CN106592766A - Grillage beam structure formed by connecting cross-shaped plates - Google Patents
Grillage beam structure formed by connecting cross-shaped plates Download PDFInfo
- Publication number
- CN106592766A CN106592766A CN201611191951.7A CN201611191951A CN106592766A CN 106592766 A CN106592766 A CN 106592766A CN 201611191951 A CN201611191951 A CN 201611191951A CN 106592766 A CN106592766 A CN 106592766A
- Authority
- CN
- China
- Prior art keywords
- raw bamboo
- connecting piece
- cross connecting
- bamboo
- raw
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/26—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/26—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
- E04B1/2604—Connections specially adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/26—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
- E04B1/2604—Connections specially adapted therefor
- E04B2001/2644—Brackets, gussets or joining plates
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Chemical And Physical Treatments For Wood And The Like (AREA)
Abstract
The invention discloses a grillage beam structure formed by connecting cross-shaped plates. The grillage beam structure comprises first bamboo, second bamboo, third bamboo, fourth bamboo, fifth bamboo, sixth bamboo, seventh bamboo, eighth bamboo, ninth bamboo, tenth bamboo, eleventh bamboo, twelfth bamboo, thirteenth bamboo, fourteenth bamboo, fifteenth bamboo, sixteenth bamboo, a plurality of first flitches, a plurality of second flitches, a plurality of third flitches, a plurality of fourth flitches, a plurality of fifth flitches, a plurality of sixth flitches, a plurality of seventh flitches, a plurality of eighth flitches, a plurality of ninth flitches, a plurality of tenth flitches, a plurality of eleventh flitches and a plurality of twelfth flitches. The grillage beam is good in structure surface smoothness and high in bearing capacity.
Description
Technical field
The present invention relates to a kind of well girder construction, and in particular to a kind of well girder construction connected by cross template.
Background technology
In the case where global timber resources lacks, bamboo have breeding easily, growth is fast, the spy such as morning and yield height of becoming a useful person
Point, meanwhile, bamboo wood texture is logical straight, color and luster are simple and elegant, material is tough and tensile, have many advantages, such as hard broadleaf, as people are to environmental protection
The continuous enhancing of consciousness, various places bamboo building is rised sheer from level ground.Due to the restriction of raw bamboo, modern bamboo structure house is difficult to make building with it
Plate and it is most be unidirectional floor, constrain the multiformity of modern bamboo structure house.Nine-squares beam structure can be good at opening up floor
Pattern, the original but in raw bamboo well beam body system used in existing bamboo structure house, in longitudinal beam and transverse beam
Bamboo is intersected staggered floor distribution and is intertwined and connected by rope by the way of original mostly so that the planarization on well Zi Liang surfaces compared with
Difference, deck-molding is difficult to control to, and bearing capacity is weaker.
The content of the invention
It is an object of the invention to overcome the shortcoming of above-mentioned prior art, there is provided a kind of well connected by cross template
Girder construction, the planarization on the well girder construction surface is preferable, and bearing capacity is stronger.
To reach above-mentioned purpose, the well girder construction connected by cross template of the present invention include the first raw bamboo, the
It is two raw bamboos, the 3rd raw bamboo, the 4th raw bamboo, the 5th raw bamboo, the 6th raw bamboo, the 7th raw bamboo, the 8th raw bamboo, the 9th raw bamboo, the tenth former
Bamboo, the 11st raw bamboo, twelve source acupoint bamboo, the 13rd raw bamboo, the 14th raw bamboo, the 15th raw bamboo, the 16th raw bamboo, some first
Pasting board, some second pasting boards, some 3rd pasting boards, some 4th pasting boards, some 5th pasting boards, some 6th pasting boards, Ruo Gan
Seven pasting boards, some 8th pasting boards, some 9th pasting boards, some tenth pasting boards, some 11st pasting boards and some 12nd pasting boards;
The end of the end of the first raw bamboo and the second raw bamboo is connected with the side of the 5th raw bamboo, the end of the 6th raw bamboo with
The end of the 7th raw bamboo is connected with the side of the 4th raw bamboo, and the first raw bamboo and the second raw bamboo are located at the surface of the 4th raw bamboo,
5th raw bamboo is located at the surface of the 6th raw bamboo and the 7th raw bamboo, and the first raw bamboo, the second raw bamboo and the 5th raw bamboo composition first
Decussate texture, the 6th raw bamboo, the 7th raw bamboo and the 4th raw bamboo constitute the second decussate texture;
The end of the 5th raw bamboo and the end of the 8th raw bamboo are connected respectively with the side of the 9th raw bamboo, the 11st raw bamboo
The end of end and twelve source acupoint bamboo is connected respectively with the side of the 7th raw bamboo, and the 5th raw bamboo and the 8th raw bamboo are located at the 7th
The surface of raw bamboo, the 9th raw bamboo is located at the surface of the 11st raw bamboo and twelve source acupoint bamboo, and the 5th raw bamboo, the 8th raw bamboo and
9th raw bamboo constitutes the 3rd decussate texture, and the 11st raw bamboo, twelve source acupoint bamboo and the 7th raw bamboo constitute the 4th decussate texture;
The end of the 9th raw bamboo and the end of the tenth raw bamboo are connected respectively with the side of the 13rd raw bamboo, the 14th raw bamboo
End and the end of the 15th raw bamboo be connected with the side of twelve source acupoint bamboo respectively, the 13rd raw bamboo is located at the 15th raw bamboo
And the 14th raw bamboo surface, the 9th raw bamboo and the tenth raw bamboo be located at the surface of twelve source acupoint bamboo, and the 9th raw bamboo, the tenth
Raw bamboo and the 13rd raw bamboo constitute the 5th decussate texture, twelve source acupoint bamboo, the 14th raw bamboo and the 15th raw bamboo composition the 6th
Decussate texture;
The end of the 4th raw bamboo and the end of the 3rd raw bamboo are connected respectively with the side of the 15th raw bamboo, the 16th raw bamboo
End and the end of the 13rd raw bamboo be connected with the end of the second raw bamboo respectively, and the 16th raw bamboo and the 13rd raw bamboo position
In the surface of the 15th raw bamboo, the second raw bamboo is located at the surface of the 3rd raw bamboo and the 4th raw bamboo, the 13rd raw bamboo, the 16th
Raw bamboo and the second raw bamboo constitute the 7th decussate texture, and the 4th raw bamboo, the 3rd raw bamboo and the 15th raw bamboo constitute the 8th cross
Structure;
First decussate texture just passes through to the second decussate texture, and the first decussate texture with the second decussate texture
First attachment structure is connected, and the 3rd decussate texture is just to the 4th decussate texture, and the 3rd decussate texture and the 40th
Character form structure is connected by the second attachment structure, and the 5th decussate texture is just to the 6th decussate texture, and the 5th cross
Structure is connected with the 6th decussate texture by the 3rd attachment structure, the 7th decussate texture just to the 8th decussate texture,
And the 7th decussate texture be connected by the 4th attachment structure with the 8th decussate texture;
The side of the first pasting board is connected with the side of the 5th raw bamboo and the side of the 6th raw bamboo, the side of the second pasting board with
The side of the side of the first raw bamboo and the 4th raw bamboo is connected, the side of the 3rd pasting board and the side of the second raw bamboo and the 4th raw bamboo
Side be connected, the side of the 4th pasting board is connected with the side of the 5th raw bamboo and the side of the 7th raw bamboo, the 5th pasting board
Side is connected with the side of the 9th raw bamboo and the side of the 11st raw bamboo, the side of the 6th pasting board and the side of the 9th raw bamboo and
The side of twelve source acupoint bamboo is connected, and the side of the 7th pasting board is connected with the side of the 8th raw bamboo and the side of the 7th raw bamboo,
The side of the 8th pasting board is connected with the side of twelve source acupoint bamboo and the side of the tenth raw bamboo, the side and the 13rd of the 9th pasting board
The side of the side of raw bamboo and the 14th raw bamboo is connected, and the side of the tenth pasting board is former with the side of the 13rd raw bamboo and the 15th
The side of bamboo is connected, and the side of the 11st pasting board is connected with the side of the side of the second raw bamboo and the 3rd raw bamboo, and the 12nd
The side of pasting board is connected with the side of the 15th raw bamboo and the side of the 16th raw bamboo.
First attachment structure includes the connection of the first cross connecting element, the second cross connecting element and the 3rd cross
Part, wherein, the first cross connecting piece is located at the top of the first decussate texture, and the second cross connecting piece is tied positioned at the first cross
Between structure and the second decussate texture, the 3rd cross connecting piece is located at the lower section of the second decussate texture;
First end, the side of the 5th raw bamboo 5, the second cross in first the first decussate texture of screw bolt passes
First end in first end, the side of the 6th raw bamboo and the 3rd cross connecting piece in connector connects the first cross
Fitting, the 5th raw bamboo, the second cross connecting piece, the 6th raw bamboo and the 3rd cross connecting piece are connected;
The cross of side second of second end, the 5th raw bamboo in second the first cross connecting piece of screw bolt passes connects
Second end in second end, the side of the 7th raw bamboo and the 3rd cross connecting piece in fitting connects the first cross
Part, the 5th raw bamboo, the second cross connecting piece, the 7th raw bamboo and the 3rd cross connecting piece are connected;
The 3rd end, the side of the first raw bamboo, the second cross in 3rd the first cross connecting piece of screw bolt passes
The 3rd end in the 3rd end, the side of the 4th raw bamboo and the 3rd cross connecting piece in connector connects the first cross
Fitting, the first raw bamboo, the second cross connecting piece, the 4th raw bamboo and the 3rd cross connecting piece are connected;
The 4th end, the side of the second raw bamboo, the second cross in 4th the first cross connecting piece of screw bolt passes
The side of the 4th end in the 4th end, the side of the 4th raw bamboo and the 3rd cross connecting piece in connector is by first
Cross connecting piece, the second raw bamboo, the second cross connecting piece, the 4th raw bamboo and the 3rd cross connecting piece are connected.
Second attachment structure includes the 4th cross connecting piece, the 5th cross connecting piece and the 6th cross connecting piece, wherein, the
Four cross connecting pieces are located at the top of the 3rd decussate texture, and the 5th cross connecting piece is located at the 3rd decussate texture and the 40th
Between character form structure, the 6th cross connecting piece is located at the lower section of the 4th decussate texture;
First end, the side of the 5th raw bamboo, the 5th cross in the cross connecting piece of 5th screw bolt passes the 4th
First end in first end, the side of the 7th raw bamboo and the 6th cross connecting piece in connector connects the 4th cross
Fitting, the 5th raw bamboo, the 5th cross connecting piece, the 7th raw bamboo and the 6th cross connecting piece are connected;
Second end, the side of the 8th raw bamboo, the 5th cross in the cross connecting piece of 6th screw bolt passes the 4th
Second end in second end, the side of the 7th raw bamboo and the 6th cross connecting piece in connector connects the 4th cross
Fitting, the 8th raw bamboo, the 5th cross connecting piece, the 7th raw bamboo and the 6th cross connecting piece are connected;
The 3rd end, the side of the 9th raw bamboo, the 5th cross in the cross connecting piece of 7th screw bolt passes the 4th
Second end in second end, the side of the 11st raw bamboo and the 6th cross connecting piece in connector is by the 4th cross
Connector, the 9th raw bamboo, the 5th cross connecting piece, the 11st raw bamboo and the 6th cross connecting piece are connected;
The 4th end, the side of the 9th raw bamboo, the 5th cross in the cross connecting piece of 8th screw bolt passes the 4th
The 4th end in the 4th end, the side of twelve source acupoint bamboo and the 6th cross connecting piece in connector is by the 4th cross
Connector, the 9th raw bamboo, the 5th cross connecting piece, twelve source acupoint bamboo and the 6th cross connecting piece are connected.
3rd attachment structure includes the 7th cross connecting piece, the 8th cross connecting piece and the 9th cross connecting piece, wherein, the
Seven cross connecting pieces are located at the top of the 5th decussate texture, and the 8th cross connecting piece is located at the 5th decussate texture and the 60th
Between character form structure, decussate texture is located at the lower section of the 6th decussate texture;
First end, the side of the 13rd raw bamboo in the cross connecting piece of 9th screw bolt passes the 7th, the 80th
The second end in first end, the side of the 15th raw bamboo and the 9th cross connecting piece in word connector is by the 7th cross
Connector, the 13rd raw bamboo, the 8th cross connecting piece, the 15th raw bamboo and the 9th cross connecting piece are connected;
Second end, the side of the 13rd raw bamboo in the cross connecting piece of tenth screw bolt passes the 7th, the 80th
Second end, the side and the 90th of the 14th raw bamboo in second end, the 8th cross connecting piece in word connector
Second end in word connector connects the 7th cross connecting piece, the 13rd raw bamboo, the 8th cross connecting piece, the 8th cross
Part, the 14th raw bamboo and the 9th cross connecting piece are connected;
The 3rd end, the side of the 9th raw bamboo in the cross connecting piece of 11st screw bolt passes the 7th, the 80th
The 3rd end in the 3rd end, the side of twelve source acupoint bamboo and the 9th cross connecting piece in word connector is by the 70th
Word connector, the 9th raw bamboo, the 8th cross connecting piece, twelve source acupoint bamboo and the 9th cross connecting piece are connected;
The 4th end, the side of the tenth raw bamboo in the cross connecting piece of 12nd screw bolt passes the 7th, the 80th
The 4th end, the side of twelve source acupoint bamboo and the 9th cross connecting piece in word connector by the 7th cross connecting piece, the tenth
Raw bamboo, the 8th cross connecting piece, twelve source acupoint bamboo and the 9th cross connecting piece are connected.
4th attachment structure includes the tenth cross connecting piece, the 11st cross connecting piece and the 12nd cross connecting piece, its
In, the tenth cross connecting piece is located at the top of the 7th decussate texture, and the 11st cross connecting piece is located at the 7th decussate texture
Between the 8th decussate texture, the 12nd cross connecting piece is located at the lower section of the 8th decussate texture;
First end, the side of the 16th raw bamboo in the cross connecting piece of 13rd screw bolt passes the tenth, the tenth
First end in first end, the side of the 15th raw bamboo and the 12nd cross connecting piece in one cross connecting piece will
Tenth cross connecting piece, the 16th raw bamboo, the 11st cross connecting piece, the 15th raw bamboo and the 12nd cross connecting piece are connected
Connect;
Second end, the side of the 13rd raw bamboo in the cross connecting piece of 14th screw bolt passes the tenth, the tenth
Second end in second end, the side of the 15th raw bamboo and the 12nd cross connecting piece in one cross connecting piece will
Tenth cross connecting piece, the 13rd raw bamboo, the 11st cross connecting piece, the 15th raw bamboo and the 12nd cross connecting piece are connected
Connect;
The 3rd end, the side of the second raw bamboo in the cross connecting piece of 15th screw bolt passes the tenth, the 11st
The 3rd end in the 3rd end, the side of the 4th raw bamboo and the 12nd cross connecting piece in cross connecting piece is by the tenth
Cross connecting piece, the second raw bamboo, the 11st cross connecting piece, the 4th raw bamboo and the 12nd cross connecting piece are connected;
The 4th end, the side of the second raw bamboo in the cross connecting piece of 16th screw bolt passes the tenth, the 11st
The 4th end in the 4th end, the side of the 3rd raw bamboo and the 12nd cross connecting piece in cross connecting piece is by the tenth
Cross connecting piece, the second raw bamboo, the 11st cross connecting piece, the 3rd raw bamboo and the 12nd cross connecting piece are connected.
Also include the 17th bolt, the 18th bolt, the 19th bolt, the 20th screw rod, the first pull bar, the second pull bar,
3rd pull bar and four-pull-rod;
One end of first pull bar is connected through the side of the 4th raw bamboo with one end of the 17th bolt, the 17th bolt
The other end is connected through the side of the 6th raw bamboo with one end of the second pull bar, the other end of the second pull bar through the 4th raw bamboo and
18th bolt is connected, and the 18th bolt is connected through the side of the 7th raw bamboo with the other end of the first pull bar;
One end of 3rd pull bar is connected through the side of the 5th raw bamboo with one end of the 19th bolt, the 19th bolt
The other end is connected through the side of the first raw bamboo with one end of four-pull-rod, and the other end of four-pull-rod is through the second raw bamboo
Side is connected with one end of the 20th bolt, and the other end of the 20th bolt passes through side and the 3rd pull bar of the second raw bamboo
The other end is connected;
Also include the 21st bolt, the 22nd bolt, the 23rd bolt, the 24th bolt, the 5th pull bar, the
Six pull bars, the 7th pull bar and the 8th pull bar;
One end of 5th pull bar is connected through the side of the 7th raw bamboo with one end of the 21st bolt, the 21st spiral shell
The other end of bolt is connected through the side of twelve source acupoint bamboo with one end of the 6th pull bar, and the other end of the 6th pull bar passes through the 7th
The side of raw bamboo is connected with one end of the 22nd bolt, and the other end of the 22nd bolt passes through the side of the 11st raw bamboo
It is connected with the other end of the 5th pull bar;
One end of 7th pull bar is connected through the side of the 9th raw bamboo with one end of the 7th pull bar, the 23rd bolt
The other end is connected through the side of the 5th raw bamboo with one end of the 8th pull bar, and the other end of the 8th pull bar is through the 9th raw bamboo
Side is connected with one end of the 24th bolt, and the other end of the 24th bolt draws through the side of the 8th raw bamboo with the 7th
The other end of bar is connected.
Also include the 25th bolt, the 26th bolt, the 27th bolt, the 28th bolt, the 9th pull bar, the
Ten pull bars, the 11st pull bar and the 12nd pull bar;
Wherein, one end of the 9th pull bar is connected through the side of twelve source acupoint bamboo with one end of the 25th bolt, the
The other end of 25 bolts is connected through the side of the 15th raw bamboo with one end of the tenth pull bar, the other end of the tenth pull bar
Side through twelve source acupoint bamboo is connected with one end of the 26th bolt, and the other end of the 26th bolt passes through the 14th
The side of raw bamboo is connected with the other end of the tenth pull bar;
One end of 11st pull bar is connected through the side of the 13rd raw bamboo with one end of 27 bolts, and the 27th
The other end of bolt is connected through the side of the tenth raw bamboo with one end of the 12nd pull bar, and the other end of the 12nd pull bar is passed through
The side of the 13rd raw bamboo is connected with one end of the 28th bolt, and the other end of the 28th bolt is through the 9th raw bamboo
Side is connected with the other end of the 11st pull bar.
Also include the 29th bolt, the 30th bolt, the 31st bolt, the 32nd bolt, the 13rd pull bar, the
Ten four-pull-rods, the 15th pull bar and the 16th pull bar;
One end of 13rd pull bar is connected through the side of the 15th raw bamboo with one end of the 29th bolt, and the 20th
The other end of nine bolts is connected through the side of the 3rd raw bamboo with one end of the tenth four-pull-rod, and the other end of the tenth four-pull-rod is worn
The side for crossing the 15th raw bamboo is connected with one end of the 30th bolt, and the other end of the 30th bolt passes through the side of the 4th raw bamboo
Face is connected with the other end of the 13rd pull bar;
One end of 15th pull bar is connected through the side of the second raw bamboo with one end of the 31st bolt, and the 31st
The other end of bolt is connected through the side of the 16th raw bamboo with one end of the 16th pull bar, and the other end of the 16th pull bar is worn
The side for crossing the second raw bamboo is connected with the other end of the 32nd bolt, and the another of the 32nd bolt is brought out through the 13rd
The side of raw bamboo is connected with the other end of the 15th pull bar.
The invention has the advantages that:
The well girder construction connected by cross template of the present invention by the first attachment structure, the second attachment structure,
Three attachment structures, the 4th attachment structure and ten six roots of sensation raw bamboos composition, wherein, well girder construction of the present invention has four connection sections
Point composition, wherein each connecting node is made up of two decussate textures being distributed up and down, and two decussate textures have three
Raw bamboo is constituted, wherein, the end of the end of first raw bamboo and second raw bamboo is connected respectively with the side of the 3rd raw bamboo,
So that the surfacing of decussate texture, while the 3rd raw bamboo in two decussate textures is in crossing distribution, so as to
Effectively ensure the bearing capacity of well beam, while the side of neighbouring two raw bamboos is connected by pasting board, so as to effective
The integrity of neighbouring two raw bamboos is ensure that, the bearing capacity of well beam is further improved, and designs relatively reasonable, can
In being widely used in the building of bamboo structure, with more wide market and using value.
Description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the structural representation of the first decussate texture and the second decussate texture in this present invention;
Fig. 3 is the schematic diagram of the first attachment structure in the present invention.
Wherein, 1 it is the first raw bamboo, 2 be the second raw bamboo, 3 be the 3rd raw bamboo, 4 be the 4th raw bamboo, 5 be the 5th raw bamboo, 6 is
6th raw bamboo, 7 be the 7th raw bamboo, 8 be the 8th raw bamboo, 9 be the 9th raw bamboo, 10 be the tenth raw bamboo, 11 be the 11st raw bamboo, 12 be
Twelve source acupoint bamboo, 13 be the 13rd raw bamboo, 14 be the 14th raw bamboo, 15 be the 15th raw bamboo, 16 be the 16th raw bamboo, 171 be
First cross connecting piece, 172 be the second cross connecting piece, 173 be the 3rd cross connecting piece, 181 be the first pasting board, 182 be the
Two pasting boards, 183 be the 3rd pasting board, 184 be the 4th pasting board, 19 be the first bolt, 20 be the second bolt, 21 be the 3rd bolt, 22
For the 4th bolt.
Specific embodiment
The present invention is described in further detail below in conjunction with the accompanying drawings:
With reference to Fig. 1, the well girder construction connected by cross template of the present invention includes the first raw bamboo 1, the second raw bamboo
2nd, the 3rd raw bamboo 3, the 4th raw bamboo 4, the 5th raw bamboo 5, the 6th raw bamboo 6, the 7th raw bamboo 7, the 8th raw bamboo 8, the 9th raw bamboo the 9, the tenth
Raw bamboo 10, the 11st raw bamboo 11, twelve source acupoint bamboo 12, the 13rd raw bamboo 13, the 14th raw bamboo 14, the 15th raw bamboo the 15, the tenth
It is six raw bamboos 16, some first pasting boards 181, some second pasting boards 182, some 3rd pasting boards 183, some 4th pasting boards 184, some
If the 5th pasting board, some 6th pasting boards, some 7th pasting boards, some 8th pasting boards, some 9th pasting boards, some tenth pasting boards,
Dry 11st pasting board and some 12nd pasting boards;The end of the end of the first raw bamboo 1 and the second raw bamboo 2 and the side of the 5th raw bamboo 5
Face is connected, and the end of the 6th raw bamboo 6 is connected with the end of the 7th raw bamboo 7 with the side of the 4th raw bamboo 4, the first raw bamboo 1 and
Second raw bamboo 2 is located at the surface of the 4th raw bamboo 4, and the 5th raw bamboo 5 is located at the surface of the 6th raw bamboo 6 and the 7th raw bamboo 7, and the
One raw bamboo 1, the second raw bamboo 2 and the 5th raw bamboo 5 constitute the first decussate texture, the 6th raw bamboo 6, the 7th raw bamboo 7 and the 4th raw bamboo 4
Constitute the second decussate texture;The end of the 5th raw bamboo 5 and the end of the 8th raw bamboo 8 are connected respectively with the side of the 9th raw bamboo 9
Connect, the end of the 11st raw bamboo 11 and the end of twelve source acupoint bamboo 12 are connected respectively with the side of the 7th raw bamboo 7, and the 5th former
The raw bamboo 8 of bamboo 5 and the 8th is located at the surface of the 7th raw bamboo 7, and the 9th raw bamboo 9 is located at the 11st raw bamboo 11 and twelve source acupoint bamboo 12
Surface, and the 5th raw bamboo 5, the 8th raw bamboo 8 and the 9th raw bamboo 9 constitute the 3rd decussate texture, the 11st raw bamboo the 11, the 12nd
Raw bamboo 12 and the 7th raw bamboo 7 constitute the 4th decussate texture;The end of the end of the 9th raw bamboo 9 and the tenth raw bamboo 10 is respectively with
The side of 13 raw bamboos 13 is connected, the end of the 14th raw bamboo 14 and the end of the 15th raw bamboo 15 respectively with twelve source acupoint bamboo
12 side is connected, and the 13rd raw bamboo 13 is located at the surface of the 15th raw bamboo 15 and the 14th raw bamboo 14, the 9th raw bamboo 9 and
Tenth raw bamboo 10 is located at the surface of twelve source acupoint bamboo 12, and the 9th raw bamboo 9, the tenth raw bamboo 10 and the 13rd raw bamboo 13 composition the
Five decussate textures, twelve source acupoint bamboo 12, the 14th raw bamboo 14 and the 15th raw bamboo 15 constitute the 6th decussate texture;4th is former
The end of the end of bamboo 4 and the 3rd raw bamboo 3 is connected respectively with the side of the 15th raw bamboo 15, the end of the 16th raw bamboo 16 and
The end of the 13rd raw bamboo 13 is connected respectively with the end of the second raw bamboo 2, and the 16th raw bamboo 16 and the 13rd raw bamboo 13
In the surface of the 15th raw bamboo 15, the second raw bamboo 2 is located at the surface of the 3rd raw bamboo 3 and the 4th raw bamboo 4, the 13rd raw bamboo
13rd, the 16th raw bamboo 16 and the second raw bamboo 2 constitute the 7th decussate texture, the 4th raw bamboo 4, the 3rd raw bamboo 3 and the 15th raw bamboo
15 the 8th decussate textures of composition;First decussate texture is just to the second decussate texture, and the first decussate texture and second
Decussate texture is connected by the first attachment structure, and the 3rd decussate texture is just to the 4th decussate texture, and the 3rd cross
Shape structure is connected with the 4th decussate texture by the second attachment structure, and the 5th decussate texture is just tied to the 6th cross
Structure, and the 5th decussate texture is connected with the 6th decussate texture by the 3rd attachment structure, the 7th decussate texture is just right
8th decussate texture, and the 7th decussate texture is connected with the 8th decussate texture by the 4th attachment structure;First patch
The side of plate 181 is connected with the side of the 5th raw bamboo 5 and the side of the 6th raw bamboo 6, and the side of the second pasting board 182 is former with first
The side of the side of bamboo 1 and the 4th raw bamboo 4 is connected, side and fourth raw bamboo of the side of the 3rd pasting board 183 with the second raw bamboo 2
4 side is connected, and the side of the 4th pasting board 184 is connected with the side of the 5th raw bamboo 5 and the side of the 7th raw bamboo 7, and the 5th
The side of pasting board is connected with the side of the 9th raw bamboo 9 and the side of the 11st raw bamboo 11, and the side of the 6th pasting board is former with the 9th
The side of bamboo 9 and the side of twelve source acupoint bamboo 12 are connected, the side of the 7th pasting board and the side of the 8th raw bamboo 8 and the 7th raw bamboo
7 side is connected, and the side of the 8th pasting board is connected with the side of twelve source acupoint bamboo 12 and the side of the tenth raw bamboo 10, and the 9th
The side of pasting board is connected with the side of the 13rd raw bamboo 13 and the side of the 14th raw bamboo 14, the side and the tenth of the tenth pasting board
The side of three raw bamboos 13 and the side of the 15th raw bamboo 15 are connected, the side of the side of the 11st pasting board and the second raw bamboo 2 and
The side of the 3rd raw bamboo 3 is connected, the side of the 12nd pasting board and the side of the 15th raw bamboo 15 and the side of the 16th raw bamboo 16
Face is connected.
First attachment structure includes the connection of the first cross connecting element, the second cross connecting element and the 3rd cross
Part, wherein, the first cross connecting piece 171 is located at the top of the first decussate texture, and the second cross connecting piece 172 is located at the 10th
Between character form structure and the second decussate texture, the 3rd cross connecting piece 173 is located at the lower section of the second decussate texture;First spiral shell
Bolt 19 is sequentially passed through in first end, the side of the 5th raw bamboo 5, the second cross connecting piece 172 in the first decussate texture
First end, the side of the 6th raw bamboo 6 and the 3rd cross connecting piece 173 in first end by the first cross connecting piece
171st, the 5th raw bamboo 5, the second cross connecting piece 172, the 6th raw bamboo 6 and the 3rd cross connecting piece 173 are connected;Second bolt 20
In sequentially passing through second end, second cross connecting piece of side 172 of the 5th raw bamboo 5 in the first cross connecting piece 171
Second end in second end, the side of the 7th raw bamboo 7 and the 3rd cross connecting piece 173 is by the first cross connecting piece
171st, the 5th raw bamboo 5, the second cross connecting piece 172, the 7th raw bamboo 7 and the 3rd cross connecting piece 173 are connected;3rd bolt 21
In sequentially passing through the 3rd end, the side of the first raw bamboo 1, the second cross connecting piece 172 in the first cross connecting piece 171
The 3rd end in 3rd end, the side of the 4th raw bamboo 4 and the 3rd cross connecting piece 173 is by the first cross connecting piece
171st, the first raw bamboo 1, the second cross connecting piece 172, the 4th raw bamboo 4 and the 3rd cross connecting piece 173 are connected;4th bolt 22
In sequentially passing through the 4th end, the side of the second raw bamboo 2, the second cross connecting piece 172 in the first cross connecting piece 171
The side of the 4th end in the 4th end, the side of the 4th raw bamboo 4 and the 3rd cross connecting piece 173 connects the first cross
Fitting 171, the second raw bamboo 2, the second cross connecting piece 172, the 4th raw bamboo 4 and the 3rd cross connecting piece 173 are connected.
Second attachment structure includes the 4th cross connecting piece, the 5th cross connecting piece and the 6th cross connecting piece, wherein, the
Four cross connecting pieces are located at the top of the 3rd decussate texture, and the 5th cross connecting piece is located at the 3rd decussate texture and the 40th
Between character form structure, the 6th cross connecting piece is located at the lower section of the 4th decussate texture;The cross of 5th screw bolt passes the 4th
First end in first end, the side of the 5th raw bamboo 5, the 5th cross connecting piece, the 7th raw bamboo 7 in connector
First end in side and the 6th cross connecting piece by the 4th cross connecting piece, the 5th raw bamboo 5, the 5th cross connecting piece,
7th raw bamboo 7 and the 6th cross connecting piece are connected;Second end in the cross connecting piece of 6th screw bolt passes the 4th,
Second end, the side of the 7th raw bamboo 7 and the 6th cross connecting piece in side, the 5th cross connecting piece of the 8th raw bamboo 8
In second end by the 4th cross connecting piece, the 8th raw bamboo 8, the 5th cross connecting piece, the 7th raw bamboo 7 and the 6th cross connect
Fitting is connected;The 3rd end, the side of the 9th raw bamboo 9 in the cross connecting piece of 7th screw bolt passes the 4th, the 5th
Second end in second end, the side of the 11st raw bamboo 11 and the 6th cross connecting piece in cross connecting piece is by
Four cross connecting pieces, the 9th raw bamboo 9, the 5th cross connecting piece, the 11st raw bamboo 11 and the 6th cross connecting piece are connected;8th
In the 4th end, the side of the 9th raw bamboo 9, the 5th cross connecting piece in the cross connecting piece of screw bolt passes the 4th
The 4th end in four ends, the side of twelve source acupoint bamboo 12 and the 6th cross connecting pieces by the 4th cross connecting piece,
Nine raw bamboos 9, the 5th cross connecting piece, the cross connecting piece of twelve source acupoint bamboo 12 and the 6th are connected.
3rd attachment structure includes the 7th cross connecting piece, the 8th cross connecting piece and the 9th cross connecting piece, wherein, the
Seven cross connecting pieces are located at the top of the 5th decussate texture, and the 8th cross connecting piece is located at the 5th decussate texture and the 60th
Between character form structure, decussate texture is located at the lower section of the 6th decussate texture;The cross of 9th screw bolt passes the 7th connects
First end, the 15th raw bamboo in first end, the side of the 13rd raw bamboo 13, the 8th cross connecting piece in fitting
The second end in 15 side and the 9th cross connecting piece connects the 7th cross connecting piece, the 13rd raw bamboo 13, the 8th cross
Fitting, the 15th raw bamboo 15 and the 9th cross connecting piece are connected;In the cross connecting piece of tenth screw bolt passes the 7th
In second end, the 8th cross connecting piece in two ends, the side of the 13rd raw bamboo 13, the 8th cross connecting pieces
Second end in two ends, the side of the 14th raw bamboo 14 and the 9th cross connecting pieces by the 7th cross connecting piece,
13 raw bamboos 13, the 8th cross connecting piece, the 8th cross connecting piece, the 14th raw bamboo 14 and the 9th cross connecting piece are connected;
The 3rd end, the side of the 9th raw bamboo 9, the 8th cross connecting piece in the cross connecting piece of 11st screw bolt passes the 7th
In the 3rd end, the side of twelve source acupoint bamboo 12 and the 9th cross connecting piece in the 3rd end the 7th cross is connected
Part, the 9th raw bamboo 9, the 8th cross connecting piece, the cross connecting piece of twelve source acupoint bamboo 12 and the 9th are connected;12nd bolt is successively
Hold through the 4th in the 4th end, the side of the tenth raw bamboo 10, the 8th cross connecting piece in the 7th cross connecting piece
Portion, the side of twelve source acupoint bamboo 12 and the 9th cross connecting piece connect the 7th cross connecting piece, the tenth raw bamboo 10, the 8th cross
Part, the cross connecting piece of twelve source acupoint bamboo 12 and the 9th are connected.
4th attachment structure includes the tenth cross connecting piece, the 11st cross connecting piece and the 12nd cross connecting piece, its
In, the tenth cross connecting piece is located at the top of the 7th decussate texture, and the 11st cross connecting piece is located at the 7th decussate texture
Between the 8th decussate texture, the 12nd cross connecting piece is located at the lower section of the 8th decussate texture;13rd bolt is successively
Through in first end, the side of the 16th raw bamboo 16, the 11st cross connecting piece in the tenth cross connecting piece first
First end in individual end, the side of the 15th raw bamboo 15 and the 12nd cross connecting piece by the tenth cross connecting piece,
16 raw bamboos 16, the 11st cross connecting piece, the 15th raw bamboo 15 and the 12nd cross connecting piece are connected;14th bolt according to
In secondary second end passed through in the tenth cross connecting piece, the side of the 13rd raw bamboo 13, the 11st cross connecting piece
Second end in two ends, the side of the 15th raw bamboo 15 and the 12nd cross connecting pieces by the tenth cross connecting piece,
13rd raw bamboo 13, the 11st cross connecting piece, the 15th raw bamboo 15 and the 12nd cross connecting piece are connected;15th bolt
Sequentially pass through the 3rd in the 3rd end, the side of the second raw bamboo 2, the 11st cross connecting piece in the tenth cross connecting piece
The 3rd end in individual end, the side of the 4th raw bamboo 4 and the 12nd cross connecting piece is by the tenth cross connecting piece, second former
Bamboo 2, the 11st cross connecting piece, the 4th raw bamboo 4 and the 12nd cross connecting piece are connected;16th screw bolt passes the tenth
The 4th end in the 4th end, the side of the second raw bamboo 2, the 11st cross connecting piece in cross connecting piece, the 3rd
The 4th end in the side of raw bamboo 3 and the 12nd cross connecting piece is by the tenth cross connecting piece, the second raw bamboo the 2, the 11st
Cross connecting piece, the 3rd raw bamboo 3 and the 12nd cross connecting piece are connected.
Present invention additionally comprises the 17th bolt, the 18th bolt, the 19th bolt, the 20th screw rod, the first pull bar, second
Pull bar, the 3rd pull bar and four-pull-rod;One end of first pull bar is through the side of the 4th raw bamboo 4 and one end phase of the 17th bolt
Connection, the other end of the 17th bolt is connected through the side of the 6th raw bamboo 6 with one end of the second pull bar, the second pull bar it is another
One end is connected through the 4th raw bamboo 4 with the 18th bolt, side and first pull bar of the 18th bolt through the 7th raw bamboo 7
The other end is connected;One end of 3rd pull bar is connected through the side of the 5th raw bamboo 5 with one end of the 19th bolt, and the 19th
The other end of bolt is connected through the side of the first raw bamboo 1 with one end of four-pull-rod, and the other end of four-pull-rod passes through the
The side of two raw bamboos 5 is connected with one end of the 20th bolt, the other end of the 20th bolt through the second raw bamboo 2 side with
The other end of the 3rd pull bar is connected;
Present invention additionally comprises the 21st bolt, the 22nd bolt, the 23rd bolt, the 24th bolt, the 5th
Pull bar, the 6th pull bar, the 7th pull bar and the 8th pull bar;Side and two ten one of the one end of 5th pull bar through the 7th raw bamboo 7
One end of bolt is connected, and the other end of the 21st bolt is through the side of twelve source acupoint bamboo 12 and one end phase of the 6th pull bar
Connection, the other end of the 6th pull bar is connected through the side of the 7th raw bamboo 7 with one end of the 22nd bolt, the 22nd spiral shell
The other end of bolt is connected through the side of the 11st raw bamboo 11 with the other end of the 5th pull bar;One end of 7th pull bar is through the
The side of nine raw bamboos 9 is connected with one end of the 7th pull bar, the other end of the 23rd bolt through the 5th raw bamboo 5 side with
One end of 8th pull bar is connected, and the other end of the 8th pull bar is through the side of the 9th raw bamboo 9 and one end of the 24th bolt
It is connected, the other end of the 24th bolt is connected through the side of the 8th raw bamboo 8 with the other end of the 7th pull bar.
Present invention additionally comprises the 25th bolt, the 26th bolt, the 27th bolt, the 28th bolt, the 9th
Pull bar, the tenth pull bar, the 11st pull bar and the 12nd pull bar;Wherein, side of the one end of the 9th pull bar through twelve source acupoint bamboo 12
Face is connected with one end of the 25th bolt, and the other end of the 25th bolt passes through the side and the tenth of the 15th raw bamboo 15
One end of pull bar is connected, and the other end of the tenth pull bar is through the side of twelve source acupoint bamboo 12 and one end phase of the 26th bolt
Connection, the other end of the 26th bolt is connected through the side of the 14th raw bamboo 14 with the other end of the tenth pull bar;Tenth
One end of one pull bar is connected through the side of the 13rd raw bamboo 13 with one end of 27 bolts, the 27th bolt it is another
End is connected through the side of the tenth raw bamboo 10 with one end of the 12nd pull bar, and the other end of the 12nd pull bar is former through the 13rd
The side of bamboo 13 is connected with one end of the 28th bolt, and the other end of the 28th bolt passes through the side of the 9th raw bamboo 9
It is connected with the other end of the 11st pull bar.
Present invention additionally comprises the 29th bolt, the 30th bolt, the 31st bolt, the 32nd bolt, the 13rd
Pull bar, the tenth four-pull-rod, the 15th pull bar and the 16th pull bar;Side of the one end of 13rd pull bar through the 15th raw bamboo 15
It is connected with one end of the 29th bolt, the other end of the 29th bolt draws through the side of the 3rd raw bamboo 3 with the 14th
One end of bar is connected, and the other end of the tenth four-pull-rod is connected through the side of the 15th raw bamboo 15 with one end of the 30th bolt
Connect, the other end of the 30th bolt is connected through the side of the 4th raw bamboo 4 with the other end of the 13rd pull bar;15th pull bar
One end be connected with one end of the 31st bolt through the side of the second raw bamboo 2, the other end of the 31st bolt is passed through
The side of the 16th raw bamboo 16 is connected with one end of the 16th pull bar, and the other end of the 16th pull bar is through the second raw bamboo 2
Side is connected with the other end of the 32nd bolt, another side brought out through the 13rd raw bamboo 13 of the 32nd bolt
It is connected with the other end of the 15th pull bar.
First raw bamboo 1, the 3rd raw bamboo 3, the 5th raw bamboo 5, the 6th raw bamboo 6, the 8th raw bamboo 8, the tenth raw bamboo the 10, the 11st are former
Filler is filled with bamboo 11, the 14th raw bamboo 14 and the 16th raw bamboo 16.
Claims (9)
1. a kind of well girder construction connected by cross template, it is characterised in that including the first raw bamboo (1), the second raw bamboo (2),
3rd raw bamboo (3), the 4th raw bamboo (4), the 5th raw bamboo (5), the 6th raw bamboo (6), the 7th raw bamboo (7), the 8th raw bamboo (8), the 9th
Raw bamboo (9), the tenth raw bamboo (10), the 11st raw bamboo (11), twelve source acupoint bamboo (12), the 13rd raw bamboo (13), the 14th raw bamboo
(14), the 15th raw bamboo (15), the 16th raw bamboo (16), some first pasting boards (181), some second pasting boards (182), Ruo Gan
Three pasting boards (183), some 4th pasting boards (184), some 5th pasting boards, some 6th pasting boards, some 7th pasting boards, some eight
Pasting board, some 9th pasting boards, some tenth pasting boards, some 11st pasting boards and some 12nd pasting boards;
The end of the first raw bamboo (1) and the end of the second raw bamboo (2) are connected with the side of the 5th raw bamboo (5), the 6th raw bamboo (6)
End be connected with the side of the 4th raw bamboo (4) with the end of the 7th raw bamboo (7), the first raw bamboo (1) and the second raw bamboo (2) position
In the surface of the 4th raw bamboo (4), the 5th raw bamboo (5) positioned at the 6th raw bamboo (6) and the surface of the 7th raw bamboo (7), and first
Raw bamboo (1), the second raw bamboo (2) and the 5th raw bamboo (5) constitute the first decussate texture, the 6th raw bamboo (6), the 7th raw bamboo (7) and
4th raw bamboo (4) constitutes the second decussate texture;
The end of the 5th raw bamboo (5) and the end of the 8th raw bamboo (8) are connected respectively with the side of the 9th raw bamboo (9), and the 11st
The end of raw bamboo (11) and the end of twelve source acupoint bamboo (12) are connected respectively with the side of the 7th raw bamboo (7), and the 5th raw bamboo
(5) and the 8th raw bamboo (8) is positioned at the surface of the 7th raw bamboo (7), the 9th raw bamboo (9) is positioned at the 11st raw bamboo (11) and the 12nd
The surface of raw bamboo (12), and the 5th raw bamboo (5), the 8th raw bamboo (8) and the 9th raw bamboo (9) constitute the 3rd decussate texture, the
11 raw bamboos (11), twelve source acupoint bamboo (12) and the 7th raw bamboo (7) constitute the 4th decussate texture;
The end of the 9th raw bamboo (9) and the end of the tenth raw bamboo (10) are connected respectively with the side of the 13rd raw bamboo (13), the
The end of the end of 14 raw bamboos (14) and the 15th raw bamboo (15) is connected respectively with the side of twelve source acupoint bamboo (12), and the tenth
Three raw bamboos (13) positioned at the 15th raw bamboo (15) and the surface of the 14th raw bamboo (14), the 9th raw bamboo (9) and the tenth raw bamboo
(10) positioned at the surface of twelve source acupoint bamboo (12), and the 9th raw bamboo (9), the tenth raw bamboo (10) and the 13rd raw bamboo (13) composition
5th decussate texture, twelve source acupoint bamboo (12), the 14th raw bamboo (14) and the 15th raw bamboo (15) constitute the 6th cross knot
Structure;
The end of the 4th raw bamboo (4) and the end of the 3rd raw bamboo (3) are connected respectively with the side of the 15th raw bamboo (15), and the tenth
The end of the end of six raw bamboos (16) and the 13rd raw bamboo (13) is connected respectively with the end of the second raw bamboo (2), and the 16th
, positioned at the surface of the 15th raw bamboo (15), the second raw bamboo (2) is positioned at the 3rd raw bamboo (3) for raw bamboo (16) and the 13rd raw bamboo (13)
And the 4th raw bamboo (4) surface, the 13rd raw bamboo (13), the 16th raw bamboo (16) and the second raw bamboo (2) constitute the 7th cross
Shape structure, the 4th raw bamboo (4), the 3rd raw bamboo (3) and the 15th raw bamboo (15) constitute the 8th decussate texture;
First decussate texture is just to the second decussate texture, and the first decussate texture and the second decussate texture pass through first
Attachment structure is connected, and the 3rd decussate texture is just to the 4th decussate texture, and the 3rd decussate texture and the 4th cross
Structure is connected by the second attachment structure, and the 5th decussate texture is just to the 6th decussate texture, and the 5th decussate texture
Be connected by the 3rd attachment structure with the 6th decussate texture, the 7th decussate texture just to the 8th decussate texture, and
Seven decussate textures are connected with the 8th decussate texture by the 4th attachment structure;
The side of the first pasting board (181) is connected with the side of the 5th raw bamboo (5) and the side of the 6th raw bamboo (6), the second pasting board
(182) side is connected with the side of the first raw bamboo (1) and the side of the 4th raw bamboo (4), the side of the 3rd pasting board (183) with
The side of the side of the second raw bamboo (2) and the 4th raw bamboo (4) is connected, side and the 5th raw bamboo (5) of the 4th pasting board (184)
The side of side and the 7th raw bamboo (7) is connected, side and ten one raw bamboo of the side of the 5th pasting board with the 9th raw bamboo (9)
(11) side is connected, and the side of the 6th pasting board is connected with the side of the 9th raw bamboo (9) and the side of twelve source acupoint bamboo (12)
Connect, the side of the 7th pasting board is connected with the side of the 8th raw bamboo (8) and the side of the 7th raw bamboo (7), the side of the 8th pasting board
It is connected with the side of twelve source acupoint bamboo (12) and the side of the tenth raw bamboo (10), side and the 13rd raw bamboo of the 9th pasting board
(13) side and the side of the 14th raw bamboo (14) is connected, the side of the side of the tenth pasting board and the 13rd raw bamboo (13) and
The side of the 15th raw bamboo (15) is connected, the side of the 11st pasting board and the side of the second raw bamboo (2) and the 3rd raw bamboo (3)
Side is connected, and the side of the 12nd pasting board is connected with the side of the 15th raw bamboo (15) and the side of the 16th raw bamboo (16)
Connect.
2. the well girder construction connected by cross template according to claim 1, it is characterised in that the first connection knot
Structure includes the first cross connecting element, the second cross connecting element and the 3rd cross connecting element, wherein, the first cross connecting piece
(171) positioned at the top of the first decussate texture, the second cross connecting piece (172) is positioned at the first decussate texture and the second cross
Between shape structure, the 3rd cross connecting piece (173) is positioned at the lower section of the second decussate texture;
First bolt (19) sequentially pass through first end in the first decussate texture, the side of the 5th raw bamboo (5), the 20th
First in first end, the side of the 6th raw bamboo (6) and the 3rd cross connecting piece (173) in word connector (172)
End is by the first cross connecting piece (171), the 5th raw bamboo (5), the second cross connecting piece (172), the 6th raw bamboo (6) and the 30th
Word connector (173) is connected;
Second bolt (20) sequentially passes through second end, the side of the 5th raw bamboo (5) in the first cross connecting piece (171)
In second end, the side of the 7th raw bamboo (7) and the 3rd cross connecting piece (173) in two cross connecting pieces (172)
Two ends are by the first cross connecting piece (171), the 5th raw bamboo (5), the second cross connecting piece (172), the 7th raw bamboo (7) and
Three cross connecting pieces (173) are connected;
3rd bolt (21) sequentially pass through the 3rd end in the first cross connecting piece (171), the side of the first raw bamboo (1),
In the 3rd end, the side of the 4th raw bamboo (4) and the 3rd cross connecting piece (173) in second cross connecting piece (172)
3rd end by the first cross connecting piece (171), the first raw bamboo (1), the second cross connecting piece (172), the 4th raw bamboo (4) and
3rd cross connecting piece (173) is connected;
4th bolt (22) sequentially pass through the 4th end in the first cross connecting piece (171), the side of the second raw bamboo (2),
In the 4th end, the side of the 4th raw bamboo (4) and the 3rd cross connecting piece (173) in second cross connecting piece (172)
The side of the 4th end is by the first cross connecting piece (171), the second raw bamboo (2), the second cross connecting piece (172), the 4th former
Bamboo (4) and the 3rd cross connecting piece (173) are connected.
3. the well girder construction connected by cross template according to claim 2, it is characterised in that the second attachment structure bag
The 4th cross connecting piece, the 5th cross connecting piece and the 6th cross connecting piece are included, wherein, the 4th cross connecting piece is located at the 30th
The top of character form structure, the 5th cross connecting piece is located between the 3rd decussate texture and the 4th decussate texture, the 6th cross
Connector is located at the lower section of the 4th decussate texture;
First end, the side of the 5th raw bamboo (5), the 5th cross in the cross connecting piece of 5th screw bolt passes the 4th connects
First end in first end, the side of the 7th raw bamboo (7) and the 6th cross connecting piece in fitting is by the 4th cross
Connector, the 5th raw bamboo (5), the 5th cross connecting piece, the 7th raw bamboo (7) and the 6th cross connecting piece are connected;
Second end, the side of the 8th raw bamboo (8), the 5th cross in the cross connecting piece of 6th screw bolt passes the 4th connects
Second end in second end, the side of the 7th raw bamboo (7) and the 6th cross connecting piece in fitting is by the 4th cross
Connector, the 8th raw bamboo (8), the 5th cross connecting piece, the 7th raw bamboo (7) and the 6th cross connecting piece are connected;
The 3rd end, the side of the 9th raw bamboo (9), the 5th cross in the cross connecting piece of 7th screw bolt passes the 4th connects
Second end in second end, the side of the 11st raw bamboo (11) and the 6th cross connecting piece in fitting is by the 40th
Word connector, the 9th raw bamboo (9), the 5th cross connecting piece, the 11st raw bamboo (11) and the 6th cross connecting piece are connected;
The 4th end, the side of the 9th raw bamboo (9), the 5th cross in the cross connecting piece of 8th screw bolt passes the 4th connects
The 4th end in the 4th end, the side of twelve source acupoint bamboo (12) and the 6th cross connecting piece in fitting is by the 40th
Word connector, the 9th raw bamboo (9), the 5th cross connecting piece, twelve source acupoint bamboo (12) and the 6th cross connecting piece are connected.
4. the well girder construction connected by cross template according to claim 3, it is characterised in that the 3rd attachment structure bag
The 7th cross connecting piece, the 8th cross connecting piece and the 9th cross connecting piece are included, wherein, the 7th cross connecting piece is located at the 50th
The top of character form structure, the 8th cross connecting piece is located between the 5th decussate texture and the 6th decussate texture, cross
Structure is located at the lower section of the 6th decussate texture;
First end, the side of the 13rd raw bamboo (13) in the cross connecting piece of 9th screw bolt passes the 7th, the 80th
The second end in first end, the side of the 15th raw bamboo (15) and the 9th cross connecting piece in word connector is by the 7th
Cross connecting piece, the 13rd raw bamboo (13), the 8th cross connecting piece, the 15th raw bamboo (15) and the 9th cross connecting piece are connected
Connect;
Second end, the side of the 13rd raw bamboo (13) in the cross connecting piece of tenth screw bolt passes the 7th, the 80th
Second end in second end, the 8th cross connecting piece, the side of the 14th raw bamboo (14) in word connector and
Second end in nine cross connecting pieces by the 7th cross connecting piece, the 13rd raw bamboo (13), the 8th cross connecting piece, the 8th
Cross connecting piece, the 14th raw bamboo (14) and the 9th cross connecting piece are connected;
The 3rd end in the cross connecting piece of 11st screw bolt passes the 7th, side, the 8th cross of the 9th raw bamboo (9)
The 3rd end in the 3rd end, the side of twelve source acupoint bamboo (12) and the 9th cross connecting piece in connector is by the 7th
Cross connecting piece, the 9th raw bamboo (9), the 8th cross connecting piece, twelve source acupoint bamboo (12) and the 9th cross connecting piece are connected;
The 4th end, the side of the tenth raw bamboo (10) in the cross connecting piece of 12nd screw bolt passes the 7th, the 80th
The 4th end, the side of twelve source acupoint bamboo (12) and the 9th cross connecting piece in word connector by the 7th cross connecting piece,
Tenth raw bamboo (10), the 8th cross connecting piece, twelve source acupoint bamboo (12) and the 9th cross connecting piece are connected.
5. the well girder construction connected by cross template according to claim 4, it is characterised in that the 4th attachment structure bag
The tenth cross connecting piece, the 11st cross connecting piece and the 12nd cross connecting piece are included, wherein, the tenth cross connecting piece is located at the
The top of seven decussate textures, the 11st cross connecting piece is located between the 7th decussate texture and the 8th decussate texture, the
12 cross connecting pieces are located at the lower section of the 8th decussate texture;
First end, the side of the 16th raw bamboo (16) in the cross connecting piece of 13rd screw bolt passes the tenth, the tenth
First end in first end, the side of the 15th raw bamboo (15) and the 12nd cross connecting piece in one cross connecting piece
Portion is by the tenth cross connecting piece, the 16th raw bamboo (16), the 11st cross connecting piece, the 15th raw bamboo (15) and the 12nd cross
Connector is connected;
Second end, the side of the 13rd raw bamboo (13) in the cross connecting piece of 14th screw bolt passes the tenth, the tenth
Second end in second end, the side of the 15th raw bamboo (15) and the 12nd cross connecting piece in one cross connecting piece
Portion is by the tenth cross connecting piece, the 13rd raw bamboo (13), the 11st cross connecting piece, the 15th raw bamboo (15) and the 12nd cross
Connector is connected;
The 3rd end, the side of the second raw bamboo (2) in the cross connecting piece of 15th screw bolt passes the tenth, the 11st
The 3rd end in the 3rd end, the side of the 4th raw bamboo (4) and the 12nd cross connecting piece in word connector is by
Ten cross connecting pieces, the second raw bamboo (2), the 11st cross connecting piece, the 4th raw bamboo (4) and the 12nd cross connecting piece are connected
Connect;
The 4th end, the side of the second raw bamboo (2) in the cross connecting piece of 16th screw bolt passes the tenth, the 11st
The 4th end in the 4th end, the side of the 3rd raw bamboo (3) and the 12nd cross connecting piece in word connector is by
Ten cross connecting pieces, the second raw bamboo (2), the 11st cross connecting piece, the 3rd raw bamboo (3) and the 12nd cross connecting piece are connected
Connect.
6. the well girder construction connected by cross template according to claim 5, it is characterised in that also including the 17th spiral shell
Bolt, the 18th bolt, the 19th bolt, the 20th screw rod, the first pull bar, the second pull bar, the 3rd pull bar and four-pull-rod;
One end of first pull bar is connected through the side of the 4th raw bamboo (4) with one end of the 17th bolt, the 17th bolt
The other end is connected through the side of the 6th raw bamboo (6) with one end of the second pull bar, and the other end of the second pull bar is former through the 4th
Bamboo (4) is connected with the 18th bolt, and the 18th bolt is connected through the side of the 7th raw bamboo (7) with the other end of the first pull bar
Connect;
One end of 3rd pull bar is connected through the side of the 5th raw bamboo (5) with one end of the 19th bolt, the 19th bolt
The other end is connected through the side of the first raw bamboo (1) with one end of four-pull-rod, and the other end of four-pull-rod is former through second
The side of bamboo (5) is connected with one end of the 20th bolt, the other end of the 20th bolt through the second raw bamboo (2) side with
The other end of the 3rd pull bar is connected.
7. the well girder construction connected by cross template according to claim 6, it is characterised in that also including the 21st
Bolt, the 22nd bolt, the 23rd bolt, the 24th bolt, the 5th pull bar, the 6th pull bar, the 7th pull bar and the 8th
Pull bar;
One end of 5th pull bar is connected through the side of the 7th raw bamboo (7) with one end of the 21st bolt, the 21st spiral shell
The other end of bolt is connected through the side of twelve source acupoint bamboo (12) with one end of the 6th pull bar, and the other end of the 6th pull bar is passed through
The side of the 7th raw bamboo (7) is connected with one end of the 22nd bolt, and the other end of the 22nd bolt is former through the 11st
The side of bamboo (11) is connected with the other end of the 5th pull bar;
One end of 7th pull bar is connected through the side of the 9th raw bamboo (9) with one end of the 7th pull bar, the 23rd bolt
The other end is connected through the side of the 5th raw bamboo (5) with one end of the 8th pull bar, and the other end of the 8th pull bar is former through the 9th
The side of bamboo (9) is connected with one end of the 24th bolt, and the other end of the 24th bolt passes through the side of the 8th raw bamboo (8)
Face is connected with the other end of the 7th pull bar.
8. the well girder construction connected by cross template according to claim 7, it is characterised in that also including the 25th
Bolt, the 26th bolt, the 27th bolt, the 28th bolt, the 9th pull bar, the tenth pull bar, the 11st pull bar and
12 pull bars;
Wherein, one end of the 9th pull bar is connected through the side of twelve source acupoint bamboo (12) with one end of the 25th bolt, the
The other end of 25 bolts is connected through the side of the 15th raw bamboo (15) with one end of the tenth pull bar, the tenth pull bar it is another
One end is connected through the side of twelve source acupoint bamboo (12) with one end of the 26th bolt, and the other end of the 26th bolt is worn
The side for crossing the 14th raw bamboo (14) is connected with the other end of the tenth pull bar;
One end of 11st pull bar is connected through the side of the 13rd raw bamboo (13) with one end of 27 bolts, and the 27th
The other end of bolt is connected through the side of the tenth raw bamboo (10) with one end of the 12nd pull bar, the other end of the 12nd pull bar
Side through the 13rd raw bamboo (13) is connected with one end of the 28th bolt, and the other end of the 28th bolt is through the
The side of nine raw bamboos (9) is connected with the other end of the 11st pull bar.
9. the well girder construction connected by cross template according to claim 8, it is characterised in that also including the 29th
Bolt, the 30th bolt, the 31st bolt, the 32nd bolt, the 13rd pull bar, the tenth four-pull-rod, the 15th pull bar and
16th pull bar;
One end of 13rd pull bar is connected through the side of the 15th raw bamboo (15) with one end of the 29th bolt, and the 20th
The other end of nine bolts is connected through the side of the 3rd raw bamboo (3) with one end of the tenth four-pull-rod, the tenth four-pull-rod it is another
End is connected through the side of the 15th raw bamboo (15) with one end of the 30th bolt, and the other end of the 30th bolt passes through the 4th
The side of raw bamboo (4) is connected with the other end of the 13rd pull bar;
One end of 15th pull bar is connected through the side of the second raw bamboo (2) with one end of the 31st bolt, and the 31st
The other end of bolt is connected through the side of the 16th raw bamboo (16) with one end of the 16th pull bar, the 16th pull bar it is another
End is connected through the side of the second raw bamboo (2) with the other end of the 32nd bolt, and another the bringing out of the 32nd bolt is worn
The side for crossing the 13rd raw bamboo (13) is connected with the other end of the 15th pull bar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611191951.7A CN106592766B (en) | 2016-12-21 | 2016-12-21 | A kind of nine-squares beam structure connected by cross template |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611191951.7A CN106592766B (en) | 2016-12-21 | 2016-12-21 | A kind of nine-squares beam structure connected by cross template |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106592766A true CN106592766A (en) | 2017-04-26 |
CN106592766B CN106592766B (en) | 2018-11-09 |
Family
ID=58600294
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611191951.7A Expired - Fee Related CN106592766B (en) | 2016-12-21 | 2016-12-21 | A kind of nine-squares beam structure connected by cross template |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106592766B (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001241107A (en) * | 2000-02-28 | 2001-09-04 | Yoshinori Okura | Connecting structure for column and beam |
CN102155053A (en) * | 2011-03-25 | 2011-08-17 | 扬州市天成建筑安装工程有限公司 | Cross energy-consumption clamping sleeve for column-beam connection |
CN202227488U (en) * | 2011-09-02 | 2012-05-23 | 安吉县文化广电新闻出版局 | Bamboo beam connecting structure on bamboo integrated house |
CN102704569A (en) * | 2012-05-25 | 2012-10-03 | 湖南大学 | Multilayer large-span assembling integral type space steel grid building structure and manufacturing method |
CN103758217A (en) * | 2014-01-22 | 2014-04-30 | 西安建筑科技大学 | Bamboo cane type binding method for raw bamboo column |
CN203701293U (en) * | 2014-01-25 | 2014-07-09 | 西安建筑科技大学 | Lattice type framework connecting piece of raw bamboo building |
CN103938726A (en) * | 2014-01-22 | 2014-07-23 | 西安建筑科技大学 | Connecting structure of raw-bamboo floor, wall and beam |
-
2016
- 2016-12-21 CN CN201611191951.7A patent/CN106592766B/en not_active Expired - Fee Related
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001241107A (en) * | 2000-02-28 | 2001-09-04 | Yoshinori Okura | Connecting structure for column and beam |
CN102155053A (en) * | 2011-03-25 | 2011-08-17 | 扬州市天成建筑安装工程有限公司 | Cross energy-consumption clamping sleeve for column-beam connection |
CN202227488U (en) * | 2011-09-02 | 2012-05-23 | 安吉县文化广电新闻出版局 | Bamboo beam connecting structure on bamboo integrated house |
CN102704569A (en) * | 2012-05-25 | 2012-10-03 | 湖南大学 | Multilayer large-span assembling integral type space steel grid building structure and manufacturing method |
CN103758217A (en) * | 2014-01-22 | 2014-04-30 | 西安建筑科技大学 | Bamboo cane type binding method for raw bamboo column |
CN103938726A (en) * | 2014-01-22 | 2014-07-23 | 西安建筑科技大学 | Connecting structure of raw-bamboo floor, wall and beam |
CN203701293U (en) * | 2014-01-25 | 2014-07-09 | 西安建筑科技大学 | Lattice type framework connecting piece of raw bamboo building |
Also Published As
Publication number | Publication date |
---|---|
CN106592766B (en) | 2018-11-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Kaware et al. | Review of bamboo as reinforcement material in concrete structure | |
CN107489090A (en) | A kind of circle bamboo space truss bridge based on novel joint make | |
CN106193408A (en) | String props up unbonded prestressed concrete arch without beam | |
CN106592766A (en) | Grillage beam structure formed by connecting cross-shaped plates | |
CN204728490U (en) | A kind of concrete beam and column node of carbon fiber-containing cloth angle steel | |
CN206438787U (en) | A kind of enhanced raw-soil wall of structure | |
CN106592767B (en) | A kind of raw bamboo cross beam connected by L-type plate | |
CN206467853U (en) | A kind of densely covered type floor construction of strip based on raw bamboo | |
CN204343563U (en) | The building in the style of the ancients cornice node that a kind of wooden construction is combined with concrete structure | |
CN206801081U (en) | A kind of flat reinforce of bucket of ancient building cross mouth sets of brackets on top of the columns repairs structure | |
CN206319464U (en) | A kind of steel I-beam raw bamboo floor | |
CN108755937A (en) | A kind of steel core concrete column connect cross abnormity node with box-girder and I-beam | |
CN213509081U (en) | Rammed earth wall based on FRP (fiber reinforced plastic) ribs | |
CN104652680A (en) | Rope towing single-layered net shell structure | |
CN204475518U (en) | Saddle-shape cable holder single-layer latticed shell | |
CN106703268A (en) | Strip-shaped dense type floor structure based on raw bamboos | |
CN205777791U (en) | Rammed earth agriculture room sliding and shock isolation position limiting structure | |
CN203878812U (en) | Wall body with opening | |
CN204456572U (en) | The low frictional resistance drag-line node of suspension cable single-layer latticed shell | |
CN204475517U (en) | The two-way low frictional resistance drag-line node of separate type of suspension cable single-layer latticed shell | |
CN111270869B (en) | Rammed earth wall reinforcing method | |
CN202152501U (en) | European style large span wood truss for ceilings | |
Shirehjini et al. | Bamboo culm buildings | |
CN206418692U (en) | A kind of green wood lightweight steel construction awning for traditional architecture | |
Jyothi | Comparative analysis of RCC and steel structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181109 Termination date: 20211221 |