CN106468152B - A kind of thick oil horizontal well intensity adjustable shutoff method - Google Patents

A kind of thick oil horizontal well intensity adjustable shutoff method Download PDF

Info

Publication number
CN106468152B
CN106468152B CN201510501778.5A CN201510501778A CN106468152B CN 106468152 B CN106468152 B CN 106468152B CN 201510501778 A CN201510501778 A CN 201510501778A CN 106468152 B CN106468152 B CN 106468152B
Authority
CN
China
Prior art keywords
agent
weight percent
gel particle
blocking agent
strength
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510501778.5A
Other languages
Chinese (zh)
Other versions
CN106468152A (en
Inventor
张丁涌
全宏
万惠平
张江
张学军
毕志峰
许德广
刘凯
刘小亮
孙超
石明明
张红丽
殷寄萍
张涛
王杨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Chemical Corp
Sinopec Shengli Oilfield Co Xianhe Oil Production Plant
Original Assignee
China Petroleum and Chemical Corp
Sinopec Shengli Oilfield Co Xianhe Oil Production Plant
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Chemical Corp, Sinopec Shengli Oilfield Co Xianhe Oil Production Plant filed Critical China Petroleum and Chemical Corp
Priority to CN201510501778.5A priority Critical patent/CN106468152B/en
Publication of CN106468152A publication Critical patent/CN106468152A/en
Application granted granted Critical
Publication of CN106468152B publication Critical patent/CN106468152B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention provides a kind of thick oil horizontal well intensity adjustable shutoff method, which includes the following steps:A. stifled tune layer position is determined by testing water detection technology;Plug agent amount and construction parameter are calculated using ellipsoid model:The blocking agent is gelled plugging agent, gel particle suspension gelled plugging agent and high-strength gel particle blocking agent;B. first injection gelled plugging agent deep water blockoff, c. are then injected into gel particle suspension gelled plugging agent and realize that strength is blocked, and d. finally injects the sealing of high-strength gel particle blocking agent.It is suitble to cold adopt of thick oil horizontal well that can be efficiently entering earth formation deep with thermal recovery water blockoff, different slug combinations, has the characteristics that water blockoff intensity height, high temperature resistant, water blockoff success rate are high, produces term of validity length, while construction risk is greatly lowered.

Description

A kind of thick oil horizontal well intensity adjustable shutoff method
Technical field
The invention belongs to oil-field thick-oil production technique field more particularly to a kind of thick oil horizontal well shutoff methods.
Background technology:
Since thick oil horizontal well has apparent advantage, the horizontal well technologies such as recovery ratio height, control reserve height to have become compared with straight well For one of the major technique of heavy oil development.With going deep into for oil field development, by edge-bottom water invasion, reservoir heterogeneity, more rounds The factors such as handle up influence, and thick oil horizontal well is aqueous to be increased year by year, high water-cut well increases year by year.Thick oil horizontal well water blockoff becomes viscous crude Oil reservoir development urgent problem to be solved.
Thick oil horizontal well water-plugging technology mainly uses water pack off and chemical water shutoff.Site operation uses same type blocking agent When, it tends to be difficult to meet the remote requirement adjusted and closely blocked up;When using multiple slugs, often fail to realize blocking agent performance, plugging strength Proper Match.Mainly have in terms of viscous crude water blockoff at present the particulate species such as traditional cements blocking agent, high temperature organogel, thermosetting resin, Gel particle blocking agent, foam class water shutoff agent.The wherein particulate species such as traditional cements blocking agent there are grain sizes big, non-selectivity, easily causes The shortcomings that reservoir damage;Thermosetting resin non-selectivity, curing rate are very sensitive to temperature, poor controllability;Gel particle is stifled Agent can not inject earth formation deep;Foam class water shutoff agent plugging strength is low, to invading well bad adaptability in strong side water.
Easily it is detained in horizontal well well section in short, current thick oil horizontal well water blockoff is primarily present blocking agent, the resistance to temperature difference, blocks half Diameter is small, construction risk is big, the low success rate of deficiency of water blockoff.
Invention content:
The purpose of the present invention, which is intended to overcome, overcomes the deficiencies of the prior art and provide that a kind of water blockoff intensity is high, water blockoff success rate Height, construction risk are small, deep can be achieved blocks up tune, heat safe thick oil horizontal well intensity adjustable shutoff method.
The purpose of the present invention can be achieved by the following technical measures:
The shutoff method includes the following steps:
A. it applies PNN, SNP etc. to test water detection technology accurately to judge to be discharged position and remaining oil distribution situation, improves water blockoff Specific aim, guidance optimization plug agent amount block slug, pressure control, stay and fill in length etc.;It improves to block water flooding degree, water breakthrough The whole understanding of situation.
According to reservoir physical parameter, well section length, blocking agent performance characteristics, using ellipsoid model, optimization calculates classification note The different plug agent amounts and construction parameter entered;
1. calculating plug agent amount using ellipsoid model
In formula, V-plug agent amount, m3;K-high permeable strip ratio, %;H-reservoir effective thickness, m;
R-blocking agent releases radius, m;L-screen casing segment length, m;Φ-effecive porosity, %;
2. construction parameter
Injection pressure:Blocking agent must be injected under the conditions of less than formation fracture pressure.When construction based on injection test pressure, 3~5MPa of pressure of climbing.It requires injection pressure to be slightly above discharged stressor layer simultaneously, ensures that the blocking agent of injection enters in the horizontal direction Earth formation deep;
Injection rate:Consider that formation contaminant wants small, note speed wants low;The construction time is taken into account, therefore injection rate again cannot be too It is low.Injection rate is optimized for 8~10m3/ h is advisable;
The blocking agent is gelled plugging agent, gel particle suspension gelled plugging agent and high-strength gel particle blocking agent;It should Blocking agent has the characteristics that:60 DEG C of low temperature become can plastic, 200 DEG C are not broken glue, I grade of gelling strength, into deep solidification, the blocking agent Injection is good, can enter water breakthrough channel forward position and form water blocking barrier;
B. gelled plugging agent deep water blockoff is first injected, the selective deep water blockoff in remote well area, the frozen glue class are carried out The phenol-formaldehyde resin modified that modified polyacrylamide that blocking agent is 0.2~0.8 by weight percent, weight percent are 0.3~1.3 Crosslinking agent, the chromium class crosslinking agent that weight percent is 0.2~1.2 add water mixture to form;
60 DEG C of low temperature of the blocking agent can plastic, 200 DEG C not break glue, I grade of gelling strength, into deep solidification.The system is injected Property it is good, can enter water breakthrough channel forward position formed water blocking barrier.
C. it is then injected into gel particle suspension gelled plugging agent and realizes that strength is blocked, hot setting is formed to have and centainly be oozed Saturating rate blocks slug, the modified polypropene acyl that the gel particle suspension gelled plugging agent is 1~2 by weight percent Amine, weight percent are 10~30, grain size is the cement of 400~800 mesh, weight percent is 0.2~0.8 phenolic resin, The organic chrome cross linker that weight percent is 0.1~0.9 adds water mixture to form;
Crosslinking agent is added after modified polyacrylamide and small particle cement mixture in the blocking agent, improves gel particle suspension Property and adsorption capacity, enhancing enter depth of stratum, form high intensity colloid mixture, not dehydration shrinkage at the formation temperature.Simultaneously System 106um sieves rate, can be effectively by the sand screen that sand block precision is 130um, into ground layer depth up to 100% Portion, absorption is resident, forms plug water construction main force water blockoff slug.
D. finally injection high-strength gel particle blocking agent sealing, quick dehydration consolidation, forms strength and seals in controllable time Mouthful, modified polyacrylamide that the high-strength gel particle blocking agent is 1~2 by weight percent, weight percent 20 ~40, grain size is that the cement plus water mixture of 400~800 mesh forms.
The blocking agent high temperature resistant, high intensity, thermostabilization, which changes with the concentration of solid phase particles, when effectively control suspends Between, after injecting near wellbore zone, in controllable time, quick dehydration forms high-strength sealing, forms protective layer to preposed attributives, together When the blocking agent have the characteristics that easily bore plug, processing time is short, be convenient for the later stage construction processing.
The purpose of the present invention can be also achieved by the following technical measures:
Further, the modified polyacrylamide, again that the gelled plugging agent described in b step is 0.4~0.6 by weight percent The chromium class crosslinking agent that phenol-formaldehyde resin modified crosslinking agent that amount percentage is 0.7~0.9, weight percent are 0.7~0.9 adds water mixed With into.
Further, the modification that the gel particle suspension gelled plugging agent described in step c is 1.4~1.6 by weight percent Polyacrylamide, weight percent are 18~20, grain size is the cement of 400~800 mesh, weight percent is 0.4~0.6 to change Property phenolic resin crosslinking agent, weight percent be 0.5~0.7 chromium class crosslinking agent add water mixture to form.
Further, the modification poly- third that the high-strength gel particle blocking agent described in Step d is 1.4~1.6 by weight percent The cement plus water mixture that acrylamide, weight percent are 28~30, grain size is 400~800 mesh forms.
The present invention adjusted layer position using test water detection technology is clearly stifled before this, then ellipsoid model computational methods was used to optimize Plug agent amount and construction parameter, it is different to blocking agent performance requirement again according to horizontal well reservoir different depth, adjust close block up in line with remote Principle, take classification inject, give full play to blocking agent performance.It is injected separately into difference in earth formation deep, zone of transition, near wellbore zone The blocking agent of type realizes the intensity adjustable water blockoff to change from weak to strong, first injects gelled plugging agent deep water blockoff, is then injected into gel particle Suspension system realizes that strength is blocked, and finally injects the sealing of high-strength gel granular system.
The intensity adjustable shutoff method of the present invention can be suitble to thick oil horizontal well is cold to adopt and hot compared with current common water-plugging technology Water blockoff is adopted, different slug combinations can be efficiently entering earth formation deep, have water blockoff intensity height, high temperature resistant, water blockoff success rate height, production The feature of term of validity length, while construction risk is greatly lowered, it can be achieved that the stifled tune in deep.
Description of the drawings
Fig. 1 is that the plug agent amount optimization of the present invention calculates ellipsoid model schematic diagram.
Specific implementation mode:
Embodiment 1:
The shutoff method includes the following steps:
A. it applies PNN, SNP etc. to test water detection technology accurately to judge to be discharged position and remaining oil distribution situation, improves water blockoff Specific aim, guidance optimization plug agent amount block slug, pressure control, stay and fill in length etc.;It improves to block water flooding degree, water breakthrough The whole understanding of situation.
According to reservoir physical parameter, well section length, blocking agent performance characteristics, using ellipsoid model, optimization calculates classification note The different plug agent amounts and construction parameter entered.
Plug agent amount optimization is calculated to be calculated using ellipsoid model:
In formula, V-plug agent amount (m3);K-high permeable strip ratio (%);H-reservoir effective thickness (m);R-blocking agent Release radius (m);L-sieve tube segment (perforated interval) length (m);Φ-active porosity (%).
Injection pressure:Blocking agent must be injected under the conditions of less than formation fracture pressure.When construction based on injection test pressure, 3~5MPa of pressure of climbing.It requires injection pressure to be slightly above discharged stressor layer simultaneously, ensures that the blocking agent of injection enters in the horizontal direction Earth formation deep.
Injection rate:Consider that formation contaminant wants small, note speed wants low;The construction time is taken into account, therefore injection rate again cannot be too It is low.Injection rate is optimized for 8m3/ h is advisable.
The blocking agent is gelled plugging agent, gel particle suspension gelled plugging agent and high-strength gel particle blocking agent;
B. it uses gelled plugging agent to squeeze, carries out the selective deep water blockoff in remote well area.The gelled plugging agent by Phenol-formaldehyde resin modified crosslinking agent that modified polyacrylamide that weight percent is 0.8, weight percent are 0.3, weight percent Than adding water mixture to form for 1.2 chromium class crosslinking agent;
C. gel particle suspension system is used to squeeze zone of transition, hot setting forms blocking with certain permeability Slug.The gel particle suspension gelled plugging agent by weight percent be 1~2 modified polyacrylamide, weight percent Than be 0.2 for cement that 10, grain size is 800 mesh, weight percent phenolic resin, weight percent be 0.9 Organic Chromium hand over Connection agent adds water mixture to form;
D. high-strength gel granular system is used to squeeze near wellbore zone, quick dehydration consolidation, forms strong in controllable time Power is sealed.Modified polyacrylamide that the high-strength gel particle blocking agent is 2 by weight percent, weight percent are 20, grain size is that the cement plus water mixture of 800 mesh forms.
Embodiment 2:
The shutoff method includes the following steps:
A. it applies PNN, SNP etc. to test water detection technology accurately to judge to be discharged position and remaining oil distribution situation, improves water blockoff Specific aim, guidance optimization plug agent amount block slug, pressure control, stay and fill in length etc.;It improves to block water flooding degree, water breakthrough The whole understanding of situation.
According to reservoir physical parameter, well section length, blocking agent performance characteristics, using ellipsoid model, optimization calculates classification note The different plug agent amounts and construction parameter entered.
Plug agent amount optimization is calculated to be calculated using ellipsoid model:
In formula, V-plug agent amount (m3);K-high permeable strip ratio (%);H-reservoir effective thickness (m);R-blocking agent Release radius (m);L-sieve tube segment (perforated interval) length (m);Φ-active porosity (%).
Injection pressure:Blocking agent must be injected under the conditions of less than formation fracture pressure.When construction based on injection test pressure, 3~5MPa of pressure of climbing.It requires injection pressure to be slightly above discharged stressor layer simultaneously, ensures that the blocking agent of injection enters in the horizontal direction Earth formation deep.
Injection rate:Consider that formation contaminant wants small, note speed wants low;The construction time is taken into account, therefore injection rate again cannot be too It is low.Injection rate is optimized for 10m3/ h is advisable.
The blocking agent is gelled plugging agent, gel particle suspension gelled plugging agent and high-strength gel particle blocking agent;
B. it uses gelled plugging agent to squeeze, carries out the selective deep water blockoff in remote well area.The gelled plugging agent by Phenol-formaldehyde resin modified crosslinking agent that modified polyacrylamide that weight percent is 0.2, weight percent are 1.3, weight percent Than adding water mixture to form for 0.2 chromium class crosslinking agent;
C. gel particle suspension system is used to squeeze zone of transition, hot setting forms blocking with certain permeability Slug.Modified polyacrylamide that the gel particle suspension gelled plugging agent is 1 by weight percent, weight percent are 30, the organic chrome cross linker that grain size is the cement of 400 mesh, weight percent is 0.8 phenolic resin, weight percent are 0.1 Water mixture is added to form;
D. high-strength gel granular system is used to squeeze near wellbore zone, quick dehydration consolidation, forms strong in controllable time Power is sealed.Modified polyacrylamide that the high-strength gel particle blocking agent is 2 by weight percent, weight percent 20 ~40, grain size is that the cement plus water mixture of 400~800 mesh forms.
Embodiment 3:
The shutoff method includes the following steps:
A. it applies PNN, SNP etc. to test water detection technology accurately to judge to be discharged position and remaining oil distribution situation, improves water blockoff Specific aim, guidance optimization plug agent amount block slug, pressure control, stay and fill in length etc.;It improves to block water flooding degree, water breakthrough The whole understanding of situation.
According to reservoir physical parameter, well section length, blocking agent performance characteristics, using ellipsoid model, optimization calculates classification note The different plug agent amounts and construction parameter entered.
Plug agent amount optimization is calculated to be calculated using ellipsoid model:
In formula, V-plug agent amount (m3);K-high permeable strip ratio (%);H-reservoir effective thickness (m);R-blocking agent Release radius (m);L-sieve tube segment (perforated interval) length (m);Φ-active porosity (%).
Injection pressure:Blocking agent must be injected under the conditions of less than formation fracture pressure.When construction based on injection test pressure, 3~5MPa of pressure of climbing.It requires injection pressure to be slightly above discharged stressor layer simultaneously, ensures that the blocking agent of injection enters in the horizontal direction Earth formation deep.
Injection rate:Consider that formation contaminant wants small, note speed wants low;The construction time is taken into account, therefore injection rate again cannot be too It is low.Injection rate is optimized for 9m3/ h is advisable.
The blocking agent is gelled plugging agent, gel particle suspension gelled plugging agent and high-strength gel particle blocking agent;
B. it uses gelled plugging agent to squeeze, carries out the selective deep water blockoff in remote well area.The gelled plugging agent by Phenol-formaldehyde resin modified crosslinking agent that modified polyacrylamide that weight percent is 0.5, weight percent are 0.8, weight percent Than adding water mixture to form for 0.8 chromium class crosslinking agent;
C. gel particle suspension system is used to squeeze zone of transition, hot setting forms blocking with certain permeability Slug.Modified polyacrylamide, weight percent of the gel particle suspension gelled plugging agent by weight percent for 1.5 For cement that 20, grain size is 800 mesh, weight percent be 0.5 phenolic resin, weight percent be 0.5 organic chrominum cross-linkage Agent adds water mixture to form;
D. high-strength gel granular system is used to squeeze near wellbore zone, quick dehydration consolidation, forms strong in controllable time Power is sealed.Modified polyacrylamide that the high-strength gel particle blocking agent is 1 by weight percent, weight percent are 40, grain size is that the cement plus water mixture of 400 mesh forms.
Embodiment 4:
The shutoff method includes the following steps:
A. it applies PNN, SNP etc. to test water detection technology accurately to judge to be discharged position and remaining oil distribution situation, improves water blockoff Specific aim, guidance optimization plug agent amount block slug, pressure control, stay and fill in length etc.;It improves to block water flooding degree, water breakthrough The whole understanding of situation.
According to reservoir physical parameter, well section length, blocking agent performance characteristics, using ellipsoid model, optimization calculates classification note The different plug agent amounts and construction parameter entered.
Plug agent amount optimization is calculated to be calculated using ellipsoid model:
In formula, V-plug agent amount (m3);K-high permeable strip ratio (%);H-reservoir effective thickness (m);R-blocking agent Release radius (m);L-sieve tube segment (perforated interval) length (m);Φ-active porosity (%).
Injection pressure:Blocking agent must be injected under the conditions of less than formation fracture pressure.When construction based on injection test pressure, 3~5MPa of pressure of climbing.It requires injection pressure to be slightly above discharged stressor layer simultaneously, ensures that the blocking agent of injection enters in the horizontal direction Earth formation deep.
Injection rate:Consider that formation contaminant wants small, note speed wants low;The construction time is taken into account, therefore injection rate again cannot be too It is low.Injection rate is optimized for 8~10m3/ h is advisable.
The blocking agent is gelled plugging agent, gel particle suspension gelled plugging agent and high-strength gel particle blocking agent;
B. it uses gelled plugging agent to squeeze, carries out the selective deep water blockoff in remote well area.The gelled plugging agent by Phenol-formaldehyde resin modified crosslinking agent that modified polyacrylamide that weight percent is 0.4, weight percent are 0.9, weight percent Than adding water mixture to form for 0.7 chromium class crosslinking agent;
C. gel particle suspension system is used to squeeze zone of transition, hot setting forms blocking with certain permeability Slug.Modified polyacrylamide, weight percent of the gel particle suspension gelled plugging agent by weight percent for 1.4 For cement that 20, grain size is 400 mesh, weight percent be 0.6 phenolic resin, weight percent be 0.5 organic chrome cross linker Water mixture forms;
D. high-strength gel granular system is used to squeeze near wellbore zone, quick dehydration consolidation, forms strong in controllable time Power is sealed.Modified polyacrylamide that the high-strength gel particle blocking agent is 1.6 by weight percent, weight percent are 28, grain size is that the cement plus water mixture of 800 mesh forms.
Embodiment 5:
The shutoff method includes the following steps:
A. it applies PNN, SNP etc. to test water detection technology accurately to judge to be discharged position and remaining oil distribution situation, improves water blockoff Specific aim, guidance optimization plug agent amount block slug, pressure control, stay and fill in length etc.;It improves to block water flooding degree, water breakthrough The whole understanding of situation.
According to reservoir physical parameter, well section length, blocking agent performance characteristics, using ellipsoid model, optimization calculates classification note The different plug agent amounts and construction parameter entered.
Plug agent amount optimization is calculated to be calculated using ellipsoid model:
In formula, V-plug agent amount (m3);K-high permeable strip ratio (%);H-reservoir effective thickness (m);R-blocking agent Release radius (m);L-sieve tube segment (perforated interval) length (m);Φ-active porosity (%).
Injection pressure:Blocking agent must be injected under the conditions of less than formation fracture pressure.When construction based on injection test pressure, 3~5MPa of pressure of climbing.It requires injection pressure to be slightly above discharged stressor layer simultaneously, ensures that the blocking agent of injection enters in the horizontal direction Earth formation deep.
Injection rate:Consider that formation contaminant wants small, note speed wants low;The construction time is taken into account, therefore injection rate again cannot be too It is low.Injection rate is optimized for 8~10m3/ h is advisable.
The blocking agent is gelled plugging agent, gel particle suspension gelled plugging agent and high-strength gel particle blocking agent;
B. it uses gelled plugging agent to squeeze, carries out the selective deep water blockoff in remote well area.The gelled plugging agent by Phenol-formaldehyde resin modified crosslinking agent that modified polyacrylamide that weight percent is 0.6, weight percent are 0.7, weight percent Than adding water mixture to form for 0.9 chromium class crosslinking agent;
C. gel particle suspension system is used to squeeze zone of transition, hot setting forms blocking with certain permeability Slug.Modified polyacrylamide, weight percent of the gel particle suspension gelled plugging agent by weight percent for 1.6 For cement that 18, grain size is 800 mesh, weight percent be 0.4 phenolic resin, weight percent be 0.7 organic chrominum cross-linkage Agent water mixture forms;
D. high-strength gel granular system is used to squeeze near wellbore zone, quick dehydration consolidation, forms strong in controllable time Power is sealed.Modified polyacrylamide that the high-strength gel particle blocking agent is 1.4 by weight percent, weight percent are 30, grain size is that the cement plus water mixture of 400 mesh forms.

Claims (4)

1. a kind of thick oil horizontal well intensity adjustable shutoff method, it is characterised in that the shutoff method includes the following steps:
A. stifled tune layer position is determined by testing water detection technology;Plug agent amount and construction parameter are calculated using ellipsoid model:
1. calculating plug agent amount using ellipsoid model
In formula, V-plug agent amount, m3;K-high permeable strip ratio, %;H-reservoir effective thickness, m;
R-blocking agent releases radius, m;L-screen casing segment length, m;Φ-effecive porosity, %;
2. construction parameter
Blocking agent is injected under the conditions of less than formation fracture pressure, and based on injection test pressure, climb 3~5MPa of pressure, notes simultaneously Enter pressure and is slightly above discharged stressor layer;Injection rate is 8~10m3/h;
The blocking agent is gelled plugging agent, gel particle suspension gelled plugging agent and high-strength gel particle blocking agent;
B. first injection gelled plugging agent deep water blockoff, the gelled plugging agent are gathered by the modification that weight percent is 0.2~0.8 The chromium class that phenol-formaldehyde resin modified crosslinking agent that acrylamide, weight percent are 0.3~1.3, weight percent are 0.2~1.2 Crosslinking agent adds water mixture to form;
C. it is then injected into gel particle suspension gelled plugging agent and realizes that strength is blocked, the gel particle suspension gelled plugging agent The modified polyacrylamide for being 1~2 by weight percent, weight percent are 10~30, grain size is 400~800 mesh cement, The organic chrome cross linker that phenolic resin that weight percent is 0.2~0.8, weight percent are 0.1~0.9 add water mixture and At;
D. finally injection high-strength gel particle blocking agent sealing, the high-strength gel particle blocking agent are 1 by weight percent ~2 modified polyacrylamide, the cement plus water mixture that weight percent is 20~40, grain size is 400~800 mesh form.
2. a kind of thick oil horizontal well intensity adjustable shutoff method according to claim 1, it is characterised in that the jelly described in b step The modified phenolic that modified polyacrylamide that glue class blocking agent is 0.4~0.6 by weight percent, weight percent are 0.7~0.9 Resin cross-linking agent, the chromium class crosslinking agent that weight percent is 0.7~0.9 add water mixture to form.
3. a kind of thick oil horizontal well intensity adjustable shutoff method according to claim 1, it is characterised in that solidifying described in step c Modified polyacrylamide that glue particle suspension gelled plugging agent is 1.4~1.6 by weight percent, weight percent be 18~ 20, grain size is the cement of 400~800 mesh, weight percent is 0.4~0.6 phenolic resin, weight percent are 0.5~0.7 Organic chrome cross linker add water mixture to form.
4. a kind of thick oil horizontal well intensity adjustable shutoff method according to claim 1, it is characterised in that the height described in Step d Modified polyacrylamide that strength gel particle blocking agent is 1.4~1.6 by weight percent, weight percent be 28~30, grain Diameter is that the cement plus water mixture of 400~800 mesh forms.
CN201510501778.5A 2015-08-14 2015-08-14 A kind of thick oil horizontal well intensity adjustable shutoff method Active CN106468152B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510501778.5A CN106468152B (en) 2015-08-14 2015-08-14 A kind of thick oil horizontal well intensity adjustable shutoff method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510501778.5A CN106468152B (en) 2015-08-14 2015-08-14 A kind of thick oil horizontal well intensity adjustable shutoff method

Publications (2)

Publication Number Publication Date
CN106468152A CN106468152A (en) 2017-03-01
CN106468152B true CN106468152B (en) 2018-10-19

Family

ID=58214655

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510501778.5A Active CN106468152B (en) 2015-08-14 2015-08-14 A kind of thick oil horizontal well intensity adjustable shutoff method

Country Status (1)

Country Link
CN (1) CN106468152B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109973062A (en) * 2017-12-28 2019-07-05 东北石油大学 A kind of five or three slug system of note of optimization
CN110118073B (en) * 2019-06-12 2020-05-05 西南石油大学 Multi-section plug grading plugging method suitable for fractured stratum
CN111577231A (en) * 2020-05-14 2020-08-25 中国石油天然气股份有限公司 Method for improving water plugging effect of flooded oil well through reverse profile control and flooding

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3718187A (en) * 1971-02-08 1973-02-27 Marathon Oil Co Method of injection well stimulation
US4064943A (en) * 1976-12-06 1977-12-27 Shell Oil Co Plugging permeable earth formation with wax
US4657944A (en) * 1984-02-09 1987-04-14 Phillips Petroleum Company CO2 -induced in-situ gelation of polymeric viscosifiers for permeability contrast correction
CN1752403A (en) * 2004-09-22 2006-03-29 中国石油天然气股份有限公司 Large channel oil reservoir deep profile controlling method of using composite slug method
CN1888374A (en) * 2005-06-28 2007-01-03 中国石油天然气股份有限公司 High-temperature and High-Salt resisting gel water packing-off method
CN101915079A (en) * 2010-06-13 2010-12-15 西安石油大学 Integrated de-plugging yield increasing process
CN102373914A (en) * 2010-08-25 2012-03-14 中国石油天然气股份有限公司 Deep profile control method for fractured oil reservoir
CN103498643A (en) * 2013-10-23 2014-01-08 天津亿利科能源科技发展股份有限公司 Composite slug deep water plugging method for oil pool with high water content
CN104100224A (en) * 2013-04-03 2014-10-15 中国石油天然气股份有限公司 Oil well water plugging method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3718187A (en) * 1971-02-08 1973-02-27 Marathon Oil Co Method of injection well stimulation
US4064943A (en) * 1976-12-06 1977-12-27 Shell Oil Co Plugging permeable earth formation with wax
US4657944A (en) * 1984-02-09 1987-04-14 Phillips Petroleum Company CO2 -induced in-situ gelation of polymeric viscosifiers for permeability contrast correction
CN1752403A (en) * 2004-09-22 2006-03-29 中国石油天然气股份有限公司 Large channel oil reservoir deep profile controlling method of using composite slug method
CN1888374A (en) * 2005-06-28 2007-01-03 中国石油天然气股份有限公司 High-temperature and High-Salt resisting gel water packing-off method
CN101915079A (en) * 2010-06-13 2010-12-15 西安石油大学 Integrated de-plugging yield increasing process
CN102373914A (en) * 2010-08-25 2012-03-14 中国石油天然气股份有限公司 Deep profile control method for fractured oil reservoir
CN104100224A (en) * 2013-04-03 2014-10-15 中国石油天然气股份有限公司 Oil well water plugging method
CN103498643A (en) * 2013-10-23 2014-01-08 天津亿利科能源科技发展股份有限公司 Composite slug deep water plugging method for oil pool with high water content

Also Published As

Publication number Publication date
CN106468152A (en) 2017-03-01

Similar Documents

Publication Publication Date Title
CN105298438B (en) More fine profile control methods in round polymer gel deep
CN104196487B (en) A kind of plugging agent adaptive experimental technique in low permeability fractured rock core of evaluating
CN103321606B (en) A kind of Fracture with low permeability oil reservoir oilwell water shutoff screen method
CN106468152B (en) A kind of thick oil horizontal well intensity adjustable shutoff method
CN106350042B (en) A kind of gel envelope alters agent and preparation method thereof and envelope alters method
CN103087699B (en) Sand-carrying profile control agent composition of fracture-cave type oil deposit and profile control method of profile control agent
CN109577909A (en) A kind of extra permeability oilfield selectivity frothy gel water plugging and profile controlling method
CN102392627B (en) Method for improving oil field recovery rate
Skrettingland et al. Snorre in-depth water diversion using sodium silicate-large scale interwell field pilot
CN104629698A (en) Water plugging agent and water plugging method of thick oil buried hill edge-bottom water reservoir
CN103411804B (en) Heterogeneous body consolidated core model with most permeable zone and preparation method thereof
CN113464087B (en) Selective water plugging method for bottom water reservoir high-water-cut oil well
CN103555305A (en) Hyperbranched slow-swelling profile control particles and preparation method thereof
CN104327435A (en) Polycationic granulated gel and its preparation method
US20140262255A1 (en) Methods for improving the sweep efficiency of gas injection
CN106089168A (en) A kind of method of medium to high permeable oil reservoir integral profile control
CN105971550A (en) Profile control method for medium-and-high-permeability reservoir
CN104100224B (en) A kind of oilwell water shutoff method
CN104929598A (en) Method for increasing foam swept volume
CN110439503A (en) A kind of Fractured Low-Permeability Reservoir multistage plug Selective Water Plugging method
CN108614910A (en) The computational methods of ion type rareearth mine in_situ leaching critical groundwater table
CN109025894A (en) A kind of heavy crude heat extraction horizontal well channeling method for blocking
Ma et al. Nitrogen foam flooding test for controlling water cut and enhance oil recovery in conventional oil reservoirs of China offshore oilfield
CN105804714A (en) Production-increasing method adopting combination of in-situ gas generation and water plugging technology
CN101747879B (en) Baffle for thin layer oilfield controlling coning of bottom water and injection method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant