower section of second perforated interval in sidetracking well section from top to bottom, then
Second cement cap is made a call to by working string;
Step S60, squeeze method closure operation is carried out to second perforated interval, and in sleeve pipe 20 and in the second hanging water
The top of the bod forms the second interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the second interim cement plug shaping;
Step S40 ', open Wellhead packer, under enter drag bit, drag bit touches the second interim cement plug, scrapes
Knife drill bit drills successively from top to bottom the second interim cement plug and the second cement cap;
Step S50 ', working string is sequentially passed through from top to bottom after the second interim cement plug and the second cement cap, after
Enter working string under continuing downwards, and make its bottom be located at the lower section of the 3rd perforated interval in sidetracking well section from top to bottom, so
Afterwards the 3rd cement cap is made a call to by working string;
Step S60 ', squeeze method closure operation is carried out to the 3rd perforated interval, and it is in sleeve pipe 20 and hanging the 3rd
The top of cement plug forms the 3rd interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the 3rd interim cement plug shaping;
Step S70, opens Wellhead packer, and drag bit cleaning sleeve pipe 20 is until artificial bottom of a well 30;In step S70,
It is during drag bit cleaning sleeve pipe 20, the interim cement plug remained in each perforated interval and cement cap cleaning is dry
Only, now the 3rd interim cement plug and the 3rd cement cap are also cleaned.
If necessary to permanent shut-in well, after the step s 70, also comprise the steps:Segmentation note is overall into sleeve pipe 20
Cement plug, makes the top surface 62 of integral cement plug positioned at the top of hanger 10;Then to the top surface 62 of well head to integral cement plug
Well section in sprue bushing protection liquid.
As such, it is possible to smoothly realize the closure operation of three perforated intervals.
If having four perforated intervals in sidetracking well section, step twice is performed between step S60 and step S70
S40 ', step S50 ' and step S60 ', in this not go into detail.
By taking the embodiment shown in Fig. 1 and Fig. 2 as an example, there is two perforated intervals, first perforated interval in sidetracking well section
The upper bound 42 and the lower bound 44 of first perforated interval between for first perforated interval from top to bottom, second perforated interval
The upper bound 52 and the lower bound 54 of second perforated interval between penetrate for second perforated interval from top to bottom, Slim Hole
The step of method for blocking of hole well section, enumerates as follows:
Wellhead packer is opened, workover fluid is injected into sleeve pipe 20, using the top of the first drift size gauge tool drifting to hanger 10
Portion, then using the artificial bottom of a well 30 of the second drift size gauge tool drifting to sidetracking well section;The main borehole of straight well section has been before sidetracking
Using wedge deflection tool and grout off;
Under enter working string, and make its bottom be located at the lower section of first perforated interval in sidetracking well section from top to bottom,
Then the first cement cap is made a call to by working string, time is coagulated to the shaping of the first cement cap;
Squeeze method closure operation is carried out to first perforated interval, and in sleeve pipe 20 and in the upper of the first cement cap
It is square into the first interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the first interim cement plug shaping;Now, first faces
When cement plug can with the first cement cap condense it is integral;
More preferably, before to first perforated interval squeeze method closure operation, working string is above carried, makes working string
Bottom is located at the top in the upper bound 42 of first perforated interval, and is more than or waits with the distance in the upper bound 42 of first perforated interval
In 5 meters, or the bottom of working string is located at the lower section of the lower bound 44 of first perforated interval and in the top of cement cap,
And it is more than or equal to 3 meters with the distance of the lower bound 44 of the first perforated interval, and less than or equal to 5 meters;
Open Wellhead packer, under enter drag bit, drag bit touches the first interim cement plug, and drag bit is successively
Drill the first interim cement plug and the first cement cap;
More preferably, after " drag bit touches the first interim cement plug ", and " drag bit is from top to bottom successively
Drill the first interim cement plug and the first cement cap " before, drag bit cleaning sleeve pipe 20 does not temporarily drill first interim
Cement plug and the first cement cap, expose the eyelet at first perforated interval, Wellhead packer are closed, to the perforation
Well section pressure testing;If pressure testing is qualified, Wellhead packer is opened, continue executing with that " drag bit drills successively from top to bottom first and faces
When cement plug and the first cement cap ";If pressure testing is unqualified, carries out squeeze method closure to first perforated interval again and make
Industry, until first perforated interval is blocked completely;
Working string enters through after the first interim cement plug and the first cement cap under continuing downwards, and makes its bottom
The lower section of second perforated interval in sidetracking well section from top to bottom, then breaks the second hanging cement by working string
Plug, time is coagulated to the shaping of the second cement cap;
Squeeze method closure operation is carried out to second perforated interval, and in sleeve pipe 20 and in the upper of the second cement cap
It is square into the second interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the second interim cement plug shaping;Now, second faces
When cement plug can with the second cement cap condense it is integral;
More preferably, before to second perforated interval squeeze method closure operation, working string is above carried, makes working string
Bottom is located at the top in the upper bound 52 of second perforated interval, and is more than or waits with the distance in the upper bound 52 of second perforated interval
In 5 meters, or the bottom of working string is located at the lower section of the lower bound 54 of second perforated interval and in the top of cement cap,
And it is more than or equal to 3 meters with the distance of the lower bound 54 of the second perforated interval, and less than or equal to 5 meters;
Wellhead packer is opened, drag bit clears up sleeve pipe 20 to artificial bottom of a well 30, and then segmentation note is whole into sleeve pipe 20
Body cement plug, makes the top surface 62 of integral cement plug positioned at the top of hanger 10;
More preferably, drag bit is entered under, after drag bit touches the second interim cement plug, drag bit cleaning set
Pipe 20, does not temporarily drill the second interim cement plug and the second cement cap, exposes the eyelet at second perforated interval
, the Wellhead packer is closed, to second perforated interval pressure testing;If pressure testing is qualified, Wellhead packer is opened,
Drag bit continues to drill the second interim cement plug and the second cement cap successively from top to bottom, and clears up sleeve pipe gradually downward
20 to artificial bottom of a well 30;If pressure testing is unqualified, squeeze method closure operation is carried out to second perforated interval again, until second
Individual perforated interval is blocked completely.
2445.7 meters~2469.8 meters of well depth and well depth are respectively with first perforated interval and second perforated interval
2652.8 meters~2680.0 meters, as a example by carrying out permanent capping operation, by following methods, it is ensured that sidetracked hole slim-hole is strong
Note is adopted by force, pressure replaces under the service condition of change, reaches effective closure of 50 years.
1st, using workover fluid kill-job;The top of drift size gauge tool (i.e. the first drift size gauge tool) drifting to hanger 10 that 118 millimeters of diameter
Portion (well depth × 2353.00 meter), drift size gauge tool (i.e. the second drift size gauge tool) drifting that 75 millimeters of diameter to artificial bottom of a well 30 (well depth ×
2766.0 rice);
2nd, first 2445.7 meters~2469.8 meters of perforated interval is blocked;
(1) working string × 2485.0 meter of 60 millimeters of diameter under, play cement cap, and the cement surface of cement cap ×
2472.0 rice;
(2) Hou Ning visits cement surface × 2472.0 meter of cement cap after 24 hours;
(3) working string × 2435.0 meter are above carried, squeezes superfine cement 2445.7 meters~2469.8 meters of perforated interval of closure;This
In embodiment, 20 meters of working string is above carried;
(4) Wellhead packer is closed, after time with pressure is solidifying 48 hours, the drag bit of 75 millimeters of lower diameter visits the water in sleeve pipe 20
Extremely × 2472.0 meters of the bod (the first interim cement plug) and drilling out, pressure testing:P=25MPa, 30min, △ P≤0.5MPa is
Qualified, pressure testing is unqualified squeeze seal must to block up again;
(5) after confirming that pressure testing is qualified, drilling out drifting is continued to × 2766.0 meters;
3rd, first 2652.8 meters~2680.0 meters of perforated interval is blocked;Concrete steps are similar with first perforated interval,
Will not be described here;
4th, segmentation note integral cement plug, 1500.0 meters~2766.0 meters of well section;
5th, top surface × 1500.0 meter of integral cement plug to well head fills casing protection liquid, and the density of casing protection liquid is
1.0g/cm3~1.1g/cm3;
6th, installing can the antitheft well head of kill-job and pressure gauge.
Particular embodiments described above, has been carried out further to the purpose of the present invention, technical scheme and beneficial effect
Describe in detail, it will be appreciated that the foregoing is only the specific embodiment of the present invention, the protection being not intended to limit the present invention
Scope.Particularly point out, to those skilled in the art, it is all within the spirit and principles in the present invention, done any repair
Change, equivalent, improvement etc., should be included within the scope of the present invention.
Claims (12)
1. a kind of method for blocking of Slim Hole perforated interval, it is characterised in that the Slim Hole perforated interval
Method for blocking comprise the steps:
Step S100, opens Wellhead packer, workover fluid is injected into sleeve pipe, using the top of the first drift size gauge tool drifting to hanger
Portion, then using the artificial bottom of a well of the second drift size gauge tool drifting to sidetracking well section;
Step S200, under enter working string, successively closure operation is carried out to each perforated interval from top to bottom, until near institute
The perforated interval for stating artificial bottom of a well completes the closure operation;
Step S300, drag bit cleaning described sleeve pipe is until the artificial bottom of a well;
Wherein, the closure operation in step S200 comprises the steps:
Step S210, cement cap, Hou Ning are beaten in the lower section of the perforated interval by the working string to the perforated interval
To cement cap shaping;
Step S220, squeeze method closure operation is carried out to the perforated interval, and in described sleeve pipe and in the cement cap
Top form the interim cement plug of the perforated interval;The Wellhead packer is closed, time with pressure is coagulated to the interim cement plug
Shaping;
Step S230, opens the Wellhead packer, under enter drag bit, the drag bit touches the interim cement
Plug, the drag bit drills successively from top to bottom the interim cement plug and the cement cap, completes the perforated interval
Closure operation.
2. the method for blocking of Slim Hole perforated interval according to claim 1, it is characterised in that in the step
In S210, the bottom of the working string is made positioned at the lower section of the perforated interval;
Also include step S215 between step S210 and step S220, above carry the working string, make the operation
The bottom of tubing string is located at the top in the upper bound of the perforated interval, or makes the bottom of the working string be located at the perforated interval
The lower section of lower bound and in the top of the cement cap.
3. the method for blocking of Slim Hole perforated interval according to claim 1, it is characterised in that the step
In S230, after the drag bit touches the interim cement plug, and bore successively from top to bottom in the drag bit
Wear and also include before the interim cement plug and the cement cap step S231, the drag bit clears up described sleeve pipe,
Expose the eyelet at the perforated interval, the Wellhead packer is closed, to perforated interval pressure testing this described;
If pressure testing is qualified, the Wellhead packer is opened, the drag bit in execution step S230 is from top to bottom successively
Drill the interim cement plug and the cement cap;If pressure testing is unqualified, step S220 is performed.
4. the method for blocking of the Slim Hole perforated interval according to any one of claims 1 to 3, it is characterised in that
In step S220, the squeeze method closure operation blocks operation to squeeze superfine cement closure operation or crowded ordinary cement.
5. the method for blocking of Slim Hole perforated interval according to claim 2, it is characterised in that the step
In S215, the bottom of the working string is located at the top in the upper bound of the perforated interval, and with the upper bound of the perforated interval away from
From more than or equal to 5 meters, or the bottom of the working string is located at the lower section of the lower bound of the perforated interval and described hanging
The top of cement plug, and it is more than or equal to 3 meters with the distance of the lower bound of the perforated interval, and less than or equal to 5 meters.
6. the method for blocking of Slim Hole perforated interval according to claim 2, it is characterised in that the step
In S215, the distance for above carrying the working string is more than or equal to 10 meters.
7. the method for blocking of Slim Hole perforated interval according to claim 1, it is characterised in that the step
In S210, the thickness of the cement cap is 10 meters.
8. the method for blocking of Slim Hole perforated interval according to claim 3, it is characterised in that the step
In S231, during pressure testing, test pressure is 25 MPas, is kept for 30 minutes, and when pressure drop is less than or equal to 0.5 MPa, pressure testing is closed
Lattice;When pressure drop is more than 0.5 MPa, pressure testing is unqualified.
9. the method for blocking of Slim Hole perforated interval according to claim 1, it is characterised in that if carried out forever
Long property capping operation, also includes step S400 after step S300, and segmentation note integral cement plug, makes institute into described sleeve pipe
The top surface for stating integral cement plug is located at the top of the hanger;Then to the well section of well head to the top surface of the integral cement plug
Interior sprue bushing protects liquid.
10. the method for blocking of Slim Hole perforated interval according to claim 1, it is characterised in that the step
It is with pressure a length of 48 hours when waiting solidifying in S220.
A kind of 11. method for blocking of Slim Hole perforated interval, it is characterised in that the Slim Hole perforated interval
Method for blocking comprise the steps:
Step S10, opens Wellhead packer, workover fluid is injected into sleeve pipe, using the top of the first drift size gauge tool drifting to hanger
Portion, then using the artificial bottom of a well of the second drift size gauge tool drifting to sidetracking well section;
Step S20, under enter working string, and make its bottom be located at first perforated interval in the sidetracking well section from top to bottom
Lower section, then the first cement cap is made a call to by the working string, time is coagulated to first cement cap shaping;
Step S30, squeeze method closure operation is carried out to first perforated interval, and in described sleeve pipe and described first
The top of cement cap forms the first interim cement plug;Wellhead packer is closed, time with pressure is coagulated to the described first interim cement
Plug shaping;
Step S40, opens the Wellhead packer, under enter drag bit, the drag bit touches the described first interim water
The bod, the drag bit drills successively from top to bottom the described first interim cement plug and first cement cap;
Step S50, the working string sequentially passes through from top to bottom the described first interim cement plug and the first hanging cement
After plug, the working string is entered under continuing downwards, and make its bottom be located at second institute in the sidetracking well section from top to bottom
The lower section of perforated interval is stated, then the second cement cap is made a call to by the working string;
Step S60, squeeze method closure operation is carried out to second perforated interval, and in described sleeve pipe and described second
The top of cement cap forms the second interim cement plug;Close the Wellhead packer, time with pressure is coagulated to described second interim
Cement plug is molded;
Step S70, opens the Wellhead packer, and the drag bit cleaning described sleeve pipe is until the artificial bottom of a well.
The method for blocking of 12. Slim Hole perforated intervals according to claim 11, it is characterised in that in the step
It is rapid also to include that there is perforated interval described at least three in step S65, the sidetracking well section between S60 and step S70, from up to
Under be pointed to successively below second perforated interval perforated interval execution step S40 ', step S50 ' and step
S60 ', until the perforated interval near the artificial bottom of a well completes squeeze method closure operation;
Step S40 ' be to open the Wellhead packer, under enter the drag bit, the drag bit touches this and penetrates
The adjacent interim cement plug in hole well section top, the drag bit drills successively from top to bottom adjacent above the perforated interval facing
When cement plug and perforated interval top adjacent cement cap;
Step S50 ' it is that the working string sequentially passes through from top to bottom the adjacent interim cement plug in the perforated interval top
After the cement cap adjacent with the perforated interval top, the working string is entered under continuing downwards, and is located at its bottom to be somebody's turn to do
The lower section of perforated interval, then plays the corresponding cement cap of the perforated interval by the working string;
Step S60 ' it is that squeeze method closure operation is carried out to perforated interval this described, and penetrate in described sleeve pipe and at this
The top of the corresponding cement cap of hole well section forms the corresponding interim cement plug of the perforated interval;Close the well head shut-in well
Device, time with pressure coagulates interim cement plug shaping corresponding to the perforated interval.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611075931.3A CN106639969B (en) | 2016-11-29 | 2016-11-29 | Plugging method for perforating well section of slim hole sidetracked well |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611075931.3A CN106639969B (en) | 2016-11-29 | 2016-11-29 | Plugging method for perforating well section of slim hole sidetracked well |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106639969A true CN106639969A (en) | 2017-05-10 |
CN106639969B CN106639969B (en) | 2019-03-15 |
Family
ID=58813112
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611075931.3A Active CN106639969B (en) | 2016-11-29 | 2016-11-29 | Plugging method for perforating well section of slim hole sidetracked well |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106639969B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108547590A (en) * | 2018-03-30 | 2018-09-18 | 重庆大学 | The method shunt in a well for a long time to salt cave storage cavern using rock salt damage self-healing characteristics |
CN109403912A (en) * | 2018-02-27 | 2019-03-01 | 中石化石油工程技术服务有限公司 | A kind of method and construction method of the water injection of horizontal well bod |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2004022903A3 (en) * | 2002-09-09 | 2005-02-17 | Kip M Robichaux | Top drive swivel apparatus and method |
CN1621658A (en) * | 2003-11-28 | 2005-06-01 | 大港油田集团有限责任公司 | Well cementing technology by center tube replacing elutriation method |
CN101718171A (en) * | 2009-11-17 | 2010-06-02 | 中国石油集团长城钻探工程有限公司 | Drilling completion matching method for sidetracking horizontal well |
CN101818619A (en) * | 2010-03-24 | 2010-09-01 | 中国石油集团川庆钻探工程有限公司 | Temporary sealing open hole casing branch well cementing and completion structure and process |
CN103184851A (en) * | 2011-12-28 | 2013-07-03 | 陈美玲 | Plugging technology for highly-deviated well with big casing pipe |
-
2016
- 2016-11-29 CN CN201611075931.3A patent/CN106639969B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2004022903A3 (en) * | 2002-09-09 | 2005-02-17 | Kip M Robichaux | Top drive swivel apparatus and method |
CN1621658A (en) * | 2003-11-28 | 2005-06-01 | 大港油田集团有限责任公司 | Well cementing technology by center tube replacing elutriation method |
CN101718171A (en) * | 2009-11-17 | 2010-06-02 | 中国石油集团长城钻探工程有限公司 | Drilling completion matching method for sidetracking horizontal well |
CN101818619A (en) * | 2010-03-24 | 2010-09-01 | 中国石油集团川庆钻探工程有限公司 | Temporary sealing open hole casing branch well cementing and completion structure and process |
CN103184851A (en) * | 2011-12-28 | 2013-07-03 | 陈美玲 | Plugging technology for highly-deviated well with big casing pipe |
Non-Patent Citations (3)
Title |
---|
中国石油天然气股份有限公司: "《勘探与生产工程监督现场技术规范》", 31 May 2009 * |
张文泽 等: "开窗侧钻小井眼、小间隙井固井应用技术", 《化学工程师》 * |
蒋海涛: "小井眼开窗侧钻井固井工艺技术", 《石油钻采工艺》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109403912A (en) * | 2018-02-27 | 2019-03-01 | 中石化石油工程技术服务有限公司 | A kind of method and construction method of the water injection of horizontal well bod |
CN108547590A (en) * | 2018-03-30 | 2018-09-18 | 重庆大学 | The method shunt in a well for a long time to salt cave storage cavern using rock salt damage self-healing characteristics |
CN108547590B (en) * | 2018-03-30 | 2020-07-31 | 重庆大学 | Method for carrying out long-term well sealing on salt cavern storage by utilizing self-healing characteristic of salt rock damage |
Also Published As
Publication number | Publication date |
---|---|
CN106639969B (en) | 2019-03-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7228908B2 (en) | Hydrocarbon sweep into horizontal transverse fractured wells | |
US5431225A (en) | Sand control well completion methods for poorly consolidated formations | |
US7234546B2 (en) | Drilling and cementing casing system | |
CN100412312C (en) | Method and device for repairing oil/gas drilling bushing | |
CN101864921A (en) | Well completion and oil production string of horizontal well and well completion and oil production processes thereof | |
CN108661618B (en) | Reservoir transformation method for L type horizontal well of coal bed gas | |
CN104153753B (en) | Horizontal well volume fracturing tubular column and method based on conventional oil tube pressure dragging | |
CN105756650B (en) | Method for realizing staged fracturing of horizontal well by adopting mixed temporary plugging agent to block tubular channeling | |
WO2011020998A2 (en) | Method for improving waterflood performance using barrier fractures and inflow control devices | |
CN112302586B (en) | Production process for putting speed pipe column with choke at tail end in well | |
CN109236186A (en) | New well drilling casing and big wellbore multilateral well quick drill completion method | |
US4529036A (en) | Method of determining subterranean formation fracture orientation | |
CN106639969B (en) | Plugging method for perforating well section of slim hole sidetracked well | |
WO2021249499A1 (en) | Wellbore segmented operation method and rubber plug for said method | |
CN208830969U (en) | Oil extraction and water injection string | |
CN106223898B (en) | Two horizontal well cementing and completion integrated pipe column devices that open | |
CN112431579B (en) | Preset small-diameter pipe internal fracturing device and method for side drilling well and small-hole well | |
CN113530511A (en) | Method for developing natural gas reservoir | |
RU2510456C2 (en) | Formation method of vertically directed fracture at hydraulic fracturing of productive formation | |
RU2391491C1 (en) | Method of completing auxiliary wellbore shaft construction and rig to this end | |
CN113323619B (en) | Plugging method for oil and gas well | |
CN114109298A (en) | Method for cementing lost-circulation zone well section | |
CN110939412B (en) | Development method for realizing advanced water injection and early water injection by utilizing horizontal well | |
CN112431583A (en) | Supporting device for drilling and completion of fishbone horizontal multilateral well in unconsolidated sandstone reservoir and supporting drilling method thereof | |
CN118065856B (en) | Fine fracturing process |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |