CN106436635A - Equipment and method for reinforcing dike - Google Patents

Equipment and method for reinforcing dike Download PDF

Info

Publication number
CN106436635A
CN106436635A CN201611009550.5A CN201611009550A CN106436635A CN 106436635 A CN106436635 A CN 106436635A CN 201611009550 A CN201611009550 A CN 201611009550A CN 106436635 A CN106436635 A CN 106436635A
Authority
CN
China
Prior art keywords
dykes
dams
equipment
dike
speed hydraulic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611009550.5A
Other languages
Chinese (zh)
Inventor
曹斌
张宝森
刘涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201611009550.5A priority Critical patent/CN106436635A/en
Publication of CN106436635A publication Critical patent/CN106436635A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B1/00Equipment or apparatus for, or methods of, general hydraulic engineering, e.g. protection of constructions against ice-strains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention relates to equipment for eliminating dike diseases and reinforcing a dike. The equipment comprises a cab, a walking device, a transmission arm, a high-speed hydraulic rammer compactor and the like. The high-speed hydraulic rammer compactor is arranged on the front portion of the transmission arm. The invention further relates to a method for reinforcing the dike through the equipment. By means of the equipment and method for reinforcing the dike, a channel in water danger can be directly cut off in the vertical direction; danger can be eliminated or the dike can be reinforced rapidly and effectively; the situation that in the traditional damage elimination process, people and equipment repeatedly tread and roll a dike which is weakened through water logging, so that a severer dangerous case such as dike burst or breach is caused easily is avoided; and the dangerous case caused by such phenomena as dike piping or leakage is eliminated fundamentally.

Description

A kind of Apparatus for () and method therefor reinforcing dykes and dams
Technical field
Originally it is related to the technical field that a kind of flood control and dykes and dams are safeguarded, specifically one kind is excluded dykes and dams disease and added The Apparatus for () and method therefor on dyke strengthening dam.
Background technology
At present, when the risk of leakage feelings such as piping in domestic dykes and dams, main employing fills in stifled method, has water side slope possible to dykes and dams The fillers such as building stones are thrown at permeable position in a large number.Though having certain effect, a large amount of human and material resources and time need to be consumed, jeopardize Personal safety.During getting rid of the danger, people and equipment are repeatedly trampled and are rolled the weak dykes and dams of water logging, are easily caused breach etc. of inrushing Bigger dangerous situation.
During embankment seepage, loose inside dam body, the method that plug blocks up permeable mouth can not solve the weak disease of dam body internal defect Evil.
Domestic high less than mobility, impact force is big, harmless pile driving equipment and localized high intensity impact compaction to dam body Equipment, can only beat small-sized timber with artificial or mini-plant, consolidation effect is poor.Dangerous.The operation principle of vibreatory hammer is soil Earth liquefaction is theoretical, loose dam body during vibration, and impact proximity structure thing is it is impossible to be used for the weak dam body emergency work construction that soaks.
During regular maintenance, dykes and dams crack need to be backfilling and compacted after being excavated under crack, and efficiency is low, costly, the pit of excavation Bottom is difficult to Effective Compaction.
Content of the invention
The present invention provides a kind of Apparatus for () and method therefor reinforced dykes and dams and remove the dangerous condition to overcome drawbacks described above.
A kind of equipment reinforcing dykes and dams, is characterized in that:Including driver's cabin, running gear, transmission arm, hydraulic system and height Fast hydraulic pressure beater, high-speed hydraulic rammer compactor is arranged on the front portion of transmission arm, and transmission arm and high-speed hydraulic rammer compactor are all and hydraulic pressure System connects, and the bottom of high-speed hydraulic rammer compactor is provided with accessory.
The method that equipment described in a kind of utilization claim 1 reinforces dykes and dams, is characterized in that:Using following steps:1st, determine The position needing reinforcement and depth, according to the observation with judge or utilize dam leakage survey meter, determine the position that dykes and dams need reinforcement Put and depth;2nd, equipment is driven to the position that dykes and dams need reinforcement, operation transmission arm makes high-speed hydraulic rammer compactor bottom be pressed in Stake upper end;3rd, starting hydraulic system makes high-speed hydraulic rammer compactor be driven piles, and stake is squeezed into inside dykes and dams, makes a driving depth Exceed the depth at disease position, formed and reinforce heap.
Beneficial effects of the present invention mainly embody from the following aspects:
The equipment reinforcing dykes and dams in the present invention is to be combined with high-speed hydraulic rammer compactor by excavator to form movable speedily carrying out rescue work Equipment, this equipment ground is less than pressure, and mobility is high, rapid on the muddy dykes and dams of immersion can reach position of being in danger, need not carry out Extra scene prepares and miscellaneous equipment auxiliary, directly constructs;Hydraulic hammer has the ability of impact skyscraper supporting pile, at a high speed Hydraulic pressure beater is a kind of hydraulic hammer application pattern that accessory is tamping plate, hit energy 10 ~ 60kJ, the bearing capacity of driven pile 500 ~ 3500kN, impact per minute 30~80 times, percussion intensity can adjust on demand, and piling strength is big, efficiency high, and speed of speedily carrying out rescue work is fast, effect Really good, large-scale solid stake and pile tube can be squeezed into;Active force during high-speed hydraulic rammer compactor piling be with stake to squeeze into direction consistent Linear force, will not be loose and destroy the neighbouring soil body and works;The hammer body of high-speed hydraulic rammer compactor is transported inside machine up and down Dynamic, the no unsafe factor such as splashing, do not affect nearby crowd and equipment construction;High-speed hydraulic rammer compactor is in the drive of digger arm Multiple modes speedily carried out rescue work or control flood can be completed down, such as permeable, piping, immersion is weak, breach a dyke and daily exclusion disease, locally Reinforce etc., implementing various operations of controlling flood or speedily carry out rescue work in the presence of digger arm need not other crane gears assist, and can stretch Operated to the close position of people's inconvenience;High-speed hydraulic rammer compactor can connect the accessory of different size model, can also basis The needing of flood control selects different type pile, also allows for drawing materials nearby.
The method of the present invention is reinforced to dykes and dams, it is possible to achieve directly vertically shortened marine insurance passage, fast and effeciently enters Row get rid of the danger or dam body consolidation it is thus also avoided that tradition is got rid of the danger, middle people and equipment are repeatedly trampled and are rolled the weak dykes and dams of water logging, It is easily caused the bigger dangerous situations such as breach that inrush, fundamentally solve the dangerous situation occurring because of phenomenons such as dike piping or seepages.
Brief description
Fig. 1 reinforces the schematic diagram of dykes and dams equipment and embodiment 1 for the present invention.
Fig. 2 is the schematic diagram of the embodiment of the present invention 2.
Fig. 3 is the schematic diagram of the embodiment of the present invention 3.
Specific embodiment
In conjunction with accompanying drawing, the present invention is described in detail, the present invention relates to a kind of Apparatus for () and method therefor reinforcing dykes and dams.
The equipment of the reinforcing dykes and dams in the present invention, including driver's cabin 11, running gear 15, transmission arm 10, hydraulic system, oil Cylinder, motor and high-speed hydraulic rammer compactor 12, high-speed hydraulic rammer compactor 12 is arranged on the front portion of transmission arm 10, transmission arm 10 and high speed Hydraulic pressure beater 12 is all connected with hydraulic system, and high-speed hydraulic rammer compactor 12 is by the use of the hydraulic power of excavator as driving, high The bottom of fast hydraulic pressure beater 12 is provided with accessory 13.The hydraulic means of high-speed hydraulic rammer compactor 12 passes through oil circuit and hydraulic system Connecting, and be controlled by the operation device in driver's cabin 11, driving high-speed hydraulic rammer compactor 12 to move thus realizing transmission arm 10 Move and stroke.High-speed hydraulic rammer compactor 12, when using operation, can impact the stake 21 of various ways, the stake in the present invention 21 can be steel pipe, prefabricated pile, steel sheet pile or timber etc., and prefabricated pile can be circular, square, tubular, plate shape etc..Permissible in steel pipe Put into filler, filler can be rubble, block stone, sandstone, strong granulated aggregate or plasticity chemical filler etc..Accessory 13 typically with Stake 21 matching used various aids, are arranged on the bottom of the lower hammer of high-speed hydraulic rammer compactor 12.Accessory 13 is acceptable Squeezing into direction and preventing lower hammer from slipping of stake 21 is controlled from stake 21, selects as needed to use and change, such as stake 21 is steel Guan Shi, accessory 13 is the heart axle in insertion stake 21.Accessory 13 both may be inserted into stake 21 in the hole positioning and can also use sleeve accessory 13 are enclosed within positioning in stake 21, and accessory 13 can also be tamping plate of sleeve, fixture or ramming etc..When stake 21 is column construction When, accessory 13 is sleeve, and its endoporus is corresponding to the profile of stake 21 and is enclosed within stake 21;When stake 21 is slab structure, accessory 13 Can be fixture, stake 21 is clamped or righting after directly impact;When stake 21 is stub or large aperture tubular-shaped structures, can not With accessory 13, directly impact after righting positioning.Running gear 15 can be crawler type can also be wheel type.
The invention still further relates to method dykes and dams reinforced using the said equipment, using following steps:1st, determining needs The position reinforcing and depth, according to the observation with judge or utilize dam leakage survey meter, determine position that dykes and dams need reinforcement and Depth;2nd, equipment is driven to the position that dykes and dams need reinforcement, operation transmission arm 10 makes high-speed hydraulic rammer compactor 12 bottom be pressed in In stake 21 to be impacted;3rd, starting hydraulic system makes high-speed hydraulic rammer compactor 12 carry out driving piles 21, and dykes and dams are squeezed in stake 21 Inside, makes stake 21 driving depth exceed the depth at be in danger position or survey meter detection, is formed and reinforce heap.
Embodiment 1:When permeable phenomenon in dykes and dams, using following steps:1st, first with dam leakage survey meter, detect With the permeable position of dykes and dams and depth determining that dykes and dams need reinforcement.2nd, equipment is driven to the position that dykes and dams need reinforcement.Typically Permeable position is in dykes and dams bottom, and the water stream channel of insertion dykes and dams, equipment is driven to survey meter and detects defined location. 3rd, stake 21 and accessory 13 are selected.The present embodiment, using cylindrical stake 21, the accessory 13 of tube-in-tube structure is installed on high-speed hydraulic Rammer compacter 12 bottom, operation transmission arm 10 makes accessory 13 be pressed in the upper end of stake 21.4th, 21 are carried out driving piles, start-up operation device is high Fast hydraulic pressure beater 12 just starts 21 work of driving piles in the presence of hydraulic system, and the stake 21 of cylindricality is quickly squeezed in dykes and dams Portion, sees Fig. 1, and until the driving depth of stake 21 exceedes permeable depth, this depth can be judged by rule of thumb or be detected using survey meter, High-speed hydraulic rammer compactor 12 stops piling 21 work, and general post driving depth exceedes permeable position 52 or survey meter investigation depth 50 Centimetre to 100 cm, serious acceptable deeper of dangerous situation, complete 21 actions of once driving piles.If the width at permeable position Larger, continue to lay a pile 21, until forming a gear wall or bundles of stake 21 groups, if the width at permeable position 52 is not Easily determine or detect, just squeeze into the stake 21 of row's wider width, its both sides exceeds the scope that may be in danger, just can be completely cut off Water-permeable passage, strengthens the dykes and dams of weakness simultaneously.The reinforcement means of the present embodiment quickly can not only intercept water-permeable passage, and perpendicular To setting stake 21 be not easy to wash away, intercept flood water slug effect good moreover it is possible to make dykes and dams more reinforce.
Embodiment 2:When piping dangerous situation in dykes and dams, piping is that the soil particle in dam body or the dam foundation is taken away by seepage flow Phenomenon, be because more permeable after lead to permeable area and periphery soil body weakness to cause it is therefore desirable to be optimal to affected part filling filler Method, the present embodiment adopts following steps:1st, the position needing reinforcement and depth are determined.Because Piping phenomenon is obvious, lead to Often can just can determine that, with judgement, the position and depth needing reinforcement according to the observation.2nd, equipment is driven to the position that dykes and dams need reinforcement Put.Step 3, selection stake 21 and accessory 13.The present embodiment uses the high-speed hydraulic rammer compactor 12 of hit energy 16kJ, and stake 21 selects Round steel pipe and the heart axle accessory 13 supporting with stake 21, the diameter of steel pipe can be at 10 centimetres -100 centimetres, and the present embodiment is straight 50 centimetres of footpath, installs accessory 13, and then operation transmission arm 10 makes the accessory 13 of high-speed hydraulic rammer compactor 12 bottom be pressed in stake 21 Upper end.4th, 21 are carried out driving piles.Start-up operation device, high-speed hydraulic rammer compactor 12 is driven piles, and makes steel pipe bottom stretch into dykes and dams Permeable position.5th, filling filler ramming into stake 21.The filler that the present embodiment uses is rubble, and filler is filled it up with steel pipe, then Secondary start-up operation device, high-speed hydraulic rammer compactor 12 impacts to the filler in stake 21, filler under the guide effect of steel pipe, Accurately the position needing reinforcement is filled with, after completing once filling action, can be entered according to the size of piping area Row is repeatedly filled.The reinforcement means of the present embodiment is mainly reinforced to dykes and dams soft regions and is controlled flood.
Embodiment 3:When needing to dykes and dams roof reinforcement or regular maintenance, to the method for dam reinforcement it is:Using following Step:1st, determine the position that dykes and dams need reinforcement, and equipment is driven to above-mentioned position.2nd, select filler.Weak according to dykes and dams Degree selects suitable filler, such as rubble, block stone or sandstone etc., the present embodiment selection block stone and sandstone to be used in mixed way, block stone Intensity is high, and in mixing, the space between block stone can be filled by sandstone, prevents Seepage.3rd, filler is positioned over needs to add Solid position, operation transmission arm 10 makes the lower hammer of high-speed hydraulic rammer compactor 12 or tamping plate 17 be aligned filler, in the present embodiment Lower hammer bottom is mounted with tamping plate 17, using tamping plate, filler is impacted.4th, starting hydraulic system makes high-speed hydraulic rammer compactor 12 pairs of fillers carry out ramming, and filler is squeezed in dykes and dams, and filler squeezes into the depth of dykes and dams typically between 0.5 meter -1 meter, just may be used Play the good result reinforcing dykes and dams.The filler of lower height can first be stacked, after squeezing in dykes and dams, from these during concrete operations Then these fillers are squeezed into dykes and dams by the filler of the stacked certain altitude of filler again, and this process can be repeated several times, until Till the filler squeezed into reaches the depth of needs.Filler can be that close-packed arrays shape is in a row or spaced.Office Filler can be squeezed into dam body and form broken stone pile, sand pile by portion reinforcing position.
The present invention can also select stake or accessory according to different flood dangers, and the present invention can be with batter piling, and operation transmission arm will High-speed hydraulic rammer compactor tilts certain angle and then carries out impacting just may be used.

Claims (2)

1. a kind of equipment reinforcing dykes and dams, is characterized in that:Including driver's cabin, running gear, transmission arm, hydraulic system and high speed Hydraulic pressure beater, high-speed hydraulic rammer compactor is arranged on the front portion of transmission arm, and transmission arm and high-speed hydraulic rammer compactor are all and hydraulic pressure system System connects, and the bottom of high-speed hydraulic rammer compactor is provided with accessory.
2. the method that equipment described in a kind of utilization claim 1 reinforces dykes and dams, is characterized in that:Using following steps:1st, determining needs Position to be reinforced and depth, according to the observation with judge or utilize dam leakage survey meter, determine the position that dykes and dams need reinforcement And depth;2nd, equipment is driven to the position that dykes and dams need reinforcement, operation transmission arm makes high-speed hydraulic rammer compactor bottom be pressed in stake Upper end;3rd, starting hydraulic system makes high-speed hydraulic rammer compactor be driven piles, and stake is squeezed into inside dykes and dams, so that a driving depth is surpassed Cross the depth at disease position, formed and reinforce heap.
CN201611009550.5A 2016-11-17 2016-11-17 Equipment and method for reinforcing dike Pending CN106436635A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611009550.5A CN106436635A (en) 2016-11-17 2016-11-17 Equipment and method for reinforcing dike

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611009550.5A CN106436635A (en) 2016-11-17 2016-11-17 Equipment and method for reinforcing dike

Publications (1)

Publication Number Publication Date
CN106436635A true CN106436635A (en) 2017-02-22

Family

ID=58220023

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611009550.5A Pending CN106436635A (en) 2016-11-17 2016-11-17 Equipment and method for reinforcing dike

Country Status (1)

Country Link
CN (1) CN106436635A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108547299A (en) * 2018-04-23 2018-09-18 青岛多德多信息技术有限公司 A kind of piling machine
CN108547298A (en) * 2018-04-23 2018-09-18 青岛破浪舟车船装备科技有限公司 A kind of method of dykes and dams piling

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58135209A (en) * 1982-02-03 1983-08-11 Hitachi Zosen Corp Reinforcing work for river bank
CN2296367Y (en) * 1997-03-24 1998-11-04 长沙高新技术产业开发区思创机电新技术开发公司 Pile machine for reinforcing dam
CN103437322A (en) * 2013-09-10 2013-12-11 宋国文 Method for flood control and reinforcement and dam protection
CN205205803U (en) * 2015-12-17 2016-05-04 中国水电建设集团十五工程局有限公司 Simple and easy hydraulic shock rammer compactor

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58135209A (en) * 1982-02-03 1983-08-11 Hitachi Zosen Corp Reinforcing work for river bank
CN2296367Y (en) * 1997-03-24 1998-11-04 长沙高新技术产业开发区思创机电新技术开发公司 Pile machine for reinforcing dam
CN103437322A (en) * 2013-09-10 2013-12-11 宋国文 Method for flood control and reinforcement and dam protection
CN205205803U (en) * 2015-12-17 2016-05-04 中国水电建设集团十五工程局有限公司 Simple and easy hydraulic shock rammer compactor

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108547299A (en) * 2018-04-23 2018-09-18 青岛多德多信息技术有限公司 A kind of piling machine
CN108547298A (en) * 2018-04-23 2018-09-18 青岛破浪舟车船装备科技有限公司 A kind of method of dykes and dams piling

Similar Documents

Publication Publication Date Title
CN106836246B (en) Open trench tunnel crosses the construction method of section building enclosure
CN102926400B (en) Combined earth retaining wall structure and construction method thereof
CN102888834B (en) A kind of construction method of major diameter broken stone pile
CN111042116A (en) Karst cave stratum pile foundation construction method
CN103031839A (en) Construction method of hand-dug piles
CN206204880U (en) A kind of side slope comprehensive regulation structure of prevention river channel erosion
CN106948340A (en) A kind of construction method of the Manual excavated pile structure of high polymer grouting protection
CN106522191A (en) Transformer substation foundation treatment method and application thereof
CN111636417A (en) Grouting type steel pipe pile and construction method thereof
CN106400744A (en) Comprehensive side-slope treatment structure for preventing river channel erosion and construction method thereof
CN106436635A (en) Equipment and method for reinforcing dike
CN104652411A (en) Composite foundation treatment method based on reinforcement, pretreatment and dynamic compaction of sandy soil
CN111455943A (en) Construction method of anti-scouring drainage groove of barrier lake
CN108411934B (en) Floating tubular pile, dam retaining structure and construction method thereof
CN204225101U (en) The construction equipment of concrete pile
CN207260082U (en) Active service refutes bank revetment and increases structure
CN206052770U (en) A kind of use cast-in-situ bored pile combines the retaining wall of compaction grouting
CN213476933U (en) Ecological steel sheet pile island-building cofferdam structure
CN210917310U (en) Disposal drainage consolidation processing system for hydraulic filling deep and thick soft foundation
CN210975403U (en) Treatment structure of high water level soft soil bridgehead roadbed
CN208309626U (en) A kind of floating tubular pole and its dykes and dams soil-baffling structure
CN210216473U (en) Anti-slide pile for slope treatment
CN208152061U (en) Method steel pipe pile cofferdam structure is unidirectionally attacked and occupied suitable for Soft Clay
CN202881971U (en) Combined retaining wall structure
CN206438522U (en) Open trench tunnel crosses section building enclosure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
CB02 Change of applicant information

Address after: 271000 Manzhuang Steel Market No. 77, Daiyue District, Taian City, Shandong Province

Applicant after: Cao Bin

Address before: 77 Anzhuang Market Road, Feicheng City, Taian City, Shandong Province

Applicant before: Cao Bin

CB02 Change of applicant information
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170222

RJ01 Rejection of invention patent application after publication