CN106567476B - The construction method of pre- crack resistence partition wall - Google Patents

The construction method of pre- crack resistence partition wall Download PDF

Info

Publication number
CN106567476B
CN106567476B CN201610890703.5A CN201610890703A CN106567476B CN 106567476 B CN106567476 B CN 106567476B CN 201610890703 A CN201610890703 A CN 201610890703A CN 106567476 B CN106567476 B CN 106567476B
Authority
CN
China
Prior art keywords
keel
day
skin plate
fixed
centre
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610890703.5A
Other languages
Chinese (zh)
Other versions
CN106567476A (en
Inventor
王辉平
王利雄
连珍
刘淳
陈帅
邓惠根
葛倩华
周漪芳
陈莹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Building Decoration Engineering Group Co Ltd
Original Assignee
Shanghai Building Decoration Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Building Decoration Engineering Group Co Ltd filed Critical Shanghai Building Decoration Engineering Group Co Ltd
Priority to CN201610890703.5A priority Critical patent/CN106567476B/en
Publication of CN106567476A publication Critical patent/CN106567476A/en
Application granted granted Critical
Publication of CN106567476B publication Critical patent/CN106567476B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/74Removable non-load-bearing partitions; Partitions with a free upper edge
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/74Removable non-load-bearing partitions; Partitions with a free upper edge
    • E04B2/7407Removable non-load-bearing partitions; Partitions with a free upper edge assembled using frames with infill panels or coverings only; made-up of panels and a support structure incorporating posts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/74Removable non-load-bearing partitions; Partitions with a free upper edge
    • E04B2/7407Removable non-load-bearing partitions; Partitions with a free upper edge assembled using frames with infill panels or coverings only; made-up of panels and a support structure incorporating posts
    • E04B2/7453Removable non-load-bearing partitions; Partitions with a free upper edge assembled using frames with infill panels or coverings only; made-up of panels and a support structure incorporating posts with panels and support posts, extending from floor to ceiling

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The present invention provides a kind of construction methods of pre- crack resistence partition wall, for traditional grid system, partition wall is integrally influenced seriously by self-deformation and structure sediment, the features such as cracking influences appearance requirement and uses function, by using new constrained procedure, change the connection type of keel and structure, so that integrally there is certain activity space in vertical direction in keel, skin plate and new grid system are fixed, Admissible displacement in vertical direction, so that there is certain movable space in vertical direction in its plane in skin plate, when building structure be subjected to displacement or itself deformation occurs when, skin plate can by can vertical telescopic day keel carry out itself it is limited without constraint freely-supported activity, alleviate longitudinal stress, reduce building settlement, the risk of the cracking of plaster board wall surface caused by horizontal wind pressure, simply, innovation, efficiently, it its keel and builds It builds between roof, no longer needing to increase rubber pad between ground joist and building ground, to do buffering deformation reserved.

Description

The construction method of pre- crack resistence partition wall
Technical field
The present invention relates to a kind of construction methods of pre- crack resistence partition wall.
Background technique
Partition wall is integrally fastened on up-down structure by traditional keel of partition wall system using nailing, bolt, keel and partition wall it Between alleviated using rubber pad consolidating settlement bring influence.Such constrained procedure, the self-deformation and structure that rubber pad is alleviated Settle limited, and after rubber pad loses activity, partition wall easily deforms cracking so that using partition wall as the wallpaper of base, Craze and transfiguration occurs for the surface layers such as ceramic tile, influences aesthetic and uses function.
Summary of the invention
The purpose of the present invention is to provide a kind of construction methods of pre- crack resistence partition wall, can prevent cracks on partition walls, and day No longer needing to increase rubber pad between keel and building roof, between ground joist and building ground, to do buffering deformation reserved.
To solve the above problems, the present invention provides a kind of construction method of pre- crack resistence partition wall, comprising:
Building roof by can vertical telescopic day keel width snap the line, and building ground press ground joist width bullet Line determines the position of day keel and ground joist, and the position of centre keel, punching keel and stull keel is determined according to the size of skin plate It sets;
By the position of the snap the line place the ground joist and can vertical telescopic day keel, by the ground joist and sky dragon Bone is fixed temporarily and is corrected horizontal position, the fixed ground joist and day keel after to be corrected;
By centre keel respectively with it is described can day keel, the ground joist of vertical telescopic be attached;
Punching keel are extended vertically through into each centre keel;
According to the arrangement of the size of skin plate and quantity setting stull keel, dragon by stull keel and is erected according to the arrangement Bone is attached;
The skin plate is fixed on the stull keel and centre keel, there are gaps between adjacent skin plate, approach Pre-determined distance is spaced between the building roof or the skin plate and building roof or building ground of building ground to form gap;
The filling elastic material in the gap.
Further, in the above-mentioned methods, when it is described can vertical telescopic day keel include be fixed on building roof cut Face is U-shaped day keel A, and the section being sheathed in the day keel A is U-shaped day keel B, the day keel A and day keel B When respectively including keel roof, the side of keel connecting with the keel roof,
The ground joist and day keel are placed by the position of the snap the line, are fixed temporarily and are corrected horizontal position, to The position of ground joist and day keel is fixed after correction, comprising:
The ground joist, day keel A are placed by the position of the snap the line, is fixed temporarily and is corrected horizontal position, to Ground joist, day keel location A are fixed after correction;
Day keel B is sheathed in day keel A, and day keel B is temporarily fixed with day keel A, the day keel A and day It is separated by pre-determined distance between the keel roof of keel B.
Further, in the above-mentioned methods, by centre keel respectively and can day keel, the ground joist of vertical telescopic be attached Later, further includes:
After the centre keel installs, being fixed temporarily for day keel A and day keel B is released.
Further, in the above-mentioned methods, by centre keel respectively and can day keel, the ground joist of vertical telescopic connect It connects, comprising: be attached centre keel with day keel B, ground joist respectively.
Further, in the above-mentioned methods, after punching keel being extended vertically through each centre keel further include:
It is fixed with centre keel junction using fastener in the punching keel.
Further, in the above-mentioned methods, the skin plate is fixed on the stull keel and centre keel, comprising:
Sequence installation skin plate, adjacent two pieces of skin plates are drawn close naturally since the side end of partition wall, wherein by cover Plate is vertically laid with, and the long side seam of the skin plate is fixed on centre keel, and the short side seam of the skin plate is fixed on On stull keel, day keel B or ground joist, the fissure of displacement is installed between the skin plate.
Further, in the above-mentioned methods, the long side seam of the skin plate is fixed on centre keel, by the cover The short side seam of plate is fixed on stull keel, day keel B or ground joist, comprising:
When the skin plate is installed, follows closely and fix to the four side tapping screws or rifle of plate from the middle part of plate, once squeeze into, from It attacks nail or rifle nail falls into the depth of skin plate 0.5mm~1mm, the constant spacing of self threading pin or rifle nail is on skin plate periphery The constant spacing of 200mm, skin plate centre self threading pin or rifle nail is 300mm, and tapping screw or rifle are followed closely and the long side of skin plate connects The distance of seam or short side seam is 10mm~15mm, described if a certain long side seam of skin plate or short side seam are cutting side The distance that side is cut off described in tapping screw or rifle pitch of nails is 16mm~20mm.
Further, in the above-mentioned methods, the short side seam of the skin plate is fixed on stull keel, comprising:
When the short side seam of the skin plate is not on the day keel B or ground joist, described not in the sky dragon Short side seam on bone B or ground joist adds stull keel, by the not short side seam on the day keel B or ground joist It is fixed on the stull keel of the addition.
Further, in the above-mentioned methods, when the edge of the skin plate is formed with groove, the skin plate is fixed After on the stull keel and centre keel, further include,
After surface dust in plate stitch between groove is removed completely, the glue solution of one of 50% concentration of brush;
Putty is embedded on the glue solution in the plate stitch between groove with small scraper, by the embedding full embedding reality of plate stitch, by seam Putty is scraped to groove and is flushed, and whether after putty parches, checking has line generation at filleting, analyzes reason when generating crack, weight New filleting;
The putty of about 1mm thickness is scraped at the groove, then pastes glass fibre belt on the putty of the 1mm thickness, it will be described Glass fibre belt compacting is pasted to strike off;
One is scraped when the putty of the 1mm thickness, which starts solidification, is still in dampness again, then on the stickup glass fibre belt Glass fibre belt is embedded in putty, and plate stitch is filled up and is struck off by road putty.
Further, in the above-mentioned methods, the long side seam of the skin plate and the lap of centre keel are not less than 15mm。
Compared with prior art, the present invention passes through integrally heavy by self-deformation and structure for traditional grid system, partition wall The features such as dropping influences seriously, and cracking influences appearance requirement and uses function changes keel and knot by using new constrained procedure The connection type of structure, so that keel integrally have certain activity space in vertical direction, skin plate and new grid system are solid Determine, in vertical direction Admissible displacement, so that skin plate has certain movable sky in its plane in vertical direction Between, when building structure be subjected to displacement or itself deformation occurs when, skin plate can by can the day keel of vertical telescopic carry out itself It is limited to alleviate longitudinal stress without constraint freely-supported activity, reduce what plaster board wall surface caused by building settlement, horizontal wind pressure cracked Risk provides the curtain wall structure of a kind of simple, innovation, efficient pre- crack resistence, between day keel and building roof, ground joist No longer needing to increase rubber pad between building ground, to do buffering deformation reserved.
Detailed description of the invention
Fig. 1 is the day keel A scheme of installation of one embodiment of the invention;
Fig. 2 is that the day keel B and day keel A of one embodiment of the invention are fixed temporarily schematic diagram;
Fig. 3 is the ground joist scheme of installation of one embodiment of the invention;
Fig. 4 is the centre keel structure chart of one embodiment of the invention;
Fig. 5 is the centre keel scheme of installation of one embodiment of the invention;
Fig. 6 is the punching keel installation schematic diagram of one embodiment of the invention;
Fig. 7 is the stull keel installation schematic diagram of one embodiment of the invention;
Fig. 8 is the skin plate scheme of installation of one embodiment of the invention;
Fig. 9 is the skin plate installation tapping screw schematic diagram of one embodiment of the invention;
Figure 10 is the skin plate top scheme of installation of one embodiment of the invention;
Figure 11 is the skin plate lower part scheme of installation of one embodiment of the invention.
Specific embodiment
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, with reference to the accompanying drawing and specific real Applying mode, the present invention is described in further detail.
As shown in Fig. 1~11, the present invention relates to a kind of partition walls of pre- crack resistence, comprising:
Be directly fixed on building roof 1 can vertical telescopic day keel;
It is directly fixed on the ground joist 3 of building ground 2;Specifically, as shown in figure 3, ground joist and building ground pass through spiral shell Bolt 4 connects, and is not added rubber pad therebetween, and 4 constant spacing of bolt takes 600mm, first fixed point from adjacent side wall be about 100~ 150mm;
The centre keel 5 being connect respectively with the day keel and ground joist 3;Specifically, as shown in Figures 4 and 5, the centre keel Upper end and the day keel B by self-drilling connection, the lower end of the centre keel and the ground joist pass through tapping screw Connection, the centre keel spacing can be set depending on partition wall panel size no more than 400mm, in practice of construction, to make partition wall Panel stays seam, and setting is slightly larger than 403mm, fixes it with day ground joist behind centre keel position and vertical correction, installs centre keel Centre keel level and spacing should be verified by root;
Through each centre keel 5 and the punching keel 6 vertical with each centre keel;Specifically, as shown in fig. 6, the punching is imperial The specific gear number of bone 6 is depending on partition wall height, herein respectively in 600mm, 1800mm, 3000mm, 4200mm height of centre keel Upper to install 4 grades of punching keel respectively, punching keel have a shaking in order to prevent, and the junction of the punching keel and centre keel passes through Fastener is fixed;
Connect the stull keel 7 between two adjacent centre keels 5, the position of the stull keel 7 and quantity and skin plate 8 Size is corresponding with quantity;Specifically, as shown in fig. 7, the stull keel are connected by self-plugging rivet with centre keel, specific location Depending on the length and width of gear number combination skin plate 8 and typesetting;
The skin plate 8 being fixed on the stull keel 7 and centre keel 5, close to the building roof 1 or building ground 2 Skin plate 8 and building roof 1 or building ground 2 between be spaced pre-determined distance, to form gap, filled with bullet in the gap Property material 9.Specifically, the lap of the skin plate and centre keel is not less than 15mm, as shown in figure 11, close to the building Gap between the skin plate and building ground on ground is greater than 10mm, as shown in Figure 10, close to the skin plate of the building roof Gap between building roof is greater than 20mm~25mm, as shown in figure 9, the skin plate 8 is solid by self threading pin or rifle nail 10 Due on the stull keel 7 and centre keel 6, the self threading pin or rifle follow closely 10 depth for falling into skin plate 0.5mm~1mm, cover The constant spacing of self threading pin or rifle nail is advisable on panel periphery with 200mm, the constant spacing of self threading pin or rifle nail among skin plate It is advisable with 300mm, tapping screw or rifle nail are 10mm~15mm at a distance from skin plate edge, if a certain edge of skin plate is to cut Cut edge then cuts off the distance on side described in the tapping screw or rifle pitch of nails as 16mm~20mm.The present invention is directed to traditional keel system The features such as system, partition wall are integrally influenced seriously by self-deformation and structure sediment, and cracking influences appearance requirement and uses function, passes through Using new constrained procedure, change the connection type of keel and structure, so that keel are whole to have certain live in vertical direction Dynamic space, skin plate and new grid system are fixed, in vertical direction Admissible displacement, so that skin plate is in its plane There is certain movable space in vertical direction, when building structure be subjected to displacement or itself deformation occurs when, skin plate can lead to Cross can vertical telescopic day keel carry out itself it is limited without constraint freely-supported activity, alleviate longitudinal stress, reduce building settlement, water The risk of the cracking of plaster board wall surface caused by flat wind pressure provides the partition wall knot of a kind of simple, innovation, efficient pre- crack resistence Structure, no longer needing to increase rubber pad between day keel and building roof, between ground joist and building ground, to do buffering deformation reserved.
Preferably, as illustrated in fig. 1 and 2, it is described can vertical telescopic day keel include be fixed on building roof section be U The day keel A of type is sheathed on the section in the day keel A as U-shaped day keel B, the day keel A and day keel B difference Including keel roof, the side of keel being connect with the keel roof, between the day keel A and the keel roof of day keel B Separated by a distance, the skin plate is connect with day keel B.Specifically, the day keel A and day keel B respectively include keel Roof connects the side of keel connecting with the keel roof, so that Formation cross-section is U-shaped day keel A and day keel B, sky dragon Bone A, day keel B, are all made of U-shaped steel.The day keel A is directly connected to building roof by nailing, and day keel A and building are pushed up Rubber pad is not added between wall, nailing spacing can use 600mm, and first fixed point is about 100~150mm from adjacent side wall.It Keel B is stuck on the downside of day keel A, and day keel B and day keel A are fixed temporarily, and does not use other connection type, for the side of installation Just, using being fixed temporarily, after centre keel is installed, dismounting is fixed temporarily, the keel top of the day keel A and day keel B Spacing between wall can be 25mm, and the upper end of the nearly skin plate for building roof and day keel B are fixed by tapping screw, forbid cover Panel and day keel A generate any connection, to guarantee that skin plate can move freely sky in the presence of certain in vertical direction Between, when building structure be subjected to displacement or itself deformation occurs when, partition wall can pass through itself it is limited without constraint freely-supported activity, alleviate Longitudinal stress reduces the risk of cracking, solves the problems, such as partition wall strain cracking.
Preferably, as shown in Fig. 1 to 3, the day keel A, day keel B and ground joist are all made of U-shaped steel.
Preferably, the edge of the skin plate is formed with groove, convenient for the gap between two pieces of adjacent skin plates into The processing of row filleting.
Detailed, as shown in Fig. 1~11, the present invention provides a kind of construction method of above-mentioned pre- crack resistence partition wall, comprising:
Building roof 1 by can vertical telescopic day keel width snap the line, and building ground 2 press ground joist width Snap the line determines the position of day keel and ground joist 3, determines centre keel 5, punching keel 6 and stull dragon according to the size of skin plate 8 The position of bone 7;Specifically, snap the line requires clear, position is accurate, in addition, design requirement is pressed, in conjunction with the length and width stepping of skin plate, To determine the position of centre keel, punching keel and stull keel;
By the position of the snap the line place the ground joist 3 and can vertical telescopic day keel, by the ground joist and day Keel are fixed temporarily and are corrected horizontal position, the fixed ground joist and day keel after to be corrected;
By centre keel 5 respectively with it is described can day keel, the ground joist 3 of vertical telescopic be attached;Specifically, by centre keel Respectively and can day keel, the ground joist of vertical telescopic be attached by tapping screw;
Punching keel 6 are extended vertically through into each centre keel 5;
According to the arrangement of the size of skin plate 8 and quantity setting stull keel 7, by stull keel and erected according to the arrangement Keel are attached;Specifically, stull keel can be connected with centre keel by self-plugging rivet according to the arrangement;
The skin plate 8 is fixed on the stull keel 7 and centre keel 5, there are gaps between adjacent skin plate, connect Interval pre-determined distance is between the nearly building roof or the skin plate and building roof or building ground of building ground to form seam Gap;Specifically, as shown in figure 11, the skin plate 8 close to the building ground can be greater than 10mm apart from building ground, avoid directly It contacts with flooring, is filled using elastic material 9, as shown in Figure 10, close to the skin plate distance building top of the building roof Wall 20mm~25mm is filled using elastic material 9;
The filling elastic material 9 in the gap.Specifically, the present invention is directed to traditional grid system, partition wall integrally by certainly The features such as body deformation and structure sediment influence seriously, and cracking influences appearance requirement and uses function, by using new constraint side Method changes the connection type of keel and structure so that integrally there is certain activity space in vertical direction in keel, skin plate and New grid system is fixed, in vertical direction Admissible displacement, so that skin plate exists in vertical direction in its plane Certain movable space, when building structure be subjected to displacement or itself deformation occurs when, skin plate can be by can vertical telescopic Its keel carries out itself limited movable without constraint freely-supported, alleviation longitudinal stress, stone caused by reduction building settlement, horizontal wind pressure The risk of cream board wall face cracking provides the curtain wall structure of a kind of simple, innovation, efficient pre- crack resistence, day keel and building No longer needing to increase rubber pad between roof, between ground joist and building ground, to do buffering deformation reserved.
Preferably, when it is described can vertical telescopic day keel include be fixed on building roof section be U-shaped day keel A, the section being sheathed in the day keel A is U-shaped day keel B, and the day keel A and day keel B respectively include keel top When wall, the side of keel being connect with the keel roof,
The ground joist and day keel are placed by the position of the snap the line, are fixed temporarily and are corrected horizontal position, to The position of ground joist and day keel is fixed after correction, comprising:
The ground joist, day keel A are placed by the position of the snap the line, is fixed temporarily and is corrected horizontal position, to Ground joist, day keel location A are fixed after correction;
Day keel B is sheathed in day keel A, and day keel B is temporarily fixed with day keel A, the day keel A and day It is separated by pre-determined distance between the keel roof of keel B, it is preferred that be separated by between the day keel A and the keel roof of day keel B Distance controlling is in 25mm or so.Specifically, solid by tapping screw close to the upper end of the skin plate of building roof and day keel B It is fixed, forbid skin plate and day keel A to generate any connection, thus guarantee skin plate can exist in vertical direction it is certain from By activity space, when building structure be subjected to displacement or itself deformation occurs when, partition wall can be limited without constraint freely-supported by itself Activity alleviates longitudinal stress, reduces the risk of cracking.
Preferably, by centre keel respectively and can vertical telescopic day keel, ground joist be attached after, further includes:
After the centre keel installs, being fixed temporarily for day keel A and day keel B is released.
Preferably, by centre keel respectively and can day keel, the ground joist of vertical telescopic be attached, comprising: by centre keel It is attached respectively with day keel B, ground joist.
Preferably, after punching keel being extended vertically through each centre keel further include:
It is fixed with centre keel junction using fastener in the punching keel, to prevent punching keel from having shaking.
Preferably, the skin plate is fixed on the stull keel and centre keel, comprising:
Sequence installation skin plate, adjacent two pieces of skin plates are drawn close naturally since the side end of partition wall, wherein by cover Plate is vertically laid with, and long side (i.e. packaging side) seam of the skin plate is fixed on centre keel, by the short side of the skin plate Seam is fixed on stull keel, day keel B or ground joist, and the fissure of displacement is installed between the skin plate;Preferably, the skin plate Long side seam and centre keel lap be not less than 15mm, the peace as shown in figure 8, keel two sides single layer skin plate must avoid the peak hour It fills, two layers of skin plate must fissure of displacement installation inside and outside keel unilateral side.
Preferably, as shown in figure 9, the long side seam of the skin plate is fixed on centre keel, by the skin plate Short side seam is fixed on stull keel, day keel B or ground joist, comprising:
It is fixed to the four side tapping screws or rifle of plate nail 10 from the middle part of plate when the skin plate 8 is installed, once beat Enter, self threading pin or rifle follow closely the depth for falling into skin plate 0.5mm~1mm, the constant spacing of self threading pin or rifle nail on skin plate periphery For 200mm, the constant spacing of skin plate centre self threading pin or rifle nail is 300mm, the long side of tapping screw or rifle nail and skin plate The distance of seam or short side seam is 10mm~15mm, if a certain long side seam of skin plate or short side seam are cutting side, institute Stating and cutting off the distance on side described in tapping screw or rifle pitch of nails is 16mm~20mm.
Preferably, the short side seam of the skin plate is fixed on stull keel, comprising:
When the short side seam of the skin plate is not on the day keel B or ground joist, described not in the sky dragon Short side seam on bone B or ground joist adds stull keel, by the not short side seam on the day keel B or ground joist It is fixed on the stull keel of the addition.
Preferably, when the edge of the skin plate is formed with groove, the skin plate is fixed on the stull keel After on centre keel, further include,
After surface dust in plate stitch between groove is removed completely, the glue solution of one of 50% concentration of brush;Specifically, cover When plate is installed, seam (general 3~6mm) is suitably stayed at plate stitch, groove connects with groove;
Putty is embedded on the glue solution in the plate stitch between groove with small scraper, by the embedding full embedding reality of plate stitch, by seam Putty is scraped to groove and is flushed, and whether after putty parches, checking has line generation at filleting, analyzes reason when generating crack, weight New filleting;
The putty of about 1mm thickness is scraped at the groove, then pastes glass fibre belt on the putty of the 1mm thickness, it will be described Glass fibre belt compacting is pasted to strike off;
One is scraped when the putty of the 1mm thickness, which starts solidification, is still in dampness again, then on the stickup glass fibre belt Glass fibre belt is embedded in putty, and plate stitch is filled up and is struck off by road putty.Specifically, the same flush joint of plate stitch processing method of inner corner trim.
The present invention for traditional grid system, partition wall by self-deformation and structure sediment by integrally being influenced seriously, cracking The features such as influencing appearance requirement and using function, is changed the connection type of keel and structure, is made by using new constrained procedure It obtains keel and integrally there is certain activity space in vertical direction, skin plate and new grid system are fixed, in vertical direction Admissible displacement, so that skin plate has certain movable space in its plane in vertical direction, when building structure is sent out Raw displacement or itself when deformation occurs, skin plate can by can the day keel of vertical telescopic to carry out itself limited without constraint freely-supported Longitudinal stress is alleviated in activity, reduces the risk that plaster board wall surface caused by building settlement, horizontal wind pressure cracks, provides one kind Simply, it innovates, the curtain wall structure of efficient pre- crack resistence, between day keel and building roof, between ground joist and building ground No longer needing to increase rubber pad, to do buffering deformation reserved.
Each embodiment in this specification is described in a progressive manner, the highlights of each of the examples are with other The difference of embodiment, the same or similar parts in each embodiment may refer to each other.
Obviously, those skilled in the art can carry out various modification and variations without departing from spirit of the invention to invention And range.If in this way, these modifications and changes of the present invention belong to the claims in the present invention and its equivalent technologies range it Interior, then the invention is also intended to include including these modification and variations.

Claims (9)

1. a kind of construction method of pre- crack resistence partition wall characterized by comprising
Building roof by can vertical telescopic day keel width snap the line, and building ground press ground joist width snap the line, The position for determining day keel and ground joist determines the position of centre keel, punching keel and stull keel according to the size of skin plate;
By the position of the snap the line place the ground joist and can vertical telescopic day keel, by the ground joist and day keel into Row is fixed temporarily and corrects horizontal position, the fixed ground joist and day keel after to be corrected;
By centre keel respectively with it is described can day keel, the ground joist of vertical telescopic be attached;
Punching keel are extended vertically through into each centre keel;
According to the arrangement of the size of skin plate and quantity setting stull keel, according to the arrangement by stull keel and centre keel into Row connection;
The skin plate is fixed on the stull keel and centre keel, there are gaps between adjacent skin plate, described in It builds and is spaced pre-determined distance between the skin plate of roof or building ground and building roof or building ground to form gap;
The filling elastic material in the gap;
Wherein, when it is described can vertical telescopic day keel include be fixed on building roof section be U-shaped day keel A, be arranged It is U-shaped day keel B in the section in the day keel A, the day keel A and day keel B respectively include keel roof and institute When stating the side of keel of keel roof connection,
The ground joist and day keel are placed by the position of the snap the line, are fixed temporarily and are corrected horizontal position, it is to be corrected The position of ground joist and day keel is fixed afterwards, comprising:
The ground joist, day keel A are placed by the position of the snap the line, is fixed temporarily and is corrected horizontal position, it is to be corrected Ground joist, day keel location A are fixed afterwards;
Day keel B is sheathed in day keel A, and day keel B is temporarily fixed with day keel A, the day keel A and day keel It is separated by pre-determined distance between the keel roof of B.
2. the construction method of pre- crack resistence partition wall as described in claim 1, which is characterized in that respectively and can be vertical by centre keel After flexible day keel, ground joist are attached, further includes:
After the centre keel installs, being fixed temporarily for day keel A and day keel B is released.
3. the construction method of pre- crack resistence partition wall as described in claim 1, which is characterized in that respectively and can be vertical by centre keel Flexible day keel, ground joist are attached, comprising: are attached centre keel with day keel B, ground joist respectively.
4. the construction method of pre- crack resistence partition wall as described in claim 1, which is characterized in that extend vertically through punching keel respectively After centre keel further include:
It is fixed with centre keel junction using fastener in the punching keel.
5. the construction method of pre- crack resistence partition wall as described in claim 1, which is characterized in that the skin plate is fixed on institute It states on stull keel and centre keel, comprising:
Sequence installation skin plate, adjacent two pieces of skin plates are drawn close naturally since the side end of partition wall, wherein erect skin plate To laying, the long side seam of the skin plate is fixed on centre keel, the short side seam of the skin plate is fixed on stull On keel, day keel B or ground joist, the fissure of displacement is installed between the skin plate.
6. the construction method of pre- crack resistence partition wall as claimed in claim 5, which is characterized in that connect the long side of the skin plate Seam is fixed on centre keel, and the short side seam of the skin plate is fixed on stull keel, day keel B or ground joist, comprising:
When the skin plate is installed, follows closely and fix to the four side tapping screws or rifle of plate from the middle part of plate, once squeeze into, self threading pin Or rifle nail falls into the depth of skin plate 0.5mm~1mm, the constant spacing of self threading pin or rifle nail is 200mm, cover on skin plate periphery The constant spacing of self threading pin or rifle nail is 300mm, the long side seam or short side of tapping screw or rifle nail and skin plate among panel The distance of seam is 10mm~15mm, if a certain long side seam of skin plate or short side seam are cutting side, the tapping screw Or it is 16mm~20mm that the distance on side is cut off described in rifle pitch of nails.
7. the construction method of pre- crack resistence partition wall as claimed in claim 5, which is characterized in that connect the short side of the skin plate Seam is fixed on stull keel, comprising:
When the short side seam of the skin plate is not on the day keel B or ground joist, it is described not in the day keel B or Short side seam on ground joist adds stull keel, and the short side seam not on the day keel B or ground joist is fixed On the stull keel of the addition.
8. the construction method of pre- crack resistence partition wall as described in claim 1, which is characterized in that when the edge shape of the skin plate When at there is groove, after the skin plate is fixed on the stull keel and centre keel, further include,
After surface dust in plate stitch between groove is removed completely, the glue solution of one of 50% concentration of brush;
Putty is embedded on the glue solution in the plate stitch between groove with small scraper, by the embedding full embedding reality of plate stitch, by joint putty It scrapes to groove and flushes, whether after putty parches, checking has line generation at filleting, analyzes reason when generating crack, again embedding Seam;
The putty of about 1mm thickness is scraped at the groove, then glass fibre belt is pasted on the putty of the 1mm thickness, by the stickup Glass fibre belt compacting strikes off;
When the putty of the 1mm thickness start solidification again still in dampness when, then scrape on the stickups glass fibre belt one it is greasy Glass fibre belt is embedded in putty, and plate stitch is filled up and is struck off by son.
9. the construction method of pre- crack resistence partition wall as claimed in claim 5, which is characterized in that the long side seam of the skin plate It is not less than 15mm with the lap of centre keel.
CN201610890703.5A 2016-10-12 2016-10-12 The construction method of pre- crack resistence partition wall Active CN106567476B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610890703.5A CN106567476B (en) 2016-10-12 2016-10-12 The construction method of pre- crack resistence partition wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610890703.5A CN106567476B (en) 2016-10-12 2016-10-12 The construction method of pre- crack resistence partition wall

Publications (2)

Publication Number Publication Date
CN106567476A CN106567476A (en) 2017-04-19
CN106567476B true CN106567476B (en) 2019-02-19

Family

ID=58532789

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610890703.5A Active CN106567476B (en) 2016-10-12 2016-10-12 The construction method of pre- crack resistence partition wall

Country Status (1)

Country Link
CN (1) CN106567476B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661209B (en) * 2018-06-07 2023-08-22 中建一局集团建设发展有限公司 Movable upright post grouting wall, connecting structure and construction method thereof
CN109403513A (en) * 2018-11-16 2019-03-01 上海市建筑装饰工程集团有限公司 A kind of super-silent sound insulating construction system and method
CN109403515A (en) * 2018-11-16 2019-03-01 上海市建筑装饰工程集团有限公司 A kind of sound insulating construction system and method for non-load bearing partition
CN109403514A (en) * 2018-11-16 2019-03-01 上海市建筑装饰工程集团有限公司 A kind of sound insulating construction system and method with anti-seismic performance
US11408168B2 (en) * 2021-01-11 2022-08-09 Pillar Patent Holdings Llc Waterproofing and safety-increasing prefabricated building framing system and method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101070713A (en) * 2006-05-08 2007-11-14 冯刚克 Environment-protection energy-saving ventilating air-conditioning sound-insulating novel building and construction method
CN203795662U (en) * 2014-04-28 2014-08-27 贵州建工集团第三建筑工程有限责任公司 Oversized fiber-reinforced silicate board firewall
EP2816167A1 (en) * 2013-06-19 2014-12-24 Unda Maris Holding N.V. Wall element
CN205296489U (en) * 2015-12-29 2016-06-08 中国建筑第六工程局有限公司 Superelevation light gauge steel fire compartment wall construction structures
CN205421627U (en) * 2016-03-07 2016-08-03 中国建筑第二工程局有限公司 Fireproof sealing structure of partition wall and roofing junction

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8209917B1 (en) * 2009-05-14 2012-07-03 DeZaio Productions, Inc. Temporary, non-load bearing wall assembly

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101070713A (en) * 2006-05-08 2007-11-14 冯刚克 Environment-protection energy-saving ventilating air-conditioning sound-insulating novel building and construction method
EP2816167A1 (en) * 2013-06-19 2014-12-24 Unda Maris Holding N.V. Wall element
CN203795662U (en) * 2014-04-28 2014-08-27 贵州建工集团第三建筑工程有限责任公司 Oversized fiber-reinforced silicate board firewall
CN205296489U (en) * 2015-12-29 2016-06-08 中国建筑第六工程局有限公司 Superelevation light gauge steel fire compartment wall construction structures
CN205421627U (en) * 2016-03-07 2016-08-03 中国建筑第二工程局有限公司 Fireproof sealing structure of partition wall and roofing junction

Also Published As

Publication number Publication date
CN106567476A (en) 2017-04-19

Similar Documents

Publication Publication Date Title
CN106567476B (en) The construction method of pre- crack resistence partition wall
CN106401024B (en) The partition wall of pre- crack resistence
US9016020B1 (en) Thin brick panel assembly system
CN106401026B (en) The lightgauge steel joist system for preventing cracks on partition walls
CN101476361B (en) Inner partition plate system and its construction method
CN104790595A (en) Construction method for adjustable tile hanging system of pitched roof
CN109930734B (en) Gypsum board suspended ceiling construction method
CN206220306U (en) Prevent the lightgauge steel joist system of cracks on partition walls
US8359799B2 (en) Building module, a method for making same, and a method for using same to construct a building
CN111042392A (en) Construction method of SDHH type disassembly-free formwork foam concrete partition wall
CN108643496A (en) A kind of wall construction method and structure
CN102677858B (en) Back hanging piece for installing decorative inorganic tetrafluoromethane veneer and construction method of back hanging piece
CN206220301U (en) The partition wall of pre- crack resistence
CN106401025B (en) The construction method for preventing the lightgauge steel joist system of cracks on partition walls
CN108979029A (en) A kind of precast stair of stable structure
CN208501980U (en) A kind of movable column grout wall and its connection structure
KR20180138315A (en) Clay bricks that can be construction without masonry joints
US10196824B2 (en) Lining board, lining panel and method for manufacturing lining board
CN201334739Y (en) Internal partition wall board system
CN208668689U (en) A kind of curtain wall structure of compound steel lightweight
CN103821358A (en) Construction method for integrally grouting wall by lightweight concrete through CCA board
JP5317272B2 (en) Tile panel construction method
CN205077649U (en) Be used in anti subassembly that splits of shear force wall and infilled wall handing -over department
CN103352543B (en) The deformable marching method of concrete roof and sheet-metal roofing and deformable connected structure
CN215483808U (en) Masonry plastering wall connection structure under full shear wall structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant