CN106523015A - Recycling-period ventilating structure for coal face and construction method of recycling-period ventilating structure - Google Patents

Recycling-period ventilating structure for coal face and construction method of recycling-period ventilating structure Download PDF

Info

Publication number
CN106523015A
CN106523015A CN201611223094.4A CN201611223094A CN106523015A CN 106523015 A CN106523015 A CN 106523015A CN 201611223094 A CN201611223094 A CN 201611223094A CN 106523015 A CN106523015 A CN 106523015A
Authority
CN
China
Prior art keywords
recycling
guide duct
period
ventilating structure
pin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611223094.4A
Other languages
Chinese (zh)
Inventor
余兆星
徐再刚
张辉元
杨光友
谢红飞
敖成杭
朱成坦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Panjiang Refined Coal Co Ltd
Original Assignee
Guizhou Panjiang Refined Coal Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Panjiang Refined Coal Co Ltd filed Critical Guizhou Panjiang Refined Coal Co Ltd
Priority to CN201611223094.4A priority Critical patent/CN106523015A/en
Publication of CN106523015A publication Critical patent/CN106523015A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F1/00Ventilation of mines or tunnels; Distribution of ventilating currents
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D19/00Provisional protective covers for working space

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Ventilation (AREA)

Abstract

The invention discloses a recycling-period ventilating structure for a coal face and a construction method of the recycling-period ventilating structure. The ventilating structure comprises a metal net, wind guide pipes and a row of wooden pillars, wherein the metal net is laid under a top plate of a fully-mechanized coal mining surface and covers all hydraulic brackets, the wind guide pipes are arranged at a coal wall support, and the wooden pillars are tightly arrayed between the wind guide pipes and a caving top plate. According to the recycling-period ventilating structure, after the hydraulic brackets are retracted, the top plate of an unprotected area sinks, the wind guide pipes are not extruded to deform by virtue of a triangular space formed by the wind guide pipes, the obstruction effect of the wooden pillars and the shielding effect of the metal net, and a wind channel is formed, so that the normal ventilation during a recycling period is guaranteed, and the problems that a triangular area is blocked and the effective ventilation cannot be guaranteed because the formed triangular area is relatively small or the top plate is crushed due to the high pressure of the top plate are solved. The recycling-period ventilating structure further has the characteristics of being simple in structure, low in cost and convenient, rapid and safe to construct.

Description

A kind of coal-face payoff period aeration structure and its construction method
Technical field
The present invention relates to a kind of coal-face payoff period aeration structure and its construction method, belong to coal-mining technique field.
Background technology
During underground coal mine coal-face is reclaimed at present, usually after face hydraulic support withdrawing is adopted, apply in empty top zone Work intersecting parallels grillage installs pin and individual prop by top plate supporting, forms airflow channel, it is ensured that ventilation, satisfaction scene makes With requiring.When partially recycled face roof pressure is larger, construction cross grillage or installs pin and be unable to effective support top Plate, easily causes empty top zone domain to close, airflow channel is blocked;During the roof cracking of recovery operation face, the spoil that top board leaks down is easy Airflow channel is blocked, normal ventilation is affected.
The content of the invention
The technical problem to be solved in the present invention is:A kind of construction method of coal-face payoff period aeration structure is provided, Easily will so that the spoil leaked down when effective support top board causes airflow channel blocking or roof cracking is unable in solution prior art Airflow channel is blocked and affects the normal problem divulged information.
The technical scheme that the present invention takes is:A kind of coal-face payoff period aeration structure, including wire netting, guide duct And pin, wire netting is laid under the top board of fully mechanized coal face and covers all hydraulic support, and guide duct is arranged at rib side, is being led Airduct and it is caving between top board and lays the compact arranged pin of a row.
A kind of construction method of coal-face payoff period aeration structure, including lay wire netting, withdraw hydraulic support, paving If ventilating duct and pin, which comprises the following steps that:
(1)When fully mechanized coal face back production is to design attitude, start layer of metal net, wire netting are laid between hydraulic support and top board All hydraulic support is covered, until stopping adopting line, is fixedly connected between adjacent two wire nettings;
(2)After work surface withdraws two hydraulic supports, in rib side laying guide duct, adjacent two guide ducts junction is using fixation Connection;
(3)After the completion of guide duct laying, in guide duct and row's pin of constructing is caving between top board;
(4)Repeat step(2)-(3), two hydraulic supports are often withdrawn, guide duct and pin construction working is repeated once, until returning Withdraw from all hydraulic support.
Beneficial effects of the present invention:Compared with prior art, the present invention after hydraulic support withdrawing, push up by empty top zone domain Plate sinks, and as the triangular space for itself being formed adds the effect of blocking of the iris action and wire netting of pin, guide duct is not Can be deformed, form airflow channel, it is ensured that the normal ventilation during recovery, after solving hydraulic support withdrawing, because of top Plate pressure causes greatly the Delta Region of formation itself less or roof cracking causes Delta Region to be blocked, it is impossible to ensure effective The problems such as ventilation, the present invention also have simple structure, low cost, safe convenient and quick construction the characteristics of.
Description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the A-A cross section structure diagrams in Fig. 1;
Fig. 3 is the B-B cross section structure diagrams in Fig. 1.
Specific embodiment
Below in conjunction with the accompanying drawings and specific embodiment is described further to the present invention.
Implement:1:As shown in Figure 1-Figure 3, a kind of coal-face payoff period aeration structure, including wire netting 2, guide duct 3 With pin 4, wire netting 2 is laid under the top board of fully mechanized coal face and covers all hydraulic support 1, and guide duct 3 is arranged at rib side, The compact arranged pin of a row 4 is laid in guide duct 3 and being caving between top board.
Embodiment 2:A kind of construction method of coal-face payoff period aeration structure, including lay wire netting 2, withdraw liquid Pressure support 1, laying ventilating duct 3 and pin 4, which comprises the following steps that:
(1)When fully mechanized coal face back production is to design attitude, start in hydraulic support(1)Layer of metal net 2, gold are laid between top board Category net 2 covers all hydraulic support 1, until stopping adopting line, is fixedly connected between adjacent two wire nettings 2;
(2)After work surface withdraws two hydraulic supports 1, in rib side laying guide duct 3, adjacent two guide ducts, 3 junction is adopted With being fixedly connected;
(3)After the completion of guide duct 3 is laid, in guide duct 3 and row's pin 4 of constructing is caving between top board;
(4)Repeat step(2)-(3), two hydraulic supports 1 are often withdrawn, guide duct 3 and 4 construction working of pin is repeated once, directly To having withdrawn all hydraulic support 1.
The above, the only specific embodiment of the present invention, but protection scope of the present invention is not limited thereto, any Those familiar with the art the invention discloses technical scope in, change or replacement can be readily occurred in, should all be contained Cover within protection scope of the present invention, therefore, protection scope of the present invention should be defined by the scope of the claims.

Claims (2)

1. a kind of coal-face payoff period aeration structure, it is characterised in that:Including wire netting(2), guide duct(3)And pin (4), wire netting(2)It is laid under the top board of fully mechanized coal face and covers all hydraulic support(1), guide duct(3)It is arranged on rib side Place, in guide duct(3)The compact arranged pin of a row is laid with being caving between top board(4).
2. the construction method of a kind of coal-face payoff period aeration structure according to claim 1, it is characterised in that:Bag Include laying wire netting(2), withdraw hydraulic support(1), laying ventilating duct(3)And pin(4), which comprises the following steps that:
(1)When fully mechanized coal face back production is to design attitude, start in hydraulic support(1)Layer of metal net is laid between top board(2), Wire netting(2)Cover all hydraulic support(1), until stopping adopting line, adjacent two wire nettings(2)Between be fixedly connected;
(2)Work surface withdraws two hydraulic supports(1)Afterwards, in rib side laying guide duct(3), adjacent two guide duct(3)Connection Place adopts and is fixedly connected;
(3)Guide duct(3)After the completion of laying, in guide duct(3)Be caving between top board row's pin of constructing(4);
(4)Repeat step(2)-(3), often withdraw two hydraulic supports(1), it is repeated once guide duct(3)With pin(4)Construction work Make, until having withdrawn all hydraulic support(1).
CN201611223094.4A 2016-12-27 2016-12-27 Recycling-period ventilating structure for coal face and construction method of recycling-period ventilating structure Pending CN106523015A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611223094.4A CN106523015A (en) 2016-12-27 2016-12-27 Recycling-period ventilating structure for coal face and construction method of recycling-period ventilating structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611223094.4A CN106523015A (en) 2016-12-27 2016-12-27 Recycling-period ventilating structure for coal face and construction method of recycling-period ventilating structure

Publications (1)

Publication Number Publication Date
CN106523015A true CN106523015A (en) 2017-03-22

Family

ID=58338867

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611223094.4A Pending CN106523015A (en) 2016-12-27 2016-12-27 Recycling-period ventilating structure for coal face and construction method of recycling-period ventilating structure

Country Status (1)

Country Link
CN (1) CN106523015A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288676A (en) * 2017-07-10 2017-10-24 中国矿业大学 Pipe laying method of ventilation during a kind of working face is withdrawn

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4760432B2 (en) * 2006-02-15 2011-08-31 株式会社大林組 Passenger vehicle protection protector and existing tunnel expansion method using this protector
CN103527226A (en) * 2013-10-15 2014-01-22 中国矿业大学 Steeply inclined seam working face shielding and retracing method
CN104389605A (en) * 2014-10-20 2015-03-04 中国矿业大学 Cover retracement method of dense steel wire ropes of coal face
CN104763456A (en) * 2015-03-17 2015-07-08 国投新集能源股份有限公司 Coal mining adit ending roadway or dead region supporting support and hydraulic support withdrawing method
CN104895592A (en) * 2015-05-26 2015-09-09 神华集团有限责任公司 Fully-mechanized coal mining and caving face support retracement supporting method
CN104975857A (en) * 2015-05-21 2015-10-14 中国矿业大学(北京) Full well work area section non-pillar goaf-side-drift-free coal mining method
CN204921004U (en) * 2015-08-12 2015-12-30 山西晋城无烟煤矿业集团有限责任公司 Combine and to adopt working face and remove anchor rope of putting up and strut system
CN206338084U (en) * 2016-12-27 2017-07-18 贵州盘江精煤股份有限公司 A kind of coal-face payoff period aeration structure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4760432B2 (en) * 2006-02-15 2011-08-31 株式会社大林組 Passenger vehicle protection protector and existing tunnel expansion method using this protector
CN103527226A (en) * 2013-10-15 2014-01-22 中国矿业大学 Steeply inclined seam working face shielding and retracing method
CN104389605A (en) * 2014-10-20 2015-03-04 中国矿业大学 Cover retracement method of dense steel wire ropes of coal face
CN104763456A (en) * 2015-03-17 2015-07-08 国投新集能源股份有限公司 Coal mining adit ending roadway or dead region supporting support and hydraulic support withdrawing method
CN104975857A (en) * 2015-05-21 2015-10-14 中国矿业大学(北京) Full well work area section non-pillar goaf-side-drift-free coal mining method
CN104895592A (en) * 2015-05-26 2015-09-09 神华集团有限责任公司 Fully-mechanized coal mining and caving face support retracement supporting method
CN204921004U (en) * 2015-08-12 2015-12-30 山西晋城无烟煤矿业集团有限责任公司 Combine and to adopt working face and remove anchor rope of putting up and strut system
CN206338084U (en) * 2016-12-27 2017-07-18 贵州盘江精煤股份有限公司 A kind of coal-face payoff period aeration structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
湖南省煤炭工业局: "《湖南煤矿开采与安全管理新技术》", 30 June 2011 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288676A (en) * 2017-07-10 2017-10-24 中国矿业大学 Pipe laying method of ventilation during a kind of working face is withdrawn

Similar Documents

Publication Publication Date Title
CN104847355B (en) Continuous mining method for hollow ground of medium-thickness steeply inclined ore body
US20220267974A1 (en) Method for constructing inner dump type strip mine pit bottom reservoirs section by section
CN107060758B (en) A kind of section fender, which stays, sets construction method
CN102661167B (en) Protected seam bottom plate upward comb-shaped drilled hole gas extraction method
CN104234749B (en) A kind of fully-mechanized mining working big cross section return channel surrounding rock control method
CN107956509B (en) Method for preventing wind leakage by stages in roof cutting gob-side entry retaining
CN108222935A (en) Equipment system of roadway-free coal-pillar-free self-retained roadway mining method
WO2018086328A1 (en) Shield support device fully enclosing soil-like coal working face
CN202544925U (en) One-hole dual-purpose tunnel drain hole structure
WO2016206616A1 (en) Equipment system for no-roadway no-coal-pillar retained roadway mining method
CN102677658B (en) hole pile construction method
CN105927232B (en) A kind of mine is without the deeply stifled shallow note grouting method in clear area and slip casting safety device
CN102383830A (en) Comprehensive outburst prevention method for outburst coal seam region
CN103266903B (en) A kind of supporting method of anti-risk top flat side
WO2018094657A1 (en) Hydraulic support for soil-like coal working face, and protection method for coal seam mining
CN104963688B (en) Prevention and control method for falling of pumice at roof and two slopes of stope in medium-long hole mining
CN106523015A (en) Recycling-period ventilating structure for coal face and construction method of recycling-period ventilating structure
RU2514933C1 (en) Method of layer mining of high steeply inclined coal bed with extraction of coal from bedding pack
CN105240012A (en) F-type section coal-mining method allowing commingled mining of coal pillars
CN206338084U (en) A kind of coal-face payoff period aeration structure
CN107701229B (en) Surface mining landfill, which is administered, drains Synergistic method with underground head middle section goaf filling
CN217327382U (en) Integrated excavation working face head-on rib-splitting prevention temporary support system
CN209211392U (en) A kind of hydraulic engineering ecological protection protective slope
CN210768846U (en) Coal mine excavation roadway support device
CN109372519B (en) Tunneling construction method for hexagonal section of roadway

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170322