- container
- chemical fertilizer
- scarfing
- fertilizer
- kilograms
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G67/00—Loading or unloading vehicles
- B65G67/60—Loading or unloading ships
- B65G67/606—Loading or unloading ships using devices specially adapted for bulk material
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65B—MACHINES, APPARATUS OR DEVICES FOR, OR METHODS OF, PACKAGING ARTICLES OR MATERIALS; UNPACKING
- B65B69/00—Unpacking of articles or materials, not otherwise provided for
- B65B69/0008—Opening and emptying bags
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65B—MACHINES, APPARATUS OR DEVICES FOR, OR METHODS OF, PACKAGING ARTICLES OR MATERIALS; UNPACKING
- B65B69/00—Unpacking of articles or materials, not otherwise provided for
- B65B69/0033—Unpacking of articles or materials, not otherwise provided for by cutting
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Aviation & Aerospace Engineering (AREA)
- Fertilizers (AREA)
- Refuse-Collection Vehicles (AREA)
Abstract
The present invention provides a kind of less than 50 kilograms bagged chemical fertilizer scarfing shipment methods, and the method includes following steps:The scarfing of less than 50 kilograms fertilizer bags;The fill of chemical fertilizer in bulk;The assembling and connection of lifting spreader;The lifting of container with topple over.The effect of the present invention is the shipment ability that can play company's existing equipment using the method, realizes that shipment tonnage is 2000 ton days.Before this shipment method, low due to loading efficiency onto ship, it is only 800 ton days per lines.After using the method, daily shipload increases by 1200 tons, monthly reach 3.6 ten thousand tons, improve work efficiency 20%.In the case of dispersion fertilizer ample supply and prompt delivery, take receipts standard by existing, you can nearly 1,700,000 yuan for company's extra earning.
Description
Technical field
The present invention relates to a kind of less than 50 kilograms bagged chemical fertilizer scarfing shipment methods.
Background technology
Pouch (50 kilogram/bag) chemical fertilizer export volume was more and more in recent years, and domestic various places transport is more to be transported to using highway
Then harbour, pile of unloading is transported to ship side using platform trailer again to goods yard, the owner of cargo require pouch to cut after by chemical fertilizer with
Form in bulk loads ship.This operating type needs to set up the bulk goods job platform that band is slipped through the net on the hatch of ship, first
Pouch chemical fertilizer is lifted to platform, pouch is cut by workman with scarfing blade, then workman catches two jiaos of the base of pouch, will
Chemical fertilizer in pouch by slipping through the net to cabin on platform, the debris such as empty bag that cuts handling time ship side.This shipment
Method needs to put into substantial amounts of operating worker, and working environment is severe, and platform needs the connection for carrying out safety and firmness with ship,
Cause non-cutting time long, man-machine consumption is big, and working performance is low;Job platform input amount is big, causes handling instrument cost to increase;Cabin
, there is workman and the hidden danger such as fall in the job platform limited area on mouth and densely populated place;Marline in operation process and
The debris such as blade are easily fallen in the chemical fertilizer in bulk in cabin, affect cargo mass, the disadvantage in these operations to make to shipping unit
Into serious harmful effect.
Content of the invention
For the disadvantage in the not enough and operation of existing bulk goods job platform quantity, it is an object of the invention to provide a kind of 50
The shipment method of bagged chemical fertilizer scarfing below kilogram, on the premise of harbour handling cost is not increased, improves the shipment of pouch chemical fertilizer
Efficiency, reduces ship in the port stopping time, while mitigating company's man-machine operation's pressure, slows down company goods yard and stores up pressure, promote company
The raising of economic benefit.
For achieving the above object, the technical solution used in the present invention is to provide a kind of less than 50 kilograms bagged chemical fertilizer scarfings dress
Ship's method, the method include following steps:
Step one, the scarfing of less than 50 kilograms fertilizer bags
1.. using fork truck by less than pile up 50 kilograms fertilizer bag scrapers on job platform, operating worker stands in flat
The outside of platform unloading port 1, lifts two jiaos of less than 50 kilograms fertilizer bags, puts it in platform unloading port 1.
2. less than .50 kilogram fertilizer bag falls into the scarfing machine for facing and stocks up in mouth 2, by scarfing from platform unloading port 1
Less than 50 kilograms fertilizer bag broken bags are made bagged chemical fertilizer become in bulk by the blade in machine, and the packaging bag that cuts enters scarfing machine and deposits
Put in bucket 3.
3.. chemical fertilizer in bulk falls on belt conveyor 4, is transported to funnel 5 by belt feeder.
Step 2, the fill of chemical fertilizer in bulk
1.. before chemical fertilizer fill in bulk, container carrier is in assigned position;
2.. container case mouth 6 is network structure, and which is docked at the underface of funnel 5, and chemical fertilizer in bulk pours into threading from there
Internal container.Fill starts front operating personnel will be locked for container side door 7.
3.. check whether the opening and closing device of funnel 5 is normal.
4.. when operation starts, operating worker is opened the switch of funnel 5 and starts blowing, and blowing total amount reaches tank-volumes
After loading the upper limit, the switch of funnel 5 is closed.
5.. container vehicle starts vehicle equipped with two section containers after above the fill of first segment container is finished
Move ahead, 6 pairs, the case mouth of second section container is made just in the lower section of funnel 5.
6.. after the whole fills of two section containers are finished, container carrier is transported to ship side.
Step 3, the assembling of lifting spreader and connection
1.. strut bar 9 is welded rectangular using channel-section steel, and strut bar is respectively welded with two shackle plates about 9, interior for hollow, has
Two.
2.. upper hoist cable 8 and lower hoist cable 10 are steel wire rope making, and nose is hung with closed ring in two ends, upper hoist cable 8 and lower hoist cable
10 respectively have four, and the top of every strut bar 9 is hung nose by one end of shackle 12 and upper hoist cable 8 and is attached, and bottom passes through shackle
12 hang nose with one end of lower hoist cable 10 is attached.
3.. base angle twist lock 11 is made for steel alloy, and bottom is provided with bearing pin 11-1, is connected with rotary handle by bearing pin 11-1
11-2 and closing piece 11-3, base angle twist lock 11 hang nose by shackle 12 with the other end of lower hoist cable 10 and are connected.
4.. operating personnel first by two strut bars 9 perpendicular to container body length direction, then by the another of upper hoist cable 8
Hang nose and be attached with the steel wire rope of door machine in one end.
5.. the hand-held base angle twist lock 11 of operating personnel, rotary handle 11-2 is adjusted to after vertical direction, closing piece 11-3 is pushed away
Enter container feet lockhole, make twist lock 11 main body in base angle be adjacent to container surface, then rotary handle 11-2 is rotated to level side
To, the locked fixations of closing piece 11-3 are made, operational approach is by four base angle twist locks 11 locked 4 bottoms in packaging lower box part respectively according to this
In the lockhole of angle.
Step 4, the lifting of container and topple over
1.. operating personnel by locked for four base angle twist locks 11 and check errorless after, door machine driver can be by commanding's
Container is steadily lifted by crane by gesture.
2.. container hoisting away from 1.8 meters of ground when, door machine driver will stop raising, treat operating personnel by container bottom
After surrounding carries out dedusting cleaning, then secondary carry out lifting operation.
3.. container body lifting will keep balancing, and forbid container body colliding vessel hatch and gear;
4.. container is entered when carrying out toppling over chemical fertilizer operation in cabin, and container body will align cabin mouth, and door machine driver will
Container is slowly dropped down onto in cabin, and container side door 7 is opened by operating personnel, and container body is slowly promoted to door machine driver 2
After meter Gao Du, by control door machine steel wire rope raising or lower general who has surrendered's container body in chemical fertilizer topple over totally.
5.. after in container body, chemical fertilizer is toppled over totally, operating personnel will be locked for container side door 7, and commander's finger waves door
Empty container handling is gone back to ship side by machine driver.
6.. after ship side transported back by empty van, rotary handle 11-2 is adjusted to vertical direction by operating personnel, makes container Special-purpose hanger
Tool releases locking state, and four closing piece 11-3 of operation handlebar are pulled out from four base angle lockholes of packaging lower box part according to this, container
Empty van is transported stockyard back and proceeds fill operation.
The effect of the present invention is the shipment ability that can play company's existing equipment using the method, realizes that shipment tonnage is
2000 ton days.Before this shipment method, low due to loading efficiency onto ship, it is only 800 ton days per lines.After using the method, per
Its shipload increases by 1200 tons, monthly reach 3.6 ten thousand tons, improve work efficiency 20%.In the case of dispersion fertilizer ample supply and prompt delivery,
Take receipts standard by existing, you can nearly 1,700,000 yuan for company's extra earning.
Description of the drawings
Fig. 1 is the scarfing and fill schematic diagram of the present invention;
Fig. 2 is the lifting schematic diagram of the present invention;
Fig. 3-1,3-2 are the structural representations of lifting device;
Fig. 4 is the operation schematic diagram of the present invention.
In figure:
1. platform unloading port 2, scarfing machine is stocked up mouth 3,4. belt conveyor of scarfing machine storage compartment
5. 9. strut bar of hoist cable on 6. 7. container side door of container case mouth of funnel, 8. steel wire rope
10. 11. base angle twist lock of hoist cable, 12. shackle 11-1. bearing pin 11-2. rotary handles under steel wire rope
11-3. closing pieces
Specific embodiment
Less than the 50 kilograms bagged chemical fertilizer scarfing shipment methods of the present invention are illustrated in conjunction with accompanying drawing.
As shown in Fig. 1,2,3-1,3-2,4, the operation of less than the 50 kilograms bagged chemical fertilizer scarfing shipment methods of the present invention
Journey is as follows:
Step one, the scarfing of less than 50 kilograms fertilizer bags
1.. using fork truck by less than pile up 50 kilograms fertilizer bag scrapers on job platform, operating worker stands in flat
The outside of platform unloading port 1, lifts two jiaos of less than 50 kilograms fertilizer bags, puts it in platform unloading port 1.
2. less than .50 kilogram fertilizer bag falls into the scarfing machine for facing and stocks up in mouth (2), by cutting from platform unloading port 1
Less than 50 kilograms fertilizer bag broken bags are made bagged chemical fertilizer become in bulk by the blade in mouth machine, and the packaging bag that cuts enters scarfing machine
In storage compartment 3.
3.. chemical fertilizer in bulk falls on belt conveyor 4, is transported to funnel 5 by belt feeder.
Step 2, the fill of chemical fertilizer in bulk
1.. before chemical fertilizer fill in bulk, container carrier is docked at assigned position.
2.. container case mouth 6 is network structure, and which is docked at the underface of funnel 5, and chemical fertilizer in bulk pours into threading from there
Internal container.Fill starts front operating personnel will be locked for container side door 7.
3.. check whether the opening and closing device of funnel 5 is normal.
4.. when operation starts, operating worker is opened the switch of funnel 5 and starts blowing, and blowing total amount reaches tank-volumes
After loading the upper limit, the switch of funnel 5 is closed.
5.. container vehicle starts vehicle equipped with two section containers after above the fill of first segment container is finished
Move ahead, 6 pairs, the case mouth of second section container is made just in the lower section of funnel 5.
6.. after the whole fills of two section containers are finished, container carrier is transported to ship side.
Step 3, the assembling of lifting spreader and connection
1.. strut bar 9 is welded rectangular using channel-section steel, and strut bar is respectively welded with two shackle plates about 9, interior for hollow, has
Two.
2.. upper hoist cable 8 and lower hoist cable 10 are steel wire rope making, and nose is hung with closed ring in two ends, upper hoist cable 8 and lower hoist cable
10 respectively have four, and the top of every strut bar 9 is hung nose by one end of shackle 12 and upper hoist cable 8 and is attached, and bottom passes through shackle
12 hang nose with one end of lower hoist cable 10 is attached.
3.. base angle twist lock 11 is made for steel alloy, and bottom is provided with bearing pin 11-1, is connected with rotary handle by bearing pin 11-1
11-2 and closing piece 11-3, base angle twist lock 11 hang nose by shackle 12 with the other end of lower hoist cable 10 and are connected.
4.. operating personnel first by two strut bars 9 perpendicular to container body length direction, then by the another of upper hoist cable 8
Hang nose and be attached with the steel wire rope of door machine in one end.
5.. the hand-held base angle twist lock 11 of operating personnel, rotary handle 11-2 is adjusted to after vertical direction, closing piece 11-3 is pushed away
Enter container feet lockhole, make twist lock 11 main body in base angle be adjacent to container surface, then rotary handle 11-2 is rotated to level side
To, the locked fixations of closing piece 11-3 are made, operational approach is by four base angle twist locks 11 locked 4 bottoms in packaging lower box part respectively according to this
In the lockhole of angle.
Step 4, the lifting of container and topple over
1.. operating personnel by locked for four base angle twist locks 11 and check errorless after, door machine driver can be by commanding's
Container is steadily lifted by crane by gesture.
2.. container hoisting away from 1.8 meters of ground when, door machine driver will stop raising, treat operating personnel by container bottom
After surrounding carries out dedusting cleaning, then secondary carry out lifting operation.
3.. container body lifting will keep balancing, and forbid container body colliding vessel hatch and gear;
4.. container is entered when carrying out toppling over chemical fertilizer operation in cabin, and container body will align cabin mouth, and door machine driver will
Container is slowly dropped down onto in cabin, and container side door 7 is opened by operating personnel, and container body is slowly promoted to door machine driver 2
After meter Gao Du, by control door machine steel wire rope raising or lower general who has surrendered's container body in chemical fertilizer topple over totally.
5.. after in container body, chemical fertilizer is toppled over totally, operating personnel will be locked for container side door 7, and commander's finger waves door
Empty container handling is gone back to ship side by machine driver.
6.. after ship side transported back by empty van, rotary handle 11-2 is adjusted to vertical direction by operating personnel, makes container Special-purpose hanger
Tool releases locking state, and four closing piece 11-3 of operation handlebar are pulled out from four base angle lockholes of packaging lower box part according to this, container
Empty van is transported stockyard back and proceeds fill operation.
Less than the 50 kilograms bagged chemical fertilizer scarfing shipment methods of the present invention are specifically realized in:
First, the scarfing of less than 50 kilograms bagged chemical fertilizers
1. the unitized pallet for having piled up pouch chemical fertilizer is shoveled and takes and be placed on job platform by truck driver;
2. job platform is mounted below scarfing machine, and the unloading port of platform faces the mouth of stocking up of scarfing machine.Before operation, should
Guarantee the safe erect-position of operating worker on platform, and be tied seat belt.
3. less than 50 kilograms bagged chemical fertilizers are lifted and are sent to the unloading port of platform by operating worker;Truck driver will be made the return trip empty
Unitized pallet shovel be put into cargo storage area.
Less than 4.50 kilograms bagged chemical fertilizers enter into the mouth of stocking up of scarfing machine from the unloading port of platform, and scarfing machine automatically will be little
Bag is cut, and chemical fertilizer is scattering on following belt conveyor, and the packaging bag that cuts is fallen in the storage compartment of scarfing drive end unit.
5., when workman is toward unloading port input goods, once a bag, at the uniform velocity throws in, it is to avoid goods is excessive in scarfing machine, affect
Packaging bag is separated with goods.
6. guarantee that platform unloading port and scarfing machine are stocked up the aligning of mouth, and prevent goods from deviateing, cause which enter scarfing
Machine.
2nd, it is changed into the fill of chemical fertilizer in bulk after scarfing
1. conveying of the chemical fertilizer after in bulk by belt feeder, is transported in funnel.
2. guarantee that funnel bottom has been switched off, without any debris in funnel.
3. before operation starts, container vehicle is docked to center position below funnel first, check container side door
Whether lock.
4. operating worker manipulates the switch below funnel, opens funnel, starts blowing, makes chemical fertilizer in bulk pass through container top
Slipping through the net for portion is filled in container.
5., after chemical fertilizer filled by container, workman closes funnel switch, and Container Transport driver is by vehicle transport to ship side.
3rd, the shipment of chemical fertilizer in bulk
(1) operation prepares
1., before operation, operation team group is in advance by the special hanger that gets and Active workings are cleaned up.
2. ship side operating personnel hangs up properly zone face safety net.
3. ship side operating personnel should coordinate a machine driver to be connected the raising rope of four rope door machines with lifting spreader
Firmly, determine on inspection errorless after, operation can be carried out.
4. special strut bar is connected with door machine steel wire rope by operating personnel perpendicular to container body length direction, then by four
Individual base angle closing piece is pushed in container base lifting hole(eyelet), makes twist lock main body be adjacent to container surface, then the rotary handle of twist lock is revolved
Horizontal level is gone to, its locked fixation, door machine driver can be steadily lifted by crane by the gesture of commanding.
5. loaded van lifting away from 1.8 meters of ground when, raising to be stopped treats that bottom surrounding is carried out dedusting cleaning by operating personnel
Afterwards, then row lifting operation.
6. loaded van raising or operation when, keep balancing, the skyborne vertical equity inclination angle of casing not should be greater than 5 °.
7. the light case that makes the return trip empty of ship-loading operation, is closed container side door after locking by ship side operating personnel, and fork truck will be in time
Empty van scraper is gone back to stockyard.
(2) shipboard operation
1. during container ship-loading operation, door machine driver is harmonious with commanding, forbids casing collision hatch and ship
Tool.
2., when cargo operation is toppled in container shipment, casing will align hatch, and door machine driver slowly drops down onto casing in cabin,
Container door is opened by operating worker.After casing to be slowly promoted to door machine driver 2 meters of height, goods in case is toppled over totally.
3. goods stowage operation, should follow first surrounding, after carry out when the operation principle equilibrium in cabin.In cabin, workman will be mixed with
Substantially the goods of impurity is chosen, and loads container bag and concentrates and goes ashore, accomplish one class one clear.
4., during topping off, operating personnel strictly will dress protective articless on request, will obtain recognizing for ship after trim
Can visa.
5., during ship-loading operation, meet and spill goods on deck, one class one clear, concentration is gone ashore, and forbids to pour cabin into
Interior.
6. after the completion of in case, chemical fertilizer is toppled over, container side door is closed locking by operating personnel, commands door machine driver by empty van
Handling goes out cabin.
Claims (1)
1. a kind of less than 50 kilograms bagged chemical fertilizer scarfing shipment methods, the method include following steps:
Step one, the scarfing of less than 50 kilograms fertilizer bags
1.. using fork truck by less than pile up 50 kilograms fertilizer bag scrapers on job platform, operating worker stands in platform and falls
The outside of goods mouth (1), lifts two jiaos of less than 50 kilograms fertilizer bags, puts it in platform unloading port (1);
2. less than .50 kilogram fertilizer bag falls into the scarfing machine for facing and stocks up in mouth (2), by scarfing from platform unloading port (1)
Less than 50 kilograms fertilizer bag broken bags are made bagged chemical fertilizer become in bulk by the blade in machine, and the packaging bag that cuts enters scarfing machine and deposits
Put in bucket (3);
3.. chemical fertilizer in bulk falls on belt conveyor (4), is transported to funnel (5) by belt feeder;
Step 2, the fill of chemical fertilizer in bulk
1.. before chemical fertilizer fill in bulk, container carrier is in assigned position;
2.. container case mouth (6) is network structure, and which is docked at the underface of funnel (5), and chemical fertilizer in bulk pours into threading from there
Internal container.Fill starts front operating personnel will be locked for container side door 7;
3.. check whether the opening and closing device of funnel (5) is normal;
4.. when operation starts, operating worker is opened the switch of funnel (5) and starts blowing, and blowing total amount reaches the dress of tank-volumes
After carrying the upper limit, the switch of funnel (5) is closed;
5.. container vehicle saves containers equipped with two, after above the fill of first segment container is finished, before starting vehicle
OK, the case mouth (6) of second section container is made to just in the lower section of funnel (5);
6.. after the whole fills of two section containers are finished, container carrier is transported to ship side;
Step 3, the assembling of lifting spreader and connection
1.. strut bar (9) is welded rectangular using channel-section steel, and strut bar (9) is respectively welded with two shackle plates up and down, interior for hollow, has
Two;
2.. upper hoist cable (8) and lower hoist cable (10) are steel wire rope making, and nose is hung with closed ring in two ends, upper hoist cable (8) and under hang
Rope (10) respectively has four, and the top of every strut bar (9) is hung nose by one end of shackle (12) and upper hoist cable (8) and is attached, under
Nose is hung by one end of shackle (12) and lower hoist cable (10) and is attached in portion;
3.. base angle twist lock (11) is made for steel alloy, and bottom is provided with bearing pin (11-1), is connected with rotation handss by bearing pin (11-1)
Handle (11-2) and closing piece (11-3), base angle twist lock (11) hang nose by shackle (12) with the other end of lower hoist cable (10) and are connected;
4.. operating personnel first by two strut bars (9) perpendicular to container body length direction, then by the another of upper hoist cable (8)
Hang nose and be attached with the steel wire rope of door machine in one end;
5.. operating personnel is hand-held base angle twist lock (11), and rotary handle (11-2) is adjusted to after vertical direction, by closing piece (11-3)
Push container feet lockhole, make base angle twist lock (11) main body be adjacent to container surface, then by rotary handle (11-2) rotate to
Horizontal direction, makes the locked fixation of closing piece (11-3), and operational approach will be locked in container respectively for four base angle twist locks (11) according to this
In 4 base angle lockholes of bottom;
Step 4, the lifting of container and topple over
1.. operating personnel by locked for four base angle twist locks (11) and check errorless after, door machine driver can be by the handss of commanding
Will definitely container steadily lift by crane;
2.. container hoisting away from 1.8 meters of ground when, door machine driver will stop raising, treat operating personnel by container bottom surrounding
After carrying out dedusting cleaning, then secondary carry out lifting operation;
3.. container body lifting will keep balancing, and forbid container body colliding vessel hatch and gear;
4.. container is entered in cabin when carrying out toppling over chemical fertilizer operation, and container body will align cabin mouth, and door machine driver is by packaging
Case is slowly dropped down onto in cabin, and container side door (7) is opened by operating personnel, and container body is slowly promoted to door machine driver 2 meters
After height, by control door machine steel wire rope raising or lower general who has surrendered's container body in chemical fertilizer topple over totally;
5.. after in container body, chemical fertilizer is toppled over totally, operating personnel will be locked for container side door (7), and commander's finger waves a machine
Empty container handling is gone back to ship side by driver;
6.. after ship side transported back by empty van, rotary handle (11-2) is adjusted to vertical direction by operating personnel, makes lifting spreader
Locking state is released, four closing pieces (11-3) of operation handlebar are pulled out from four base angle lockholes of packaging lower box part according to this, container
Empty van is transported stockyard back and proceeds fill operation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610854927.0A CN106494913B (en) | 2016-11-23 | 2016-11-23 | 50 kilograms or less bagged chemical fertilizer scarfing shipment methods |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610854927.0A CN106494913B (en) | 2016-11-23 | 2016-11-23 | 50 kilograms or less bagged chemical fertilizer scarfing shipment methods |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106494913A true CN106494913A (en) | 2017-03-15 |
CN106494913B CN106494913B (en) | 2018-08-28 |
Family
ID=58290537
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610854927.0A Active CN106494913B (en) | 2016-11-23 | 2016-11-23 | 50 kilograms or less bagged chemical fertilizer scarfing shipment methods |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106494913B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106882612A (en) * | 2017-04-14 | 2017-06-23 | 蔡健珊 | To inland river bulk freighter unload the operational method and platform of direct Stuff (to) |
CN109592117A (en) * | 2018-11-29 | 2019-04-09 | 天津港物流发展有限公司 | Found box Bulk Grain Stuff (to) method for loading and unloading and bulk grain binning funnel |
CN114229521A (en) * | 2021-12-02 | 2022-03-25 | 唐山港集团港机船舶维修有限公司 | Container tilting lifting appliance for portal crane |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1343607A (en) * | 2001-01-22 | 2002-04-10 | 天津港第二港埠有限公司 | Method and apparatus for pouring bulk material in bags at port |
FR2861714A1 (en) * | 2003-11-04 | 2005-05-06 | Eurotech | Object e.g. bag with commodities, loading process, involves transferring layers constituted on upper flap on to empty pallet at start of loading cycle, where subsequent layer is constituted on flap while bringing pallet to loading station |
CN202046465U (en) * | 2011-04-02 | 2011-11-23 | 张辉 | Bag unpacking machine of high efficiency with automatic bag loading function |
CN204642343U (en) * | 2015-06-02 | 2015-09-16 | 姚常鹏 | Steamed sandwich crushing conveyor structure concentrated by a kind of harbour chemical fertilizer |
CN105711894A (en) * | 2016-04-25 | 2016-06-29 | 安丘博阳机械制造有限公司 | Marine packaging and conveying mechanism and process thereof |
-
2016
- 2016-11-23 CN CN201610854927.0A patent/CN106494913B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1343607A (en) * | 2001-01-22 | 2002-04-10 | 天津港第二港埠有限公司 | Method and apparatus for pouring bulk material in bags at port |
FR2861714A1 (en) * | 2003-11-04 | 2005-05-06 | Eurotech | Object e.g. bag with commodities, loading process, involves transferring layers constituted on upper flap on to empty pallet at start of loading cycle, where subsequent layer is constituted on flap while bringing pallet to loading station |
CN202046465U (en) * | 2011-04-02 | 2011-11-23 | 张辉 | Bag unpacking machine of high efficiency with automatic bag loading function |
CN204642343U (en) * | 2015-06-02 | 2015-09-16 | 姚常鹏 | Steamed sandwich crushing conveyor structure concentrated by a kind of harbour chemical fertilizer |
CN105711894A (en) * | 2016-04-25 | 2016-06-29 | 安丘博阳机械制造有限公司 | Marine packaging and conveying mechanism and process thereof |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106882612A (en) * | 2017-04-14 | 2017-06-23 | 蔡健珊 | To inland river bulk freighter unload the operational method and platform of direct Stuff (to) |
CN109592117A (en) * | 2018-11-29 | 2019-04-09 | 天津港物流发展有限公司 | Found box Bulk Grain Stuff (to) method for loading and unloading and bulk grain binning funnel |
CN114229521A (en) * | 2021-12-02 | 2022-03-25 | 唐山港集团港机船舶维修有限公司 | Container tilting lifting appliance for portal crane |
Also Published As
Publication number | Publication date |
---|---|
CN106494913B (en) | 2018-08-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106458437B (en) | It is used to support the transport of agent and the equipment of storage | |
AU2023202763A1 (en) | System of delivering and storing proppant for use at a well site and container for such proppant | |
CN106494913B (en) | 50 kilograms or less bagged chemical fertilizer scarfing shipment methods | |
CN111727157B (en) | Lightweight transport, storage and delivery system | |
CN105600180A (en) | Cargo shipping container with top-access roof cover | |
US10793349B2 (en) | Intermodal storage and transportation container | |
CN208747439U (en) | A kind of vertical rotary lifting of container | |
CN108675104A (en) | A kind of cantilevered railway container is vertical to turn handling facilities and operational method | |
AU2014100919A4 (en) | Apparatus and Method for Containerised bulk Handling to load and discharge dry bulk goods | |
AU2013100395B4 (en) | Structure for use with container-handling apparatus | |
CN108657935A (en) | A kind of straddle-type railway container is vertical to turn handling facilities and operational method | |
CN101575077A (en) | Method for transporting bagged materials | |
CN106882612A (en) | To inland river bulk freighter unload the operational method and platform of direct Stuff (to) | |
AU2014100229A4 (en) | Structure for use with container-handling apparatus | |
CN111994772A (en) | Container turning hanger system and application method thereof | |
CN102020119A (en) | Method and device for simultaneously filling bulk cargos in two containers | |
CN206562188U (en) | The automatic lower boat equipment of urea ton packaging | |
CN206654575U (en) | To inland river bulk freighter unload the job platform of direct Stuff (to) | |
CN106276295A (en) | A kind of handling way of transportation for harbour outlet chemical fertilizer | |
RU76442U1 (en) | MIXING CHARGING MACHINE | |
CN205916808U (en) | Standdle carrier railway carriage or compartment doffer on loading funnel | |
CN215478483U (en) | Turnover container loading machine | |
CN110271882A (en) | A kind of transfer platform of automatic dock gantry crane crane | |
US3107802A (en) | Side discharging containers and vehicles | |
CN217706637U (en) | Portable chemical fertilizer cuts a packet device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |