CN106567499B - Assembled steel reinforced concrete joining column structure and its implementation method - Google Patents

Assembled steel reinforced concrete joining column structure and its implementation method Download PDF

Info

Publication number
CN106567499B
CN106567499B CN201610954391.XA CN201610954391A CN106567499B CN 106567499 B CN106567499 B CN 106567499B CN 201610954391 A CN201610954391 A CN 201610954391A CN 106567499 B CN106567499 B CN 106567499B
Authority
CN
China
Prior art keywords
steel
column
concrete
internal stress
toughened internal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610954391.XA
Other languages
Chinese (zh)
Other versions
CN106567499A (en
Inventor
何余良
吴旭东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
University of Shaoxing
Original Assignee
University of Shaoxing
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by University of Shaoxing filed Critical University of Shaoxing
Priority to CN201610954391.XA priority Critical patent/CN106567499B/en
Publication of CN106567499A publication Critical patent/CN106567499A/en
Application granted granted Critical
Publication of CN106567499B publication Critical patent/CN106567499B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/32Columns; Pillars; Struts of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/34Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a kind of assembled steel reinforced concrete joining column structure and its implementation methods.The present invention includes concrete column, toughened internal stress, short steel column.Concrete column is pricked screw-thread steel by concrete, reinforcing bar, punching device and essence and is formed, short steel column is made of fashioned iron, ribbed stiffener and connecting plate, and toughened internal stress is made of shear connector, concrete, ribbed stiffener, anchoring system, reinforcing bar, end plate, upper steel flange plate and lower steel flange plate;Steel reinforced concrete-adapter section concrete is attached with the steel edge of a wing by shear connector, bears external force jointly.Connecting plate is arranged in short steel column end in the stability that ribbed stiffener is used to improve short steel column.The present invention is the advantages of combining concrete column and with steel column, steel and concrete are connected by toughened internal stress, sufficiently send out the excellent performance of both materials, improve the mechanical property and constructing operation performance of rod structure, and such structure can be constructed using quick assemblingization, accelerate speed of application, shortens the construction period, there is preferable economic benefit.

Description

Assembled steel reinforced concrete joining column structure and its implementation method
Technical field
The invention belongs to construction engineering technical fields, and in particular to a kind of assembled steel reinforced concrete joining column structure and its embodiment party Method.
Background technique
In current architectural engineering, mainly had using the structure type of column: reinforced column, steel core concrete column and type Steel concrete column etc..The build model of reinforced column mainly uses conventional on-site pouring construction, it is difficult to industrialize big Production, long construction period are such build model the problems such as there are high energy consumption, high pollution, poor efficiency, extensive style, and current new Type urbanization, industrialization, Informatization Development requirement are incompatible.Steel core concrete column, can be by way of bolt or welding Prefabricated construction is carried out, but is difficult to carry out the factorial production, due to being increased with steel so that construction cost is high, the anti-corrosion of steel pipe is prevented fires Need to carry out technical treatment, and steel core concrete column causes column that local buckling occurs due to concrete vibrating leakiness.Fashioned iron Concrete column solves the anti-corrosion fire safety problem of steel by external wrapping concrete, but it is relatively difficult to pour external wrapping concrete, steel using amount It is complex with the connection of beams of concrete than armored concrete pillar height.
Summary of the invention
The technical problem to be solved by the present invention is to overcome the deficiencies in the prior art, provide it is a kind of it is economical and practical, structure is simple, Assembled steel reinforced concrete joining column structure easy for construction and its implementation method.
In order to solve the above technical problems, technical solution proposed by the present invention is as follows:
Assembled steel reinforced concrete joining column structure, including concrete column, toughened internal stress, short steel column;Toughened internal stress is coagulation The linkage section of earth pillar and short steel column;Concrete column includes that concrete, reinforcing bar, punching device and essence prick screw-thread steel;Short steel column includes Fashioned iron, ribbed stiffener and connecting plate;Toughened internal stress is by shear connector, concrete, ribbed stiffener, anchoring system, reinforcing bar, end plate, Zuo Gang Flange plate and right steel flange plate are constituted;The concrete of toughened internal stress is with end plate, left steel flange plate and right steel flange plate by cutting Power key is attached, and bears external force jointly;Ribbed stiffener is used to improve the stability of short steel column;It is arranged in short steel column end and connects Plate;Concrete column is reinforced concrete structure, to reinforce the connection between concrete column and toughened internal stress, in concrete column and steel Fining twisted steel is installed inside mixed adapter section.
Shear connector in toughened internal stress symmetrically be welded on end plate, left steel flange plate and right steel flange plate enclose and At medial surface on;The size and specification of shear connector pass through according to the dead load being applied on steel reinforced concrete column and the size of mobile load The calculation method of existing specification determines.
The fashioned iron section form of short steel column uses H-type or box-type section, and the arrangement of the ribbed stiffener of short steel column is true according to specification Determine
It is by shear connector and fining twisted steel that concrete and both different materials of steel is close at toughened internal stress Connection improves its globality, and connecting plate is arranged in the outer end of short steel column, using two kinds of hybrid modes of bolt and welding and outside The connection of portion's steel node.
The implementation method of assembled steel reinforced concrete joining column structure, the specific steps are as follows:
Step 1: short steel column, welded end plate, left steel flange plate at toughened internal stress end being processed according to design drawing in factory And right steel flange plate, shear connector being welded on symmetrically is interior made of end plate, upper steel flange plate and lower steel flange plate enclose On side;The connecting plate being connected with steel node is welded in the toughened internal stress other end, and is connected in connecting plate and with short steel column Prepared screw-bolt hole hole on the end plate connect;
Step 2: the short steel column of the good two panels of factory process being fixed, the installation template between short steel column, by design binding Reinforcing bar installs punching device and fining twisted steel in concrete column and toughened internal stress in advance;
Step 3: casting concrete column and toughened internal stress conserve beam in factory, reach to concrete column intensity To after day intensity, form removal system;
Step 4: anchoring system being installed on the end plate of toughened internal stress, opens fining twisted steel by design control stretching force It draws in place;
Step 5: steel reinforced concrete column being transported to construction site, passes through two kinds of hybrid modes of bolt and welding and external steel section Point connection, completes installation.
Compared with the prior art, the advantages of the present invention are as follows:
1, the factorial production can be carried out, guarantees architecture quality
, can be prefabricated with the progress batch production of overall process combining information technology using the present invention, guarantee architecture quality, improves it Durability, and it is encoded in process of production, the performance and quality to column in production process carry out life-cycle retrospect.
2, quick assembled type construction can be used, accelerate construction progress, small to surrounding environment influence,
Using the present invention, compared with traditional rod structure, finished product beam is transported to construction site after plant produced is complete, using spiral shell Two kinds of hybrid modes of bolt and welding are connect with steel node, are reduced situ wet operation, are constructed, greatly accelerated using quick assemblingization Engineering construction progress, save the cost greatly reduce surrounding environment influence.
3, the advantages of making full use of steel and concrete, economic indicator is low
Using the present invention, the advantages of being combined using steel reinforced concrete in assembled steel reinforced concrete joining column structure, both played concrete structure, Played that steel connect with steel again is easy to application property.Steel dosage is greatly reduced compared with steel construction reduces cost, reduces steel knot The fire prevention of structure anti-corrosion and later maintenance maintenance cost;There is no wet seam compared with cast-in-situ concrete columns, at bean column node, makes construction speed Degree is accelerated, and shortens the construction period, save the cost.
Detailed description of the invention
Steel reinforced concrete column floor plan Fig. 1 (a) of the invention;
Steel reinforced concrete column floor plan Fig. 1 (b) of the invention;
Toughened internal stress layout drawing Fig. 2 of the invention;
Concrete column sectional view Fig. 3 of the invention;
Toughened internal stress sectional view Fig. 4 of the invention;
Short steel column sectional view Fig. 5 of the invention.
Specific embodiment
Present invention will be further explained below with reference to the attached drawings and examples.
Assembled steel reinforced concrete joining column structure, including concrete column 1, toughened internal stress 2, short steel column 3;Toughened internal stress 2 is The linkage section of concrete column 1 and short steel column 3.Wherein, concrete column 1 pricks screw thread by concrete 4, reinforcing bar 5, punching device 6 and essence Steel 7 forms, and short steel column 3 is made of fashioned iron 8, ribbed stiffener 9 and connecting plate 10, toughened internal stress 2 by shear connector 11, concrete 4 plus Strength rib 9, anchoring system 12, reinforcing bar 5, end plate 13, left steel flange plate 14 and right steel flange plate 15 are constituted, and toughened internal stress 2 is mixed The changeover portion of solidifying earth pillar 1 and short steel column 3, the concrete 4 of toughened internal stress 2 and end plate 13, left steel flange plate 14 and the right steel edge of a wing Plate 15 is attached by shear connector 11, bears external force jointly.Ribbed stiffener 9 is then the stability for improving short steel column 3, avoids its hair Raw local buckling.It is easily attached for convenience of steel reinforced concrete combination intercolumniation, connecting plate 10 is set in short 3 end of steel column, using bolt and weldering The mode of combining is connect to connect with steel node.Concrete column 1 is reinforced concrete structure, to reinforce concrete column 1 in conjunction with steel reinforced concrete Fining twisted steel 7 is installed in connection between section 2 inside them.
Assembled steel reinforced concrete joining column structure of the present invention is made of concrete column 1, toughened internal stress 2, short steel column 3, coagulates earth pillar 1, toughened internal stress 2, the size of short steel column 3 and construction, it is true by existing proper calculation according to structure type and external load size It is fixed.
In the present invention, 5 grade specification of reinforcing bar and the ratio of reinforcement in concrete column 1, according to external load size and beam size, root It is determined according to existing proper calculation method.
In the present invention, toughened internal stress 2 is by shear connector 11, concrete 4, ribbed stiffener 9, anchoring system 12, reinforcing bar 5, end plate 13, left steel flange plate 14 and right steel flange plate 15 composition, 5 ratio of reinforcement of reinforcing bar and grade in toughened internal stress 2, according to being applied to The size of load on toughened internal stress is determined by the calculation method of existing specification.
In the present invention, shear connector 11 in toughened internal stress 2 should be arranged symmetrically, the size and specification of shear connector 11 According to the size of the dead load and mobile load that are applied on steel reinforced concrete column, determined by the calculation method of existing specification.
In the present invention, length, quantity and the arrangement of fining twisted steel 7 in toughened internal stress 2 and concrete column 1, according to perseverance Load and the size of mobile load and the size of column are determined by the calculation method of existing specification.
In the present invention, short steel column 3 is made of fashioned iron 8, ribbed stiffener 9 and connecting plate 10,8 section form of fashioned iron of short steel column 3 Using H-type or box-type section, the arrangement of the ribbed stiffener 9 of short steel column 3 is determined according to specification.
Assembled steel reinforced concrete column is made of concrete column 1, toughened internal stress 2, short steel column 3, and steel reinforced concrete column uses steel Reinforced concrete column, by shear connector 11 and fining twisted steel 7 by concrete and steel both different materials at toughened internal stress 2 The close connection of material improves its globality, and connecting plate 10 is arranged at column both ends, using two kinds of hybrid modes of bolt and welding and The connection of steel node, reduces the wet construction at connecting node, is constructed, is accelerated construction progress using quick assemblingization, saves the duration.
The implementation method of assembled steel reinforced concrete joining column structure, the specific steps are as follows:
Step 1: short steel column 3 being processed according to design drawing in factory, in 2 one end welded end plate 13 of toughened internal stress, Zuo Gang Flange plate 14 and right steel flange plate 15, by shear connector 11 symmetrically be welded on end plate 13, left steel flange plate 14 and the right steel wing On medial surface made of listrium 15 encloses;The connecting plate 10 being connected with steel node is welded in 2 other end of toughened internal stress, and even Prepared screw-bolt hole hole on fishplate bar 10 and the end plate 13 being connected with short steel column 3.
Step 2: the short steel column 3 of the two panels factory processed being fixed, the installation template between short steel column 3 is tied up by design It wire-ties, punching device 6 and fining twisted steel 7 is installed in advance in concrete column 1 and toughened internal stress 2.
Step 3: casting concrete column 1 and toughened internal stress 2 conserve beam in factory, to concrete column intensity After reaching 28 days intensity, form removal system.
Step 4: anchoring system 12 being installed on the end plate 13 of toughened internal stress 2, controls stretching force for finish rolling spiral shell by design 7 tensioning of line steel is in place.
Step 5: steel reinforced concrete column being transported to construction site, is connected by two kinds of hybrid modes of bolt and welding and steel node It connects, completes installation.
Embodiment:
The assembled steel reinforced concrete column of the present embodiment is arranged as shown in Fig. 1 (a), 1 (b) and 2.Steel reinforced concrete combination column length 3~4 Rice, the size of column are 400mm × 400mm.It is made of concrete column 1, toughened internal stress 2 and short steel column 3, steel reinforced concrete combined segment 2 A length of 250mm, a height of 400mm, width 400mm;Short steel column 3 is made of H profile steel 8, ribbed stiffener 9 and connecting plate 10, H profile steel 8 The edge of a wing and web thickness obtain according to corresponding proper calculation,
The concrete column 1 and toughened internal stress 2 of the present embodiment as shown in figs. 34, arrange certain amount in concrete column 1 Longitudinal reinforcement 5, the ratio of reinforcement is obtained according to practical engineering calculation, and steel reinforced concrete junction carry out stirrup encryption, steel reinforced concrete combine Section 2 is made of multiple shear connectors 11, end plate 13, left steel flange plate 14 and right steel flange plate 15, end plate 13, left steel flange plate 14 and Right 15 thickness 20mm of steel flange plate, 11 diameter of shear connector are 10mm, bond distance 70mm, and the spacing between shear connector 11 is according to proper calculation It obtains.
The short steel column 3 of the present embodiment is as shown in figure 5, the hybrid mode come in connects steel node, bolt with welding using bolt It is obtained with weld size according to corresponding proper calculation, connects plate thickness 20mm.

Claims (3)

1. assembled steel reinforced concrete joining column structure, it is characterised in that including concrete column (1), toughened internal stress (2), short steel column (3); Toughened internal stress (2) is the linkage section of concrete column (1) and short steel column (3);Concrete column (1) includes concrete (4), reinforcing bar (5), punching device (6) He Jingzha screw-thread steel (7);Short steel column (3) includes fashioned iron (8), ribbed stiffener (9) and connecting plate (10);Steel Mixed adapter section (2) are by shear connector (11), concrete (4), ribbed stiffener (9), anchoring system (12), reinforcing bar (5), end plate (13), a left side Steel flange plate (14) Ji Yougang flange plate (15) is constituted;The concrete (4) of toughened internal stress (2) and end plate (13), the left steel edge of a wing Plate (14) Ji Yougang flange plate (15) is attached by shear connector (11), bears external force jointly;Ribbed stiffener (9) is short for improving The stability of steel column (3);In short steel column (3) end, connecting plate (10) are set;Concrete column (1) is reinforced concrete structure, is Reinforce the connection between concrete column (1) and toughened internal stress (2), the installation essence inside concrete column (1) and toughened internal stress (2) It pricks screw-thread steel (7);
Shear connector (11) in toughened internal stress (2) symmetrically be welded on end plate (13), left steel flange plate (14) Ji Yougang On medial surface made of flange plate (15) encloses;The size and specification of shear connector (11) are according to the perseverance being applied on steel reinforced concrete column The size with mobile load is carried, is determined by the calculation method of existing specification;
By shear connector (11) and fining twisted steel (7) by concrete and steel both difference materials at toughened internal stress (2) The close connection of material improves its globality, and connecting plate (10) is arranged in the outer end of short steel column (3), using bolt and welding two Kind hybrid mode is connect with external steel node.
2. assembled steel reinforced concrete joining column structure according to claim 1, it is characterised in that the fashioned iron (8) of short steel column (3) is cut Face form uses H-type or box-type section, and the arrangement of the ribbed stiffener (9) of short steel column (3) is determined according to specification.
3. the implementation method of assembled steel reinforced concrete joining column structure according to claim 1, it is characterised in that specific steps are such as Under:
Step 1: short steel column (3) being processed according to design drawing in factory, holds welded end plate (13), Zuo Gang in toughened internal stress (2) Flange plate (14) Ji Yougang flange plate (15), by shear connector (11) symmetrically be welded on end plate (13), left steel flange plate (14) on medial surface made of Ji Yougang flange plate (15) encloses;The company being connected with steel node is welded in short steel column (3) other end Fishplate bar (10), and the prepared screw-bolt hole hole on connecting plate (10) and the end plate (13) being connected with short steel column (3);
Step 2: the short steel column of the good two panels of factory process (3) being fixed, the installation template between short steel column (3) is tied up by design It wire-ties, punching device (6) and fining twisted steel (7) is installed in advance in concrete column (1) and toughened internal stress (2);
Step 3: casting concrete column (1) and toughened internal stress (2), to concrete column (1) and toughened internal stress (2) in factory It is conserved, after concrete column intensity reaches 28 days intensity, form removal system;
Step 4: anchoring system (12) being installed on the end plate (13) of toughened internal stress (2), control stretching force for finish rolling by design Screw-thread steel (7) tensioning is in place;
Step 5: steel reinforced concrete column being transported to construction site, is connected by two kinds of hybrid modes of bolt and welding and external steel node It connects, completes installation.
CN201610954391.XA 2016-10-27 2016-10-27 Assembled steel reinforced concrete joining column structure and its implementation method Active CN106567499B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610954391.XA CN106567499B (en) 2016-10-27 2016-10-27 Assembled steel reinforced concrete joining column structure and its implementation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610954391.XA CN106567499B (en) 2016-10-27 2016-10-27 Assembled steel reinforced concrete joining column structure and its implementation method

Publications (2)

Publication Number Publication Date
CN106567499A CN106567499A (en) 2017-04-19
CN106567499B true CN106567499B (en) 2019-10-15

Family

ID=58535271

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610954391.XA Active CN106567499B (en) 2016-10-27 2016-10-27 Assembled steel reinforced concrete joining column structure and its implementation method

Country Status (1)

Country Link
CN (1) CN106567499B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109162197B (en) * 2018-09-29 2020-08-25 中国建筑第八工程局有限公司 Bridge pier structure and construction method thereof
CN109610295B (en) * 2018-11-20 2021-01-29 温州集程建设有限公司 Reinforced concrete simple structure and manufacturing method thereof
CN110029863B (en) * 2019-05-13 2020-09-01 江苏中南建筑产业集团有限责任公司 Reinforced concrete steel column and construction method thereof
CN110424253A (en) * 2019-09-06 2019-11-08 同济大学建筑设计研究院(集团)有限公司 A kind of cross-section steel concrete combination double-layered pressure-bearing plate power transmission anchor structure
CN112112180A (en) * 2020-08-26 2020-12-22 绍兴文理学院 Connecting system of assembled combined pier and bearing platform and construction method thereof
CN112030727A (en) * 2020-08-26 2020-12-04 绍兴文理学院 Assembled prefabricated steel-concrete combined pier and construction method thereof
CN116427269B (en) * 2023-05-22 2024-01-23 浙江中天恒筑钢构有限公司 Variable-section inclined tower column steel-concrete combined section double-layer anchoring structure and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003074120A (en) * 2001-09-07 2003-03-12 Taisei Corp Method for executing concrete-filled steel-pipe column
JP2005307702A (en) * 2004-04-26 2005-11-04 Shimizu Corp Column structure
CN101831866A (en) * 2010-05-11 2010-09-15 天津市市政工程设计研究院 Steel-concrete joint section structure of beams
KR20110053831A (en) * 2009-11-16 2011-05-24 경희대학교 산학협력단 Steel reinforcement and concrete composite column having vertically coupling means and construction method using the same
CN105239723A (en) * 2015-11-02 2016-01-13 上海市机械施工集团有限公司 Prefabricated concrete column in butting connection by steel nodes
CN105464458A (en) * 2015-10-14 2016-04-06 中铁五局集团路桥工程有限责任公司 Urban rail transit overhead station and section steel and concrete combined column thereof
CN106049754A (en) * 2016-07-22 2016-10-26 广东省建筑设计研究院 Standard assembly section of assembly-type concrete composite column and composite column formed through assembly section

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003074120A (en) * 2001-09-07 2003-03-12 Taisei Corp Method for executing concrete-filled steel-pipe column
JP2005307702A (en) * 2004-04-26 2005-11-04 Shimizu Corp Column structure
KR20110053831A (en) * 2009-11-16 2011-05-24 경희대학교 산학협력단 Steel reinforcement and concrete composite column having vertically coupling means and construction method using the same
CN101831866A (en) * 2010-05-11 2010-09-15 天津市市政工程设计研究院 Steel-concrete joint section structure of beams
CN105464458A (en) * 2015-10-14 2016-04-06 中铁五局集团路桥工程有限责任公司 Urban rail transit overhead station and section steel and concrete combined column thereof
CN105239723A (en) * 2015-11-02 2016-01-13 上海市机械施工集团有限公司 Prefabricated concrete column in butting connection by steel nodes
CN106049754A (en) * 2016-07-22 2016-10-26 广东省建筑设计研究院 Standard assembly section of assembly-type concrete composite column and composite column formed through assembly section

Also Published As

Publication number Publication date
CN106567499A (en) 2017-04-19

Similar Documents

Publication Publication Date Title
CN106567499B (en) Assembled steel reinforced concrete joining column structure and its implementation method
CN106481023B (en) Assembled steel-concrete composite beam structure and its implementation method
CN106869315B (en) Concrete-filled steel tubular frame and its construction method with presstressed reinforcing steel
CN105863111B (en) The steel frame construction of embedded precast concrete shear wall bending resistance simultaneously
CN104631659B (en) Prefabricated assembled band steel plate concealed bracings overlaid plate type concrete coupled shear wall
CN106567458B (en) Assembled steel-is mixed to combine Beam-post Frame Structure system
CN108487453B (en) Connecting structure and connecting method for steel tube concrete column and reinforced concrete beam
CN205777098U (en) A kind of detachable assembling type concrete-filled circular steel tube column
CN205894313U (en) Prefabricated assembled steel pipe retrains frame node entirely
CN206016309U (en) A kind of overall assembled building system
CN203238780U (en) Prefabricated stirrup cage of beam column core area
CN106284655A (en) Precast concrete beam stud connects node and method of attachment in succession
CN209260897U (en) Assembly concrete beam column sleeve combination connecting node
CN107217787A (en) A kind of assembled coupling beam of built-in profiled sheet groove structure
CN108532796A (en) Assembly concrete shear wall and face inner beam rigid connection node and construction method
CN106759873A (en) A kind of new prefabricated integral frame structure prefabricated post is constructed with prefabricated beam connecting node
CN106948476B (en) The frame and its construction method that prestressing with bond combination beam is constituted
CN203440993U (en) Connection joint of prefabricated reinforced concrete beam
CN206844316U (en) A kind of assembled steel reinforced concrete column with well and post splicing node
CN108775098A (en) The production method of across floor PEC shear walls-steel coupling beam coupled wall connecting node
CN107447873A (en) Connect the device and installation method of prefabricated overlapping coupling beam and precast shear wall
CN111894193A (en) Assembled concrete inclined roof
CN208472958U (en) A kind of partial precast assembled steel reinforced concrete giant frame structure
CN207892021U (en) A kind of novel fabricated steel-regeneration concrete combination frame structural system
CN206784661U (en) The steel plate concrete combined shear wall of steel plate built in the middle part of the outsourcing of end

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant