CN204530494U CN201520097562.2U CN201520097562U CN204530494U CN 204530494 U CN204530494 U CN 204530494U CN 201520097562 U CN201520097562 U CN 201520097562U CN 204530494 U CN204530494 U CN 204530494U
Authority
CN
China
Prior art keywords
high pier
longeron
wedge
template
dismounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520097562.2U
Other languages
Chinese (zh)
Inventor
孙中华
秦德进
刘晓栋
李傲龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 3 Engineering Group Co Ltd
Six Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Original Assignee
China Railway No 3 Engineering Group Co Ltd
Six Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 3 Engineering Group Co Ltd, Six Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd filed Critical China Railway No 3 Engineering Group Co Ltd
Priority to CN201520097562.2U priority Critical patent/CN204530494U/en
Application granted granted Critical
Publication of CN204530494U publication Critical patent/CN204530494U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model belongs to high pier constructing tie beam technical field, for solving the technical problem that high pier binder template is set up, providing a kind of high pier binder template sets up with support, comprise some longerons, the two ends of every root longeron are all seated on the brace summer that is arranged on many rod irons, some longeron intervals are arranged on brace summer, rod iron is plugged in the pvc pipe that is embedded in advance in high pier, dismounting is provided with to wedge I between rod iron and brace summer, on longeron, vertical rack is provided with some crossbeams, dismounting is provided with to wedge II between longeron and crossbeam, crossbeam lays wooden form.The utility model, by pre-buried pvc pipe in high pier, inserts rod iron method as the strong point to set up template, improves safety and the efficiency of construction of construction in pvc pipe; Solve pre-embedded steel slab or i iron in the past to cut after using, cut surface process, cut surface is vulnerable to the problem of corroding simultaneously; Adopt dismounting to wedge adjustable die plate height and be convenient to template dismounting.

Description

High pier binder template is set up and is used support
Technical field
The utility model belongs to high pier constructing tie beam technical field, is specifically related to a kind of high pier binder template and sets up and use support.
Background technology
Due to high-speed railway, the developing rapidly of speedway, mountain construction extensively adopts bridge to pass through, high pier bridge construction gets more and more, how high pier binder template is set up is urgent problem, because high pier binder span is comparatively large and higher apart from ground, conventional setting up is taked to land the construction method of framed bent frame shuttering, not only to consume a large amount of tubing, cost has high input, construction speed is slow, and framed bent is set up and removes difficulty, be also difficult to ensure construction quality simultaneously, also there is larger potential safety hazard.In order to head it off, to adopt at the appropriate location pre-embedded steel slab of bridge pier or i iron as the strong point to set up template, but pre-embedded steel slab or i iron need to carry out cutting and cut surface process after using, and cut surface is vulnerable to corrode in the past.
Summary of the invention
The utility model is solve the technical problem that high pier binder template sets up, and provides a kind of high pier binder template and sets up and use support.
The technical solution adopted in the utility model is as follows:
A kind of high pier binder template is set up with support, comprise some longerons, the two ends of every root longeron are all seated on the brace summer that is arranged on many rod irons, some longeron intervals are arranged on brace summer, and rod iron is plugged in the pvc pipe that is embedded in advance in high pier, are provided with dismounting to wedge I between rod iron and brace summer, on longeron, vertical rack is provided with some crossbeams, some girder spaces are arranged on longeron, be provided with dismounting to wedge II, crossbeam lays wooden form between longeron and crossbeam.
Dismounting is provided with backing plate between wedge I and rod iron.
Described longeron adopts 32a i iron, and the distance between adjacent two longerons is 50cm.
Described crossbeam adopts 20a i iron, and the distance between adjacent two crossbeams is 30cm.
The diameter of described pvc pipe is 10cm, and the diameter of rod iron is 9cm.
The beneficial effects of the utility model:
1. the utility model adopts pre-buried pvc pipe in high pier, inserts rod iron method as the strong point to set up template, improve safety and the efficiency of construction of construction in pvc pipe.
2. rear rod iron of the present utility model of having constructed can be extracted out and recycle, reserving hole is repaired, by pvc pipe pre-buried in high pier, solve pre-embedded steel slab or i iron in the past to cut after using, cut surface process, cut surface is vulnerable to the problem of corroding, and improves efficiency of construction, increases working security.
3. dismounting of the present utility model to wedge adjustable die plate height and be convenient to template dismounting, ensure construction fast and safely, drop into little.
Accompanying drawing explanation
Fig. 1 is front view of the present utility model;
Fig. 2 is the a-a sectional drawing of Fig. 1;
In figure: 1-longeron, 2-rod iron, 3-brace summer, 4-PVC manages, and 5-dismounting is to wedge I, 6-crossbeam, and 7-dismantles wedge II, 8-wooden form, 9-backing plate, 10-high pier.
Detailed description of the invention
As Fig. 1, shown in 2, a kind of high pier binder template is set up with support, comprise some longerons 1, described longeron 1 adopts 32a i iron, the two ends of every root longeron 1 are all seated on the brace summer 3 that is arranged on many rod irons 2, some longerons 1 are equidistantly arranged on brace summer 3 in interval, distance between adjacent two longerons 1 is 50cm, rod iron 2 is plugged in the pvc pipe 4 that is embedded in advance in high pier 10, the diameter of described pvc pipe 4 is 10cm, the diameter of rod iron 2 is 9cm, height for the ease of adjusting template dismantles template with being convenient to, be provided with between rod iron 2 and brace summer 3 and dismantle wedge I5, in order to ensure dismantle to wedge I5 stable be placed on rod iron 2, rod iron 2 is placed a backing plate 9, on longeron 1, vertical rack is provided with some crossbeams 6, described crossbeam 6 adopts 20a i iron, some crossbeams 6 are equidistantly arranged on longeron 1 in interval, distance between adjacent two crossbeams 6 is 30cm, be provided with between longeron 1 and crossbeam 6 and dismantle wedge II7, crossbeam 6 is laid wooden form 8.
The utility model is the pvc pipe of 10cm by shifting to an earlier date pre-buried diameter when high bridge pier stud is constructed, inserting diameter is wherein that the rod iron of 9cm does the strong point and sets up binder template, in conjunction with the dismounting of model sheetinstallat and dismounting to wedge adjustable die plate height be convenient to template dismounting, ensure construction fast and safely, drop into little.
Rear rod iron of the present utility model of having constructed can be extracted out and recycle, and repairs reserving hole.The method solves pre-embedded steel slab or i iron in the past and cuts after using, cut surface process, and cut surface is vulnerable to the problems such as corrosion, improves efficiency of construction, increases working security.

Claims (5)

1. a high pier binder template is set up with support, it is characterized in that: comprise some longerons (1), the two ends of every root longeron (1) are all seated on the brace summer (3) that is arranged on many rod irons (2), some longeron (1) intervals are arranged on brace summer (3), rod iron (2) is plugged in the pvc pipe (4) that is embedded in advance in high pier (10), be provided with between rod iron (2) and brace summer (3) and dismantle wedge I(5), the upper vertical rack of longeron (1) is provided with some crossbeams (6), some crossbeam (6) intervals are arranged on longeron (1), be provided with between longeron (1) and crossbeam (6) and dismantle wedge II(7), crossbeam (6) is laid wooden form (8).
2. a kind of high pier binder template according to claim 1 is set up with support, it is characterized in that: dismantle wedge I(5) and rod iron (2) between be provided with backing plate (9).
3. a kind of high pier binder template according to claim 1 is set up with support, it is characterized in that: described longeron (1) adopts 32a i iron, and the distance between adjacent two longerons (1) is 50cm.
4. a kind of high pier binder template according to claim 1 is set up with support, it is characterized in that: described crossbeam (6) adopts 20a i iron, and the distance between adjacent two crossbeams (6) is 30cm.
5. a kind of high pier binder template according to claim 1 is set up with support, and it is characterized in that: the diameter of described pvc pipe (4) is 10cm, the diameter of rod iron (2) is 9cm.
CN201520097562.2U 2015-02-11 2015-02-11 High pier binder template is set up and is used support Expired - Fee Related CN204530494U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520097562.2U CN204530494U (en) 2015-02-11 2015-02-11 High pier binder template is set up and is used support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520097562.2U CN204530494U (en) 2015-02-11 2015-02-11 High pier binder template is set up and is used support

Publications (1)

Publication Number Publication Date
CN204530494U true CN204530494U (en) 2015-08-05

Family

ID=53744516

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520097562.2U Expired - Fee Related CN204530494U (en) 2015-02-11 2015-02-11 High pier binder template is set up and is used support

Country Status (1)

Country Link
CN (1) CN204530494U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106087751A (en) * 2016-06-30 2016-11-09 中交航局第四工程有限公司 Operating platform in a kind of hollow thin-walled high pier
CN106638336A (en) * 2016-10-21 2017-05-10 中国水利水电第八工程局有限公司 Over-line continuous beam removing method and support for removing
CN107700676A (en) * 2017-09-20 2018-02-16 中国建筑股份有限公司 A kind of dry method connecting plate type structural system and its construction method
CN110700105A (en) * 2019-10-21 2020-01-17 中交一公局第七工程有限公司 Synchronous construction method for high pier column and tie beam and template used in same
CN111236087A (en) * 2020-03-23 2020-06-05 贵州省公路工程集团有限公司 A sliding type high pier tied beam formwork support system and construction method
CN111877177A (en) * 2020-08-03 2020-11-03 重庆交通建设(集团)有限责任公司 Construction method of underwater pier bearing platform
CN112962427A (en) * 2021-04-20 2021-06-15 中铁三局集团有限公司 Off-standard span cast-in-place beam support across valley and construction method
CN113202026A (en) * 2021-04-01 2021-08-03 中铁六局集团有限公司 Construction method for tie beam between pier columns

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106087751A (en) * 2016-06-30 2016-11-09 中交航局第四工程有限公司 Operating platform in a kind of hollow thin-walled high pier
CN106638336A (en) * 2016-10-21 2017-05-10 中国水利水电第八工程局有限公司 Over-line continuous beam removing method and support for removing
CN106638336B (en) * 2016-10-21 2018-08-10 中国水利水电第八工程局有限公司 Cross-line continuous beam method for dismounting and dismounting holder
CN107700676A (en) * 2017-09-20 2018-02-16 中国建筑股份有限公司 A kind of dry method connecting plate type structural system and its construction method
CN107700676B (en) * 2017-09-20 2023-11-10 中国建筑股份有限公司 Dry-method connection plate type structural system and construction method thereof
CN110700105A (en) * 2019-10-21 2020-01-17 中交一公局第七工程有限公司 Synchronous construction method for high pier column and tie beam and template used in same
CN111236087A (en) * 2020-03-23 2020-06-05 贵州省公路工程集团有限公司 A sliding type high pier tied beam formwork support system and construction method
CN111877177A (en) * 2020-08-03 2020-11-03 重庆交通建设(集团)有限责任公司 Construction method of underwater pier bearing platform
CN113202026A (en) * 2021-04-01 2021-08-03 中铁六局集团有限公司 Construction method for tie beam between pier columns
CN112962427A (en) * 2021-04-20 2021-06-15 中铁三局集团有限公司 Off-standard span cast-in-place beam support across valley and construction method

Similar Documents

Publication Publication Date Title
CN204530494U (en) High pier binder template is set up and is used support
CN104099872B (en) A kind of undercrossing tunnel large span box culvert is vertical to be chosen and horizontal lifts jacking construction method
CN204876547U (en) Big template system of APC shell structure
CN204960342U (en) But height -adjusting's roof beam reinforcement supports instrument
CN204781970U (en) Template fixing device with adjustable
CN204001436U (en) A kind of constructing structure that guarantees topping at the bottom of beam, deck-molding and thickness of slab
CN204001776U (en) Cast-in-place anticollision barrier reinforcing bar location moulding bed
CN205036096U (en) Be used for accessible device that passes through of three -dimensional support of reinforcing bar
CN204603626U (en) The flange of steel tube tower and C template positioner
CN203307730U (en) Pump pipe fixing device for bridge tower concrete construction
CN204801846U (en) Civil engineering pipe fitting rack
CN208618838U (en) A kind of safety device
CN202031309U (en) Suspending operation platform for structural concrete constructions
CN104900147A (en) Hardware fitting special for rod number marking
CN205822014U (en) A kind of Hollow High Pier pier top entity section template rigid frame
CN204370828U (en) Tool-type protective screening
CN202323720U (en) Capping beam template supporting device
CN203603490U (en) Supporting structure used for erecting formwork truss on prefabricated beam
CN103938877B (en) The installation method of crab-bolt stock
CN103397779B (en) A kind of method for supporting of large height shear wall formwork
CN202227281U (en) Triangular bracket for constructing zero block by box girder cantilever
CN105370046B (en) A kind of application method of beam steel installation tool
CN205134963U (en) Roof beam rebar installation instrument
CN206267039U (en) A kind of jack support platform of hollow slab girder jack-up construction
CN203938972U (en) The continuous girder bridge box type girder cast-in-place bracing frame that possesses whole vertical shift function

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150805