CN106638331B - A kind of installation method of tower with suspended cable - Google Patents

A kind of installation method of tower with suspended cable Download PDF

Info

Publication number
CN106638331B
CN106638331B CN201710035633.XA CN201710035633A CN106638331B CN 106638331 B CN106638331 B CN 106638331B CN 201710035633 A CN201710035633 A CN 201710035633A CN 106638331 B CN106638331 B CN 106638331B
Authority
CN
China
Prior art keywords
tower
cable
suspended cable
suspended
lagging jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710035633.XA
Other languages
Chinese (zh)
Other versions
CN106638331A (en
Inventor
邓玉平
洪立
陈治任
潘东发
吴方明
宋小三
涂满明
毛伟琦
田继开
周超舟
刘玲晶
聂井华
刘生奇
王武力
刘志燕
陈凤金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
Original Assignee
China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Group Co Ltd MBEC filed Critical China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority to CN201710035633.XA priority Critical patent/CN106638331B/en
Publication of CN106638331A publication Critical patent/CN106638331A/en
Application granted granted Critical
Publication of CN106638331B publication Critical patent/CN106638331B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of installation methods of tower with suspended cable, it is related to field of bridge construction, comprising steps of S1: after the completion of the construction of end bay steel lagging jack, along vertical bridge to assembled tower with suspended cable section by section on end bay steel lagging jack, and across steel lagging jack in installing, and the position mounting seat across steel lagging jack in end bay steel lagging jack is close, tower with suspended cable one end and the pedestal is hinged;S2: after the completion of tower with suspended cable is assembled, in the rear hoist cable that the other end of tower with suspended cable is installed the preceding hoist cable extended in across steel lagging jack and extended to end bay steel lagging jack, cable crane lifting tower with suspended cable simultaneously makes tower with suspended cable turn to vertical state;S3: the preceding hoist cable of tensioning and rear hoist cable, and preceding hoist cable is connect in across steel lagging jack, rear hoist cable is connect with end bay steel lagging jack, completes the installation of tower with suspended cable.The installation method of tower with suspended cable of the invention, construction is simple is easy for installation, save the cost.

Description

A kind of installation method of tower with suspended cable
Technical field
The present invention relates to field of bridge construction, and in particular to a kind of installation method of tower with suspended cable.
Background technique
Tower with suspended cable plays very important effect in the construction of the cantilever erection of steel truss arched bridge and steel truss girder, is constructing In the process, end bay steel lagging jack and mid-span part steel lagging jack are first set up, then using tower crane end bay steel lagging jack and in across steel lagging jack Vertical segmented assembled tower with suspended cable at the steel beam joint to connect, and interim wind cable is arranged in the two sides of pylon during assembly, For by end bay steel lagging jack, in connect with pylon across steel lagging jack, with enhance stability of tower with suspended cable during assembly and Wind loading rating.
In above-mentioned work progress, since pylon is using vertical segmented assembly, need using to large-scale tower crane, difficulty of construction It is larger;And due to the installation of tower with suspended cable need to rely on two sides end bay steel lagging jack and in across steel lagging jack, it is necessary in end bay steel Arch rib can just carry out the assembly of tower with suspended cable in after the completion of across steel lagging jack construction, need after tower with suspended cable is installed, Can carry out the installation of next segment bridge, therefore, such mode installs tower with suspended cable, occupy the main structure construction duration compared with It is long, so that the bridge construction duration is longer, higher cost.
Summary of the invention
In view of the deficiencies in the prior art, the purpose of the present invention is to provide a kind of installation method of tower with suspended cable, Construction is simple, easy for installation, save the cost.
To achieve the above objectives, the technical solution adopted by the present invention is that:
A kind of installation method of tower with suspended cable, includes the following steps:
S1: it after the completion of the construction of end bay steel lagging jack, along vertical bridge to assembled tower with suspended cable section by section on end bay steel lagging jack, and installs In across steel lagging jack, and end bay steel lagging jack close in the position mounting seat across steel lagging jack, by tower with suspended cable one end and the bottom Seat is hinged;
S2: after the completion of tower with suspended cable is assembled, tower with suspended cable the other end install extend in across steel lagging jack before hang Rope and the rear hoist cable extended to end bay steel lagging jack, cable crane lifting tower with suspended cable simultaneously make tower with suspended cable turn to vertical state;
S3: the preceding hoist cable of tensioning and rear hoist cable, and preceding hoist cable is connect in across steel lagging jack, rear hoist cable and end bay steel lagging jack connect It connects, completes the installation of tower with suspended cable.
Based on the above technical solution, across steel lagging jack in being installed while assembled tower with suspended cable in step S1.
Based on the above technical solution, step S2 further include: tower with suspended cable two sides respectively install one for adjust hang The interim wind cable that Sarasota frame is spent vertically, interim wind cable are connected with jack, when tower with suspended cable is turned to close to vertical state, open Dynamic jack, and tower with suspended cable is turned to by vertical state by interim wind cable.
Based on the above technical solution, step S1 further include: bracket is set on end bay steel lagging jack, on bracket by Save assembled tower with suspended cable.
Based on the above technical solution, at the top of tower with suspended cable, end bay steel lagging jack and in across being respectively mounted on steel lagging jack Anchor case, preceding hoist cable both ends respectively with tower with suspended cable and in across steel lagging jack anchoring, rear hoist cable both ends respectively with tower with suspended cable and end bay Steel lagging jack anchoring.
Based on the above technical solution, two bottoms are horizontally mounted in the position across steel lagging jack in end bay steel lagging jack Seat, and the bottom end of the tower with suspended cable and two pedestals is hinged.
Compared with the prior art, the advantages of the present invention are as follows:
(1) in the present invention tower with suspended cable installation method, using along vertical bridge to by the way of segmented on end bay steel lagging jack Assembled tower with suspended cable can carry out assembly using common crawler crane or truck crane, without using large-scale tower crane, construction is simple, peace Dress is convenient, save the cost.
(2) in the installation method of tower with suspended cable of the present invention, while across steel lagging jack in an installation, the spelling of tower with suspended cable is carried out Dress, the assembled process of tower with suspended cable will not occupy the main structure construction time, shorten the bridge construction duration, reduce cost.
(3) first tower with suspended cable is turned to close to vertical state with cable crane in the present invention, reuses jack tension and faces When wind cable tower with suspended cable turned into vertical state, since jack control precision is high, can make tower with suspended cable gradually rotate to Vertical state improves the precision of tower with suspended cable vertical state.
Detailed description of the invention
Fig. 1 is the schematic diagram of the assembled process of tower with suspended cable in the embodiment of the present invention;
Fig. 2 is the scheme of installation of tower with suspended cable in the embodiment of the present invention.
In figure: 1- end bay steel lagging jack, 2- tower with suspended cable, 21- column, 22- lateral connection system, 3- pedestal, across steel arch in 4- Rib, hoist cable before 5-, hoist cable after 6-, the interim wind cable of 7-, 8- bracket, 9- anchor case.
Specific embodiment
Invention is further described in detail with reference to the accompanying drawings and embodiments.
Referring to figure 1 and figure 2, the embodiment of the invention provides a kind of installation methods of tower with suspended cable, including walk as follows It is rapid:
S1: after the completion of end bay steel lagging jack 1 is constructed, along vertical bridge to assembled tower with suspended cable 2 section by section on end bay steel lagging jack 1, and Across steel lagging jack 4 in installation, and the position mounting seat 3 across steel lagging jack 4 in end bay steel lagging jack 1 is close, by 2 one end of tower with suspended cable It is hinged with pedestal 3;
S2: after the completion of 2 assembly of tower with suspended cable, tower with suspended cable 2 the other end install in across steel lagging jack 4 extend before Hoist cable 5 and the rear hoist cable 6 extended to end bay steel lagging jack 1, cable crane lifting tower with suspended cable 2 and to turn to tower with suspended cable 2 perpendicular Straight state;
S3: the preceding hoist cable 5 of tensioning and rear hoist cable 6, and preceding hoist cable 5 is connect in across steel lagging jack 4, rear hoist cable 6 and end bay steel Arch rib 1 connects, and completes the installation of tower with suspended cable.
The installation method of tower with suspended cable in the present invention, using along vertical bridge to being spelled on end bay steel lagging jack 1 by the way of segmented Tower with suspended cable 2 is filled, assembly can be carried out using common crawler crane or truck crane, without using large-scale tower crane, construction is simple, installation It is convenient, save the cost.
Across steel lagging jack 4 in being installed while assembled tower with suspended cable 2 in step S1.The assembled process of tower with suspended cable 2 will not The main structure construction time is occupied, shortens the bridge construction duration, reduces cost.
Step S2 further include: respectively install an interim wind cable spent vertically for adjusting tower with suspended cable 2 in 2 two sides of tower with suspended cable 7, interim wind cable 7 is connected with jack, when tower with suspended cable 2 is turned to close to vertical state, starts jack, and by interim Tower with suspended cable 2 is turned to vertical state by wind cable 7.Since jack control precision is high, can make tower with suspended cable 2 gradually rotate to Vertical state improves the precision of 2 vertical state of tower with suspended cable.
Step S1 further include: bracket 8 is set on end bay steel lagging jack 1, the assembled tower with suspended cable 2 section by section on bracket 8.
In above-mentioned installation process, the top of tower with suspended cable 2, end bay steel lagging jack 1 and in across being respectively mounted anchor case on steel lagging jack 4 9, preceding 5 both ends of hoist cable respectively with tower with suspended cable 2 and in across steel lagging jack 4 anchor, rear 6 both ends of hoist cable respectively with tower with suspended cable 2 and side It is anchored across steel lagging jack 1.Two pedestals 3 are horizontally mounted in the position across steel lagging jack 4 in end bay steel lagging jack 1, and by hoist cable tower The bottom end of frame 2 is hinged with two pedestals 3.
In the present invention, tower with suspended cable 2 is assembled section by section by four columns and lateral connection system.
The present invention is not limited to the above-described embodiments, for those skilled in the art, is not departing from Under the premise of the principle of the invention, several improvements and modifications can also be made, these improvements and modifications are also considered as protection of the invention Within the scope of.The content being not described in detail in this specification belongs to the prior art well known to professional and technical personnel in the field.

Claims (5)

1. a kind of installation method of tower with suspended cable, which comprises the steps of:
S1: after the completion of end bay steel lagging jack (1) construction, along vertical bridge to assembled tower with suspended cable (2) section by section on end bay steel lagging jack (1), And across steel lagging jack (4) in installing, and the position mounting seat (3) across steel lagging jack (4) in end bay steel lagging jack (1) is close, it will hang Sarasota frame (2) one end and the pedestal (3) are hinged;
S2: it after the completion of tower with suspended cable (2) is assembled, installs in the other end of tower with suspended cable (2) across steel lagging jack (4) extension Preceding hoist cable (5) and to end bay steel lagging jack (1) extend rear hoist cable (6), tower with suspended cable (2) two sides respectively install one for adjust hang The interim wind cable (7) that Sarasota frame (2) is spent vertically, interim wind cable (7) are connected with jack, and cable crane lifts by crane tower with suspended cable (2) And tower with suspended cable (2) is made to turn to vertical state, when tower with suspended cable (2) is turned to close to vertical state, start jack, and Tower with suspended cable (2) is turned into vertical state by interim wind cable (7);
S3: the preceding hoist cable of tensioning (5) and rear hoist cable (6), and preceding hoist cable (5) is connect in across steel lagging jack (4), rear hoist cable (6) with End bay steel lagging jack (1) connection, completes the installation of tower with suspended cable.
2. the installation method of tower with suspended cable as described in claim 1, it is characterised in that: in assembled tower with suspended cable in step S1 (2) across steel lagging jack (4) in installation while.
3. the installation method of tower with suspended cable as described in claim 1, which is characterized in that step S1 further include: in end bay steel arch Bracket (8) are set on rib (1), the assembled tower with suspended cable (2) section by section on bracket (8).
4. the installation method of tower with suspended cable as described in claim 1, it is characterised in that: at the top of tower with suspended cable (2), end bay steel Arch rib (1) and in across being respectively mounted anchor case (9) on steel lagging jack (4), preceding hoist cable (5) both ends respectively with tower with suspended cable (2) and in across steel Arch rib (4) anchoring, rear hoist cable (6) both ends are anchored with tower with suspended cable (2) and end bay steel lagging jack (1) respectively.
5. the installation method of tower with suspended cable as described in claim 1, it is characterised in that: end bay steel lagging jack (1) close in across The position of steel lagging jack (4) is horizontally mounted two pedestals (3), and by the bottom end of the tower with suspended cable (2) and two pedestals (3) Hingedly.
CN201710035633.XA 2017-01-18 2017-01-18 A kind of installation method of tower with suspended cable Active CN106638331B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710035633.XA CN106638331B (en) 2017-01-18 2017-01-18 A kind of installation method of tower with suspended cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710035633.XA CN106638331B (en) 2017-01-18 2017-01-18 A kind of installation method of tower with suspended cable

Publications (2)

Publication Number Publication Date
CN106638331A CN106638331A (en) 2017-05-10
CN106638331B true CN106638331B (en) 2019-03-22

Family

ID=58840647

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710035633.XA Active CN106638331B (en) 2017-01-18 2017-01-18 A kind of installation method of tower with suspended cable

Country Status (1)

Country Link
CN (1) CN106638331B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111560854B (en) * 2020-05-25 2022-05-20 武船重型工程股份有限公司 Single-point buckling and hanging construction method and single-point buckling and hanging construction system for steel truss arch bridge

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0220709A (en) * 1988-07-08 1990-01-24 Mitsubishi Heavy Ind Ltd Oblique hanging method for building arch bridge
CN101117792A (en) * 2007-08-22 2008-02-06 中铁大桥局股份有限公司 Erection method of large-span continuous steel truss arch
CN101289836A (en) * 2007-12-05 2008-10-22 中铁大桥局股份有限公司 Auxiliary erection method of horizontal cable of steel truss arched bridge
JP4962252B2 (en) * 2007-10-09 2012-06-27 Jfeエンジニアリング株式会社 Bridge erection method and erection device
CN103255726A (en) * 2013-05-28 2013-08-21 中铁上海设计院集团有限公司 Construction method for continuous beam and arch combination bridge
CN103938552A (en) * 2014-04-04 2014-07-23 中铁第四勘察设计院集团有限公司 Self-balancing cantilevering construction method for large-span steel truss arch bridge and main pier limiting supports
CN104532757A (en) * 2014-12-15 2015-04-22 武汉市市政建设集团有限公司 Bi-directional traction vertical rotation construction device for cable-stayed bridge steel arch tower

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0220709A (en) * 1988-07-08 1990-01-24 Mitsubishi Heavy Ind Ltd Oblique hanging method for building arch bridge
CN101117792A (en) * 2007-08-22 2008-02-06 中铁大桥局股份有限公司 Erection method of large-span continuous steel truss arch
JP4962252B2 (en) * 2007-10-09 2012-06-27 Jfeエンジニアリング株式会社 Bridge erection method and erection device
CN101289836A (en) * 2007-12-05 2008-10-22 中铁大桥局股份有限公司 Auxiliary erection method of horizontal cable of steel truss arched bridge
CN103255726A (en) * 2013-05-28 2013-08-21 中铁上海设计院集团有限公司 Construction method for continuous beam and arch combination bridge
CN103938552A (en) * 2014-04-04 2014-07-23 中铁第四勘察设计院集团有限公司 Self-balancing cantilevering construction method for large-span steel truss arch bridge and main pier limiting supports
CN104532757A (en) * 2014-12-15 2015-04-22 武汉市市政建设集团有限公司 Bi-directional traction vertical rotation construction device for cable-stayed bridge steel arch tower

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
"贵广铁路广州东平水道钢桁拱桥安装施工技术";许佳平;《辽宁省交通高等专科学校学报》;20110430;第13卷(第2期);第1页第1节-第4页第5节,图2-3、施工步骤图

Also Published As

Publication number Publication date
CN106638331A (en) 2017-05-10

Similar Documents

Publication Publication Date Title
CN104746883B (en) A kind of arcuate space truss lifts construction method of installation with three machines
CN107044090B (en) A kind of construction method of dual deck bridge
CN103243658B (en) The spelling method of cable stayed bridge dragging suspension basket
CN106758767B (en) A kind of suspension bridge segmented cat road and its construction method
CN202248941U (en) Integral lifting, positioning and mounting device for large-scale steel members
CN104652283A (en) Asynchronous splicing construction method for symmetrically splicing main steel girder erection cranes of cable-stayed bridge
CN101845912A (en) Segmental-body assembly type emergency communication tower
CN108978499A (en) A kind of oblique pull suspension cable co-operative system bridge erection method
CN208899886U (en) Cantilever frame platform
CN105970819A (en) Installation construction method for steel anchor beams
CN108103949A (en) A kind of Cable stayed Bridge Main Tower composite steel anchor beam integral assembling process
CN105256728A (en) Cable-stayed bridge warren steel truss cantilever erection method
CN104314013B (en) Two Cantilever Construction Methods of a kind of pole asymmetrical array beam
CN106638331B (en) A kind of installation method of tower with suspended cable
CN108643364A (en) It is single to encircle gradual rack installation method
CN105755957B (en) A kind of across rail overpass fast hoisting method of large span
CN110468734A (en) Steel lagging jack pushing tow system and steel lagging jack push construction method
CN106758855B (en) Arc-shaped pier cap construction arch support component and arc-shaped pier cap construction method
CN109138431A (en) A kind of Super High pump line Overbridge device and its construction method
CN107130517B (en) It is a kind of fine-tuning from promotion closure mould bases base apparatus and its operating method
CN105696470B (en) Synchronous quick steel box girder in-situ incremental launching and tower column construction method
CN109653102B (en) Swivel construction device and construction method for middle-high steel arch bridge
CN204983693U (en) Hoist device slides in mountain area corridor truss high altitude
CN207244425U (en) Part earth anchored suspension bridge
JP3516056B2 (en) Rotary lift-up construction method for dome roof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant