CN106481083A - 一种球形建筑钢结构的安装方法 - Google Patents

一种球形建筑钢结构的安装方法 Download PDF

Info

Publication number
CN106481083A
CN106481083A CN201510520226.9A CN201510520226A CN106481083A CN 106481083 A CN106481083 A CN 106481083A CN 201510520226 A CN201510520226 A CN 201510520226A CN 106481083 A CN106481083 A CN 106481083A
Authority
CN
China
Prior art keywords
installation
layer
crossbeam
ring
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510520226.9A
Other languages
English (en)
Inventor
陈爱坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huaye Group Co Ltd
North China Metallurgical Construction Engineering Construction Co Ltd
Original Assignee
China Huaye Group Co Ltd
North China Metallurgical Construction Engineering Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huaye Group Co Ltd, North China Metallurgical Construction Engineering Construction Co Ltd filed Critical China Huaye Group Co Ltd
Priority to CN201510520226.9A priority Critical patent/CN106481083A/zh
Publication of CN106481083A publication Critical patent/CN106481083A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明涉及一种球形建筑钢结构的安装方法,其包括以下步骤:(1)基础检查验收,测量点定位;(2由下至上安装钢柱,每层安装完后,再安装上一层;(3)钢柱安装先外环、再中环、然后外环与中环之间横梁、最后内环及内环与中环之间的横梁,按此顺序依次完成下一个截面,再联接两截面之间横梁,形成平面结构,依此类推,完成本层平面后,交予土建进行平台施工;(4)重复步骤(2)~(3)完成上一层结构安装,直至结构施工到顶;(5)顶部为网壳结构,网壳安装先以室内结构桁架中心部位开始为拼装起点,向四周扩展拼装焊接,然后开始提升,直至提升达到设计标高并完成拼装;(6)网壳就位、找正、焊接全部完成,经检验合格后进行结构卸载。

Description

一种球形建筑钢结构的安装方法
技术领域
本发明属于建筑工程技术领域,具体涉及一种球形建筑钢结构的安装方法。
背景技术
近年来民用建筑中的异型钢结构逐渐增多,而异型钢结构的安装较常规结构安装难度大,技术水平要求高,安装工艺复杂。
在球形钢结构施工中,难度较大的是弧型钢柱的安装及屋面结构的安装。以鄂尔多斯低碳谷研究院工程为例说明:1#楼建筑面积42000m2,呈不规则鸭蛋形,以中轴线对称,长轴约91m,短轴约72m,地下一层,地上五层,建筑高度29.6m,顶盖为钢拱,竖向为折线形钢结构,顶盖结构为空间钢网架结构,外形为椭圆形结构,面积67m×51m;钢结构之间采用钢管相贯焊结,结构所用材料规格为Φ159-Φ325mm的无缝钢管,每格网架网格尺寸4m×4m、四/三角网形状不等,网架正中心点与支座部位落差约7m,整个屋面网架支撑在四周28根箱型结构钢柱上。
发明内容
发明目的:本发明针对上述现有技术存在的问题做出改进,即本发明公开了一种球形建筑钢结构的安装方法。
技术方案:一种球形建筑钢结构的安装方法,包括以下步骤:
(1)基础检查验收,测量点定位;
(2)钢结构钢柱采取由下至上的安装顺序,每层安装完后,再安装上一层,每吊装层都分两个作业面同时对称进行;
(3)钢柱安装先外环,再中环,然后外环与中环之间横梁,最后内环及内环与中环之间的横梁,按此顺序依次完成下一个截面,再联接两截面之间横梁,形成平面结构,依此类推,完成本层平面后,交予土建进行平台施工;
(4)重复步骤(2)~(3)完成上一层结构安装,直至结构施工到顶;
(5)顶部为网壳结构,网壳安装先以室内结构桁架中心部位开始为拼装起点,向四周扩展拼装焊接,然后开始提升,直至提升达到设计标高并完成拼装;
(6)网壳就位、找正、焊接全部完成,经检验合格后进行结构卸载。
进一步,弧形钢柱安装时采用支撑及钢索临时固定。
进一步地,步骤(5)中网壳的安装包括以下步骤:
(51)在地面上预定位置设置8组拔杆,每组拔杆设置4个吊装点;
(52)将屋盖结构提升到设计标高处,然后向外扩展,与28根支撑柱连接,
(53)全部安装完成合格后进行结构卸载。
有益效果:本发明公开的一种球形建筑钢结构的安装方法具有以下有益效果
(1)、优化安装工序,使安装工艺更加合理。弧形钢柱安装采用分段安装,临时支撑及钢拉索固定措施,待一层完成后,再施工上一层,大大减少了临时支架的使用量,降低了措施费用;
(2)、针对工程的具体情况,结合当前的施工技术水平,采用网壳整体吊装的施工工艺,用格构式拔杆作为网壳提升设备,它有拆卸方便、提升重量大、安全系数高等优点。此办法代替了满堂红脚手架操作平台,提高了安全系数,降低了施工措施成本。
(3)、传统的施工工艺,弧形钢柱整体安装,采作临时支架作为安装支撑架,每一钢柱吊装前都要把支架安装好,需要临时支架数量多,完工后才能拆除,措施成本高,而采用本方法,大大降低了支架的使用量,降低了措施成本。穹顶网壳安装采用满堂红脚手架作为操作平台,在上面安装网壳,需要成本高,施工安全系数低,此方法应用提高了施工安全性,降低了施工成本,提高了项目效益。
附图说明
图1为弧形钢柱的安装示意图;
图2为网壳的示意图。
具体实施方式:
下面对本发明的具体实施方式详细说明。
一种球形建筑钢结构的安装方法,包括以下步骤:
(1)基础检查验收,测量点定位;
(2)钢结构钢柱采取由下至上的安装顺序,每层安装完后,再安装上一层,每吊装层都分两个作业面同时对称进行;
(3)钢柱安装先外环,再中环,然后外环与中环之间横梁,最后内环及内环与中环之间的横梁,按此顺序依次完成下一个截面,再联接两截面之间横梁,形成平面结构,依此类推,完成本层平面后,交予土建进行平台施工;
(4)重复步骤(2)~(3)完成上一层结构安装,直至结构施工到顶;
(5)顶部为网壳结构(如图2所示),网壳安装先以室内结构桁架中心部位开始为拼装起点,向四周扩展拼装焊接,然后开始提升,直至提升达到设计标高并完成拼装;
(6)网壳就位、找正、焊接全部完成,经检验合格后进行结构卸载。
进一步,弧形钢柱安装时采用支撑及钢索临时固定。
如图1所示,钢柱的地下部分按要求安装完毕。B环钢柱地上部分分为下、中、上三节。先安装B环钢柱下节(含地上一层和地上二层),为增加下节钢柱安装的稳定度,在地上一层钢柱悬挑梁下加设临时支撑。B环钢柱下节就位固定后,安装B-1环钢柱,B-1环钢柱从+1.02米标高往上整体吊装。B-1环钢柱安装就位后,安装B环至B-1环问平台梁及A环钢柱。
A环钢柱地上部分也分下、中、上三节,先安装A环钢柱下节(含地上一层和地上二层)为增加A环钢柱下节的安装稳度,在地上一层钢柱悬挑梁下及地下一层平台梁上焊接临时拉环,增加临时拉索。A环钢柱下节安装就位后安装B-1环至A环间平台梁。
一层、二层钢结构安装完成,形成封闭的结构后即拆除临时支撑和临时拉索。三层、四层钢结构的安装同一、二层钢结构。五层钢结构A轴钢柱、B轴钢柱及A轴与B轴间的钢梁组装成整体后吊装(也可分开成散件吊装,步骤方法同三、四层)。
进一步地,步骤(5)中网壳的安装包括以下步骤:
(51)在地面上预定位置设置8组拔杆,每组拔杆设置4个吊装点;
(52)将屋盖结构提升到设计标高处,然后向外扩展,与28根支撑柱连接,
(53)全部安装完成合格后进行结构卸载。
关于卸载的进一步说明:
(1)卸载前,卸掉所有临时荷载,对网架进行全面检查,确认周圈焊接无漏点;
(2)现场焊缝超声波检验合格后方可卸载;
(3)8个支架32个吊点卸载同时进行;
(4)卸载分阶段进行,每次松开20mm,进行一次测量检查;
(5)卸载必须统一指挥,统一操作;
(6)卸载后,复测网架最后高度和起拱度,作为最终资料。
上面对本发明的实施方式做了详细说明。但是本发明并不限于上述实施方式,在所属技术领域普通技术人员所具备的知识范围内,还可以在不脱离本发明宗旨的前提下做出各种变化。

Claims (3)

1.一种球形建筑钢结构的安装方法,其特征在于,包括以下步骤:
(1)基础检查验收,测量点定位;
(2)钢结构钢柱采取由下至上的安装顺序,每层安装完后,再安装上一层,每吊装层都分两个作业面同时对称进行;
(3)钢柱安装先外环,再中环,然后外环与中环之间横梁,最后内环及内环与中环之间的横梁,按此顺序依次完成下一个截面,再联接两截面之间横梁,形成平面结构,依此类推,完成本层平面后,交予土建进行平台施工;
(4)重复步骤(2)~(3)完成上一层结构安装,直至结构施工到顶;
(5)顶部为网壳结构,网壳安装先以室内结构桁架中心部位开始为拼装起点,向四周扩展拼装焊接,然后开始提升,直至提升达到设计标高并完成拼装;
(6)网壳就位、找正、焊接全部完成,经检验合格后进行结构卸载。
2.根据权利要求1所述的一种球形建筑钢结构的安装方法,其特征在于,弧形钢柱安装时采用支撑及钢索临时固定。
3.根据权利要求1所述的一种球形建筑钢结构的安装方法,其特征在于,步骤(5)中网壳的安装包括以下步骤:
(51)在地面上预定位置设置8组拔杆,每组拔杆设置4个吊装点;
(52)将屋盖结构提升到设计标高处,然后向外扩展,与28根支撑柱连接,
(53)全部安装完成合格后进行结构卸载。
CN201510520226.9A 2015-08-24 2015-08-24 一种球形建筑钢结构的安装方法 Pending CN106481083A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510520226.9A CN106481083A (zh) 2015-08-24 2015-08-24 一种球形建筑钢结构的安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510520226.9A CN106481083A (zh) 2015-08-24 2015-08-24 一种球形建筑钢结构的安装方法

Publications (1)

Publication Number Publication Date
CN106481083A true CN106481083A (zh) 2017-03-08

Family

ID=58233151

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510520226.9A Pending CN106481083A (zh) 2015-08-24 2015-08-24 一种球形建筑钢结构的安装方法

Country Status (1)

Country Link
CN (1) CN106481083A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107575032A (zh) * 2017-07-18 2018-01-12 江苏绿色辉煌节能科技有限公司 一种螺栓球网架屋面安装方法
CN113323154A (zh) * 2021-06-10 2021-08-31 中国建筑第八工程局有限公司 带悬挑结构的单层网壳结构罩棚的施工方法
CN114482381A (zh) * 2022-02-17 2022-05-13 中建八局新型建造工程有限公司 用于穹顶钢结构的散件安装方法
CN115012679A (zh) * 2022-06-10 2022-09-06 中国五冶集团有限公司 球体钢结构内挑钢柱的空间定位和安装方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001146813A (ja) * 1999-11-22 2001-05-29 Mitsubishi Heavy Ind Ltd ドーム屋根旋回工法及び格点構造
CN102425326A (zh) * 2011-09-14 2012-04-25 徐州中煤百甲重钢结构有限公司 螺栓球网架筒壳储料仓逆安装施工工艺
CN102518204A (zh) * 2011-12-19 2012-06-27 江苏沪宁钢机股份有限公司 一种大佛宝盖及其制作方法
CN103711322A (zh) * 2014-01-19 2014-04-09 芜湖天航科技(集团)股份有限公司 一种悬挑安装大跨度半球形网壳的施工方法
CN204356970U (zh) * 2014-12-26 2015-05-27 江苏沪宁钢机股份有限公司 基于混凝土建筑的单层网壳钢结构屋面系统

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001146813A (ja) * 1999-11-22 2001-05-29 Mitsubishi Heavy Ind Ltd ドーム屋根旋回工法及び格点構造
CN102425326A (zh) * 2011-09-14 2012-04-25 徐州中煤百甲重钢结构有限公司 螺栓球网架筒壳储料仓逆安装施工工艺
CN102518204A (zh) * 2011-12-19 2012-06-27 江苏沪宁钢机股份有限公司 一种大佛宝盖及其制作方法
CN103711322A (zh) * 2014-01-19 2014-04-09 芜湖天航科技(集团)股份有限公司 一种悬挑安装大跨度半球形网壳的施工方法
CN204356970U (zh) * 2014-12-26 2015-05-27 江苏沪宁钢机股份有限公司 基于混凝土建筑的单层网壳钢结构屋面系统

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107575032A (zh) * 2017-07-18 2018-01-12 江苏绿色辉煌节能科技有限公司 一种螺栓球网架屋面安装方法
CN113323154A (zh) * 2021-06-10 2021-08-31 中国建筑第八工程局有限公司 带悬挑结构的单层网壳结构罩棚的施工方法
CN114482381A (zh) * 2022-02-17 2022-05-13 中建八局新型建造工程有限公司 用于穹顶钢结构的散件安装方法
CN114482381B (zh) * 2022-02-17 2024-04-16 中建八局新型建造工程有限公司 用于穹顶钢结构的散件安装方法
CN115012679A (zh) * 2022-06-10 2022-09-06 中国五冶集团有限公司 球体钢结构内挑钢柱的空间定位和安装方法

Similar Documents

Publication Publication Date Title
CN106481083A (zh) 一种球形建筑钢结构的安装方法
CN106759883B (zh) 大型钢结构空冷塔的塔吊施工方法
CN106836498A (zh) 一种超大跨度体育场看台屋盖钢桁架吊装施工工法
CN102913137B (zh) 一种凿井钢管井架及该凿井钢管井架的安装方法
CN107090932A (zh) 基于劲性环梁的大跨度薄壁平面拱桁架的施工方法
CN106284663A (zh) 一种椭圆形弦支穹顶结构的施工方法
CN106337501A (zh) 一种拱形网壳倒装提升安装方法
CN105298100A (zh) 一种筒体建筑超高现浇外飘结构悬挑施工平台的施工方法
CN110374200A (zh) 大跨度刚度不均匀混合网架高空散装方法
CN109138454A (zh) 一种超高层建筑外框带状桁架的安装方法
CN106193780A (zh) 一种分段高耸钢结构建筑的总体安装方法
CN115613699B (zh) 一种钢铝组合式单层曲面网壳结构及施工方法
CN111691681A (zh) 斜交钢管网格柱外框筒体结构安装方法
CN105804400A (zh) 一种曲面网架提升施工方法
CN103352576A (zh) 中/小跨度钢结构屋面网架外扩拼装转换提升方法
CN108166660B (zh) 一种曲面单层网壳结构安装方法
CN109853964A (zh) 一种用于钢结构钢筋混凝土混合结构的施工方法
CN108842954A (zh) 一种翼型屋面巨型异截面蜂窝梁结构体系安装施工方法
CN111997191B (zh) 异形钢结构的安装方法及钢网架结构的安装方法
CN104775363B (zh) 上塔柱钢筋节段的组拼方法
CN105863173A (zh) 一种采光顶的安装方法
CN102926547B (zh) 一种曲面屋面网架安装方法
CN105239804B (zh) 一种间接空冷系统展宽平台组合吊装安装方法
CN1109176C (zh) 原子能发电设施的建设施工方法
CN114941433B (zh) 一种大重量船型采光顶钢结构的施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170308

RJ01 Rejection of invention patent application after publication