CN106638650A - Assembled type concrete base structure - Google Patents

Assembled type concrete base structure Download PDF

Info

Publication number
CN106638650A
CN106638650A CN201510741213.4A CN201510741213A CN106638650A CN 106638650 A CN106638650 A CN 106638650A CN 201510741213 A CN201510741213 A CN 201510741213A CN 106638650 A CN106638650 A CN 106638650A
Authority
CN
China
Prior art keywords
fastener
steel column
foundation beam
assembly concrete
foundation structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510741213.4A
Other languages
Chinese (zh)
Other versions
CN106638650B (en
Inventor
彭礼
王明星
夏晶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI TAIDA BUILDING TECHNOLOGY Co Ltd
Original Assignee
SHANGHAI TAIDA BUILDING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI TAIDA BUILDING TECHNOLOGY Co Ltd filed Critical SHANGHAI TAIDA BUILDING TECHNOLOGY Co Ltd
Priority to CN201510741213.4A priority Critical patent/CN106638650B/en
Publication of CN106638650A publication Critical patent/CN106638650A/en
Application granted granted Critical
Publication of CN106638650B publication Critical patent/CN106638650B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention provides an assembled type concrete base structure which comprises a pre-fabricated first foundation beam, a steel column, a fastener group and an independent foundation, wherein the fastener group is provided with fasteners; the fasteners are provided with fastener bolts; the fasteners encircle the first foundation beam; the fastener bolts pass through the steel column and are fixed by fastener nuts; the independent foundation comprises anchor bolts; and the anchor bolts penetrate through the fasteners and are fixed by nuts. The assembled type concrete base structure has the advantages that the sizes of all foundations in the system adopt standard modulus, and all the foundations can be produced in advance; and the specification and the quantity of the foundations can be directly selected according to actual bearing capacity of the ground during project construction, so that the on-site construction period is greatly shortened. Meanwhile, the concrete foundation beam in the system can also be produced in advance, and no embedded parts are arranged according to the position of the steel column in actual engineering, so that the construction is convenient and quick.

Description

Assembly concrete foundation structure
Technical field
The present invention relates to a kind of assembly concrete foundation structure, more particularly to a kind of assembled independence Foundation structure.
Background technology
With the development and perfection of assembled technology, increasing building adopts fabricated construction body System, carries and shortens construction period significantly.But the part of current employing assembled technology office always It is limited to more than ground to build, the basis of under ground portion is waited does not have ripe mounting technology.Underground part The bottleneck of whole assembling system is divided into, the duration of assembling structure is seriously constrained.
The content of the invention
For problem above, it is an object of the invention to provide a kind of assembled isolated footing structure, can To realize being connected with each other under various common situations such as prefabricated foundation, prefabricated foundation beam, steel column, With supplement vacancy of the prior art.
The present invention provides a kind of assembly concrete foundation structure, it is characterised in that:Including prefabricated First foundation beam, steel column, securing member group and isolated footing;Securing member group has fastener;Fastener has There is fastening bolt;Fastener is encircled on first foundation beam, and fastening bolt crosses steel column, by fastener spiral shell Mother is fixed;Isolated footing includes crab-bolt;Crab-bolt passes through fastener, is fixed by nut.
The present invention provides a kind of assembly concrete foundation structure, can also have the feature that: Steel column has column base plate, and bolt passes through column base plate.
The present invention provides a kind of assembly concrete foundation structure, can also have the feature that: Crab-bolt configures top nut and lower nut;Securing member group has supporting construction;Supporting construction is arranged on button Between part and isolated footing;Lower nut is arranged on supporting construction lower section, and top nut is arranged on fastener Side.
The present invention provides a kind of assembly concrete foundation structure, can also have the feature that: Leveling space is reserved between foundation beam and isolated footing end face, is installed in rear leveling space and is arranged Ungauged regions material;Gap is installed between steel column and foundation beam, is installed in post gap and is arranged without receipts Compression material.
The present invention provides a kind of assembly concrete foundation structure, can also have the feature that: Also include the second prefabricated foundation beam, it is perpendicular with first foundation beam;Second basic beam end has Reserved steel bar, uses Concrete Filled tip-clearance after foundation beam leveling.
The present invention provides a kind of assembly concrete foundation structure, can also have the feature that: Assembly concrete foundation structure under steel column without isolated footing.
The beneficial effect of the invention
All of isolated footing size adopts standard module in the structure, can produce in advance, for work Isolated footing size and number is directly selected according to actual foundation bearing capacity during journey, production is greatly shortened Duration.Meanwhile, the concrete foundation beam in the structure also can be produced in advance, without the need for according to actual work Steel column locations arrangement built-in fitting in journey etc., it is convenient and swift.
Description of the drawings
Fig. 1 is the assembly concrete foundation structure schematic diagram of embodiment one.
Fig. 2 is the partial enlarged drawing of Fig. 3.
Fig. 3 is the assembly concrete foundation structure schematic diagram of embodiment two.
Fig. 4 is the partial enlarged drawing of Fig. 5.
Fig. 5 is the assembly concrete foundation structure schematic diagram of embodiment three.
Fig. 6 is the partial enlarged drawing of Fig. 1.
Specific embodiment
Below in conjunction with the accompanying drawings the present invention will be further described with specific embodiment.
Embodiment one
Fig. 1 is the assembly concrete foundation structure schematic diagram of embodiment one.
Fig. 2 is the partial enlarged drawing of Fig. 3.
As depicted in figs. 1 and 2, the present embodiment is unidirectional assembly concrete foundation structure, including: Isolated footing 10, prefabricated first foundation beam 20, steel column 30 and fastening assembly group 40.
Steel column 30 has column base plate 30-1.Securing member group 40 has U-shaped fastener 43, fastener 43 With fastening bolt 43-1.
Fastener 43 is encircled on foundation beam 20, and fastening bolt 43-1 passes through the column base plate 30-1 of steel column, Fixed by fastener nut.
Isolated footing 10 includes crab-bolt 41.Crab-bolt 41 configures top nut 41-1 and lower nut 41-2.
Securing member group 40 has supporting construction 42.Supporting construction 42 is arranged on fastener 43 and independence Between basis 10.
Lower nut 41-2 is arranged on the lower section of supporting construction 42, and top nut 41-1 is arranged on fastener top.
Leveling space is reserved between foundation beam 20 and the top surface of isolated footing 10, rear leveling is installed Ungauged regions material is set in space.
Gap is installed between steel column 30 and foundation beam 20, is installed and arrange in post gap ungauged regions Material.
Local wharf's pavement quality during 20 top surface in-site installation of prefabricated foundation beam under column base plate 30-1;Post Base plate 30-1 ground is provided with the gap between shear key each column base plate 30-1 and prefabricated foundation beam 20 Fill with ungauged regions material after installing.
Embodiment two
Fig. 3 is the assembly concrete foundation structure schematic diagram of embodiment three.
Fig. 4 is the partial enlarged drawing of Fig. 3.
As shown in Figure 3 and Figure 4, the present embodiment is two-way assembly concrete foundation structure, including: Isolated footing 10, prefabricated first foundation beam 20, the second foundation beam 20-1, steel column 30 and fastening Component group 40.
Structure except the foundation beam 20-1 of first foundation beam 20 and second and connection in the present embodiment Outward, other structures are all identical with embodiment two, and narration is not repeated.
Second foundation beam 20-1, is mutually perpendicular to first foundation beam 20.
Second foundation beam 20-1 ends have reserved steel bar 43-2.Foundation beam 20,20-1 is held on In supporting construction 42, Concrete Filled tip-clearance is used after leveling.
Assembly concrete foundation structure assembling process:
Factory's casting concrete first foundation beam 20, the second foundation beam 20-1, isolated footing 10, Crab-bolt 41 is embedded in isolated footing 20.Screw rod 43-1 is welded in advance in factory with U-shaped fastener 43 Connect.
Scene, first installs isolated footing assembling.The first foundation beam 20 of concrete is installed again, every In individual crab-bolt 41, a regulation lower nut 41-2 is screwed into, then supporting construction 42 is attached into anchor Bolt 41, is subsequently held on the upper surface of supporting construction 42 and by adjusting by concrete first foundation beam 20 Section nut adjusts concrete foundation beam to specified altitude assignment, and is adjusted to level, installs U-shaped fastener 43, It is last again to lock U-shaped fastener with top nut 41-1 with each crab-bolt 41.
If isolated footing end face has the orthogonal foundation beam 20-1 of first foundation beam 20 and second simultaneously When, foundation beam 20,20-1 is held on into supporting construction 42 and is made after leveling, will with concrete Fill in beam-ends gap.
When being positioned at the steel column of isolated footing end face, directly by the steel column of the 30-1 with column base plate 30 are locked using securing member 43-1.
After beams of concrete 20, steel column 50 and isolated footing 10 install, ungauged regions material is used The space of isolated footing end face to beams of concrete bottom surface is filled, by beams of concrete and steel column base plate it Between space filling.
Embodiment three
Fig. 5 is the assembly concrete foundation structure schematic diagram of embodiment three.
Fig. 6 is the partial enlarged drawing of Fig. 1.
As shown in Figure 5 and Figure 6, the present embodiment is the assembly concrete without isolated footing under steel column Foundation structure, including:Prefabricated first foundation beam 20, steel column 30 and fastening assembly group 50.
Steel column 30 has column base plate 30-1.Securing member group 50 has double embrace c-type fastener 51, fastener 51 have fastening bolt 51-1.
Fastener is encircled on foundation beam 20, and fastening bolt 51-1 passes through the column base plate 30-1 of steel column, Fixed by fastener nut.
When being positioned at the steel column of isolated footing span centre, first by the double embrace with fastening bolt 51-1 C-type fastener 51 holds tightly on concrete first foundation beam 20 from concrete both sides, afterwards by steel column 30 Column base plate 30-1 locked with beams of concrete 20 by fastening bolt 51-1.
Local wharf's pavement quality during 20 top surface in-site installation of prefabricated foundation beam under column base plate 30-1;Post Base plate 30-1 ground is provided with the gap between shear key each column base plate 30-1 and prefabricated foundation beam 20 Fill with ungauged regions material after installing.

Claims (6)

1. a kind of assembly concrete foundation structure, it is characterised in that:Including the first prefabricated base Plinth beam, steel column, securing member group and isolated footing;
The securing member group has fastener;The fastener has fastening bolt;
The fastener is encircled on the first foundation beam, the excessively described steel column of the fastening bolt, Fixed by fastener nut;
The isolated footing includes crab-bolt;The crab-bolt passes through the fastener, is fixed by nut.
2. assembly concrete foundation structure according to claim 1, it is characterised in that:
Wherein, the steel column has column base plate, and the bolt passes through the column base plate.
3. assembly concrete foundation structure according to claim 1, it is characterised in that:
Wherein, the crab-bolt configuration top nut and lower nut;
The securing member group has supporting construction;The supporting construction is arranged on the fastener and institute State between isolated footing;
The lower nut is arranged on supporting construction lower section, and the top nut is arranged on the fastener Side.
4. assembly concrete foundation structure according to claim 1, it is characterised in that:
Wherein, leveling space is reserved between the first foundation beam and the isolated footing end face, Ungauged regions material is set after installing in the leveling space;
Fill without receipts after installing in gap between the steel column and the first foundation beam Compression material.
5. assembly concrete foundation structure according to claim 1, it is characterised in that:
Also include the second prefabricated foundation beam, it is perpendicular with the first foundation beam;
Described second basic beam end has reserved steel bar, will make after the second foundation beam leveling Use Concrete Filled tip-clearance.
6. assembly concrete foundation structure according to claim 1, it is characterised in that: Without isolated footing under steel column in described assembly concrete foundation structure.
CN201510741213.4A 2015-11-03 2015-11-03 Fabricated concrete foundation structure Active CN106638650B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510741213.4A CN106638650B (en) 2015-11-03 2015-11-03 Fabricated concrete foundation structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510741213.4A CN106638650B (en) 2015-11-03 2015-11-03 Fabricated concrete foundation structure

Publications (2)

Publication Number Publication Date
CN106638650A true CN106638650A (en) 2017-05-10
CN106638650B CN106638650B (en) 2020-03-17

Family

ID=58851350

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510741213.4A Active CN106638650B (en) 2015-11-03 2015-11-03 Fabricated concrete foundation structure

Country Status (1)

Country Link
CN (1) CN106638650B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984203A (en) * 2019-11-18 2020-04-10 中国建筑材料科学研究总院有限公司 Precast concrete foundation, ground beam, connecting structure and mounting method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11200490A (en) * 1998-01-19 1999-07-27 Yoshinori Okura Joint of wooden building and connecting structure using the same
JPH11229402A (en) * 1998-02-17 1999-08-24 Daiwa House Ind Co Ltd Foundation and construction for steel frame structure
JP2001200588A (en) * 2000-01-18 2001-07-27 Nippon Eisei Center:Kk Base joining tool for house
CN103343547A (en) * 2013-07-19 2013-10-09 中国建筑股份有限公司 Assembly type shape steel concrete four tetrastyle foundation of container type movable house and construction method
CN205088700U (en) * 2015-11-03 2016-03-16 上海泰大建筑科技有限公司 Assembled concrete foundation system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11200490A (en) * 1998-01-19 1999-07-27 Yoshinori Okura Joint of wooden building and connecting structure using the same
JPH11229402A (en) * 1998-02-17 1999-08-24 Daiwa House Ind Co Ltd Foundation and construction for steel frame structure
JP2001200588A (en) * 2000-01-18 2001-07-27 Nippon Eisei Center:Kk Base joining tool for house
CN103343547A (en) * 2013-07-19 2013-10-09 中国建筑股份有限公司 Assembly type shape steel concrete four tetrastyle foundation of container type movable house and construction method
CN205088700U (en) * 2015-11-03 2016-03-16 上海泰大建筑科技有限公司 Assembled concrete foundation system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984203A (en) * 2019-11-18 2020-04-10 中国建筑材料科学研究总院有限公司 Precast concrete foundation, ground beam, connecting structure and mounting method
CN110984203B (en) * 2019-11-18 2022-02-18 中国建筑材料科学研究总院有限公司 Precast concrete foundation, ground beam, connecting structure and mounting method

Also Published As

Publication number Publication date
CN106638650B (en) 2020-03-17

Similar Documents

Publication Publication Date Title
JP5737554B2 (en) Seismic isolation foundation construction method
US20160233818A1 (en) Solar canopy support system
US20100132769A1 (en) Solar canopy support system
JP2007527971A (en) How to set up a tower
US20110094088A1 (en) Solar canopy construction method
CN107268430A (en) A kind of anchor suitable for beam bridge and height-adjustable supports and its construction method
CN110145024A (en) A kind of prefabricated assembled bean column node using pressure-bearing steel plate
CN204112525U (en) Band perps precast shear wall structure in strong concrete precast frame
CN207244435U (en) A kind of anchor and height-adjustable supports suitable for beam bridge
KR101739126B1 (en) Method for Forming Top-down-typed Underground Strucutre
CN106638650A (en) Assembled type concrete base structure
US9512610B2 (en) Column shoe
JP6139831B2 (en) Installation structure and construction method of solar panel mount
US20200173163A1 (en) System and method for anchoring air separation unit structures to concrete foundations
KR102595835B1 (en) Seismic retrofit system using foundation integrated PC panel
CN205088700U (en) Assembled concrete foundation system
JP3843896B2 (en) Structure and construction method of steel pipe column and steel pipe pile
CN207582806U (en) A kind of fire-proof shock-proof cylinder system constructing structure
CN204876084U (en) Steel column foot crab -bolt fixed bolster
KR101772938B1 (en) Precast foundation structure buried support of road facility and method for constructing this same
KR20130066094A (en) Base for pillar of composite handrail
US20200063457A1 (en) Adjustable cap for column foundation
CN206396887U (en) Pit structure
KR20090009128U (en) Basic Fabric for Facilities Supporting
KR20160059533A (en) Vertical degree control apparatus

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant