CN210975403U - A treatment structure for high water level soft soil bridgehead subgrade - Google Patents

A treatment structure for high water level soft soil bridgehead subgrade Download PDF

Info

Publication number
CN210975403U
CN210975403U CN201921542590.5U CN201921542590U CN210975403U CN 210975403 U CN210975403 U CN 210975403U CN 201921542590 U CN201921542590 U CN 201921542590U CN 210975403 U CN210975403 U CN 210975403U
Authority
CN
China
Prior art keywords
pipe
bridgehead
water level
road
buoyancy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921542590.5U
Other languages
Chinese (zh)
Inventor
马小斐
张东长
李海平
阎宗岭
徐建强
苟栋元
王洋
刘朝辉
付玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Merchants Chongqing Communications Research and Design Institute Co Ltd
Original Assignee
China Merchants Chongqing Communications Research and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Merchants Chongqing Communications Research and Design Institute Co Ltd filed Critical China Merchants Chongqing Communications Research and Design Institute Co Ltd
Priority to CN201921542590.5U priority Critical patent/CN210975403U/en
Application granted granted Critical
Publication of CN210975403U publication Critical patent/CN210975403U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a high water level weak soil bridgehead road bed's punishment structure, include: a buoyancy body arranged below the underground water level of the soft soil layer and having a bulk density of not more than 1.0g/cm3The floating bodies are arranged at intervals along the passing direction of the road, and each floating body is horizontally arranged along the width direction of the road; the upper part of each buoyancy body is provided with one jacking pipe which is horizontally arranged in the same direction as the buoyancy bodies and is a half part with an opening at one sideThe opening of the top pipe is buckled on the upper surface of the buoyancy body; and the rigid connecting body is connected between the two adjacent jacking pipes. The treatment structure can effectively treat differential settlement of high-water-level soft foundation bridge head subgrades of a newly-built road and an existing road, and solves the problem of bridge head bumping caused by the differential settlement.

Description

一种高水位软土桥头路基的处治结构A treatment structure for high water level soft soil bridgehead subgrade

技术领域technical field

本实用新型涉及土木工程中深厚软基地层的防沉降处治技术领域,具体涉及一种高水位软土桥头路基的处治结构。The utility model relates to the technical field of anti-settling treatment of deep soft ground layers in civil engineering, in particular to a treatment structure for high water level soft soil bridgehead subgrades.

背景技术Background technique

深厚软基地区由于其土层通常具有:压缩性高、强度低、渗透性小、固结缓慢、且灵敏度高的特点,在此基础上修建公路时,如不对其下软土采取有效措施进行处治,在其上路堤荷载的作用下,软土层固结压缩,产生较大沉降,对后期运营影响安全与舒适影响较大。Due to the characteristics of the soil layer in the deep soft foundation area: high compressibility, low strength, low permeability, slow consolidation, and high sensitivity, when constructing a highway on this basis, if no effective measures are taken to the soft soil beneath it. Under the action of the embankment load, the soft soil layer is consolidated and compressed, resulting in a large settlement, which has a great impact on the safety and comfort of the later operation.

特别是在桥头路基段,由于桥梁桩基往往支承在其下的硬持力层上,故完工后不再产生沉降,而与桥梁相连的桥头路基段,受造价与技术、施工可行性等因素的影响,往往不能采取深入到深厚软基层的处治方案。这就导致公路完工运行一段时间后,桥头与路基段出现有较大差异沉降,为使得该差异不影响通行质量,现有处治方式中,通常是在桥梁和桥头路基之间设置一定长度的过渡段进行顺接过渡,从而缓解差异性沉降。Especially in the subgrade section at the bridgehead, since the bridge pile foundation is often supported on the hard bearing layer below it, there will be no settlement after completion, and the subgrade section at the bridgehead connected to the bridge is affected by factors such as cost, technology, and construction feasibility. The impact of the disease often cannot be adopted in the treatment plan that penetrates into the deep soft grass-roots level. This leads to a large difference in settlement between the bridge head and the subgrade after the highway is completed and operated for a period of time. In order to make the difference not affect the traffic quality, in the existing treatment methods, a certain length of transition is usually set between the bridge and the subgrade at the bridge head. The transition is carried out in succession, thereby alleviating differential settlement.

然而,若软基厚度较大(厚度达到50~60m),地下水位较高,根据理论,其变形压缩层(附加应力小于等于自重应力的0.1倍的地层)较厚,设置桥头过渡段的处治方式难以在这种环境下实现,而常规的处治措施如:排水固结体+ 堆载预压、粉喷桩、高压旋喷桩、预应力管桩等,也不可能将变形压缩层全部进行处治,故而实际施工中往往仅能处理0.3~0.6倍压缩层厚度,加之施工质量的控制困难,竣工后仍然会产生较大的工后沉降量,导致严重的桥头跳车现象。However, if the thickness of the soft foundation is large (the thickness reaches 50-60m) and the groundwater level is high, according to the theory, the deformation and compression layer (the layer with the additional stress less than or equal to 0.1 times the self-weight stress) is thick, and the bridgehead transition section is set up to deal with it. It is difficult to realize the method in this environment, and conventional treatment measures such as: drainage consolidation + heap load preloading, powder injection piles, high-pressure rotary injection piles, prestressed pipe piles, etc., it is impossible to carry out all the deformation and compression layers. Therefore, in actual construction, only 0.3 to 0.6 times the thickness of the compression layer can be handled. In addition, the control of construction quality is difficult. After completion, there will still be a large amount of post-construction settlement, resulting in serious bridge head jumping.

因此,对于此类高水位软基桥头路基的防差异性沉降处治,现有处治措施均无法达到满意的效果。Therefore, the existing treatment measures cannot achieve satisfactory results in the treatment of differential settlement of such high-water soft-foundation bridgehead subgrades.

实用新型内容Utility model content

有介于此,本实用新型提出一种高水位软土桥头路基的处治结构,以有效处治高水位软基桥头路基的差异性沉降,解决因其产生的桥头跳车问题。In view of this, the present utility model proposes a treatment structure for high water level soft soil bridgehead subgrade to effectively treat the differential settlement of the high water level soft foundation bridgehead subgrade and solve the problem of bridgehead jumping caused by it.

为解决上述技术问题,本实用新型提出一种高水位软土桥头路基的处治结构,设置在桥头路基段路面结构层下方的土体内,其包括:In order to solve the above-mentioned technical problems, the utility model proposes a treatment structure for high water level soft soil bridgehead subgrade, which is arranged in the soil body below the pavement structure layer of the bridgehead subgrade section, which includes:

浮力体,设置于地下水位以下的土体内,且为体积密度不大于1.0g/cm3 的不透水材质,所述浮力体沿道路的通行方向间隔布置有多个,每一浮力体沿道路的宽度方向水平设置;The buoyant body is arranged in the soil below the groundwater level, and is an impermeable material with a bulk density of not more than 1.0g/cm3. The buoyancy bodies are arranged at intervals along the passage direction of the road, and each buoyant body is along the width of the road. Orientation level setting;

顶管,在每一所述浮力体的上部各设置一个,且与浮力体同向水平布置,所述顶管为一侧开口的半管结构,顶管的开口扣合在浮力体的上表面;及A jacking pipe is provided on the upper part of each of the buoyancy bodies, and is arranged horizontally in the same direction as the buoyancy body. The jacking pipe is a half-pipe structure with an opening on one side, and the opening of the jacking pipe is fastened on the upper surface of the buoyancy body. ;and

刚性连接体,连接在相邻两顶管之间。Rigid connecting body, connected between two adjacent top pipes.

进一步地,所述浮力体为中空的箱体结构。Further, the buoyancy body is a hollow box structure.

进一步地,所述刚性连接体包括:水平连接在相邻两所述顶管的开口下沿的注浆管和砂浆板,所述注浆管包覆在砂浆板中,注浆管的管壁上开设有多个注浆孔,注浆管沿顶管的长度方向均匀间隔布置多个。Further, the rigid connecting body includes: a grouting pipe and a mortar board that are horizontally connected at the lower edges of the openings of the adjacent two jacking pipes, the grouting pipe is wrapped in the mortar board, and the pipe wall of the grouting pipe is A plurality of grouting holes are opened on the upper part, and a plurality of grouting pipes are evenly spaced along the length direction of the jacking pipe.

进一步地,所述顶管的靠近开口的侧壁上开设有布管孔,所述布管孔沿顶管的长度方向均匀间隔布置多个,所述注浆管的两端分别卡装于相邻两顶管的对应布管孔内。Further, the side wall of the top pipe close to the opening is provided with pipe layout holes, and the pipe layout holes are evenly spaced along the length direction of the top pipe, and the two ends of the grouting pipe are respectively clamped to in the corresponding piping holes of the two adjacent top pipes.

与现有技术相比,本实用新型的有益效果有:Compared with the prior art, the beneficial effects of the present utility model are:

本实用新型采用顶管+浮力体的组合结构,在高水位深厚软基桥头路基段进行施工;通过置入薄壁的顶管,将管腔中的路堤土置换,从而减轻路堤自重,且通过顶管的弧形顶面承受地层压力,受力均匀,地层受力的整体性更佳,同时可将顶管作为过水涵洞使用,排出软土中的水体,改善深厚软基的地质环境,且通过顶管提供的拱形空间,后期的养护和再施工更加方便;通过将两个顶管通过刚性连接体连接,形成一个整体,保证共同受力和同步沉降;通过下设的不透水轻质材料的浮力体进行填筑,一方面减轻地基层的自重,另一方面为在地下水作用下,浮力体受浮力,从而对路堤产生向上的作用力,消减下沉作用力;由此,路堤以及软土层上的地基自重有较大幅度的减轻,而作用在深厚软土层的下沉作用力又大幅度减小,由此达到控制高水位软基桥头路基差异性沉降的目的,从而有效解决因其产生的桥头跳车问题。The utility model adopts the combined structure of jacking pipe and buoyancy body to carry out construction in the subgrade section of the bridgehead with high water level and deep soft foundation; by inserting the thin-walled jacking pipe, the embankment soil in the pipe cavity is replaced, so as to reduce the self-weight of the embankment and pass the The arc top surface of the jacking pipe bears the formation pressure, and the force is uniform, and the integrity of the formation force is better. At the same time, the jacking pipe can be used as a water-passing culvert to discharge the water body in the soft soil and improve the geological environment of the deep soft foundation. And through the arch space provided by the jacking pipe, the later maintenance and re-construction are more convenient; by connecting the two jacking pipes through a rigid connecting body, a whole is formed to ensure common stress and synchronous settlement; On the one hand, the weight of the base layer is reduced, and on the other hand, under the action of groundwater, the buoyant body is subjected to buoyancy, thereby producing an upward force on the embankment and reducing the sinking force; thus, the embankment is And the weight of the foundation on the soft soil layer is greatly reduced, and the subsidence force acting on the deep soft soil layer is greatly reduced, so as to achieve the purpose of controlling the differential settlement of the subgrade at the high water level soft foundation bridgehead, thereby Effectively solve the bridge jumping problem caused by it.

附图说明Description of drawings

图1为本实用新型实施例沿道路通行方向的侧视结构示意图;Fig. 1 is the side view structure schematic diagram of the embodiment of the present utility model along the road passing direction;

图2为图1中A部的结构放大示意图;Fig. 2 is the structural enlargement schematic diagram of A part in Fig. 1;

图3为图1沿B-B断面(即道路宽度方向)的剖视结构示意图;FIG. 3 is a schematic cross-sectional structure diagram of FIG. 1 along the B-B section (that is, the road width direction);

图4为图3中C部的结构放大示意图;Fig. 4 is the structural enlarged schematic diagram of C part in Fig. 3;

附图标记:Reference number:

1-浮力体,11-浮力箱,12-盖板1-buoyancy body, 11-buoyancy box, 12-cover plate

2-顶管,21-布管孔,2-pipe top, 21-pipe hole,

3-刚性连接体,31-注浆管,32-砂浆板,3- Rigid connecting body, 31- Grouting pipe, 32- Mortar board,

4-路面结构层,5-路堤填土,6-软土层。4- Pavement structure layer, 5- Embankment filling, 6- Soft soil layer.

具体实施方式Detailed ways

下面将结合附图对本实用新型技术方案的实施例进行详细的描述。以下实施例仅用于更加清楚地说明本实用新型的技术方案,因此只作为示例,而不能以此来限制本实用新型的保护范围。在本实用新型申请的描述中,需要理解的是,术语“上”、“下”、“前”、“后”、“左”、“右”等,指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本实用新型和简化描述,而不是指示或暗示所指的部件或结构必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本实用新型的限制。The embodiments of the technical solutions of the present utility model will be described in detail below with reference to the accompanying drawings. The following embodiments are only used to illustrate the technical solutions of the present invention more clearly, and are therefore only used as examples, and cannot be used to limit the protection scope of the present invention. In the description of the present utility model application, it should be understood that the terms "upper", "lower", "front", "rear", "left", "right", etc., indicate the orientation or positional relationship based on the accompanying drawings The orientation or positional relationship shown is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the components or structures referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a Utility Model Restrictions.

如图1至图4所示,为解决高水位软土桥头路基的差异性沉降问题,本实用新型提出一种高水位软土桥头路基的处治结构,适宜在地下水位较高的深厚软基地区进行施工,具体设置在容易发生差异性沉降的桥头路基段路面结构层 4下方的土体内,其具体结构包括:浮力体1、顶管2和刚性连接体3。As shown in Figures 1 to 4, in order to solve the problem of differential settlement of high water level soft soil bridgehead subgrade, the present utility model proposes a treatment structure for high water level soft soil bridgehead subgrade, which is suitable for deep soft foundation areas with high groundwater level The construction is carried out, and it is specifically arranged in the soil body below the pavement structure layer 4 of the bridgehead subgrade section, which is prone to differential settlement.

参见图1,浮力体1设置于地下水位以下土体内,且为体积密度不大于 1.0g/cm3的不透水材质,从而可以在高水位的软土环境中获得较大的向上浮力,用以对抗和消减软土环境下的下沉压力。参见图2,浮力体1最好是不透水轻质空心箱体结构,以便更加有效的减轻地基层的自重,并对路堤产生更大向上的作用力。Referring to Fig. 1, the buoyant body 1 is arranged in the soil body below the groundwater level, and is an impermeable material with a bulk density of not more than 1.0g/ cm3 , so that a large upward buoyancy can be obtained in a soft soil environment with a high water level, which is used for Combat and reduce subsidence pressure in soft soil environments. Referring to Fig. 2, the buoyant body 1 is preferably a water-impermeable light-weight hollow box structure, so as to more effectively reduce the self-weight of the ground layer and generate a greater upward force on the embankment.

参见图2,本实施例中的浮力体1,可具体设置为上端敞口的浮力箱11,并在浮力箱11上密封的盖设一个盖板12,以此形成空心箱体结构,从而最大限度的减小浮力体1的体积密度,并且方便浮力体1的制作和施工。Referring to FIG. 2 , the buoyancy body 1 in this embodiment can be specifically configured as a buoyancy box 11 with an open upper end, and a cover plate 12 is sealed on the buoyancy box 11 to form a hollow box structure, so that the maximum The bulk density of the buoyancy body 1 is reduced to the limit, and the manufacture and construction of the buoyancy body 1 are facilitated.

上述的浮力体1沿道路的通行方向间隔布置有多个,每一浮力体1沿道路的宽度方向水平设置,从而形成多个浮力提供点。The above-mentioned buoyancy bodies 1 are arranged at intervals along the passage direction of the road, and each buoyancy body 1 is horizontally arranged along the width direction of the road, thereby forming a plurality of buoyancy providing points.

如图1所示,顶管2在每一浮力体1的上部各设置一个,且与浮力体1同向水平布置;同时,顶管2为一侧开口的半管结构,且顶管2的开口扣合在浮力体1的上表面。以中空的顶管2将管腔中的路堤土置换,从而进一步减轻路堤自重,同时可将顶管2作为过水涵洞使用,排出软土中的水体,改善深厚软基的地质环境,且通过顶管2提供的拱形空间,后期的养护和再施工更加方便;且在后期盖覆土体之后,通过顶管2的弧形顶面承受地层压力,受力均匀,地层受力的整体性更佳。As shown in Figure 1, one jacking pipe 2 is provided on the upper part of each buoyancy body 1, and is arranged horizontally in the same direction as the buoyancy body 1; at the same time, the jacking pipe 2 is a half-pipe structure with one side open, and the The opening is fastened on the upper surface of the buoyancy body 1 . The embankment soil in the lumen is replaced by the hollow jacking pipe 2, thereby further reducing the weight of the embankment. At the same time, the jacking pipe 2 can be used as a water-passing culvert to discharge the water in the soft soil, improve the geological environment of the deep soft foundation, and pass The arched space provided by the jacking pipe 2 is more convenient for maintenance and re-construction in the later stage; and after the soil is covered in the later stage, the arc top surface of the jacking pipe 2 can bear the formation pressure, and the force is uniform and the integrity of the formation force is better. good.

本实施例中,顶管2采用管径0.8m~1.5m,管壁厚度0.15m左右的薄壁钢筋混凝土管或者薄壁钢管,形成强度较高的薄壁管,可在满足强度要求的情况下,最大限度的减轻自重,并置换出更多的路堤土体,减轻路堤自重。In this embodiment, the jacking pipe 2 adopts a thin-walled reinforced concrete pipe or a thin-walled steel pipe with a pipe diameter of 0.8m to 1.5m and a pipe wall thickness of about 0.15m to form a thin-walled pipe with high strength, which can meet the strength requirements. To reduce the self-weight to the maximum extent, and replace more embankment soil, reduce the self-weight of the embankment.

同时,为方便刚性连接体3的布置,可在顶管2的靠近开口的侧壁上开设布管孔21,并将该布管孔21沿顶管2的长度方向均匀间隔布置多个。Meanwhile, in order to facilitate the arrangement of the rigid connecting body 3 , pipe routing holes 21 can be opened on the side wall of the jacking pipe 2 near the opening, and a plurality of the pipe routing holes 21 can be evenly spaced along the length direction of the jacking pipe 2 .

参见图1和图3,刚性连接体3连接在相邻两顶管2之间,以将各顶管2 形成一个整体,保证共同受力和同步沉降。Referring to FIG. 1 and FIG. 3 , a rigid connecting body 3 is connected between two adjacent jacking pipes 2 to form a whole of each jacking pipe 2 to ensure common stress and synchronous settlement.

参见图3和图4,刚性连接体3的最佳形式为水平连接在顶管2开口下沿的板状结构,从而为周围的软基土体提供极佳的受力和结构稳定性。具体到本实施例而言,刚性连接体3包括:水平连接在相邻两顶管2的开口下沿的注浆管31和砂浆板32,注浆管31包覆在砂浆板32中,注浆管31的管壁上开设有多个注浆孔,注浆管31沿顶管2的长度方向均匀间隔布置多个。具体实施时,可先将注浆管31的两端分别卡装于相邻两顶管2的对应布管孔21内,之后通过注浆管31浇筑砂浆,砂浆从注浆管31的注浆孔中深入到周边的松软的土体中,最后固结形成砂浆板32,砂浆板32以注浆管31为骨架,将相邻的顶管2 固定连接为一体。Referring to Figures 3 and 4, the best form of the rigid connecting body 3 is a plate-like structure horizontally connected to the lower edge of the opening of the top pipe 2, so as to provide excellent force and structural stability for the surrounding soft soil. Specifically to this embodiment, the rigid connecting body 3 includes: a grouting pipe 31 and a mortar board 32 horizontally connected to the lower edges of the openings of the adjacent two jack pipes 2 , the grouting pipe 31 is wrapped in the mortar board 32, A plurality of grouting holes are opened on the pipe wall of the slurry pipe 31 , and a plurality of grouting pipes 31 are evenly spaced along the length direction of the jacking pipe 2 . In the specific implementation, the two ends of the grouting pipe 31 can be clamped into the corresponding pipe holes 21 of the two adjacent jacking pipes 2 respectively, and then the mortar is poured through the grouting pipe 31, and the mortar is poured from the grouting pipe 31. The hole penetrates deep into the surrounding soft soil, and is finally consolidated to form a mortar board 32 .

当然,若是在开挖施工的环境下,刚性连接体3的施工可直接采用钢筋混凝土浇筑的形式,现在相邻两顶管2之间设置钢筋笼作为骨架,之后浇筑砂浆或者混凝土形成连接两顶管2的板状结构即可,结构稳固,施工方便。Of course, in the case of excavation construction, the construction of the rigid connector 3 can be directly cast in the form of reinforced concrete. Now, a reinforced cage is set between the two adjacent jacking pipes 2 as a skeleton, and then mortar or concrete is poured to form a connection between the two roofs. The plate-like structure of the pipe 2 is sufficient, the structure is stable, and the construction is convenient.

上述的处治结构在高水位深厚软基桥头路基段进行施工,采用顶管2加浮力体1的组合结构,并将相邻两个顶管2通过刚性连接体3连接,形成一个整体,保证共同受力和同步沉降;一方面通过顶管2和浮力体1减轻地层自重,另一方面利用高水位深厚软基地层的地下水提供的浮力,从而对路堤产生向上的作用力,消减下沉作用力;由此,路堤以及软土层6上的地基自重有较大幅度的减轻,而作用在深厚软土层6的下沉作用力又大幅度减小,由此达到控制高水位软基桥头路基差异性沉降的目的,从而有效解决因其产生的桥头跳车问题。The above-mentioned treatment structure is constructed in the subgrade section of the high water level and deep soft foundation bridgehead. Force and synchronous subsidence; on the one hand, the self-weight of the stratum is reduced by the jacking pipe 2 and the buoyant body 1; As a result, the dead weight of the embankment and the foundation on the soft soil layer 6 is greatly reduced, and the subsidence force acting on the deep soft soil layer 6 is greatly reduced, thereby achieving the control of the high water level soft foundation bridgehead subgrade The purpose of differential settlement, so as to effectively solve the problem of bridge head jumping caused by it.

上述的高水位软土桥头路基的处治结构,可适用于新建高水位软土桥头路基的处治,施工可操作性强,工艺简单,其具体施工方法,包括如下步骤:The above-mentioned treatment structure for high-water-level soft soil bridgehead subgrade can be applied to the treatment of newly-built high-water-level soft soil bridgehead subgrade, with strong construction operability and simple process. The specific construction method includes the following steps:

S11.在桥头段的高水位软土地面开挖,开挖深度到土体的地下水位附近,并进一步挖掘基坑,基坑沿道路的宽度方向水平贯通,并沿道路的通行方向均匀间隔的挖掘多个,从而提供多个埋设浮力体1的空间;S11. Excavate the high water level soft ground in the bridgehead section, excavate to the depth near the groundwater level of the soil body, and further excavate the foundation pit. The foundation pit runs horizontally along the width of the road and is evenly spaced along the road direction Excavate multiple, thereby providing multiple spaces for burying the buoyant body 1;

S12.在每一基坑中对应埋设一个浮力体1;此步骤中所使用的浮力体1,优选采用浮力箱11加盖板12的结构,施工时需先在基坑中放置上端敞口的浮力箱11,再在浮力箱11的上部浇筑或安装钢筋混凝土板,密封该浮力箱11形成轻质、中空、且不透水的浮力体1;S12. A buoyant body 1 is correspondingly buried in each foundation pit; the buoyancy body 1 used in this step preferably adopts the structure of the buoyancy box 11 and the cover plate 12. During construction, it is necessary to place an open top in the foundation pit first. The buoyancy box 11, and then pour or install a reinforced concrete slab on the upper part of the buoyancy box 11, and seal the buoyancy box 11 to form a lightweight, hollow, and impermeable buoyant body 1;

S13.在每个浮力体1的上方各放置一根顶管2,顶管2的下侧开口并扣合在浮力体1的上表面;S13. Place a jacking pipe 2 above each buoyancy body 1, and the lower side of the jacking pipe 2 is opened and fastened to the upper surface of the buoyancy body 1;

S14.将相邻两顶管2通过刚性连接体3连接;刚性连接体3的现场施工,可先在相邻两顶管2的开口下沿之间连接刚性支撑件,该刚性支撑件可以是常用的钢筋笼,也可以直接采用前述处治结构中的注浆管31,将注浆管31分别与一侧的顶管2连接,之后浇筑砂浆或者混凝土形成连接两顶管2的板状结构即可;S14. Connect the two adjacent jacking pipes 2 through the rigid connecting body 3; for the on-site construction of the rigid connecting body 3, a rigid support can be connected between the lower edges of the openings of the adjacent two jacking pipes 2 first, and the rigid support can be The commonly used steel cage can also directly use the grouting pipe 31 in the aforementioned treatment structure, and connect the grouting pipe 31 to the jacking pipe 2 on one side, and then pour mortar or concrete to form a plate-like structure connecting the two jacking pipes 2. Can;

S15.在开挖部分内填筑路堤填料,形成严实度满足要求且与路堤高度匹配的路基。S15. Fill in the embankment filler in the excavated part to form a subgrade whose rigidity meets the requirements and matches the height of the embankment.

至此,便完成了新建公路环境下的高水位软土桥头路基处治,之后如常规公路施工一样,在路基上表面铺设路面结构层4,顺接桥头和路面即可。So far, the treatment of the high water level soft soil bridgehead subgrade in the new highway environment has been completed. After that, as in conventional highway construction, pavement structure layer 4 is laid on the upper surface of the subgrade, and the bridgehead and the road surface can be connected.

同时,前述的高水位软土桥头路基的处治结构,同样非常适合对既有通行公路的高水位软土桥头路基进行非开挖处治,在不阻断交通的情况下完成路基处治,解决桥头跳车问题,具体施工方法如下:At the same time, the aforementioned treatment structure of the high-water-level soft soil bridgehead subgrade is also very suitable for the trenchless treatment of the high-water-level soft soil bridgehead subgrade of the existing highway. Vehicle problems, the specific construction methods are as follows:

S21.在桥头段路堤土体的地下水位附近顶入圆管体,使圆管体沿道路的宽度方向水平贯通路堤,且圆管体沿道路的通行方向均匀间隔布置多个;此处需要说明的是,因处在高水位软基土层的环境之下,公路因施工时的人工填筑路堤,以及在运营后经长时间的碾压,路堤土体出现了明显的严实度区别,即如图1中所示的,地下水位以上的土体较为严实,这一情况与前述新建高水位软土桥头路基的处治施工时,步骤S15的人工填筑路堤填料压实形成的路堤较为相似,当然也可能是车辆运行碾压而自然形成的,但本领域的技术人员习惯性的统一称这一部分的土体为路堤填土5,而地下水位以下的土体,因水含量较高,土体软化仍然保持松软土质的缘故,称其为软土层6;S21. Push the circular pipe body near the groundwater level of the embankment soil body at the bridgehead section, so that the circular pipe body horizontally penetrates the road embankment along the width direction of the road, and the circular pipe bodies are evenly spaced along the traffic direction of the road; it needs to be explained here However, due to the environment of high water level and soft soil layer, the road embankment is artificially filled during construction, and after long-term rolling after operation, the soil mass of the embankment has obvious differences in severity, that is, As shown in Figure 1, the soil above the groundwater level is relatively tight, and this situation is similar to the embankment formed by the artificial embankment filling in step S15 during the treatment and construction of the newly built high-water-level soft soil bridgehead subgrade. Of course, it may also be formed naturally by the rolling of vehicles, but those skilled in the art habitually call this part of the soil body as embankment fill 5, and the soil body below the groundwater level, due to the high water content, soil It is called soft soil layer 6 because the body softens and still maintains the soft soil quality;

此步骤中,圆管体的具体顶入方式,采用基建施工中常用的压力顶进、夯管锤锤进等方式均可;且此处使用的圆管体,可以是完整的薄壁钢筋混凝土管,此类完整的管体其两侧中部管壁上预设的布管孔21,且布管孔21沿管体的长度方向均匀间隔布置多个;圆管体也可以是两个半管结构拼装而成的组合管,顶入时两个半管呈上下位置排布,管体上同样设置布管孔21,布管孔21具体开设在上方的半管体上,且位置靠近该半管体的下沿开口,并同样沿半管的长度方向均匀间隔布置多个;In this step, the specific jacking method of the circular pipe body can be carried out by means of pressure jacking, pipe ramming hammer hammering, etc. commonly used in infrastructure construction; and the circular pipe body used here can be a complete thin-walled reinforced concrete Pipe, such a complete pipe body has pre-set pipe routing holes 21 on the middle pipe wall on both sides, and the pipe routing holes 21 are evenly spaced along the length direction of the pipe body; the round pipe body can also be two half pipes For the combined pipe assembled by the structure, the two half pipes are arranged in the upper and lower positions when they are jacked in. The pipe body is also provided with pipe routing holes 21. The pipe routing holes 21 are specifically opened on the upper half pipe body, and the position is close to the half pipe body. The lower edge of the pipe body is opened, and a plurality of them are equally spaced along the length direction of the half pipe;

S22.去除圆管体内的土体;S22. Remove the soil in the circular tube;

S23.通过圆管体两侧中部管壁上预设的布管孔21,向圆管体外侧的土体内打入刚性连接体3,使相邻两个圆管体通过刚性连接体3连接为一体;现场施工时,优选采用如下方法:先通过圆管体上的布管孔21向外侧土体内打入注浆管31,使注浆管31的另一端插入相邻圆管体上的布管孔21内,再通过注浆管 31灌注砂浆,使砂浆通过注浆管31管壁上的注浆孔渗入土体,尤其是向软土层6中渗入更多,多根注浆管31周围的砂浆连成一片形成平铺状,砂浆固化形成固定连接圆管体、注浆管31和土体的刚性连接体3;S23. Drive the rigid connecting body 3 into the soil outside the cylindrical body through the preset piping holes 21 on the pipe wall in the middle of both sides of the cylindrical body, so that the two adjacent cylindrical bodies are connected by the rigid connecting body 3 as In the on-site construction, the following method is preferably used: first, drive the grouting pipe 31 into the outer soil through the pipe distribution hole 21 on the circular pipe body, and insert the other end of the grouting pipe 31 into the cloth on the adjacent circular pipe body. In the pipe hole 21, the mortar is poured through the grouting pipe 31, so that the mortar penetrates into the soil through the grouting hole on the pipe wall of the grouting pipe 31, especially into the soft soil layer 6, and multiple grouting pipes 31 The surrounding mortar is connected into one piece to form a tiled shape, and the mortar solidifies to form a rigid connection body 3 that fixedly connects the circular pipe body, the grouting pipe 31 and the soil body;

S24.去除圆管体的位于刚性连接体3下方的管壁,使圆管体形成半管状拱形结构的顶管2;此步骤中,若步骤S21中采用的是完整的薄壁钢筋混凝土管,则破碎圆管体的位于刚性连接体3下方的管壁,形成半管状的顶管2即可;若步骤S21中采用的是两个半管结构拼装而成的组合管,则抽出下部的半管体,以上部的半管体作为顶管2即可;S24. Remove the pipe wall below the rigid connecting body 3 of the circular pipe body, so that the circular pipe body forms the jacking pipe 2 of the semi-tubular arch structure; in this step, if the complete thin-walled reinforced concrete pipe is used in step S21 , then the pipe wall of the circular pipe body below the rigid connecting body 3 is broken to form a semi-tubular top pipe 2; if the combined pipe assembled by two half-pipe structures is used in step S21, the lower part is extracted. Half-pipe body, the upper half-pipe body can be used as the top pipe 2;

S25.挖掘顶管2下方的土体(具体为图1中所示的软土层6),形成沿道路的宽度方向水平贯通的基坑,基坑的尺寸应与浮力体1的大小相适应;S25. Excavate the soil body below the jacking pipe 2 (specifically, the soft soil layer 6 shown in FIG. 1 ) to form a foundation pit that runs horizontally along the width direction of the road. The size of the foundation pit should be adapted to the size of the buoyant body 1 ;

S26.向基坑中置入浮力体1,使浮力体1的上表面顶压在顶管2和部分刚性连接体3的下部。S26. Place the buoyant body 1 into the foundation pit, so that the upper surface of the buoyancy body 1 is pressed against the lower part of the jacking pipe 2 and part of the rigid connecting body 3 .

需要说明的是,以上优选实施例仅用以说明本实用新型的技术方案,而非对其限制;尽管参照前述实施例对本实用新型进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述实施例所记载的技术方案进行修改,或者对其中部分或者全部技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本实用新型实施例技术方案的范围,其均应涵盖在本实用新型的权利要求和说明书的范围当中。It should be noted that the above preferred embodiments are only used to illustrate the technical solutions of the present utility model, but not to limit them; although the present utility model has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: The technical solutions described in the foregoing embodiments can still be modified, or some or all of the technical features thereof can be equivalently replaced; and these modifications or replacements do not make the essence of the corresponding technical solutions depart from the scope of the technical solutions of the embodiments of the present invention , which shall be included in the scope of the claims and description of the present invention.

Claims (4)

1. The utility model provides a high water level weak soil bridgehead road bed's punishment structure, sets up in the soil body of bridgehead road bed section road surface structure layer below, its characterized in that includes:
a buoyancy body arranged in the soil body below the underground water level and having a volume density of not more than 1.0g/cm3The floating bodies are arranged at intervals along the passing direction of the road, and each floating body is horizontally arranged along the width direction of the road;
the upper part of each buoyancy body is provided with one jacking pipe which is horizontally arranged in the same direction as the buoyancy bodies, the jacking pipes are of a half-pipe structure with one side opened, and the openings of the jacking pipes are buckled on the upper surfaces of the buoyancy bodies; and
and the rigid connecting body is connected between the two adjacent jacking pipes.
2. The treatment structure of a high water level soft soil bridgehead subgrade according to claim 1,
the buoyancy body is a hollow box structure.
3. The treatment structure of a high water level soft soil bridgehead subgrade according to claim 1,
the rigid connector includes: the grouting pipe and the mortar board are horizontally connected to the lower edges of the openings of the two adjacent jacking pipes, the grouting pipe is coated in the mortar board, a plurality of grouting holes are formed in the pipe wall of the grouting pipe, and the grouting pipes are uniformly arranged at intervals along the length direction of the jacking pipes.
4. The treatment structure of a high water level soft soil bridgehead subgrade according to claim 3,
the side wall of the top pipe, which is close to the opening, is provided with a plurality of pipe distribution holes, the pipe distribution holes are uniformly arranged at intervals along the length direction of the top pipe, and two ends of the grouting pipe are respectively clamped in the corresponding pipe distribution holes of two adjacent top pipes.
CN201921542590.5U 2019-09-17 2019-09-17 A treatment structure for high water level soft soil bridgehead subgrade Expired - Fee Related CN210975403U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921542590.5U CN210975403U (en) 2019-09-17 2019-09-17 A treatment structure for high water level soft soil bridgehead subgrade

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921542590.5U CN210975403U (en) 2019-09-17 2019-09-17 A treatment structure for high water level soft soil bridgehead subgrade

Publications (1)

Publication Number Publication Date
CN210975403U true CN210975403U (en) 2020-07-10

Family

ID=71443832

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921542590.5U Expired - Fee Related CN210975403U (en) 2019-09-17 2019-09-17 A treatment structure for high water level soft soil bridgehead subgrade

Country Status (1)

Country Link
CN (1) CN210975403U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110485230A (en) * 2019-09-17 2019-11-22 招商局重庆交通科研设计院有限公司 A kind for the treatment of structures and construction method of high water level weak soil Bridgehead by Blastig

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110485230A (en) * 2019-09-17 2019-11-22 招商局重庆交通科研设计院有限公司 A kind for the treatment of structures and construction method of high water level weak soil Bridgehead by Blastig
CN110485230B (en) * 2019-09-17 2024-04-02 招商局重庆交通科研设计院有限公司 Treatment structure and construction method of high-water-level soft soil bridge head roadbed

Similar Documents

Publication Publication Date Title
CN108560568B (en) High-fill tunnel load shedding protection structure and construction method thereof
CN109137942B (en) Deformation self-adaptive drainage slide-resistant pile for expansive soil slope and construction method
CN108560542B (en) A kind of bidirectional reinforcement of waste tire covering building slag and construction method thereof
CN110004991B (en) Underground structure anti-floating system based on convex wing foot plate and construction method
CN104846840B (en) A kind of shallow embedding reinforcement of soft soil integrated pipe canal device and construction method
CN109750571B (en) Road collapse emergency and permanent retaining integrated structure and construction method
CN103774674B (en) A kind of steel pipe underpinned pile and anchor pole deep foundation pit supporting structure and construction method thereof
CN107100179B (en) Light combined retaining structure and method for treating large-range high-fill slope engineering
CN106049196B (en) Flexible pile combines ballastless track roadbed construction method with stake raft with section
CN111677095A (en) Construction method of drainage pipeline
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN111305027A (en) Rapid repair construction method and repair structure for pavement collapse in karst area
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN107288120A (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash
CN112681374A (en) Shallow-buried underground-excavated channel cover excavation top-down construction method under complex conditions
CN110485230A (en) A kind for the treatment of structures and construction method of high water level weak soil Bridgehead by Blastig
CN107700521B (en) A building foundation reinforcement underpinning pier and its construction method
CN203834468U (en) Internal expansion type miniature concrete pile
CN112647468A (en) Filling structure and method for high slope permeable site
CN108035379A (en) A kind of pipe gallery and its construction method
CN108824412B (en) Soft foundation treatment method based on gabion wall reinforced soil and dynamic compaction
CN207032212U (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash
CN210975403U (en) A treatment structure for high water level soft soil bridgehead subgrade
CN106836034B (en) A flexible load-reducing system and construction method of high-fill cover slab culvert
CN219018369U (en) A portal structure for non-excavation reinforcement of existing cable trenches

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200710