CN106638336A - Over-line continuous beam removing method and support for removing - Google Patents

Over-line continuous beam removing method and support for removing Download PDF

Info

Publication number
CN106638336A
CN106638336A CN201610918643.3A CN201610918643A CN106638336A CN 106638336 A CN106638336 A CN 106638336A CN 201610918643 A CN201610918643 A CN 201610918643A CN 106638336 A CN106638336 A CN 106638336A
Authority
CN
China
Prior art keywords
support
bridge pier
support member
distribution beam
distribution
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610918643.3A
Other languages
Chinese (zh)
Other versions
CN106638336B (en
Inventor
李亚民
艾祖斌
陈钒
黄巍
卢超
高天
卓越
杨霁
蒋帆
朱向阳
袁野
李�杰
何志兰
熊利
苏坤
黄深镜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 8 Co Ltd
Original Assignee
Sinohydro Bureau 8 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 8 Co Ltd filed Critical Sinohydro Bureau 8 Co Ltd
Priority to CN201610918643.3A priority Critical patent/CN106638336B/en
Publication of CN106638336A publication Critical patent/CN106638336A/en
Application granted granted Critical
Publication of CN106638336B publication Critical patent/CN106638336B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses an over-line continuous beam removing method. The method comprises the following steps of 1 support erecting, 2 temporary pier beam padding, 3 transverse stripping, 4 blocking hanging and 5 support removing. The invention further discloses a support for removing in the method. The support comprises supporting pieces and hoops, the supporting pieces are arranged on bearing platforms on the peripheries of the bottoms of the corresponding piers and are parallel to the piers, the supporting pieces are clamped on the sides of the piers through the hoops, distribution beam groups are installed on the tops of the adjacent two supporting pieces in an overlapping mode, and a bearing support used for bearing the weight of a bridge when the bridge is removed is installed on the tops of the distribution beam groups. The method has the advantages of being safe, stable, environmentally friendly in construction and the like, and the support has the advantages of being convenient to operate, capable of reasonably utilizing the mechanics principle and high in construction efficiency.

Description

Cross-line continuous beam method for dismounting and dismounting support
Technical field
The invention mainly relates to as bridge structure demolition technique field, a kind of more particularly to cross-line continuous beam method for dismounting, Further relate to the cross-line continuous beam dismounting support of aforementioned cross-line continuous beam method for dismounting.
Background technology
Current bridge application is sorted out, demolition blasting method and machinery can be divided into(Non- explosion)Two big classes of dismounting method Not, each classification contains various different applications again, there is the respective scope of application.Using blasting procedure, straight more than bridging toughening The method of abolishing, mechanical hoisting method are connect, but is typically removed using Mechanical Method across the existing circuit bridge that is open to traffic.Mechanical removal method refers to utilization The forms such as plant equipment is crushed to bridge, split, handling are removed.Removed using crane barge lifting more than water Bridge, land Floor-engaging frame method is frequently with compared with the dismounting of large-tonnage loop wheel machine bulk.But, there is security protection in existing cross-line continuous beam method for dismounting The problems such as not in place, supporting construction is unreasonable, hanging device model used is big, have impact on to a certain extent safe construction.
The content of the invention
The technical problem to be solved in the present invention is to overcome the deficiencies in the prior art, there is provided a kind of safety and stability, construction environmental protection Cross-line continuous beam method for dismounting, correspondingly provide in preceding method it is used it is a kind of easy to operate, rationally utilize mechanics principle The cross-line continuous beam dismounting support high with efficiency of construction.
To solve above-mentioned technical problem, the present invention is employed the following technical solutions:
A kind of cross-line continuous beam method for dismounting, comprises the following steps:
S1:Set up support:With bridge pier, cross-line road surface as basis is set up, support is set up along bridge pier sidepiece, the beam body of bridge is integrally held It is loaded on support;
S2:The interim pads of Dun Liang:By in across beam body and bridge pier between space snapped up temporarily with rubber cushion blocks and padded, really Beam body is protected in cutting process, load is effectively passed to bridge pier;
S3:Laterally slitting:Therefrom across span centre position cut-out beam body, with stress of the bridge pier for padding position as beam body that snap up temporarily The strong point, from bridge pier direction that place of incision pads position to snapping up temporarily cutting beam body while, self extending stitches position to facing When snap up and pad the bridge pier direction at position and symmetrically cut beam body successively, the horizontal slitting of beam body is cut into plate beam element, plate-girder list Unit falls on support;
S4:Piecemeal hangs:The plate beam element of cutting is hung successively to specified location using hanging device;
S5:Removal bracket:After the completion for the treatment of that plate beam element hangs, support is dismantled.
As the further improvement to above-mentioned technical proposal.
The step of setting up support in step S1 is specially:The support member parallel to bridge pier is set up along bridge pier sidepiece, with To support, distribution beam group and support bracket, the support bracket are set up in the top between the support member of adjacent bridge pier to support member Top be close to the bottom of beam body.
Concretely comprising the following steps for distribution beam group and support bracket is set up in step S1:Between the support member of adjacent bridge pier Top set up distribution beam group, distribution beam group top laying support bracket until support bracket at the top of be close to beam body Bottom, gap carries out snapping up padding using wedge type block between distribution beam group and support bracket.
The concrete steps of distribution beam group and support bracket are set up in step S1 also to be included:In beam body both sides support bracket Top erection construction occasional passage, construction occasional passage on the outside of safety device is set.
Hanging device is located on the same track on plate beam element place cross-line road surface to be hung in step S4.
Step S5 is concretely comprised the following steps:In same cut direction, after the completion for the treatment of that all plate beam elements hang, to Hang the support below plate beam element to dismantle by cross from top to down.
Device therefor is cut in step S3 for rope saw.
As a total inventive concept, present invention also offers a kind of cross-line continuous beam used by preceding method is removed using Support, the support includes support member and anchor ear, and the support member is arranged on the cushion cap of corresponding bridge pier bottom periphery and and bridge Pier is parallel, and support member is by the anchor ear lock ring in bridge pier sidepiece, and adjacent two support members top is taken equipped with distribution beam group, described Distribution beam group top is equiped with the support bracket for bearing bridge weight when bridge is removed.
As the further improvement to above-mentioned technical proposal:
Support member positioned at bridge both ends is arranged on the inside portion of corresponding bridge pier, and centrally located support member is arranged on phase Answer the both sides of bridge pier.
The support also includes connector and diagonal brace, and the two ends of the distribution beam group are fixed on adjacent by the connector Two support members top, described diagonal brace one end is affixed with support member waist, and the other end is affixed with the bottom on distribution beam group side edge.
The distribution beam group includes plural longitudinal stake top distribution beam, Bailey beam and horizontal little distribution beam, the shellfish Lei Liang is fixed between longitudinal stake top distribution beam and the horizontal little distribution beam, and the middle part of longitudinal stake top distribution beam leads to The top that the connector is fixed on the support member is crossed, the bottom on the side edge of longitudinal stake top distribution beam passes through the diagonal brace One end be fixed on the support member waist, the Bailey beam is welded in the top of longitudinal stake top distribution beam, described to hold Weight support is installed on the top of horizontal little distribution beam.
The support bracket is full hall scaffold.
The support member is connected on the cushion cap by reinforcing bar and Interal fixation.
The support member is steel column.
Compared with prior art, it is an advantage of the current invention that:
The cross-line continuous beam method for dismounting of the present invention, support member plays interim carrying and cuts beam body;By in across beam body and Space between bridge pier is snapped up and is padded temporarily with rubber cushion blocks, the beam body weight after cut-out is concentrated and is transferred to bridge pier bottom In structure, the carrying risk of support is reduced;Therefrom across span centre position cut-out beam body after, it is horizontal to intermediate pier direction along place of incision To symmetrical cutting, rationally using mechanics principle, reduce cutting difficulty, improve the security of construction.
The present invention cross-line continuous beam dismounting support, support member be arranged on the cushion cap of corresponding bridge pier bottom periphery and with Bridge pier is parallel, and support member by the anchor ear lock ring in bridge pier sidepiece, take equipped with distribution beam group by adjacent two support members top, point The support bracket for bearing bridge weight when bridge is removed is equiped with beam group top.The support member generation being supported on cushion cap Vibration hammer Driven-in Pile Foundations have been replaced, construction, saving time, reduces cost has been facilitated.Support member is by anchor ear lock ring in bridge pier side Portion, reduces construction input, it is ensured that the stability of support member.Installing distribution beam group is taken at the top of mounted adjacent supporting piece And support bracket, improve the security of construction, easy construction, efficiency high.Support bracket holds out against with the beam body of bridge, i.e. beam portion Load pass to support bracket, be then passed to support member and cushion cap.
Description of the drawings
Fig. 1 is the flow chart of cross-line continuous beam method for dismounting of the present invention.
Fig. 2 is the construction front view of cross-line continuous beam method for dismounting of the present invention.
Fig. 3 is the construction top view of cross-line continuous beam method for dismounting of the present invention.
Fig. 4 is laterally slitting beam body cut direction schematic diagram of the invention.
Fig. 5 is the construction hoisting figure of cross-line continuous beam method for dismounting of the present invention.
Fig. 6 is the installation procedure figure of cross-line continuous beam dismounting support of the present invention.
Each label is represented in figure:
1st, cushion cap;2nd, support;22nd, support member;24th, anchor ear;25th, distribution beam group;251st, longitudinal stake top distribution beam;252nd, Bei Lei Beam;253rd, horizontal little distribution beam;26th, connector;27th, support bracket;28th, diagonal brace;3rd, beam body;31st, plate beam element;4th, cross-line Road surface;5th, construction occasional passage;6th, safety device;7th, bridge pier;8th, hanging device;9th, rubber cushion blocks.
Specific embodiment
The present invention is described in further details below with reference to Figure of description and specific embodiment.
As shown in Fig. 1 to 5, a kind of cross-line continuous beam method for dismounting of the present invention is comprised the following steps:
S1:Set up support:With bridge pier 7, cross-line road surface 4 as basis is set up, along the sidepiece of bridge pier 7 support 2, the beam body 3 of bridge are set up Integrated carrying is on support 2;
S2:The interim pads of Dun Liang:By in across beam body 3 and bridge pier 7 between space snapped up temporarily with rubber cushion blocks 9 pad It is real, it is ensured that in cutting process, load is effectively passed to bridge pier 7 to beam body 3;
S3:Laterally slitting:Therefrom across span centre position cut-out beam body 3, the bridge pier 7 for padding position to snap up temporarily is as beam body 3 The stress strong point, while cutting beam body 3 from the direction of bridge pier 7 that place of incision pads position to snapping up temporarily, self extending seam position Put the direction of bridge pier 7 for padding position to snapping up temporarily and symmetrically cut beam body 3 successively, the horizontal slitting of beam body 3 is cut into plate-girder list Unit 31, plate beam element 31 falls on support 2;
S4:Piecemeal hangs:The plate beam element 31 of cutting is hung successively to specified location using hanging device 8;
S5:Removal bracket:After the completion for the treatment of that plate beam element 31 hangs, support 2 is dismantled.
Support member 22 plays interim carrying and cuts beam body 3;By in across beam body 3 and bridge pier 7 between space use rubber Rubber cushion block 9 is snapped up and is padded temporarily, the weight of beam body 3 after cut-out is concentrated and is transferred in the substructure of bridge pier 7, reduces support 2 carrying risk;Therefrom across span centre position cut-out beam body 3 after, along place of incision to the lateral symmetry cutting in intermediate pier direction, close Reason utilizes mechanics principle, reduces cutting difficulty, improves the security of construction.
The step of support 2 are set up in step S1 is specially:The support member 22 parallel to bridge pier 7 is set up along the sidepiece of bridge pier 7, with To support, distribution beam group 25 and support bracket 27, load-bearing are set up in the top between the support member 22 of adjacent bridge pier 7 to support member 22 It is close to the bottom of beam body 3 in the top of support 27.
Concretely comprising the following steps for distribution beam group 25 and support bracket 27 is set up in step S1:In the support member 22 of adjacent bridge pier 7 Between top set up distribution beam group 25, distribution beam group 25 top laying support bracket 27 until support bracket 27 top It is close to the bottom of beam body 3, gap carries out snapping up padding using wedge type block between distribution beam group 25 and support bracket 27.
The concrete steps of distribution beam group 25 and support bracket 27 are set up in step S1 also to be included:In the both sides load-bearing of beam body 3 The top erection construction occasional passage 5 of frame 27, in the outside of construction occasional passage 5 safety device 6 is arranged.
Hanging device 8 is located on the same track on the place cross-line road surface 4 of plate beam element 31 to be hung in step S4.This reality In applying example, hanging device used 8 is loop wheel machine, and unit type is relatively small when the relatively large beam body of loop wheel machine is released, loop wheel machine erect-position with treat The position consistency of 31 place cross-line road surface of plate beam element 4 of cutting, it is to avoid to disturbing to runway driving, reducing construction right The impact of original traffic, meets and protects logical requirement.
Step S5 is concretely comprised the following steps:In same cut direction, after the completion for the treatment of that all plate beam elements 31 hang, to hanging The support 2 for putting the lower section of plate beam element 31 is dismantled by cross from top to bottom.
Device therefor is cut in step S3 for rope saw.
The cut direction of horizontal slitting beam body is in step S3:Main span successively by span centre to pier top, end bay by abutment pier into Across pier top.
The present invention cross-line continuous beam method for dismounting using full Support Method machine cuts dismounting, will beam body to be removed 3 use The support 2 of pier beam type closed supports+steel pipe scaffold combination is supported, and the weight of beam body 3 is all born by support 2, then Sawed with cutting equipment, i.e. rope, transverse cuts beam body 3 is lifted the plate beam element 31 that beam body 3 is decomposed into fritter, completes bridge Beam is removed, and construction method is more ripe.
As shown in figure 5, a kind of cross-line continuous beam dismounting support of the present invention, support 2 includes support member 22 and anchor ear 24, Support member 22 be arranged in it is on the cushion cap 1 of the bottom periphery of corresponding bridge pier 7 and parallel with bridge pier 7, support member 22 pass through the lock ring of anchor ear 24 In the sidepiece of bridge pier 7, the adjacent top of two support member 22 is taken equipped with distribution beam group 25, and the top of distribution beam group 25 is equiped with for tearing open The support bracket 27 of bridge weight is born during except bridge.The support member 22 being supported on cushion cap 1 instead of vibration hammer and squeeze into pile foundation Plinth, facilitates construction, saving time, reduces cost.Support member 22, in the sidepiece of bridge pier 7, reduces construction by the lock ring of anchor ear 24 Input, it is ensured that the stability of support member 22.Installing distribution beam group 25 and load-bearing are taken at the top of mounted adjacent supporting piece 22 Support 27, improves the security of construction, easy construction, efficiency high.Support bracket 27 holds out against with the beam body of bridge, i.e. beam portion Load passes to support bracket 27, is then passed to support member 22 and cushion cap 1.
Support member 22 positioned at bridge both ends is arranged on the inside portion of corresponding bridge pier 7, centrally located support member 22 both sides for being arranged on corresponding bridge pier 7.
Support 2 also includes connector 26 and diagonal brace 28, and the two ends of distribution beam group 25 are fixed on adjacent by connector 26 The top of two support members 22, one end of diagonal brace 28 is affixed with the waist of support member 22, and the other end is consolidated with the bottom on the side edge of distribution beam group 25 Connect.
Distribution beam group 25 includes plural longitudinal stake top distribution beam 251, Bailey beam 252 and horizontal little distribution beam 253, Bailey beam 252 is fixed between longitudinal stake top distribution beam 251 and horizontal little distribution beam 253, the middle part of longitudinal stake top distribution beam 251 The top of support member 22 is fixed on by connector 26, the bottom on the side edge of longitudinal stake top distribution beam 251 passes through the one of diagonal brace 28 End is fixed on the waist of support member 22, and Bailey beam 252 is welded in the top of longitudinal stake top distribution beam 251, and support bracket 27 is installed In the top of horizontal little distribution beam 253.
In the present embodiment, support bracket 27 is full hall scaffold.
In the present embodiment, support member 22 is connected on cushion cap 1 by reinforcing bar and Interal fixation.
In the present embodiment, longitudinal stake top distribution beam 251 is column top-type steel distribution beam.
In the present embodiment, support member 22 is steel column.
As shown in fig. 6, the installation method of the cross-line continuous beam dismounting support of the present embodiment is comprised the following steps that:
(1)Cushion cap datum level is levelling:Carry out just levelling post-installing rebar on cushion cap 1 to construct again steel plate, it is ensured that the lotus of support member 22 Load is uniformly transferred, it is ensured that the stability of support member 22, globality;
(2)Support member is installed:Basis is set up as support by the use of cushion cap 1, support member 22 is installed on cushion cap 1, hold cushion cap 1 The beam body and support gravity of support are carried, support will not fall, and further increase the safety assurance coefficient of construction;
(3)Anchor ear is constructed:Support member 22 is fixedly connected by anchor ear 24 with bridge pier 7, makes support attachment be fixed on bridge pier 7, it is ensured that the stability of support member 22, so as to improve the stability of bridging toughening;
(4)Distribution beam group is installed:
(4-1)Longitudinal stake top distribution beam is installed:Longitudinal stake top distribution beam 251 is added at the top of mounted support member 22 and make It is connected with connector 26, so arranges and both combined Bridge Types, quick, convenient, safety is installed again, so that bridge Beam is removed simple;
(4-2)Bailey beam, laterally little distribution beam are installed:Bailey beam 252 is installed in longitudinal stake top distribution beam 251 using loop wheel machine, Load is uniformly transferred by steel plate welding, then mounted thereon laterally little distribution beam 253;
(5)Support bracket is installed:Full framing is set up in distribution beam group 25 as support bracket, is so arranged, bridge lower section All supported with support, on the one hand can improve the security of construction, on the other hand can reduce the staffing of job site.
Continuous beam is three-span continuous beam in the present embodiment, and beam body 3 is split up into the plate beam element 31 of six equal portions, its application tool Body is as follows:First set up support 2 along bridge pier 7;The bottom of beam body 3 is snapped up with support 2 and is padded, pad meet require after, therefrom across across Middle position cuts off beam body 3, is cutting to the symmetric transverse bridge pier 7 for padding position that snaps up temporarily at along place of incision or expansion joint position Cut;The plate beam element 31 that cutting is formed is hung successively with automobile loop wheel machine;After the completion for the treatment of that plate beam element 31 hangs, to support 2 are dismantled.
In the present embodiment, in step sl, after support 2 is set up, by across beam body 3 and bridge pier 7 between space face When snap up and pad so that in across beam body 3 and the tight note reality of bridge pier 7, sturdy short position is adjusted with support, it is ensured that cutting Plate beam element 31 after beam body 3 can steadily fall on support 2, while arranging construction occasional passage 5 in the both sides of beam body 3, construction is faced The outsides of Shi Tongdao 5 plus safety device 6, the present embodiment is close mesh bar-mat reinforcement and green king, and arranges safety guide rail, further Improve the security of construction.
It is to be changed into approximate statically determinate system from maneuvering system when beam body 3 is cut in step s3 in the present embodiment, cuts Cut and should ensure that, when the bridge pier 7 for padding position to snapping up temporarily along span centre position cuts, self extending stitches position to the pad that snaps up temporarily The direction of bridge pier 7 of real part position simultaneously symmetrical should successively cut beam body 3, it is ensured that beam body to be cut 3 and the substructure of bridge pier 7 all the time into T-shaped.
In the present embodiment, before step S2 is carried out, first the wing plate of cross-line continuous beam is carried out into excision and hung, can guarantee that plate The main body of beam element 31 is slip gauge cuboid then, stress when being easy to plate beam element 31 to hang, and makes to hang process more steady It is reliable.
In the present embodiment, cut using rope saw, it is convenient and reliable using rope saw cut, noise can be reduced to surrounding environment 's.
In the present embodiment, in step s 4, the erect-position of hanging device 8 is identical with the place overbridge road surface position of beam body 3, treats After the completion of all plate beam elements 31 hang, support 2 is carried out to dismantle from top to bottom, by cross, so operated, on the one hand can be improved and apply The security of work, on the other hand can reduce the staffing of job site, can realize hanging work substantially synchronous with dismantlement work Carry out, efficiency of construction can be improved, while reducing to the interference to runway, meeting and protecting logical requirement.
Although the present invention is disclosed as above with preferred embodiment, but is not limited to the present invention.It is any to be familiar with ability The technical staff in domain, in the case of without departing from technical solution of the present invention scope, all using the technology contents pair of the disclosure above Technical solution of the present invention makes many possible variations and modification, or the Equivalent embodiments for being revised as equivalent variations.Therefore, it is every Without departing from the content of technical solution of the present invention, according to the technology of the present invention essence to any simple modification made for any of the above embodiments, Equivalent variations and modification, all should fall in the range of technical solution of the present invention protection.

Claims (14)

1. a kind of cross-line continuous beam method for dismounting, it is characterised in that comprise the following steps:
S1:Set up support:With bridge pier(7), cross-line road surface(4)To set up basis, along bridge pier(7)Sidepiece sets up support(2), bridge Beam body(3)Integrated carrying is in support(2)On;
S2:The interim pads of Dun Liang:By in across beam body(3)And bridge pier(7)Between space rubber cushion blocks(9)Copied temporarily Heelpiece reality, it is ensured that beam body(3)In cutting process, load is effectively passed to bridge pier(7);
S3:Laterally slitting:Therefrom across span centre position cut-out beam body(3), the bridge pier for padding position to snap up temporarily(7)For beam body (3)The stress strong point, from the bridge pier that place of incision pads position to snapping up temporarily(7)Cut beam body in direction(3)While, from Expansion joint position pads the bridge pier at position to snapping up temporarily(7)Beam body is symmetrically cut successively in direction(3), by beam body(3)Laterally divide Bar cuts into plate beam element(31), plate beam element(31)Fall in support(2)On;
S4:Piecemeal hangs:Using hanging device(8)By the plate beam element of cutting(31)Hung successively to specified location;
S5:Removal bracket:Treat plate beam element(31)After the completion of hanging, to support(2)Dismantled.
2. method according to claim 1, it is characterised in that:Support is set up in step S1(2)The step of be specially:Edge Bridge pier(7)Sidepiece is set up parallel to bridge pier(7)Support member(22), with support member(22)To support, in adjacent bridge pier(7) Support member(22)Between top set up distribution beam group(25)And support bracket(27), the support bracket(27)Top be close to Beam body(3)Bottom.
3. method according to claim 3, it is characterised in that:Distribution beam group is set up in step S1(25)And support bracket (27)Concretely comprise the following steps:In adjacent bridge pier(7)Support member(22)Between top set up distribution beam group(25), in distribution beam Group(25)Top laying support bracket(27)Until support bracket(27)Top be close to beam body(3)Bottom, distribution Beam group(25)With support bracket(27)Between gap carry out snapping up using wedge type block padding.
4. according to method described in claim 3, it is characterised in that:Distribution beam group is set up in step S1(25)With load-bearing Frame(27)Concrete steps also include:In beam body(3)Both sides support bracket(27)Top erection construction occasional passage(5), Construction occasional passage(5)Outside arranges safety device(6).
5. the method according to any one of Claims 1-4, it is characterised in that:Hanging device in step S4(8)It is located at Plate beam element to be hung(31)Place cross-line road surface(4)Same track on.
6. method according to claim 5, it is characterised in that:Step S5 is concretely comprised the following steps:In same cutting side Upwards, all plate beam elements are treated(31)Hang and complete, to hanging plate beam element(31)The support of lower section(2)From top to bottom by cross Dismounting.
7. the method according to any one of Claims 1-4, it is characterised in that:Device therefor is cut in step S3 is Rope saw.
8. the cross-line continuous beam dismounting support of a kind of method according to any one of claim 1 to 7, it is characterised in that: The support(2)Including support member(22)And anchor ear(24), the support member(22)It is arranged in corresponding bridge pier(7)Bottom periphery Cushion cap(1)Upper and and bridge pier(7)It is parallel, support member(22)By the anchor ear(24)Lock ring is in bridge pier(7)Sidepiece, adjacent two Support member(22)Take equipped with distribution beam group at top(25), the distribution beam group(25)Top is equiped with for holding when bridge is removed By the support bracket of bridge weight(27).
9. support according to claim 8, it is characterised in that:Positioned at the support member at bridge both ends(22)It is arranged on corresponding bridge Pier(7)Inside portion, centrally located support member(22)It is arranged on corresponding bridge pier(7)Both sides.
10. support according to claim 9, it is characterised in that:The support(2)Also include connector(26)And diagonal brace (28), the distribution beam group(25)Two ends pass through the connector(26)It is fixed on two adjacent support members(22)Top, The diagonal brace(28)One end and support member(22)Waist is affixed, the other end and distribution beam group(25)The bottom on side edge is affixed.
11. supports according to claim 10, it is characterised in that:The distribution beam group(25)Including plural longitudinal stake Top distribution beam(251), Bailey beam(252)With horizontal little distribution beam(253), the Bailey beam(252)It is fixed on longitudinal stake Top distribution beam(251)With the laterally little distribution beam(253)Between, longitudinal stake top distribution beam(251)Middle part pass through institute State connector(26)It is fixed on the support member(22)Top, longitudinal stake top distribution beam(251)Side edge bottom lead to Cross the diagonal brace(28)One end be fixed on the support member(22)On waist, the Bailey beam(252)It is welded in the longitudinal direction Stake top distribution beam(251)Top, the support bracket(27)It is installed on horizontal little distribution beam(253)Top.
12. according to any one of claim 8 to 11 support, it is characterised in that:The support bracket(27)For full hall pin hand Frame.
13. according to any one of claim 8 to 11 support, it is characterised in that:The support member(22)By reinforcing bar and steel Plate is fixedly connected on the cushion cap(1)On.
14. according to any one of claim 8 to 11 support, it is characterised in that:The support member(22)For steel column.
CN201610918643.3A 2016-10-21 2016-10-21 Cross-line continuous beam method for dismounting and dismounting holder Active CN106638336B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610918643.3A CN106638336B (en) 2016-10-21 2016-10-21 Cross-line continuous beam method for dismounting and dismounting holder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610918643.3A CN106638336B (en) 2016-10-21 2016-10-21 Cross-line continuous beam method for dismounting and dismounting holder

Publications (2)

Publication Number Publication Date
CN106638336A true CN106638336A (en) 2017-05-10
CN106638336B CN106638336B (en) 2018-08-10

Family

ID=58855783

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610918643.3A Active CN106638336B (en) 2016-10-21 2016-10-21 Cross-line continuous beam method for dismounting and dismounting holder

Country Status (1)

Country Link
CN (1) CN106638336B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107268463A (en) * 2017-08-18 2017-10-20 中铁二局集团有限公司 A kind of continuous beam method for dismounting
CN107447687A (en) * 2017-09-29 2017-12-08 中国水利水电第八工程局有限公司 Cross-line continuous beam is whole across method for dismounting and dismounting sectional shelf-unit
CN108589564A (en) * 2018-04-17 2018-09-28 成都西南交大研究院有限公司 A kind of bridge static state cutting whole into sections method for dismounting based on non-explosion
CN111535190A (en) * 2020-05-08 2020-08-14 安徽伟宏钢结构集团股份有限公司 Bridge mounting and dismounting construction method with high safety
CN113089510A (en) * 2021-04-14 2021-07-09 四川省交通建设集团股份有限公司 Method for dismantling reinforced concrete continuous box girder overpass bridge
CN113774821A (en) * 2021-08-28 2021-12-10 中交一公局集团有限公司 Bridge disassembling process

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10237823A (en) * 1997-02-27 1998-09-08 Nkk Corp Method for replacing overhead bridge
JP2007321473A (en) * 2006-06-01 2007-12-13 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Rebuilding method for bridge
CN102995571A (en) * 2012-09-05 2013-03-27 武汉二航路桥特种工程有限责任公司 Method for prepressing single large-tonnage temporary steel pipe support and then resisting beam bottom during dismantling bridge beam body, and device thereof
CN103343512A (en) * 2013-07-03 2013-10-09 上海市机械施工集团有限公司 Method for dismantling large-section concrete box girders and hoisting device
CN103711078A (en) * 2013-12-17 2014-04-09 北京工业大学 Temporary girder-type support for bridge construction and dismantling method thereof
CN104631349A (en) * 2015-02-04 2015-05-20 中铁十八局集团第一工程有限公司 Disassembly and storage method of urban viaduct steel box girder
CN204530494U (en) * 2015-02-11 2015-08-05 中铁三局集团有限公司 High pier binder template is set up and is used support

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10237823A (en) * 1997-02-27 1998-09-08 Nkk Corp Method for replacing overhead bridge
JP2007321473A (en) * 2006-06-01 2007-12-13 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Rebuilding method for bridge
CN102995571A (en) * 2012-09-05 2013-03-27 武汉二航路桥特种工程有限责任公司 Method for prepressing single large-tonnage temporary steel pipe support and then resisting beam bottom during dismantling bridge beam body, and device thereof
CN103343512A (en) * 2013-07-03 2013-10-09 上海市机械施工集团有限公司 Method for dismantling large-section concrete box girders and hoisting device
CN103711078A (en) * 2013-12-17 2014-04-09 北京工业大学 Temporary girder-type support for bridge construction and dismantling method thereof
CN104631349A (en) * 2015-02-04 2015-05-20 中铁十八局集团第一工程有限公司 Disassembly and storage method of urban viaduct steel box girder
CN204530494U (en) * 2015-02-11 2015-08-05 中铁三局集团有限公司 High pier binder template is set up and is used support

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107268463A (en) * 2017-08-18 2017-10-20 中铁二局集团有限公司 A kind of continuous beam method for dismounting
CN107447687A (en) * 2017-09-29 2017-12-08 中国水利水电第八工程局有限公司 Cross-line continuous beam is whole across method for dismounting and dismounting sectional shelf-unit
CN108589564A (en) * 2018-04-17 2018-09-28 成都西南交大研究院有限公司 A kind of bridge static state cutting whole into sections method for dismounting based on non-explosion
CN111535190A (en) * 2020-05-08 2020-08-14 安徽伟宏钢结构集团股份有限公司 Bridge mounting and dismounting construction method with high safety
CN113089510A (en) * 2021-04-14 2021-07-09 四川省交通建设集团股份有限公司 Method for dismantling reinforced concrete continuous box girder overpass bridge
CN113774821A (en) * 2021-08-28 2021-12-10 中交一公局集团有限公司 Bridge disassembling process

Also Published As

Publication number Publication date
CN106638336B (en) 2018-08-10

Similar Documents

Publication Publication Date Title
CN106638336A (en) Over-line continuous beam removing method and support for removing
CN109695206B (en) Method for dismantling superstructure of cable-stayed bridge of water-borne lean cable system
CN106978784B (en) A kind of Long span highway suspension bridge Demolition Construction method
CN109235290A (en) Bridge peace tears construction method open
CN107268463A (en) A kind of continuous beam method for dismounting
CN105350454B (en) Steel arch rib outer wrapped concrete construction method for steel trussed arch bridge
CN110512895A (en) A kind of high-rise cast-in-place concrete building demolition construction method
CN105155428B (en) Across railway in operation large-scale prefabricated PC concrete continuous T beam construction method
CN110172929A (en) A kind of concrete box beam flange plate cutting disassembling stabilising arrangement and cutting disassembling method
CN206887794U (en) A kind of supporting apparatus system during the segmentation dismounting for Continuous Bridge
CN113089510A (en) Method for dismantling reinforced concrete continuous box girder overpass bridge
CN109610353A (en) Saw cut technology of restricting removes Arch Bridge Construction engineering method
CN203530855U (en) Device for bridge capping beam construction by using steel bars through simple supporting method
CN110904867A (en) Construction method for dismantling upper-span existing line arch bridge
CN206143650U (en) Cross -line continuous beam is demolishd and is used support
CN206512605U (en) A kind of overall demolition, installation anticollision wall form and its walking track crane move system
CN106320192B (en) A kind of beam section replacing and reinforcing method for large span concrete continuous beam bridge
JP5015049B2 (en) Pier extension method
CN112921838B (en) Method for dismantling suspension line non-hinge rib arch bridge
CN206887771U (en) A kind of small across footpath plate-beam construction platform structure
CN204662929U (en) A kind of cross-line walking fence operation device
CN102493367B (en) Non-blasting construction method for dismantling pier to land bridge
CN112726434B (en) Three-span deck reinforced concrete arch bridge dismantling method
CN111593681B (en) Pier stud retaining cast-in-place box girder ecological dismantling system and construction method
CN205223849U (en) Bridge anticollision barrier template is lifted by crane and concrete defect patching device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant