CN106639610A - Iron tower tail edge continuous leveling method - Google Patents

Iron tower tail edge continuous leveling method Download PDF

Info

Publication number
CN106639610A
CN106639610A CN201611132003.6A CN201611132003A CN106639610A CN 106639610 A CN106639610 A CN 106639610A CN 201611132003 A CN201611132003 A CN 201611132003A CN 106639610 A CN106639610 A CN 106639610A
Authority
CN
China
Prior art keywords
continues
bolt
iron tower
nut
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611132003.6A
Other languages
Chinese (zh)
Inventor
要粮安
任海平
任昱星
任进朝
姚聚杰
白贵勇
王建军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Jinzhong Power Supply Co of State Grid Shanxi Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Jinzhong Power Supply Co of State Grid Shanxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Jinzhong Power Supply Co of State Grid Shanxi Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201611132003.6A priority Critical patent/CN106639610A/en
Publication of CN106639610A publication Critical patent/CN106639610A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • E04H12/344Arrangements for lifting tower sections for placing additional sections under them

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

Disclosed is an iron tower tail edge continuous leveling method. Tail edge bolts of which the extending length is limited can further extend through continuous bolts and continuous nuts, so that lifting heights of iron tower tail edges are increased; the iron tower tail edge continuous leveling method is especially applicable to rectifying of an inclined iron tower, particularly rectifying of a tower in a goaf; and construction difficulty is reduced, the construction period is shortened, and a large amount of manpower and material resources are saved. Reinforcing screws are arranged to further increase the strength of a device, stability maintaining of the device in long-time using is guaranteed, and breaking and deformation are avoided effectively. Filling holes in an upper flange and a lower flange can guarantee integrated cement pouring without bubbles remaining.

Description

A kind of foundation of iron tower continues leveling method
Technical field
The present invention relates to a kind of foundation of iron tower method for maintaining, more particularly to a kind of foundation of iron tower continues leveling method.
Background technology
Steel tower such as is widely used in transmitting electricity, communicates the field, steel tower in use, it occur frequently that column foot sedimentation phenomenon, Especially in mined out region, sedimentation phenomenon is particularly evident.If Iron tower incline angle is excessive, have to change steel tower, and change steel tower work Journey amount is big, and mountain area field is distributed in steel tower more, not only big to difficulty of construction, and the easy productive life to local resident is caused Affect.Existing column foot foundation bolt has certain length in reserve, but can only tackle and its small sedimentation, some foundation of iron tower Oil cylinder is pre-set when mounted, and lifting is carried out by oil cylinder when column foot is settled, but installation oil cylinder is relatively costly, it is long Phase is susceptible to damage, reveals in open air, and stability cannot ensure.
The content of the invention
For the deficiencies in the prior art, the present invention provides a kind of foundation of iron tower and continues leveling method.
The technical solution used in the present invention is:A kind of foundation of iron tower continues leveling method, comprises the steps:
(1)Calculating each column foot needs hoisting depth, and column foot foundation bolt is separated with foundation of iron tower, using lifting appliance by iron Tower inclines column foot pin pull-up, and pull-out altitude is than calculating highly high 50mm;
(2)Lower flange plate is installed on foundation bolt, is fixed with nut, the lower flange plate is square, and middle part is opened and fills in hole;
(3)Foundation bolt top is continued nut, and the nut top that continues continues bolt, and the length that continues is according to Iron tower incline The actual measuring and calculating of degree;
(4)Continues the flanged plate that install on bolt, and upper flange plate bottom arranges nut and fixes, the upper flange plate and the laxative remedy Blue hardened structure is identical;
(5)Steel tower column foot is inserted in and is continued on bolt, two ends are fixedly clamped with nut;
(6)All column foots that need to be continued are installed as stated above, and continue bolt and the nut that continues are finely tuned, make iron The all column foots of tower are in the same plane;
(7)Coating butter on above-mentioned all connectors, and wind polybag;
(8)The outer fixing mould of above-mentioned junction structure, the filling cement into mould after theing cement solidifies, removes lifting appliance.
A kind of described foundation of iron tower continues leveling method, it is characterized in that:Step(4)In, pacify around the bolt that continues per root Four reinforcement screws are filled, reinforcement screw is fixed on upper and lower flanged plate by the reinforcement nut for matching, and four reinforcement screws are uniform It is distributed in around the corresponding bolt that continues.
The present invention is further prolonged by the foundation bolt that the bolt that continues, the nut that continues enable itself to expand limited length Stretch, increase the hoisting depth of foundation of iron tower, be particularly well-suited to incline the correction of steel tower, the especially correction of goaf steel tower, drop Low difficulty of construction, shortens construction period, saves a large amount of manpower and materials.Installing reinforcement screw can further increase device Intensity, it is ensured that device can keep stable in long-time use, be prevented effectively from fracture and deform.Filling out on upper and lower flange Orifice can guarantee that cement grouting is complete, not stay bubble.
Description of the drawings
Fig. 1 is junction structure top view of the present invention;
Fig. 2 is junction structure front view of the present invention;
Fig. 3 continue for the present invention after the completion of structural representation;
In figure:1- upper flange plates, 2- lower flange plates, 3- foundation bolts, 4- continues bolt, and 5- continues nut, fixing nut under 6-, The upper levelling nuts of 7-, the upper fixing nuts of 8-, 9- reinforcement screws, 10- reinforcement nuts, 11- fills in hole.
Specific embodiment
A kind of foundation of iron tower continues leveling method, and the inclined degree of steel tower and the sedimentation depth of each column foot are measured first, The height lifted so as to calculate each column foot to need.Contact column foot is fixedly connected with foundation bolt, will using lifting appliance Column foot pull-up, pull-out altitude ratio needs the high 50mm of hoisting depth.As shown in Figure 1, 2, each column foot has four foundation bolts 3, will Lower flange plate 2 is installed on foundation bolt 3, is fixed by lower fixing nut 6, and continue nut 5 on foundation bolt, and continue spiral shell Female bolt 4 that continues, installs flanged plate 1 on the bolt that continues, upper flange plate 1 is positioned by the upper levelling nut 7 of its bottom, often Continue bolt, the nut that continues, foundation bolt periphery of group installs four reinforcement screws 9, and the annular of reinforcement screw 9 is uniformly distributed in and continues Around bolt, the nut that continues, foundation bolt, reinforcement screw 9 is fixed on upper and lower flanged plate by reinforcement nut 10, described upper and lower Flanged plate is square structure, and middle part is opened and fills in hole 11.Upper flange plate top arranges fixing nut 8 on a pair, column foot is put into and is connect On continuous bolt 4, above fixing nut 8 is fixed.Other need the column foot for being lifted to fix also with said method, and fixation is finished Afterwards, continue to each bolt that continues nut again and reinforcement screw be finely adjusted, make all column foots of steel tower in the same plane, After fine setting is finished, the coating butter on all connectors, and wind polybag.In the outer fixing mould of attachment structure, into mould Cement injection, band cement solidify completely after, remove lifting appliance, so as to complete lower margin continue it is levelling, as shown in Figure 3.

Claims (2)

1. a kind of foundation of iron tower continues leveling method, it is characterized in that:Comprise the steps:
(1)Calculating each column foot needs hoisting depth, and column foot foundation bolt is separated with foundation of iron tower, using lifting appliance by iron Tower inclines column foot pin pull-up, and pull-out altitude is than calculating highly high 50mm;
(2)Lower flange plate is installed on foundation bolt, is fixed with nut, the lower flange plate is square, and middle part is opened and fills in hole;
(3)Foundation bolt top is continued nut, and the nut top that continues continues bolt, and the length that continues is according to Iron tower incline The actual measuring and calculating of degree;
(4)Continues the flanged plate that install on bolt, and upper flange plate bottom arranges nut and fixes, the upper flange plate and the laxative remedy Blue hardened structure is identical;
(5)Steel tower column foot is inserted in and is continued on bolt, two ends are fixedly clamped with nut;
(6)All column foots that need to be continued are installed as stated above, and continue bolt and the nut that continues are finely tuned, make iron The all column foots of tower are in the same plane;
(7)Coating butter on above-mentioned all connectors, and wind polybag;
(8)The outer fixing mould of above-mentioned junction structure, the filling cement into mould after theing cement solidifies, removes lifting appliance.
2. a kind of foundation of iron tower according to claim 1 continues leveling method, it is characterized in that:Step(4)In, continue per root Four reinforcement screws are installed, reinforcement screw is fixed on upper and lower flanged plate by the reinforcement nut for matching around bolt, four benefits Strong screw is uniformly distributed in around the corresponding bolt that continues.
CN201611132003.6A 2016-12-09 2016-12-09 Iron tower tail edge continuous leveling method Pending CN106639610A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611132003.6A CN106639610A (en) 2016-12-09 2016-12-09 Iron tower tail edge continuous leveling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611132003.6A CN106639610A (en) 2016-12-09 2016-12-09 Iron tower tail edge continuous leveling method

Publications (1)

Publication Number Publication Date
CN106639610A true CN106639610A (en) 2017-05-10

Family

ID=58824153

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611132003.6A Pending CN106639610A (en) 2016-12-09 2016-12-09 Iron tower tail edge continuous leveling method

Country Status (1)

Country Link
CN (1) CN106639610A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112482870A (en) * 2020-11-24 2021-03-12 广东顺德电力设计院有限公司 Pole tower in-situ lifting device

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201771056U (en) * 2010-08-06 2011-03-23 上海电信工程有限公司 Ground anchor bolt support
CN102758445A (en) * 2011-04-27 2012-10-31 华锐风电科技(集团)股份有限公司 Foundation leveling device, foundation assembly and foundation forming method for wind driven generator tower
CN103938912A (en) * 2014-05-08 2014-07-23 北京中水恒信环境科技发展有限公司 Device for connecting high-rise structure with foundation and manufacturing method of device
CN203960920U (en) * 2013-11-18 2014-11-26 国家电网公司 Colliery minery electric power pylon inclination adjusting device
CN204151813U (en) * 2014-10-10 2015-02-11 中国能源建设集团安徽省电力设计院 A kind of adjustable basis for correcting electric power pylon foundation settlement
FR2922563B1 (en) * 2007-10-19 2016-07-01 Technip France DEVICE FOR ADJUSTING THE INCLINATION OF AN EQUIPMENT ARRANGED ON AN ANCHOR SUPPORT ON A MARINE BACKGROUND
CN205663228U (en) * 2016-06-02 2016-10-26 中国新兴建筑工程总公司 Ground auxiliary stay levelling device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2922563B1 (en) * 2007-10-19 2016-07-01 Technip France DEVICE FOR ADJUSTING THE INCLINATION OF AN EQUIPMENT ARRANGED ON AN ANCHOR SUPPORT ON A MARINE BACKGROUND
CN201771056U (en) * 2010-08-06 2011-03-23 上海电信工程有限公司 Ground anchor bolt support
CN102758445A (en) * 2011-04-27 2012-10-31 华锐风电科技(集团)股份有限公司 Foundation leveling device, foundation assembly and foundation forming method for wind driven generator tower
CN203960920U (en) * 2013-11-18 2014-11-26 国家电网公司 Colliery minery electric power pylon inclination adjusting device
CN103938912A (en) * 2014-05-08 2014-07-23 北京中水恒信环境科技发展有限公司 Device for connecting high-rise structure with foundation and manufacturing method of device
CN204151813U (en) * 2014-10-10 2015-02-11 中国能源建设集团安徽省电力设计院 A kind of adjustable basis for correcting electric power pylon foundation settlement
CN205663228U (en) * 2016-06-02 2016-10-26 中国新兴建筑工程总公司 Ground auxiliary stay levelling device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112482870A (en) * 2020-11-24 2021-03-12 广东顺德电力设计院有限公司 Pole tower in-situ lifting device

Similar Documents

Publication Publication Date Title
CN109555311A (en) Adjustable waterproof guide wall form board support construction and its operational method
CN106639610A (en) Iron tower tail edge continuous leveling method
CN207700077U (en) A kind of height-adjustable high-speed rail bridge pinner rising device
CN204343319U (en) Cableway pipe patten pre-embedded anchoring bolts jig
CN206128106U (en) Bloated tight column foot of quick installation
CN208533556U (en) A kind of combination unit poured convenient for mixed tower blower foundation
CN209652949U (en) A kind of slope protection barricade masonry formwork structure
CN206329604U (en) The steel tower that a kind of electric power pylon tilts correction bolt and its application continues deviation correcting device
CN106223540B (en) A kind of crane steel ladder platform column and its manufacturing method
CN210712562U (en) Tower crane system for construction of cast-in-situ tower column of cable-stayed bridge
CN105484282A (en) Leveling device inside cup-shaped foundation of pipe steel support and usage method of leveling device
CN211250565U (en) Pouring die for beam
CN207131421U (en) Tunnel vault concrete mortar device for casting
CN209469540U (en) The lower tower segments of concrete tower and concrete tower with it
CN206328788U (en) A kind of electric power pylon foundation bolt continues deviation correcting device
CN209469002U (en) Adjustable waterproof guide wall form board support construction
CN209443671U (en) A kind of grouting connection structure of prefabricated components
CN210459198U (en) Prestressed concrete pipe pile mould
CN207794761U (en) A kind of large bending moment electrical pole
CN202273243U (en) Adjustable height type pole and tower foundation
CN205421021U (en) Integral hoisting roof beam sand box that falls
CN209799528U (en) Prefabricated base of communication tower
CN202007527U (en) Cast-in-place steel reinforcing bar concrete column template fixing device
CN206438424U (en) A kind of bridge strengthening device with shock insulation function
CN104120733B (en) Power transmission line iron tower foundation sinks to making up the difference component

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170510

RJ01 Rejection of invention patent application after publication