CN106545015A - Karst Fissures region concrete filling pile pours anti-leaking method - Google Patents

Karst Fissures region concrete filling pile pours anti-leaking method Download PDF

Info

Publication number
CN106545015A
CN106545015A CN201510592243.3A CN201510592243A CN106545015A CN 106545015 A CN106545015 A CN 106545015A CN 201510592243 A CN201510592243 A CN 201510592243A CN 106545015 A CN106545015 A CN 106545015A
Authority
CN
China
Prior art keywords
concrete
pile
geotextiles
righting
positioner
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510592243.3A
Other languages
Chinese (zh)
Inventor
杨前
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201510592243.3A priority Critical patent/CN106545015A/en
Publication of CN106545015A publication Critical patent/CN106545015A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to concrete filling pile, more particularly to concrete filling pile casting method.A kind of Karst Fissures region concrete filling pile pours anti-leaking method, and it includes:Step one, formation area construction bored concrete pile spots localization drilling, borehole cleaning;Step 2, makes filling pile cage of reinforcement, welding righting positioner;Righting positioner is the semicircle ring being overlapped between adjacent two sections of steel reinforcement cages;Step 3, welds bored concrete pile back cover plug steel plate;Step 4, outsourcing elasticity geotextiles, can be open at righting positioner, elastic geotextiles is located in location centralizing device;Step 5, geotextiles are fastenedly connected with back cover plug;Step 6, steel reinforcement cage install tremie placing concrete after putting well.The present invention prevents Karst Fissures region drill-pouring pile concrete to be lost in.

Description

Karst Fissures region concrete filling pile pours anti-leaking method
Technical field
The present invention relates to concrete filling pile, more particularly to concrete filling pile casting method.
Background technology
When cast-in-situ bored pile is located at formation area construction, because there is rock crack development and karst hole etc. in many places formation area.After pouring pile hole is put into steel reinforcement cage, because the presence in karst hole and crack can be such that the concrete for pouring into is lost in a large number, cause greatly to waste and hidden danger of quality.
The content of the invention
Present invention seek to address that the drawbacks described above of prior art, there is provided a kind of Karst Fissures region concrete filling pile pours anti-leaking method.The present invention prevents Karst Fissures region drill-pouring pile concrete to be lost in.
What the present invention was realized in:A kind of Karst Fissures region concrete filling pile pours anti-leaking method, and it includes:
Step one, formation area construction bored concrete pile spots localization drilling, borehole cleaning;
Step 2, makes filling pile cage of reinforcement, welding righting positioner;Righting positioner is the semicircle ring being overlapped between adjacent two sections of steel reinforcement cages;
Step 3, welds bored concrete pile back cover plug steel plate;
Step 4, outsourcing elasticity geotextiles, can be open at righting positioner, elastic geotextiles is located in location centralizing device;
Step 5, geotextiles are fastenedly connected with back cover plug;
Step 6, steel reinforcement cage install tremie placing concrete after putting well.
Concrete pressure effect after the present invention is poured expands outwardly can elastic geotextiles, be clipped between rock stratum and cast-in-place pile concrete, be brought into close contact therewith, close karst hole and crack, prevent the concrete for pouring into be lost in a large number;Play a part of to isolate karst hole and crack, can guarantee that concrete pouring pile integrity and construction quality again.
Specific embodiment
When making steel reinforcement cage after pore-forming, in steel reinforcement cage bottom, the back cover plug less than pouring pile hole aperture is set, location centralizing device is symmetrically welded in cage bar on the outside of steel reinforcement cage, then outsourcing elasticity geotextiles, geotextiles bottom is fastenedly connected with back cover plug, then steel reinforcement cage is put in priming concrete pile hole, casting concrete, concrete pressure effect after pouring expands outwardly can elastic geotextiles, it is clipped between rock stratum and cast-in-place pile concrete, it is brought into close contact therewith, play a part of to isolate karst hole and crack, concrete pouring pile integrity and construction quality are can guarantee that again.

Claims (1)

1. a kind of Karst Fissures region concrete filling pile pours anti-leaking method, it is characterised in that it includes:
Step one, formation area construction bored concrete pile spots localization drilling, borehole cleaning;
Step 2, makes filling pile cage of reinforcement, welding righting positioner;Righting positioner is the semicircle ring being overlapped between adjacent two sections of steel reinforcement cages;
Step 3, welds bored concrete pile back cover plug steel plate;
Step 4, outsourcing elasticity geotextiles, can be open at righting positioner, elastic geotextiles is located in location centralizing device;
Step 5, geotextiles are fastenedly connected with back cover plug;
Step 6, steel reinforcement cage install tremie placing concrete after putting well.
CN201510592243.3A 2015-09-17 2015-09-17 Karst Fissures region concrete filling pile pours anti-leaking method Pending CN106545015A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510592243.3A CN106545015A (en) 2015-09-17 2015-09-17 Karst Fissures region concrete filling pile pours anti-leaking method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510592243.3A CN106545015A (en) 2015-09-17 2015-09-17 Karst Fissures region concrete filling pile pours anti-leaking method

Publications (1)

Publication Number Publication Date
CN106545015A true CN106545015A (en) 2017-03-29

Family

ID=58362779

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510592243.3A Pending CN106545015A (en) 2015-09-17 2015-09-17 Karst Fissures region concrete filling pile pours anti-leaking method

Country Status (1)

Country Link
CN (1) CN106545015A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984151A (en) * 2019-11-20 2020-04-10 中冶天工集团有限公司 Novel fastening device for cast-in-place pile concrete pouring guide pipe

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1507518A (en) * 1975-10-10 1978-04-19 Higgs & Hill Ltd Pile construction
JP2004360240A (en) * 2003-06-03 2004-12-24 Kubota Corp Joining method for pile head part and footing and structure of its joining part
CN202265821U (en) * 2011-08-26 2012-06-06 中天建设集团有限公司 Positioning structure for protective layer of bored cast-in-place pile
CN203200747U (en) * 2013-04-17 2013-09-18 广州华磊建筑基础工程有限公司 Cast-in-place pile applicable to karst cave geology
CN104612143A (en) * 2014-12-31 2015-05-13 云南建工基础工程有限责任公司 Bored composite pile structure under karst cave/soil cave geological condition

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1507518A (en) * 1975-10-10 1978-04-19 Higgs & Hill Ltd Pile construction
JP2004360240A (en) * 2003-06-03 2004-12-24 Kubota Corp Joining method for pile head part and footing and structure of its joining part
CN202265821U (en) * 2011-08-26 2012-06-06 中天建设集团有限公司 Positioning structure for protective layer of bored cast-in-place pile
CN203200747U (en) * 2013-04-17 2013-09-18 广州华磊建筑基础工程有限公司 Cast-in-place pile applicable to karst cave geology
CN104612143A (en) * 2014-12-31 2015-05-13 云南建工基础工程有限责任公司 Bored composite pile structure under karst cave/soil cave geological condition

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984151A (en) * 2019-11-20 2020-04-10 中冶天工集团有限公司 Novel fastening device for cast-in-place pile concrete pouring guide pipe

Similar Documents

Publication Publication Date Title
US11028574B2 (en) Steel-plate-encased precast concrete column foot joint and construction method therefor
CN104404983B (en) A kind of ride well device and construction method thereof for jacking construction
CN103205964B (en) Cast-in-place pile construction method using steel pipe column splicing piles
CN105862722A (en) Three-dimensional treatment method of subway deep foundation pit in karst intense development region
CN103132537A (en) Steel latticed column homocentric-square-shaped concrete bearing platform combination type tower crane base structure and construction method
CN106759881B (en) Prefabricated column connecting node grouting plugging structure and method
CN103122632A (en) Construction method for drilling hole and casting pile in plastic flow stratum or karst cave stratum
CN103556623B (en) Across the continuous wall construction method of buried heavy civil pipeline
KR101644498B1 (en) Micropile reinforcement structure and Reinforcing method of foot concrete using it
CN105464105B (en) One kind is without friction pile pile making method
CN106545015A (en) Karst Fissures region concrete filling pile pours anti-leaking method
CN109024710A (en) A kind of method for blocking of deep-foundation pit engineering artesian water piping
KR20150025409A (en) the tunnel structure using the small diameter steel pipe and the construction method thereof
CN203654272U (en) Lateral friction boring filling pile for isolation pile
CN204326104U (en) A kind of well device of riding for jacking construction
CN103850251B (en) A kind of Model analysis
CN104060622B (en) Steel drum Yield rainfall relation method is cheated in a kind of hole
KR100977526B1 (en) Small dia. pile and constructure method for it
CN103397637B (en) Pre-embedding method of grouting sleeve under raft foundation
CN102220764A (en) Deep foundation pit bracing system and construction method thereof
CN108999227B (en) Reinforcing structure of building foundation and construction method thereof
JP4373824B2 (en) Joining method of cast-in-place pile and steel pipe column
CN103924599A (en) Method for processing support steel column construction not in place in foundation pits
CN204252168U (en) Circular inspection well protective device
CN206681043U (en) Deep layer mud extraction element

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170329