Base structure for steel bridge field installation temporary support Download PDF

Info

Publication number
CN106522105A
CN106522105A CN201611199137.XA CN201611199137A CN106522105A CN 106522105 A CN106522105 A CN 106522105A CN 201611199137 A CN201611199137 A CN 201611199137A CN 106522105 A CN106522105 A CN 106522105A
Authority
CN
China
Prior art keywords
flange
temporary support
falsework
base structure
round pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611199137.XA
Other languages
Chinese (zh)
Inventor
黄道元
祝建明
张永庆
梁明慧
段常智
李燚红
王希龙
王勇
王超
王庆强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan DR Construction Group Co Ltd
Original Assignee
Henan DR Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan DR Construction Group Co Ltd filed Critical Henan DR Construction Group Co Ltd
Priority to CN201611199137.XA priority Critical patent/CN106522105A/en
Publication of CN106522105A publication Critical patent/CN106522105A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/02Scaffold feet, e.g. with arrangements for adjustment

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a base structure for a steel bridge field installation temporary support. The base structure comprises a temporary support. A vertical round pipe is arranged at the center of the upper surface of a bottom plate. A flange matched with a flange at the lower end of the temporary support is arranged at the upper end of the vertical round pipe. The flange at the upper end of the vertical round pipe is provided with a hole opposite to a screw hole in the flange at the lower end of the temporary support. Reinforcing rib plates are evenly distributed between the bottom plate outside the vertical round pipe and the flange on the vertical round pipe. Compared with the prior art, the base structure has the significant advantages of being short in construction period and low in cost.

Description

A kind of steel bridge in-site installation falsework understructure
Technical field
The present invention relates to a kind of base, particularly a kind of steel bridge in-site installation falsework understructure.
Background technology
During steel structure bridge in-site installation, falsework to be used, this falsework are made up of four vertical duct, pipe Between be provided with connected support structure, the lower end of each pipe is provided with flange, due to the gravity born when mounted by support it is very big, need to be Four concrete beds are done on ground, pre-buried screw relative with the screw hole of end flanges under falsework on base, by falsework It is fixed on concrete pad, after steel structure bridge builds up, dismounting falsework is standby, needs to be torn open each base on ground Remove, both wasted reinforcing bar and cement, and waste of time.
The content of the invention
It is an object of the invention to provide a kind of cost-effective and reusable base.
The technical scheme is that, a kind of steel bridge in-site installation falsework understructure, including falsework, its It is characterised by:The center of plate upper surface is provided with vertical pipe, and the upper end of this vertical pipe is provided with and the falsework The flange that lower end flanges match, the flange of vertical pipe upper end are provided with the screw hole phase on the flange with falsework lower end To hole, be evenly equipped with reinforcement gusset between the flange on base plate and vertical pipe outside vertical pipe.
The present invention has the remarkable advantage of short construction period and low cost compared with the prior art.
Description of the drawings
Fig. 1 is the front view of the present invention;Fig. 2 is the top view of Fig. 1.
Specific embodiment
In order to solve the defect that above-mentioned prior art is present, using technical scheme as shown in Figure 1-2, the centre of base plate 1 A vertical pipe 3 is provided with, flange 4 is fixed on the upper end of the pipe, is provided with and falsework lower end on the flange outside pipe The corresponding hole of screw hole on flange, has been evenly distributed reinforcement gusset 2, between the flange on base plate and pipe the bottom of due to Very big its area of the weight of plate load-bearing is sufficiently large, and the base plate is placed on the cement layer on ground.
The using method of the present invention, four bases are individually placed on ground, and falsework is hung to base by lifting appliance Top, the flange of falsework lower end is placed on base flange, and after making the alignment of each screw hole, just can be thrown with screw fastening Enter to use.After bridge builds up, remove falsework after, base is just removable, can also afterwards bridge construction when use.

Claims (1)

1. a kind of steel bridge in-site installation falsework understructure, including falsework, it is characterised in that:Plate upper surface Center is provided with vertical pipe, and the upper end of this vertical pipe is provided with the flange matched with end flanges under the falsework, erects To the flange of pipe upper end be provided with the hole relative with the screw hole on the flange of falsework lower end, outside vertical pipe Base plate and vertical pipe on flange between be evenly equipped with reinforcement gusset.
CN201611199137.XA 2016-12-22 2016-12-22 Base structure for steel bridge field installation temporary support Pending CN106522105A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611199137.XA CN106522105A (en) 2016-12-22 2016-12-22 Base structure for steel bridge field installation temporary support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611199137.XA CN106522105A (en) 2016-12-22 2016-12-22 Base structure for steel bridge field installation temporary support

Publications (1)

Publication Number Publication Date
CN106522105A true CN106522105A (en) 2017-03-22

Family

ID=58341282

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611199137.XA Pending CN106522105A (en) 2016-12-22 2016-12-22 Base structure for steel bridge field installation temporary support

Country Status (1)

Country Link
CN (1) CN106522105A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476293A (en) * 2009-01-16 2009-07-08 广东省长大公路工程有限公司 Non-stand construction method for large bridge arch rib
KR20090130798A (en) * 2008-06-16 2009-12-24 (주)씨디텍엔지니어링 Temporary bridge construction system using a steel pipe structure
KR20100099495A (en) * 2009-03-03 2010-09-13 (주)에스앤씨산업 Central connecting apparatus engaged with lattice type steel pipe pile and construction method of assembling slab bridge using the same
CN201704632U (en) * 2010-06-24 2011-01-12 郑州市第一建筑工程集团有限公司 Sand-cylinder-type temporary support for bridge construction
CN102953337A (en) * 2012-04-01 2013-03-06 吴钦凡 Bridge construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090130798A (en) * 2008-06-16 2009-12-24 (주)씨디텍엔지니어링 Temporary bridge construction system using a steel pipe structure
CN101476293A (en) * 2009-01-16 2009-07-08 广东省长大公路工程有限公司 Non-stand construction method for large bridge arch rib
KR20100099495A (en) * 2009-03-03 2010-09-13 (주)에스앤씨산업 Central connecting apparatus engaged with lattice type steel pipe pile and construction method of assembling slab bridge using the same
CN201704632U (en) * 2010-06-24 2011-01-12 郑州市第一建筑工程集团有限公司 Sand-cylinder-type temporary support for bridge construction
CN102953337A (en) * 2012-04-01 2013-03-06 吴钦凡 Bridge construction method

Similar Documents

Publication Publication Date Title
CN201695681U (en) Integral self-elevating type elevator hoistway tube mold
CN103526929A (en) Super high-rise steel pipe column interior concrete pouring construction method
CN105178330B (en) Underground structure post-cast strip support replacement method
CN204151823U (en) Along building the one-sided cantilever hydraulic template trolley of side wall under covered back-digging structural slab
CN201738250U (en) Arch culvert and arch ring steel die trolley
CN109944435A (en) A kind of formwork-support and construction method for the construction of silo conical shell
CN207296408U (en) Portable concrete constructional column irrigation device
CN104499706B (en) Hoistway formwork platform and construction method thereof
CN103552911B (en) A kind of movable boom hoisting and the construction installation method of use thereof
KR20100073881A (en) Dummy bearing for bridge using sand and upper structure of bridge supporting method thterewith
CN203462754U (en) Free-disassembly suspension template
CN106522105A (en) Base structure for steel bridge field installation temporary support
CN210061545U (en) Prefabricated T roof beam concrete placement platform truck
CN206337508U (en) A kind of steel bridge in-site installation falsework understructure
KR101452403B1 (en) Mold for manufacturing covering block, method for manufacturing covering block, covering block using thereof and the structures constructed by covering block
CN206267520U (en) A kind of self-supporting post-cast strip is poured with hanging mould
CN202645000U (en) Discarding and scattering prevention device for pumped concrete discharge pipe orifice
CN205314539U (en) Large -scale cantilever type combination steel form
CN205976472U (en) Pour mould of building post -cast strip
CN204626965U (en) For the steel stair template of poured up at a time between architectural stair
CN210975566U (en) Temporary supporting structure for suspended basket pier top of cast-in-place bridge
CN103174299A (en) An installment and construction method of laminate rubber support and flat plate slipping support
CN213297137U (en) Formwork reinforcing device for improving concrete construction quality of falling plate type toilet
CN110130634A (en) Umbrella shape high-supported formwork supporting arrangement and its assembly and disassembly methods
CN206607580U (en) A kind of steel reinforcement cage hanging steel bar of reusable edible

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170322