CN106638336A - Over-line continuous beam removing method and support for removing - Google Patents
Over-line continuous beam removing method and support for removing Download PDFInfo
- Publication number
- CN106638336A CN106638336A CN201610918643.3A CN201610918643A CN106638336A CN 106638336 A CN106638336 A CN 106638336A CN 201610918643 A CN201610918643 A CN 201610918643A CN 106638336 A CN106638336 A CN 106638336A
- Authority
- CN
- China
- Prior art keywords
- support
- bridge pier
- support member
- distribution beam
- distribution
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D22/00—Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses an over-line continuous beam removing method. The method comprises the following steps of 1 support erecting, 2 temporary pier beam padding, 3 transverse stripping, 4 blocking hanging and 5 support removing. The invention further discloses a support for removing in the method. The support comprises supporting pieces and hoops, the supporting pieces are arranged on bearing platforms on the peripheries of the bottoms of the corresponding piers and are parallel to the piers, the supporting pieces are clamped on the sides of the piers through the hoops, distribution beam groups are installed on the tops of the adjacent two supporting pieces in an overlapping mode, and a bearing support used for bearing the weight of a bridge when the bridge is removed is installed on the tops of the distribution beam groups. The method has the advantages of being safe, stable, environmentally friendly in construction and the like, and the support has the advantages of being convenient to operate, capable of reasonably utilizing the mechanics principle and high in construction efficiency.
Description
Technical field
The invention mainly relates to as bridge structure demolition technique field, a kind of more particularly to cross-line continuous beam method for dismounting,
Further relate to the cross-line continuous beam dismounting support of aforementioned cross-line continuous beam method for dismounting.
Background technology
Current bridge application is sorted out, demolition blasting method and machinery can be divided into(Non- explosion)Two big classes of dismounting method
Not, each classification contains various different applications again, there is the respective scope of application.Using blasting procedure, straight more than bridging toughening
The method of abolishing, mechanical hoisting method are connect, but is typically removed using Mechanical Method across the existing circuit bridge that is open to traffic.Mechanical removal method refers to utilization
The forms such as plant equipment is crushed to bridge, split, handling are removed.Removed using crane barge lifting more than water Bridge, land
Floor-engaging frame method is frequently with compared with the dismounting of large-tonnage loop wheel machine bulk.But, there is security protection in existing cross-line continuous beam method for dismounting
The problems such as not in place, supporting construction is unreasonable, hanging device model used is big, have impact on to a certain extent safe construction.
The content of the invention
The technical problem to be solved in the present invention is to overcome the deficiencies in the prior art, there is provided a kind of safety and stability, construction environmental protection
Cross-line continuous beam method for dismounting, correspondingly provide in preceding method it is used it is a kind of easy to operate, rationally utilize mechanics principle
The cross-line continuous beam dismounting support high with efficiency of construction.
To solve above-mentioned technical problem, the present invention is employed the following technical solutions:
A kind of cross-line continuous beam method for dismounting, comprises the following steps:
S1:Set up support:With bridge pier, cross-line road surface as basis is set up, support is set up along bridge pier sidepiece, the beam body of bridge is integrally held
It is loaded on support;
S2:The interim pads of Dun Liang:By in across beam body and bridge pier between space snapped up temporarily with rubber cushion blocks and padded, really
Beam body is protected in cutting process, load is effectively passed to bridge pier;
S3:Laterally slitting:Therefrom across span centre position cut-out beam body, with stress of the bridge pier for padding position as beam body that snap up temporarily
The strong point, from bridge pier direction that place of incision pads position to snapping up temporarily cutting beam body while, self extending stitches position to facing
When snap up and pad the bridge pier direction at position and symmetrically cut beam body successively, the horizontal slitting of beam body is cut into plate beam element, plate-girder list
Unit falls on support;
S4:Piecemeal hangs:The plate beam element of cutting is hung successively to specified location using hanging device;
S5:Removal bracket:After the completion for the treatment of that plate beam element hangs, support is dismantled.
As the further improvement to above-mentioned technical proposal.
The step of setting up support in step S1 is specially:The support member parallel to bridge pier is set up along bridge pier sidepiece, with
To support, distribution beam group and support bracket, the support bracket are set up in the top between the support member of adjacent bridge pier to support member
Top be close to the bottom of beam body.
Concretely comprising the following steps for distribution beam group and support bracket is set up in step S1:Between the support member of adjacent bridge pier
Top set up distribution beam group, distribution beam group top laying support bracket until support bracket at the top of be close to beam body
Bottom, gap carries out snapping up padding using wedge type block between distribution beam group and support bracket.
The concrete steps of distribution beam group and support bracket are set up in step S1 also to be included:In beam body both sides support bracket
Top erection construction occasional passage, construction occasional passage on the outside of safety device is set.
Hanging device is located on the same track on plate beam element place cross-line road surface to be hung in step S4.
Step S5 is concretely comprised the following steps:In same cut direction, after the completion for the treatment of that all plate beam elements hang, to
Hang the support below plate beam element to dismantle by cross from top to down.
Device therefor is cut in step S3 for rope saw.
As a total inventive concept, present invention also offers a kind of cross-line continuous beam used by preceding method is removed using
Support, the support includes support member and anchor ear, and the support member is arranged on the cushion cap of corresponding bridge pier bottom periphery and and bridge
Pier is parallel, and support member is by the anchor ear lock ring in bridge pier sidepiece, and adjacent two support members top is taken equipped with distribution beam group, described
Distribution beam group top is equiped with the support bracket for bearing bridge weight when bridge is removed.
As the further improvement to above-mentioned technical proposal:
Support member positioned at bridge both ends is arranged on the inside portion of corresponding bridge pier, and centrally located support member is arranged on phase
Answer the both sides of bridge pier.
The support also includes connector and diagonal brace, and the two ends of the distribution beam group are fixed on adjacent by the connector
Two support members top, described diagonal brace one end is affixed with support member waist, and the other end is affixed with the bottom on distribution beam group side edge.
The distribution beam group includes plural longitudinal stake top distribution beam, Bailey beam and horizontal little distribution beam, the shellfish
Lei Liang is fixed between longitudinal stake top distribution beam and the horizontal little distribution beam, and the middle part of longitudinal stake top distribution beam leads to
The top that the connector is fixed on the support member is crossed, the bottom on the side edge of longitudinal stake top distribution beam passes through the diagonal brace
One end be fixed on the support member waist, the Bailey beam is welded in the top of longitudinal stake top distribution beam, described to hold
Weight support is installed on the top of horizontal little distribution beam.
The support bracket is full hall scaffold.
The support member is connected on the cushion cap by reinforcing bar and Interal fixation.
The support member is steel column.
Compared with prior art, it is an advantage of the current invention that:
The cross-line continuous beam method for dismounting of the present invention, support member plays interim carrying and cuts beam body;By in across beam body and
Space between bridge pier is snapped up and is padded temporarily with rubber cushion blocks, the beam body weight after cut-out is concentrated and is transferred to bridge pier bottom
In structure, the carrying risk of support is reduced;Therefrom across span centre position cut-out beam body after, it is horizontal to intermediate pier direction along place of incision
To symmetrical cutting, rationally using mechanics principle, reduce cutting difficulty, improve the security of construction.
The present invention cross-line continuous beam dismounting support, support member be arranged on the cushion cap of corresponding bridge pier bottom periphery and with
Bridge pier is parallel, and support member by the anchor ear lock ring in bridge pier sidepiece, take equipped with distribution beam group by adjacent two support members top, point
The support bracket for bearing bridge weight when bridge is removed is equiped with beam group top.The support member generation being supported on cushion cap
Vibration hammer Driven-in Pile Foundations have been replaced, construction, saving time, reduces cost has been facilitated.Support member is by anchor ear lock ring in bridge pier side
Portion, reduces construction input, it is ensured that the stability of support member.Installing distribution beam group is taken at the top of mounted adjacent supporting piece
And support bracket, improve the security of construction, easy construction, efficiency high.Support bracket holds out against with the beam body of bridge, i.e. beam portion
Load pass to support bracket, be then passed to support member and cushion cap.
Description of the drawings
Fig. 1 is the flow chart of cross-line continuous beam method for dismounting of the present invention.
Fig. 2 is the construction front view of cross-line continuous beam method for dismounting of the present invention.
Fig. 3 is the construction top view of cross-line continuous beam method for dismounting of the present invention.
Fig. 4 is laterally slitting beam body cut direction schematic diagram of the invention.
Fig. 5 is the construction hoisting figure of cross-line continuous beam method for dismounting of the present invention.
Fig. 6 is the installation procedure figure of cross-line continuous beam dismounting support of the present invention.
Each label is represented in figure:
1st, cushion cap;2nd, support;22nd, support member;24th, anchor ear;25th, distribution beam group;251st, longitudinal stake top distribution beam;252nd, Bei Lei
Beam;253rd, horizontal little distribution beam;26th, connector;27th, support bracket;28th, diagonal brace;3rd, beam body;31st, plate beam element;4th, cross-line
Road surface;5th, construction occasional passage;6th, safety device;7th, bridge pier;8th, hanging device;9th, rubber cushion blocks.
Specific embodiment
The present invention is described in further details below with reference to Figure of description and specific embodiment.
As shown in Fig. 1 to 5, a kind of cross-line continuous beam method for dismounting of the present invention is comprised the following steps:
S1:Set up support:With bridge pier 7, cross-line road surface 4 as basis is set up, along the sidepiece of bridge pier 7 support 2, the beam body 3 of bridge are set up
Integrated carrying is on support 2;
S2:The interim pads of Dun Liang:By in across beam body 3 and bridge pier 7 between space snapped up temporarily with rubber cushion blocks 9 pad
It is real, it is ensured that in cutting process, load is effectively passed to bridge pier 7 to beam body 3;
S3:Laterally slitting:Therefrom across span centre position cut-out beam body 3, the bridge pier 7 for padding position to snap up temporarily is as beam body 3
The stress strong point, while cutting beam body 3 from the direction of bridge pier 7 that place of incision pads position to snapping up temporarily, self extending seam position
Put the direction of bridge pier 7 for padding position to snapping up temporarily and symmetrically cut beam body 3 successively, the horizontal slitting of beam body 3 is cut into plate-girder list
Unit 31, plate beam element 31 falls on support 2;
S4:Piecemeal hangs:The plate beam element 31 of cutting is hung successively to specified location using hanging device 8;
S5:Removal bracket:After the completion for the treatment of that plate beam element 31 hangs, support 2 is dismantled.
Support member 22 plays interim carrying and cuts beam body 3;By in across beam body 3 and bridge pier 7 between space use rubber
Rubber cushion block 9 is snapped up and is padded temporarily, the weight of beam body 3 after cut-out is concentrated and is transferred in the substructure of bridge pier 7, reduces support
2 carrying risk;Therefrom across span centre position cut-out beam body 3 after, along place of incision to the lateral symmetry cutting in intermediate pier direction, close
Reason utilizes mechanics principle, reduces cutting difficulty, improves the security of construction.
The step of support 2 are set up in step S1 is specially:The support member 22 parallel to bridge pier 7 is set up along the sidepiece of bridge pier 7, with
To support, distribution beam group 25 and support bracket 27, load-bearing are set up in the top between the support member 22 of adjacent bridge pier 7 to support member 22
It is close to the bottom of beam body 3 in the top of support 27.
Concretely comprising the following steps for distribution beam group 25 and support bracket 27 is set up in step S1:In the support member 22 of adjacent bridge pier 7
Between top set up distribution beam group 25, distribution beam group 25 top laying support bracket 27 until support bracket 27 top
It is close to the bottom of beam body 3, gap carries out snapping up padding using wedge type block between distribution beam group 25 and support bracket 27.
The concrete steps of distribution beam group 25 and support bracket 27 are set up in step S1 also to be included:In the both sides load-bearing of beam body 3
The top erection construction occasional passage 5 of frame 27, in the outside of construction occasional passage 5 safety device 6 is arranged.
Hanging device 8 is located on the same track on the place cross-line road surface 4 of plate beam element 31 to be hung in step S4.This reality
In applying example, hanging device used 8 is loop wheel machine, and unit type is relatively small when the relatively large beam body of loop wheel machine is released, loop wheel machine erect-position with treat
The position consistency of 31 place cross-line road surface of plate beam element 4 of cutting, it is to avoid to disturbing to runway driving, reducing construction right
The impact of original traffic, meets and protects logical requirement.
Step S5 is concretely comprised the following steps:In same cut direction, after the completion for the treatment of that all plate beam elements 31 hang, to hanging
The support 2 for putting the lower section of plate beam element 31 is dismantled by cross from top to bottom.
Device therefor is cut in step S3 for rope saw.
The cut direction of horizontal slitting beam body is in step S3:Main span successively by span centre to pier top, end bay by abutment pier into
Across pier top.
The present invention cross-line continuous beam method for dismounting using full Support Method machine cuts dismounting, will beam body to be removed 3 use
The support 2 of pier beam type closed supports+steel pipe scaffold combination is supported, and the weight of beam body 3 is all born by support 2, then
Sawed with cutting equipment, i.e. rope, transverse cuts beam body 3 is lifted the plate beam element 31 that beam body 3 is decomposed into fritter, completes bridge
Beam is removed, and construction method is more ripe.
As shown in figure 5, a kind of cross-line continuous beam dismounting support of the present invention, support 2 includes support member 22 and anchor ear 24,
Support member 22 be arranged in it is on the cushion cap 1 of the bottom periphery of corresponding bridge pier 7 and parallel with bridge pier 7, support member 22 pass through the lock ring of anchor ear 24
In the sidepiece of bridge pier 7, the adjacent top of two support member 22 is taken equipped with distribution beam group 25, and the top of distribution beam group 25 is equiped with for tearing open
The support bracket 27 of bridge weight is born during except bridge.The support member 22 being supported on cushion cap 1 instead of vibration hammer and squeeze into pile foundation
Plinth, facilitates construction, saving time, reduces cost.Support member 22, in the sidepiece of bridge pier 7, reduces construction by the lock ring of anchor ear 24
Input, it is ensured that the stability of support member 22.Installing distribution beam group 25 and load-bearing are taken at the top of mounted adjacent supporting piece 22
Support 27, improves the security of construction, easy construction, efficiency high.Support bracket 27 holds out against with the beam body of bridge, i.e. beam portion
Load passes to support bracket 27, is then passed to support member 22 and cushion cap 1.
Support member 22 positioned at bridge both ends is arranged on the inside portion of corresponding bridge pier 7, centrally located support member
22 both sides for being arranged on corresponding bridge pier 7.
Support 2 also includes connector 26 and diagonal brace 28, and the two ends of distribution beam group 25 are fixed on adjacent by connector 26
The top of two support members 22, one end of diagonal brace 28 is affixed with the waist of support member 22, and the other end is consolidated with the bottom on the side edge of distribution beam group 25
Connect.
Distribution beam group 25 includes plural longitudinal stake top distribution beam 251, Bailey beam 252 and horizontal little distribution beam 253,
Bailey beam 252 is fixed between longitudinal stake top distribution beam 251 and horizontal little distribution beam 253, the middle part of longitudinal stake top distribution beam 251
The top of support member 22 is fixed on by connector 26, the bottom on the side edge of longitudinal stake top distribution beam 251 passes through the one of diagonal brace 28
End is fixed on the waist of support member 22, and Bailey beam 252 is welded in the top of longitudinal stake top distribution beam 251, and support bracket 27 is installed
In the top of horizontal little distribution beam 253.
In the present embodiment, support bracket 27 is full hall scaffold.
In the present embodiment, support member 22 is connected on cushion cap 1 by reinforcing bar and Interal fixation.
In the present embodiment, longitudinal stake top distribution beam 251 is column top-type steel distribution beam.
In the present embodiment, support member 22 is steel column.
As shown in fig. 6, the installation method of the cross-line continuous beam dismounting support of the present embodiment is comprised the following steps that:
(1)Cushion cap datum level is levelling:Carry out just levelling post-installing rebar on cushion cap 1 to construct again steel plate, it is ensured that the lotus of support member 22
Load is uniformly transferred, it is ensured that the stability of support member 22, globality;
(2)Support member is installed:Basis is set up as support by the use of cushion cap 1, support member 22 is installed on cushion cap 1, hold cushion cap 1
The beam body and support gravity of support are carried, support will not fall, and further increase the safety assurance coefficient of construction;
(3)Anchor ear is constructed:Support member 22 is fixedly connected by anchor ear 24 with bridge pier 7, makes support attachment be fixed on bridge pier
7, it is ensured that the stability of support member 22, so as to improve the stability of bridging toughening;
(4)Distribution beam group is installed:
(4-1)Longitudinal stake top distribution beam is installed:Longitudinal stake top distribution beam 251 is added at the top of mounted support member 22 and make
It is connected with connector 26, so arranges and both combined Bridge Types, quick, convenient, safety is installed again, so that bridge
Beam is removed simple;
(4-2)Bailey beam, laterally little distribution beam are installed:Bailey beam 252 is installed in longitudinal stake top distribution beam 251 using loop wheel machine,
Load is uniformly transferred by steel plate welding, then mounted thereon laterally little distribution beam 253;
(5)Support bracket is installed:Full framing is set up in distribution beam group 25 as support bracket, is so arranged, bridge lower section
All supported with support, on the one hand can improve the security of construction, on the other hand can reduce the staffing of job site.
Continuous beam is three-span continuous beam in the present embodiment, and beam body 3 is split up into the plate beam element 31 of six equal portions, its application tool
Body is as follows:First set up support 2 along bridge pier 7;The bottom of beam body 3 is snapped up with support 2 and is padded, pad meet require after, therefrom across across
Middle position cuts off beam body 3, is cutting to the symmetric transverse bridge pier 7 for padding position that snaps up temporarily at along place of incision or expansion joint position
Cut;The plate beam element 31 that cutting is formed is hung successively with automobile loop wheel machine;After the completion for the treatment of that plate beam element 31 hangs, to support
2 are dismantled.
In the present embodiment, in step sl, after support 2 is set up, by across beam body 3 and bridge pier 7 between space face
When snap up and pad so that in across beam body 3 and the tight note reality of bridge pier 7, sturdy short position is adjusted with support, it is ensured that cutting
Plate beam element 31 after beam body 3 can steadily fall on support 2, while arranging construction occasional passage 5 in the both sides of beam body 3, construction is faced
The outsides of Shi Tongdao 5 plus safety device 6, the present embodiment is close mesh bar-mat reinforcement and green king, and arranges safety guide rail, further
Improve the security of construction.
It is to be changed into approximate statically determinate system from maneuvering system when beam body 3 is cut in step s3 in the present embodiment, cuts
Cut and should ensure that, when the bridge pier 7 for padding position to snapping up temporarily along span centre position cuts, self extending stitches position to the pad that snaps up temporarily
The direction of bridge pier 7 of real part position simultaneously symmetrical should successively cut beam body 3, it is ensured that beam body to be cut 3 and the substructure of bridge pier 7 all the time into
T-shaped.
In the present embodiment, before step S2 is carried out, first the wing plate of cross-line continuous beam is carried out into excision and hung, can guarantee that plate
The main body of beam element 31 is slip gauge cuboid then, stress when being easy to plate beam element 31 to hang, and makes to hang process more steady
It is reliable.
In the present embodiment, cut using rope saw, it is convenient and reliable using rope saw cut, noise can be reduced to surrounding environment
's.
In the present embodiment, in step s 4, the erect-position of hanging device 8 is identical with the place overbridge road surface position of beam body 3, treats
After the completion of all plate beam elements 31 hang, support 2 is carried out to dismantle from top to bottom, by cross, so operated, on the one hand can be improved and apply
The security of work, on the other hand can reduce the staffing of job site, can realize hanging work substantially synchronous with dismantlement work
Carry out, efficiency of construction can be improved, while reducing to the interference to runway, meeting and protecting logical requirement.
Although the present invention is disclosed as above with preferred embodiment, but is not limited to the present invention.It is any to be familiar with ability
The technical staff in domain, in the case of without departing from technical solution of the present invention scope, all using the technology contents pair of the disclosure above
Technical solution of the present invention makes many possible variations and modification, or the Equivalent embodiments for being revised as equivalent variations.Therefore, it is every
Without departing from the content of technical solution of the present invention, according to the technology of the present invention essence to any simple modification made for any of the above embodiments,
Equivalent variations and modification, all should fall in the range of technical solution of the present invention protection.
Claims (14)
1. a kind of cross-line continuous beam method for dismounting, it is characterised in that comprise the following steps:
S1:Set up support:With bridge pier(7), cross-line road surface(4)To set up basis, along bridge pier(7)Sidepiece sets up support(2), bridge
Beam body(3)Integrated carrying is in support(2)On;
S2:The interim pads of Dun Liang:By in across beam body(3)And bridge pier(7)Between space rubber cushion blocks(9)Copied temporarily
Heelpiece reality, it is ensured that beam body(3)In cutting process, load is effectively passed to bridge pier(7);
S3:Laterally slitting:Therefrom across span centre position cut-out beam body(3), the bridge pier for padding position to snap up temporarily(7)For beam body
(3)The stress strong point, from the bridge pier that place of incision pads position to snapping up temporarily(7)Cut beam body in direction(3)While, from
Expansion joint position pads the bridge pier at position to snapping up temporarily(7)Beam body is symmetrically cut successively in direction(3), by beam body(3)Laterally divide
Bar cuts into plate beam element(31), plate beam element(31)Fall in support(2)On;
S4:Piecemeal hangs:Using hanging device(8)By the plate beam element of cutting(31)Hung successively to specified location;
S5:Removal bracket:Treat plate beam element(31)After the completion of hanging, to support(2)Dismantled.
2. method according to claim 1, it is characterised in that:Support is set up in step S1(2)The step of be specially:Edge
Bridge pier(7)Sidepiece is set up parallel to bridge pier(7)Support member(22), with support member(22)To support, in adjacent bridge pier(7)
Support member(22)Between top set up distribution beam group(25)And support bracket(27), the support bracket(27)Top be close to
Beam body(3)Bottom.
3. method according to claim 3, it is characterised in that:Distribution beam group is set up in step S1(25)And support bracket
(27)Concretely comprise the following steps:In adjacent bridge pier(7)Support member(22)Between top set up distribution beam group(25), in distribution beam
Group(25)Top laying support bracket(27)Until support bracket(27)Top be close to beam body(3)Bottom, distribution
Beam group(25)With support bracket(27)Between gap carry out snapping up using wedge type block padding.
4. according to method described in claim 3, it is characterised in that:Distribution beam group is set up in step S1(25)With load-bearing
Frame(27)Concrete steps also include:In beam body(3)Both sides support bracket(27)Top erection construction occasional passage(5),
Construction occasional passage(5)Outside arranges safety device(6).
5. the method according to any one of Claims 1-4, it is characterised in that:Hanging device in step S4(8)It is located at
Plate beam element to be hung(31)Place cross-line road surface(4)Same track on.
6. method according to claim 5, it is characterised in that:Step S5 is concretely comprised the following steps:In same cutting side
Upwards, all plate beam elements are treated(31)Hang and complete, to hanging plate beam element(31)The support of lower section(2)From top to bottom by cross
Dismounting.
7. the method according to any one of Claims 1-4, it is characterised in that:Device therefor is cut in step S3 is
Rope saw.
8. the cross-line continuous beam dismounting support of a kind of method according to any one of claim 1 to 7, it is characterised in that:
The support(2)Including support member(22)And anchor ear(24), the support member(22)It is arranged in corresponding bridge pier(7)Bottom periphery
Cushion cap(1)Upper and and bridge pier(7)It is parallel, support member(22)By the anchor ear(24)Lock ring is in bridge pier(7)Sidepiece, adjacent two
Support member(22)Take equipped with distribution beam group at top(25), the distribution beam group(25)Top is equiped with for holding when bridge is removed
By the support bracket of bridge weight(27).
9. support according to claim 8, it is characterised in that:Positioned at the support member at bridge both ends(22)It is arranged on corresponding bridge
Pier(7)Inside portion, centrally located support member(22)It is arranged on corresponding bridge pier(7)Both sides.
10. support according to claim 9, it is characterised in that:The support(2)Also include connector(26)And diagonal brace
(28), the distribution beam group(25)Two ends pass through the connector(26)It is fixed on two adjacent support members(22)Top,
The diagonal brace(28)One end and support member(22)Waist is affixed, the other end and distribution beam group(25)The bottom on side edge is affixed.
11. supports according to claim 10, it is characterised in that:The distribution beam group(25)Including plural longitudinal stake
Top distribution beam(251), Bailey beam(252)With horizontal little distribution beam(253), the Bailey beam(252)It is fixed on longitudinal stake
Top distribution beam(251)With the laterally little distribution beam(253)Between, longitudinal stake top distribution beam(251)Middle part pass through institute
State connector(26)It is fixed on the support member(22)Top, longitudinal stake top distribution beam(251)Side edge bottom lead to
Cross the diagonal brace(28)One end be fixed on the support member(22)On waist, the Bailey beam(252)It is welded in the longitudinal direction
Stake top distribution beam(251)Top, the support bracket(27)It is installed on horizontal little distribution beam(253)Top.
12. according to any one of claim 8 to 11 support, it is characterised in that:The support bracket(27)For full hall pin hand
Frame.
13. according to any one of claim 8 to 11 support, it is characterised in that:The support member(22)By reinforcing bar and steel
Plate is fixedly connected on the cushion cap(1)On.
14. according to any one of claim 8 to 11 support, it is characterised in that:The support member(22)For steel column.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610918643.3A CN106638336B (en) | 2016-10-21 | 2016-10-21 | Cross-line continuous beam method for dismounting and dismounting holder |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610918643.3A CN106638336B (en) | 2016-10-21 | 2016-10-21 | Cross-line continuous beam method for dismounting and dismounting holder |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106638336A true CN106638336A (en) | 2017-05-10 |
CN106638336B CN106638336B (en) | 2018-08-10 |
Family
ID=58855783
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610918643.3A Active CN106638336B (en) | 2016-10-21 | 2016-10-21 | Cross-line continuous beam method for dismounting and dismounting holder |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106638336B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107268463A (en) * | 2017-08-18 | 2017-10-20 | 中铁二局集团有限公司 | A kind of continuous beam method for dismounting |
CN107447687A (en) * | 2017-09-29 | 2017-12-08 | 中国水利水电第八工程局有限公司 | Cross-line continuous beam is whole across method for dismounting and dismounting sectional shelf-unit |
CN108589564A (en) * | 2018-04-17 | 2018-09-28 | 成都西南交大研究院有限公司 | A kind of bridge static state cutting whole into sections method for dismounting based on non-explosion |
CN111535190A (en) * | 2020-05-08 | 2020-08-14 | 安徽伟宏钢结构集团股份有限公司 | Bridge mounting and dismounting construction method with high safety |
CN113089510A (en) * | 2021-04-14 | 2021-07-09 | 四川省交通建设集团股份有限公司 | Method for dismantling reinforced concrete continuous box girder overpass bridge |
CN113774821A (en) * | 2021-08-28 | 2021-12-10 | 中交一公局集团有限公司 | Bridge disassembling process |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10237823A (en) * | 1997-02-27 | 1998-09-08 | Nkk Corp | Method for replacing overhead bridge |
JP2007321473A (en) * | 2006-06-01 | 2007-12-13 | Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd | Rebuilding method for bridge |
CN102995571A (en) * | 2012-09-05 | 2013-03-27 | 武汉二航路桥特种工程有限责任公司 | Method for prepressing single large-tonnage temporary steel pipe support and then resisting beam bottom during dismantling bridge beam body, and device thereof |
CN103343512A (en) * | 2013-07-03 | 2013-10-09 | 上海市机械施工集团有限公司 | Method for dismantling large-section concrete box girders and hoisting device |
CN103711078A (en) * | 2013-12-17 | 2014-04-09 | 北京工业大学 | Temporary girder-type support for bridge construction and dismantling method thereof |
CN104631349A (en) * | 2015-02-04 | 2015-05-20 | 中铁十八局集团第一工程有限公司 | Disassembly and storage method of urban viaduct steel box girder |
CN204530494U (en) * | 2015-02-11 | 2015-08-05 | 中铁三局集团有限公司 | High pier binder template is set up and is used support |
-
2016
- 2016-10-21 CN CN201610918643.3A patent/CN106638336B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10237823A (en) * | 1997-02-27 | 1998-09-08 | Nkk Corp | Method for replacing overhead bridge |
JP2007321473A (en) * | 2006-06-01 | 2007-12-13 | Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd | Rebuilding method for bridge |
CN102995571A (en) * | 2012-09-05 | 2013-03-27 | 武汉二航路桥特种工程有限责任公司 | Method for prepressing single large-tonnage temporary steel pipe support and then resisting beam bottom during dismantling bridge beam body, and device thereof |
CN103343512A (en) * | 2013-07-03 | 2013-10-09 | 上海市机械施工集团有限公司 | Method for dismantling large-section concrete box girders and hoisting device |
CN103711078A (en) * | 2013-12-17 | 2014-04-09 | 北京工业大学 | Temporary girder-type support for bridge construction and dismantling method thereof |
CN104631349A (en) * | 2015-02-04 | 2015-05-20 | 中铁十八局集团第一工程有限公司 | Disassembly and storage method of urban viaduct steel box girder |
CN204530494U (en) * | 2015-02-11 | 2015-08-05 | 中铁三局集团有限公司 | High pier binder template is set up and is used support |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107268463A (en) * | 2017-08-18 | 2017-10-20 | 中铁二局集团有限公司 | A kind of continuous beam method for dismounting |
CN107447687A (en) * | 2017-09-29 | 2017-12-08 | 中国水利水电第八工程局有限公司 | Cross-line continuous beam is whole across method for dismounting and dismounting sectional shelf-unit |
CN108589564A (en) * | 2018-04-17 | 2018-09-28 | 成都西南交大研究院有限公司 | A kind of bridge static state cutting whole into sections method for dismounting based on non-explosion |
CN111535190A (en) * | 2020-05-08 | 2020-08-14 | 安徽伟宏钢结构集团股份有限公司 | Bridge mounting and dismounting construction method with high safety |
CN113089510A (en) * | 2021-04-14 | 2021-07-09 | 四川省交通建设集团股份有限公司 | Method for dismantling reinforced concrete continuous box girder overpass bridge |
CN113774821A (en) * | 2021-08-28 | 2021-12-10 | 中交一公局集团有限公司 | Bridge disassembling process |
Also Published As
Publication number | Publication date |
---|---|
CN106638336B (en) | 2018-08-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106638336A (en) | Over-line continuous beam removing method and support for removing | |
CN109695206B (en) | Method for dismantling superstructure of cable-stayed bridge of water-borne lean cable system | |
CN106978784B (en) | A kind of Long span highway suspension bridge Demolition Construction method | |
CN109235290A (en) | Bridge peace tears construction method open | |
CN107268463A (en) | A kind of continuous beam method for dismounting | |
CN105350454B (en) | Steel arch rib outer wrapped concrete construction method for steel trussed arch bridge | |
CN110512895A (en) | A kind of high-rise cast-in-place concrete building demolition construction method | |
CN105155428B (en) | Across railway in operation large-scale prefabricated PC concrete continuous T beam construction method | |
CN110172929A (en) | A kind of concrete box beam flange plate cutting disassembling stabilising arrangement and cutting disassembling method | |
CN206887794U (en) | A kind of supporting apparatus system during the segmentation dismounting for Continuous Bridge | |
CN113089510A (en) | Method for dismantling reinforced concrete continuous box girder overpass bridge | |
CN109610353A (en) | Saw cut technology of restricting removes Arch Bridge Construction engineering method | |
CN203530855U (en) | Device for bridge capping beam construction by using steel bars through simple supporting method | |
CN110904867A (en) | Construction method for dismantling upper-span existing line arch bridge | |
CN206143650U (en) | Cross -line continuous beam is demolishd and is used support | |
CN206512605U (en) | A kind of overall demolition, installation anticollision wall form and its walking track crane move system | |
CN106320192B (en) | A kind of beam section replacing and reinforcing method for large span concrete continuous beam bridge | |
JP5015049B2 (en) | Pier extension method | |
CN112921838B (en) | Method for dismantling suspension line non-hinge rib arch bridge | |
CN206887771U (en) | A kind of small across footpath plate-beam construction platform structure | |
CN204662929U (en) | A kind of cross-line walking fence operation device | |
CN102493367B (en) | Non-blasting construction method for dismantling pier to land bridge | |
CN112726434B (en) | Three-span deck reinforced concrete arch bridge dismantling method | |
CN111593681B (en) | Pier stud retaining cast-in-place box girder ecological dismantling system and construction method | |
CN205223849U (en) | Bridge anticollision barrier template is lifted by crane and concrete defect patching device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |