CN106545015A - Karst Fissures region concrete filling pile pours anti-leaking method - Google Patents
Karst Fissures region concrete filling pile pours anti-leaking method Download PDFInfo
- Publication number
- CN106545015A CN106545015A CN201510592243.3A CN201510592243A CN106545015A CN 106545015 A CN106545015 A CN 106545015A CN 201510592243 A CN201510592243 A CN 201510592243A CN 106545015 A CN106545015 A CN 106545015A
- Authority
- CN
- China
- Prior art keywords
- concrete
- pile
- geotextiles
- righting
- positioner
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The present invention relates to concrete filling pile, more particularly to concrete filling pile casting method.A kind of Karst Fissures region concrete filling pile pours anti-leaking method, and it includes:Step one, formation area construction bored concrete pile spots localization drilling, borehole cleaning;Step 2, makes filling pile cage of reinforcement, welding righting positioner;Righting positioner is the semicircle ring being overlapped between adjacent two sections of steel reinforcement cages;Step 3, welds bored concrete pile back cover plug steel plate;Step 4, outsourcing elasticity geotextiles, can be open at righting positioner, elastic geotextiles is located in location centralizing device;Step 5, geotextiles are fastenedly connected with back cover plug;Step 6, steel reinforcement cage install tremie placing concrete after putting well.The present invention prevents Karst Fissures region drill-pouring pile concrete to be lost in.
Description
Technical field
The present invention relates to concrete filling pile, more particularly to concrete filling pile casting method.
Background technology
When cast-in-situ bored pile is located at formation area construction, because there is rock crack development and karst hole etc. in many places formation area.After pouring pile hole is put into steel reinforcement cage, because the presence in karst hole and crack can be such that the concrete for pouring into is lost in a large number, cause greatly to waste and hidden danger of quality.
The content of the invention
Present invention seek to address that the drawbacks described above of prior art, there is provided a kind of Karst Fissures region concrete filling pile pours anti-leaking method.The present invention prevents Karst Fissures region drill-pouring pile concrete to be lost in.
What the present invention was realized in:A kind of Karst Fissures region concrete filling pile pours anti-leaking method, and it includes:
Step one, formation area construction bored concrete pile spots localization drilling, borehole cleaning;
Step 2, makes filling pile cage of reinforcement, welding righting positioner;Righting positioner is the semicircle ring being overlapped between adjacent two sections of steel reinforcement cages;
Step 3, welds bored concrete pile back cover plug steel plate;
Step 4, outsourcing elasticity geotextiles, can be open at righting positioner, elastic geotextiles is located in location centralizing device;
Step 5, geotextiles are fastenedly connected with back cover plug;
Step 6, steel reinforcement cage install tremie placing concrete after putting well.
Concrete pressure effect after the present invention is poured expands outwardly can elastic geotextiles, be clipped between rock stratum and cast-in-place pile concrete, be brought into close contact therewith, close karst hole and crack, prevent the concrete for pouring into be lost in a large number;Play a part of to isolate karst hole and crack, can guarantee that concrete pouring pile integrity and construction quality again.
Specific embodiment
When making steel reinforcement cage after pore-forming, in steel reinforcement cage bottom, the back cover plug less than pouring pile hole aperture is set, location centralizing device is symmetrically welded in cage bar on the outside of steel reinforcement cage, then outsourcing elasticity geotextiles, geotextiles bottom is fastenedly connected with back cover plug, then steel reinforcement cage is put in priming concrete pile hole, casting concrete, concrete pressure effect after pouring expands outwardly can elastic geotextiles, it is clipped between rock stratum and cast-in-place pile concrete, it is brought into close contact therewith, play a part of to isolate karst hole and crack, concrete pouring pile integrity and construction quality are can guarantee that again.
Claims (1)
1. a kind of Karst Fissures region concrete filling pile pours anti-leaking method, it is characterised in that it includes:
Step one, formation area construction bored concrete pile spots localization drilling, borehole cleaning;
Step 2, makes filling pile cage of reinforcement, welding righting positioner;Righting positioner is the semicircle ring being overlapped between adjacent two sections of steel reinforcement cages;
Step 3, welds bored concrete pile back cover plug steel plate;
Step 4, outsourcing elasticity geotextiles, can be open at righting positioner, elastic geotextiles is located in location centralizing device;
Step 5, geotextiles are fastenedly connected with back cover plug;
Step 6, steel reinforcement cage install tremie placing concrete after putting well.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510592243.3A CN106545015A (en) | 2015-09-17 | 2015-09-17 | Karst Fissures region concrete filling pile pours anti-leaking method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510592243.3A CN106545015A (en) | 2015-09-17 | 2015-09-17 | Karst Fissures region concrete filling pile pours anti-leaking method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106545015A true CN106545015A (en) | 2017-03-29 |
Family
ID=58362779
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510592243.3A Pending CN106545015A (en) | 2015-09-17 | 2015-09-17 | Karst Fissures region concrete filling pile pours anti-leaking method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106545015A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110984151A (en) * | 2019-11-20 | 2020-04-10 | 中冶天工集团有限公司 | Novel fastening device for cast-in-place pile concrete pouring guide pipe |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1507518A (en) * | 1975-10-10 | 1978-04-19 | Higgs & Hill Ltd | Pile construction |
JP2004360240A (en) * | 2003-06-03 | 2004-12-24 | Kubota Corp | Joining method for pile head part and footing and structure of its joining part |
CN202265821U (en) * | 2011-08-26 | 2012-06-06 | 中天建设集团有限公司 | Positioning structure for protective layer of bored cast-in-place pile |
CN203200747U (en) * | 2013-04-17 | 2013-09-18 | 广州华磊建筑基础工程有限公司 | Cast-in-place pile applicable to karst cave geology |
CN104612143A (en) * | 2014-12-31 | 2015-05-13 | 云南建工基础工程有限责任公司 | Bored composite pile structure under karst cave/soil cave geological condition |
-
2015
- 2015-09-17 CN CN201510592243.3A patent/CN106545015A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1507518A (en) * | 1975-10-10 | 1978-04-19 | Higgs & Hill Ltd | Pile construction |
JP2004360240A (en) * | 2003-06-03 | 2004-12-24 | Kubota Corp | Joining method for pile head part and footing and structure of its joining part |
CN202265821U (en) * | 2011-08-26 | 2012-06-06 | 中天建设集团有限公司 | Positioning structure for protective layer of bored cast-in-place pile |
CN203200747U (en) * | 2013-04-17 | 2013-09-18 | 广州华磊建筑基础工程有限公司 | Cast-in-place pile applicable to karst cave geology |
CN104612143A (en) * | 2014-12-31 | 2015-05-13 | 云南建工基础工程有限责任公司 | Bored composite pile structure under karst cave/soil cave geological condition |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110984151A (en) * | 2019-11-20 | 2020-04-10 | 中冶天工集团有限公司 | Novel fastening device for cast-in-place pile concrete pouring guide pipe |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11028574B2 (en) | Steel-plate-encased precast concrete column foot joint and construction method therefor | |
CN104404983B (en) | A kind of ride well device and construction method thereof for jacking construction | |
CN103205964B (en) | Cast-in-place pile construction method using steel pipe column splicing piles | |
CN105862722A (en) | Three-dimensional treatment method of subway deep foundation pit in karst intense development region | |
CN103132537A (en) | Steel latticed column homocentric-square-shaped concrete bearing platform combination type tower crane base structure and construction method | |
CN106759881B (en) | Prefabricated column connecting node grouting plugging structure and method | |
CN103122632A (en) | Construction method for drilling hole and casting pile in plastic flow stratum or karst cave stratum | |
CN103556623B (en) | Across the continuous wall construction method of buried heavy civil pipeline | |
KR101644498B1 (en) | Micropile reinforcement structure and Reinforcing method of foot concrete using it | |
CN105464105B (en) | One kind is without friction pile pile making method | |
CN106545015A (en) | Karst Fissures region concrete filling pile pours anti-leaking method | |
CN109024710A (en) | A kind of method for blocking of deep-foundation pit engineering artesian water piping | |
KR20150025409A (en) | the tunnel structure using the small diameter steel pipe and the construction method thereof | |
CN203654272U (en) | Lateral friction boring filling pile for isolation pile | |
CN204326104U (en) | A kind of well device of riding for jacking construction | |
CN103850251B (en) | A kind of Model analysis | |
CN104060622B (en) | Steel drum Yield rainfall relation method is cheated in a kind of hole | |
KR100977526B1 (en) | Small dia. pile and constructure method for it | |
CN103397637B (en) | Pre-embedding method of grouting sleeve under raft foundation | |
CN102220764A (en) | Deep foundation pit bracing system and construction method thereof | |
CN108999227B (en) | Reinforcing structure of building foundation and construction method thereof | |
JP4373824B2 (en) | Joining method of cast-in-place pile and steel pipe column | |
CN103924599A (en) | Method for processing support steel column construction not in place in foundation pits | |
CN204252168U (en) | Circular inspection well protective device | |
CN206681043U (en) | Deep layer mud extraction element |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170329 |