CN106424165B - For processing the loop system and its operation method of steel band - Google Patents

For processing the loop system and its operation method of steel band Download PDF

Info

Publication number
CN106424165B
CN106424165B CN201611070673.XA CN201611070673A CN106424165B CN 106424165 B CN106424165 B CN 106424165B CN 201611070673 A CN201611070673 A CN 201611070673A CN 106424165 B CN106424165 B CN 106424165B
Authority
CN
China
Prior art keywords
swing arm
arm door
steel band
looping car
guide rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611070673.XA
Other languages
Chinese (zh)
Other versions
CN106424165A (en
Inventor
朱继乔
胡军
朱国荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUJIAN HONGWANG INDUSTRIAL Co.,Ltd.
Hongwang Holding Group Co.,Ltd.
Original Assignee
Hong Wang Investor Group Co Ltd
Fujian Wang Wang Industrial Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hong Wang Investor Group Co Ltd, Fujian Wang Wang Industrial Co Ltd filed Critical Hong Wang Investor Group Co Ltd
Priority to CN201611070673.XA priority Critical patent/CN106424165B/en
Publication of CN106424165A publication Critical patent/CN106424165A/en
Application granted granted Critical
Publication of CN106424165B publication Critical patent/CN106424165B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B41/00Guiding, conveying, or accumulating easily-flexible work, e.g. wire, sheet metal bands, in loops or curves; Loop lifters

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Power-Operated Mechanisms For Wings (AREA)
  • Transmission Devices (AREA)

Abstract

The present invention provides a kind of for processing the loop system of steel band, including guide rail, it is placed in slidable looping car on guide rail, looping car is driven to fill the driving mechanism of set to steel band, it drives looping car to put the jockey pulley of set to steel band and swing arm door machine structure of the guide rail two sides to lift steel band is set, looping car includes car body and two sliding rails in "eight" shape separation on the car body, swing arm door machine structure includes that the swing arm door being oppositely arranged and the swing arm door for driving swing arm door to rotate lead and turn component, swing arm door, which is led, to be turned component one end and is fixed on swing arm door, the cooperation of the sliding rail of the other end and looping car.The present invention also provides a kind of for processing the operation method of the loop system of steel band.The present invention is used to process looping car in the loop system of steel band and occupies little space, and looping car can quickly complete automatically through swing arm door machine structure and cover and put set to filling for steel band, improve loop system the degree of automation.

Description

For processing the loop system and its operation method of steel band
Technical field
The present invention relates to the manufacture field of steel band more particularly to a kind of loop systems and its operation side for processing steel band Method.
Background technique
For stainless steel belt during processing, carrying out annealing to the steel band after mill milling is the weight in process One of step is wanted, to eliminate the hardening effect of steel strip surface, improves the mechanical performance of steel band.In the mistake that steel band is made annealing treatment Cheng Zhong, need to use loop system store, conveying steel belt, to guarantee that whole production line still is able to continuously in roll change Operation.
Existing loop system has multiple looping cars, and during filling set, the looping car in system can pull open one by one, The amount of storage of steel band is improved, when steel band conveys change of lap, i.e., when front end stops conveying steel belt, to pass through the steel band amount of storage Still can continuously it convey to the back-end, when detailed process is that the first handling rolls of output end have conveyed fastly, the first handling rolls steel band Tail end stop conveying on the conveyor line, the second handling rolls are changed on carriage, and the steel band front end of the second handling rolls is pulled to The tail end of the steel band of pipeline and the first handling rolls welds, and forms a continuous steel band, in welding, the first handling rolls steel band Rear end conveying always, loop system be in put set during, more looping cars in system can be close one by one, will store Amount conveying, whole process can be understood as a large-scale reciprocal broken line, become a small-sized reciprocal broken line, the break of broken line Quantity is unchanged, the amount of storage output of steel band in change procedure.So will not because of change of lap the second handling rolls steel band front end with Stop the conveying (such as sending band to annealing furnace) of steel band rear end when the tail end welding of the first handling rolls steel band.Currently, existing In loop system, the loop trolley for needing a looping car to cooperate several, loop trolley quantity is more, entire loop system knot Structure is complicated, and occupied space is big.
Summary of the invention
In view of the above, it is necessary to provide one kind to occupy little space by the present invention, and high degree of automation for processing The loop system of steel band.
Technical solution provided by the invention is as follows: it is a kind of for processing the loop system of steel band, to store steel band, including lead Rail, be placed in slidable looping car on guide rail, to provide the driving mechanism of pulling force when looping car fills set to steel band, to maintain The jockey pulley of pulling force and several groups swing arm door machine of the guide rail two sides to lift steel band is set when looping car puts set to steel band Structure, looping car include car body and two sliding rails in "eight" shape separation on the car body, and each group of swing arm door machine structure includes phase It swing arm door to setting and drives the swing arm door of swing arm door rotation to lead to turn component, swing arm door, which is led, to be turned one end of component and be fixed on pendulum On arm door, the sliding rail in the other end and looping car cooperates, to pull car body along guide rail in driving mechanism pulling or jockey pulley tension When upper movement, the swing arm door on swing arm door machine structure lead turn component accordingly cooperate on the slide rail driving swing arm door rotation, with open Or closure swing arm door.
Further, each swing arm door includes rotation axis and is vertically arranged several swing arms on the rotating shaft, Rotation axis is rotationally built up in the side of guide rail, the parallel spaced set of several swing arms.
Further, there is rotatable roller in the top surface of each swing arm, and roller is installed along swing arm extending direction.
Further, each swing arm door machine structure includes the mounting rack for being relatively built up in guide rail two sides two-by-two, each Mounting rack includes two support rods being arranged along guide rail extending direction, is mounted between two support rods and set up and down first connects The first connecting shaft that fishplate bar and the second connecting plate and fixedly setting up is connected between the first connecting plate and the second connecting plate with And second connecting shaft, the swing arm door lead turn component include affixed arm, connect with affixed arm first rotate part, rotate with first The hinged connecting rod of part, rotate part with connecting rod hinged second, and one end of affixed arm is fixed in the rotation axis of swing arm door, and second It rotates one end of part and the sliding rail of looping car cooperates, described first, which rotates, offers axle sleeve hole on part, for the first connecting bushing Enter, so that first part that rotates can be rotated around the first connecting shaft, second rotates part equipped with overlap aperture, for the second connecting bushing Enter, so that second part that rotates can be rotated around the second connecting shaft.
Further, the driving mechanism is arranged in guide rail side, to drive looping car to move on guide rail, driving machine Structure includes hoist engine, and the hoist engine includes shaft, the reel that is set in shaft, offers helix groove, spiral on reel Wire casing is built-in with wirerope, and wirerope is connect with the looping car, and the reel is equipped with retainer, retainer and reel it Between gap be less than wirerope diameter.
Further, the looping car includes the deflecting roller of car body and setting on the car body, and the deflecting roller is two, if It sets in chassis one end of car body, to cooperate with the wirerope of driving mechanism.
Further, the driving mechanism further includes directive wheel and fixing seat, and directive wheel is two, and is lived apart in guide rail The two sides of one end, the race of steel wire penetrating directive wheel simultaneously bypass in looping car after the race of two directive wheels, connect with fixing seat It connects, fixed seating is in the extension line direction for being located at guide rail end.
In addition, it is necessary to provide a kind of for processing the operation method of the loop system of steel band by the present invention.
It is a kind of for processing the operation method of the loop system of steel band, when filling set, the swing arm door of several swing arm door machine structures is in Opening state, driving mechanism starting, an end motion of the looping car on guide rail to separate jockey pulley, when looping car moves to a pendulum When arm door machine structure, the swing arm door on swing arm door machine structure is led at the narrow end for turning the sliding rail that component accordingly enters looping car, and with Looping car continues to move on guide rail, and swing arm door, which is led, turns component on the slide rail from narrow end to wide end gradually transition, and swing arm door is closed, Looping car passes through, and the swing arm of the swing arm door of closure holds up the steel band that looping car fills set;
When putting set, the swing arm door in several swing arm door machine structures is in closed state, and jockey pulley tension drives looping car along guide rail An end motion to jockey pulley, when looping car moves to a swing arm door machine structure, the swing arm door on swing arm door machine structure, which is led, turns component Accordingly at the wide end of the sliding rail of looping car, and as looping car continues to move on guide rail, swing arm door, which is led, to be turned component and exists From wide end to narrow end gradually transition on sliding rail, swing arm door opens simultaneously looping car and passes through.
Compared with prior art, the present invention be used to process the loop system of steel band by design swing arm door machine structure and with pendulum One looping car of arm door machine structure cooperation, to reduce the cost of loop system, and looping car occupies sky in the loop system Between it is small, swing arm door machine structure is passed through by looping car flexible automaticly, quickly completes filling set and put set to steel band, raising loop System automation degree.
Detailed description of the invention
Fig. 1 is the present invention for processing the structural front view when loop system of steel band fills set;
Fig. 2 is the top view of Fig. 1;
Fig. 3 is the present invention for processing the structural front view when loop system of steel band puts set;
Fig. 4 is the top view of Fig. 3;
Fig. 5 is the main view of looping car;
Fig. 6 is the top view of Fig. 5;
Fig. 7 is the main view of wherein one group of swing arm door machine structure;
Fig. 8 is the top view of Fig. 7;
Fig. 9 is that the swing arm door Yu swing arm door of swing arm door machine structure wherein side in Fig. 7 lead the schematic perspective view for turning component;
Figure 10 is the main view of swing arm door closed state in swing arm door machine structure of the invention;
Figure 11 is the top view of swing arm door closed state in swing arm door machine structure of the invention;
Figure 12 is the top view of swing arm door opening state in swing arm door machine structure of the invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments, not In the case where conflict, the features in the embodiments and the embodiments of the present application be can be combined with each other, and below with reference to the accompanying drawings and be tied Conjunction embodiment is next, and the present invention will be described in detail.
It is a kind of for processing the loop system of steel band referring to FIG. 1 to FIG. 4, to store steel band 100, including guide rail 10, set In the looping car 20 on guide rail 10, the driving mechanism to drive looping car 20 to move along guide rail 10 when steel band 100 fills set 30, to the jockey pulley (not shown) that drives looping car 20 to move along guide rail 10 when steel band 100 puts set and it is arranged in guide rail Several groups swing arm door machine structure 40 of 10 two sides to lift steel band 100.Fig. 1, Fig. 2 show set process of filling, and looping car 20 is driving Under motivation structure 30 acts on, moved from diagram location A to B location along guide rail 10, by the composite steel band formed back and forth it is round-trip away from One end from elongation, i.e. relative tension roller is more and more remoter, improves 100 amount of storage of steel band, can continuously not so as in steel band change of lap The amount of storage of disconnected ground conveying steel belt 100, maintains production line continuously to run, and the support layering of each swing arm door machine structure 40 Steel band 100;Fig. 3, Fig. 4 show set process of putting, and looping car 20 is under the action of jockey pulley, from diagram B on guide rail 10 It sets to position A movement, i.e. one end of relative tension roller is more and more closer, and the amount of storage of steel band 100 is continuously delivered to tension One end of roller exports, and provides the coil of strip change of lap time without stopping conveying.
Guide rail 10 is two, is set in parallel on the ground, to support and guide looping car 20.Please refer to Fig. 5, Fig. 6, looping car 20 include car body 21, several rubber rollers 22 being mounted in car body 21 and deflecting roller 23, are placed in car body 21 1 Several steel band carrying rollers 24 at end and the sliding rail 25 for being fixed on 21 top of car body.Car body 21 includes chassis 211, is formed in chassis The support frame 212 at 211 both ends, the upper frame 213 for being connected to two support frames, 212 top and the idler wheel being arranged under chassis 211 214, idler wheel 214 is accordingly placed on guide rail 10.In the present embodiment, rubber roller 22 is three, is arranged in parallel in the chassis of car body 21 On 211, the spacing between every adjacent two rubber rollers 22 is equal.Specifically, the both ends of each 22 roll shaft of rubber roller pass through an axis respectively Seat 221 is held to be mounted on chassis 211, the roll surface of rubber roller 22 is contacted with 100 surface of steel band of transmission, the roll surface of rubber roller 22 by with Friction is generated between steel band 100, and then the bearing block 221 of 22 opposite end of rubber roller is driven to rotate.
Deflecting roller 23 be two (please referring to top view shown in Fig. 6), 211 one end of chassis of car body 21 is set, to Driving mechanism 30 cooperates, and drives looping car 20 to slide on guide rail 10 by driving mechanism 30.
On the support frame 212 that several steel band carrying rollers 24 are lived apart in car body 21 towards jockey pulley one end, far from 23 institute of deflecting roller One end, steel band carrying roller 24 cooperate rubber roller 22, realize the rotating in 21 one end of car body of steel band 100.It is appreciated that in jockey pulley One end be correspondingly provided with the roll body (not shown) of corresponding 22 quantity of rubber roller, with 22 corresponding matching of rubber roller on looping car 20 It rotates, to be formed between jockey pulley one end and looping car 20 with the steel band that multilayer is round-trip.Specifically, steel band is processed On line, steel band is discharged by handling rolls and is sent out (after bundle machine pressure is thinning) along pipeline, looping car 20 and tension are then passed through Roller end it is round-trip after, exported in one end of jockey pulley, into following process section, such as enter annealed wire or pickling line.Steel band 100 exists It is equipped with the guidance of steel band carrying roller 24 when each rubber roller 22 of one end coiling of looping car 20, i.e., is passing through a steel band before entering rubber roller 22 Carrying roller 24 introduces, and is drawn after laying out rubber roller 22 by a steel band carrying roller 24, specifically, steel band 100 draws from a steel band carrying roller 24 Enter after the roll surface of rubber roller 22 rotates, then drawn through another steel band carrying roller 24, generates and rub between the roll surface and steel band 100 of rubber roller 22 It wipes, and then the bearing block 221 of 22 opposite end of rubber roller is driven to rotate.
Sliding rail 25 is fixed on the upper frame 213 of car body 21, to cooperate with swing arm door machine structure 40.Sliding rail 25 is two, and In "eight" shape separation (refering to Fig. 6) on the upper frame 213 of car body 21.Sliding slot 251 is offered on every sliding rail 25, to pass through vehicle Body 21 moves on guide rail 10, the sliding slot 251 for entering one group of pulley 4226 on swing arm door machine structure 40 accordingly on sliding rail 25 Interior (please referring to Fig. 2 or Fig. 4), to drive opening or closing for swing arm door machine structure 40, for work when swing arm door machine structure 40 is opened Harness an animal to a cart 20 processes, when swing arm door machine structure 40 is closed after lift steel band.
Fig. 2 or Fig. 4 is please referred to, driving mechanism 30 is arranged in 10 side of guide rail, to drive looping car 20 in guide rail It is moved on 10.In Fig. 2, driving mechanism 30 is when being pulled to B location from location A for looping car 20, one end of steel band relative tension roller Increasingly remoter, the amount of storage of steel band increases, and realizes that the set that fills to steel band, i.e. steel band gradually become long round-trip long from short round-trip length Degree, so stores steel band.Driving mechanism 30 include motor 31, hoist engine 32, reduction gearbox 33, bracket 34, directive wheel 35 and Fixing seat 36.The main shaft of motor 31 is connect by reduction gearbox 33 with the shaft of hoist engine 32, is rotated by motor 31, and elevator is driven Machine 32 rotates, and makes 32 retractable wirerope 322 of hoist engine.Further, hoist engine 32 includes shaft, is fixedly set in shaft On reel, offer helix groove on reel, helix groove is built-in with wirerope 322, and wirerope 322 passes through the looping car that rotates 20 two deflecting rollers 23 realize that return rotates to adjust the direction that rotates.Refering to Fig. 6, in this implementation specifically, wirerope 322 It rotates two deflecting rollers 23 in horizontal U-shaped, the periphery side contacts with two deflecting rollers 23.When hoist engine 32 rotates, wirerope 322 receive or put on the helix groove on the reel of hoist engine 32, and deflecting roller 23 can be driven to rotate.In shown in Fig. 2, wirerope 322, which are located at putting for hoist engine 32, holds end, puts the state of holding in maximum, there is hoist engine 32 winding to pull and support looping car 20 from A It sets to the trend of B location.
Further, reel periphery is equipped with the retainer (not shown) axially extending along reel, between retainer and reel Gap be less than the diameter of wirerope 322, during can so preventing 322 retractable of wirerope on reel in helix groove The wrong rail on helix groove.
Several 34 supporting steel-cables 322 of the bracket;The directive wheel 35, which is mounted on wirerope 322, needs corner, realizes The corner of wirerope, directive wheel 35 is two in the present embodiment, and is lived apart in the two sides of 10 one end of guide rail.322 one end of wirerope It is connected on hoist engine, after the race of two deflecting rollers 23 in the race of directive wheel 35 and looping car 20, wirerope 322 Terminal part is connected in fixing seat 36, and 322 end of wirerope is fixed;Fixing seat 36 can be placed on the extension line of guide rail end Direction realizes wirerope 322 along guide rail direction folding and unfolding.Support roller 361 can be further equipped in fixing seat 36, for wirerope 322 By improving 322 tension of wirerope.When filling set, motor 31 is rotated, and is driven hoist engine 32 to rotate, is made 32 reel 321 of hoist engine On wirerope 322, overcome the pulling force of tension roller end, and then looping car 20 is driven to move on guide rail 10, realize to steel band 100 Fill set, store steel band amount.
Jockey pulley is to when motor 31 stops providing and fills the active force of set, the pulling force that tension roller end maintains can be by looping car 20 retract, and looping car 20 is driven to move along guide rail 10, realize that steel band 100 puts set.Shown in Fig. 4, jockey pulley by looping car 20 from B When position is pulled to location A, the amount of storage of steel band is reduced, and realizes that the set of putting to steel band, i.e. steel band gradually become from long round-trip length Short round-trip length so releases the amount of storage of steel band.During this, hoist engine 32 rotates under the pulling force effect of jockey pulley, Cooperation release wirerope 322.In Fig. 4, wirerope 322 is located at the winding end of hoist engine 32, in maximum winding state, has Meet looping car 20 and moves required 322 burst size of wirerope from B location to location A.
Several swing arm door machine structures 40 are equidistantly mounted on 10 outside of guide rail, to lift the steel band for filling set or putting during covering 100, otherwise steel band can not achieve if without that can hang under the effect of gravity if lifting in filling set elongation and fill set.Swing arm door machine structure 40 when looping car 20 passes through opening, looping car 20 pass through after close.Referring to Fig. 8, Fig. 9, each group of swing arm door machine structure 40 Led including the swing arm door 421 that is oppositely arranged and the swing arm door to drive corresponding swing arm door 421 to rotate turn component 42 and The mounting rack 43 for turning the installation of component 42 is led for corresponding swing arm door.Being oppositely arranged swing arm door 421 opposite can open or close, relatively The swing arm door 421 of setting may be provided on a bottom plate 41 (swing arm door shown in Fig. 8 is in off state).Each swing arm door 421 includes Rotation axis 4211 and several swing arms 4212 being vertically set in rotation axis 4211, rotation axis 4211 are rotationally built up in guide rail 10 side, in the present embodiment, the bottom of guide rail 10 is equipped with bottom plate 41, and rotation axis 4211 is rotationally built up on bottom plate 41. There are rotatable roller 4213 in the parallel spaced set of several swing arms 4212, the top surface of each swing arm 4212, and roller 4213 is along pendulum The installation of arm extending direction reduces the friction with steel band can rotate under the drive of steel band when support carries steel band 100.It is opposite to set When the swing arm door 421 set is closed, the swing arm 4212 on two swing arm doors 421 aligns to form several support beams two-by-two, if support carries Dried layer steel band 100.
Mounting rack 43 is relatively built up in the two sides of guide rail 10 two-by-two, the swing arm of side where each mounting rack 43 is used to install Door, which is led, turns component 42, and mounting rack 43 can be fixedly arranged on bottom plate 41.Referring to Fig. 7, each mounting rack 43 includes extending along guide rail 10 It two support rods 431 of direction setting and is mounted between two support rods 431 and the first connecting plate 432 set up and down and the Two connecting plates 433.The progress of mounting rack 43 one include fixedly set up be connected to the first connecting plate 432 and the second connecting plate 433 it Between the first connecting shaft 4343 and the second connecting shaft 4345, for cooperate swing arm door lead turn component 42 install.
Each swing arm door, which is led, to be turned component 42 and is arranged between the first connecting plate 432 of mounting rack 43 and the second connecting plate 433, And it is coupled with the first connecting shaft 4343 and the second connecting shaft 4345.Swing arm door, which is led, to be turned 42 one end of component and is fixed in swing arm In the rotation axis 4211 of door 421, the sliding slot 251 on the other end and 20 sliding rail 25 of looping car cooperates, to drive 421 turns of swing arm door It is dynamic, so that swing arm 4212 is opened simultaneously or is closed at.Please refer to Fig. 9, swing arm door lead turn component 42 include affixed arm 4221, First connect with affixed arm 4221 rotate part 4222, rotate part 4222 hinged connecting rod 4223 and connecting rod with first 4223 hinged second rotate part (figure is not marked).
One end of affixed arm 4221 is fixed in the rotation axis 4211 of swing arm door 421, offers sliding on affixed arm 4221 Slot 4227, first rotates part 4222 including being fixedly connected with each other two cranks at one end, and two cranks are formed with angle and open in fixing position Equipped with axle sleeve hole, so that the first connecting shaft 4343 is inserted in, so that first part 4222 that rotates can be rotated around the first connecting shaft 4343, In a crank far from one end of axle sleeve hole be formed with slide protrusion 4228, slide protrusion 4228 is placed in sliding groove 4227, with It is rotated by first part 4222 that rotates, slide protrusion 4228 drives affixed arm 4221 to rotate.The first another song for rotating part 4222 Handle bar that is articulated and connected 4223, the other end of connecting rod 4223 and second part that rotates are hinged.Second rotate part include first body of rod 4224 and second body of rod 4225, one end of first body of rod 4224 and one end of second body of rod 4225 are affixed, and set in fixing position It is equipped with overlap aperture, so that the second connecting shaft 4345 is inserted in, so that second part that rotates can be rotated around the second connecting shaft 4345.First bar The one end of body 4224 far from overlap aperture and connecting rod 4223 are hinged, and second body of rod 4225 is equipped with pulley far from one end of overlap aperture 4226, pulley 4226 is for accordingly sliding into the sliding slot 251 on sliding rail 25.
When filling set or putting set, as looping car 20 moves on guide rail 10, two pulleys of each group of swing arm door machine structure 40 4226 accordingly enter in the sliding slot 251 on splayed sliding rail 25, and slide in sliding slot 251, drive second to rotate part around the Two connecting shafts 4345 rotation, second rotate part drive connecting rod 4223 swing, and then drive first rotate part 4222 around first connect Spindle 4343 rotates, and the first slide protrusion 4228 to rotate on part 4222 drives affixed arm 4221 to rotate, and drives and affixed arm 4221 rotation axis 4211 being fixedly connected rotate, so that entire swing arm door 421 be driven to rotate.Two swing arm doors so can be achieved 421 open simultaneously or are closed at.
The loop system operational process that the present invention processes steel band is as follows:
It please refers to Fig. 1, Fig. 2 and combines Figure 10 to Figure 12, when filling set, the swing arm 4212 in several swing arm door machine structures 40 is initial In opened condition, looping car 20 is placed at the A in figure at B and moves, and the motor 31 in driving mechanism 30 rotates forward, by subtracting Fast case 33 drives hoist engine 32 to rotate, and hoist engine 32 is made to receive wirerope 322, and looping car 20 moves (figure from A to B on guide rail 10 Direction shown in middle horizontal arrow), one group of cunning when looping car 20 moves to one group of swing arm door machine structure 40, on swing arm door machine structure 40 Wheel 4226 accordingly enters in the sliding slot 251 of the narrow end of the splayed sliding rail 25 of looping car 20, and as looping car 20 is in guide rail Continue to move at B on 10, pulley 4226 in the sliding slot 251 on splayed sliding rail 25 from narrow end to wide end gradually transition, the Two parts that rotate will be rotated around the second connecting shaft 4345, and connecting rod 4223 is driven to swing, and then drive first to rotate part 4222 around the The rotation of one connecting shaft 4343, makes the first slide protrusion 4228 to rotate on part 4222 that affixed arm 4221 be driven to rotate, in this way, driving Rotation axis 4211 rotates, so that entire swing arm door 421 be driven to rotate, two swing arm doors 421 relatively rotate closure.Swing arm door 421 After closure, steel band 100 of the swing arm 4212 of closure to hold up the layering of looping car 20.Looping car 20 passes through several swing arm door machine structures After 40, looping car 20 is placed at the B in figure, and close to set extreme position is filled, set is filled in completion, so as in steel band change of lap, steel band 100 Amount of storage it is exportable.
It please refers to shown in Fig. 3, Fig. 4, when steel band change of lap, the output end of steel band is continued to output, and loop system, which is in put, to be covered Journey, the swing arm 4212 in swing arm door machine structure 40 is initially in closed state, and looping car 20 is located at the B in figure, and jockey pulley drives work Harness an animal to a cart 20 along guide rail 10 from B to moving (direction shown in horizontal arrow in figure), under the action of jockey pulley tension, elevator at A Machine 32 discharges wirerope 322, one group of pulley when looping car 20 moves to a swing arm door machine structure 40, on swing arm door machine structure 40 4226 accordingly enter in the sliding slot 251 of the wide end of the splayed sliding rail 25 of looping car 20, and as looping car 20 is in guide rail 10 On continue to move to A, pulley 4226, from wide end to narrow end gradually transition, drives the in the sliding slot 251 on splayed sliding rail 25 Two parts that rotate are rotated around the second connecting shaft 4345, and then connecting rod 4223 is driven to swing, so drive first rotate part 4222 around The rotation of first connecting shaft 4343, drives affixed arm 4221 to rotate, and rotation axis 4211 is driven to rotate, and drives entire swing arm door 421 Rotation, so, it can be achieved that the opposite opening of two swing arm doors 421, after swing arm door 421 is opened, looping car 20 passes through the swing arm door machine Structure 40.Similarly, after looping car 20 passes through several swing arm door machine structures 40, looping car 20 is placed at the A in figure, covers limit position close to putting It sets, set is put in completion.
In conclusion the present invention be used to process the loop system of steel band by design swing arm door machine structure and with swing arm door machine One looping car of structure cooperation, to reduce the cost of loop system, and looping car occupies little space in the loop system, passes through work Harness an animal to a cart flexible automaticly pass through swing arm door machine structure, quickly complete to steel band fill set with put set, loop system the degree of automation It is high.
The above description is only an embodiment of the present invention, is not intended to limit the scope of the invention, all to utilize this hair Equivalent structure or equivalent flow shift made by bright description is applied directly or indirectly in other relevant technology necks Domain is included within the scope of the present invention.

Claims (7)

1. it is a kind of for processing the loop system of steel band, to store steel band (100), it is characterised in that: including guide rail (10), be placed in Slidable looping car (20) on guide rail (10), to provide the driving machine of pulling force when looping car (20) fills set to steel band (100) Structure (30), to maintain looping car (20) to put set to steel band (100) when pulling force jockey pulley and be arranged in guide rail (10) two sides To lift the several groups swing arm door machine structure (40) of steel band (100), looping car (20) includes car body (21) and is in "eight" shape Two sliding rails (25) of the separation on car body (21), each group of swing arm door machine structure (40) includes the swing arm door (421) being oppositely arranged And the swing arm door of swing arm door (421) rotation is driven to lead and turn component (42), swing arm door, which is led, to be turned one end of component (42) and is fixed on pendulum On arm door (421), the sliding rail (25) in the other end and looping car (20) cooperates, in driving mechanism (30) pulling or jockey pulley Power pulls car body (21) when moving along guide rail (10), and the swing arm door on swing arm door machine structure (40), which is led, to be turned component (42) and accordingly match It closes and drives swing arm door (421) rotation on sliding rail (25), with open or close swing arm door (421), sliding rail (25) is fixed on car body (21) on upper frame (213),
Each swing arm door machine structure (40) includes the mounting rack (43) for being relatively built up in guide rail (10) two sides two-by-two, Mei Yian (43) are shelved to include two support rods (431) being arranged along guide rail (10) extending direction, be mounted between two support rods (431) and be in It first connecting plate (432) setting up and down and the second connecting plate (433) and fixedly sets up and is connected to the first connecting plate (432) The first connecting shaft (4343) and the second connecting shaft (4345) between the second connecting plate (433), the swing arm door, which is led, turns group Part (42) includes affixed arm (4221), connect with affixed arm (4221) first rotate part (4222), rotate part with first (4222) hinged connecting rod (4223), hinged with connecting rod (4223) second rotate part, and one end of affixed arm (4221) is solid Connect in the rotation axis (4211) of swing arm door (421), second rotate part one end and looping car (20) sliding rail (25) cooperate, institute It states first and rotates and offer axle sleeve hole on part (4222), so that the first connecting shaft (4343) is inserted in, so that first rotates part (4222) it can be rotated around the first connecting shaft (4343), second rotates part equipped with overlap aperture, for the second connecting shaft (4345) set Enter, so that second part that rotates can be rotated around the second connecting shaft (4345).
2. according to claim 1 for processing the loop system of steel band, it is characterised in that: each swing arm door It (421) include rotation axis (4211) and several swing arms (4212) being vertically set on rotation axis (4211), rotation axis (4211) Rotationally it is built up in the side of guide rail (10), the parallel spaced set of several swing arms (4212).
3. according to claim 2 for processing the loop system of steel band, it is characterised in that: the top of each swing arm (4212) Face has rotatable roller (4213), and roller (4213) is installed along swing arm (4212) extending direction.
4. according to claim 1 for processing the loop system of steel band, it is characterised in that: the driving mechanism (30) sets It sets in guide rail (10) side, to drive looping car (20) to move on guide rail (10), driving mechanism (30) includes hoist engine (32), the hoist engine (32) include shaft, the reel that is set in shaft, offer helix groove, helix groove on reel It is built-in with wirerope (322), wirerope (322) is connect with the looping car (20), and the reel is equipped with retainer, blocking Gap between part and reel is less than the diameter of wirerope (322).
5. according to claim 4 for processing the loop system of steel band, it is characterised in that: the looping car (20) includes The deflecting roller (23) of car body (21) and setting on the car body, the deflecting roller (23) are two, and the chassis in car body (21) is arranged (211) one end, to cooperate with the wirerope (322) of driving mechanism (30).
6. according to claim 5 for processing the loop system of steel band, it is characterised in that: the driving mechanism (30) is also Including directive wheel (35) and fixing seat (36), directive wheel (35) is two, and is lived apart in the two sides of guide rail (10) one end, steel Cord (322) pass through the race of directive wheel (35) and around the race of two deflecting rollers (23) in looping car (20) after, and it is described Fixing seat (36) connection, fixing seat (36) are located at the extension line direction of guide rail end.
7. a kind of described in any one of claims 1-6 for processing the operation method of the loop system of steel band, it is characterised in that:
When filling set, in opened condition, driving mechanism (30) starts the swing arm door (421) of several swing arm door machine structures (40), looping car (20) to the end motion far from jockey pulley on guide rail (10), when looping car (20) moves to a swing arm door machine structure (40), Swing arm door on swing arm door machine structure (40) lead turn component (42) accordingly into looping car (20) sliding rail (25) narrow end at, and As looping car (20) continues to move on guide rail (10), swing arm door, which is led, turns component (42) on sliding rail (25) from narrow end to wide end Gradually transition, swing arm door (421) closure, looping car (20) pass through, and the swing arm of the swing arm door (421) of closure holds up looping car (20) Fill the steel band (100) of set;
When putting set, the swing arm door (421) in several swing arm door machine structures (40) is in closed state, and jockey pulley tension drives looping car (20) end motion along guide rail (10) to jockey pulley, when looping car (20) moves to a swing arm door machine structure (40), swing arm door Swing arm door in mechanism (40), which is led, turns component (42) accordingly at the wide end of the sliding rail (25) of looping car (20), and with work Harness an animal to a cart (20) continue to move on guide rail (10), swing arm door, which is led, turns component (42) on sliding rail (25) from wide end to narrow end gradually mistake It crosses, swing arm door (421) opens simultaneously, and looping car (20) passes through.
CN201611070673.XA 2016-11-29 2016-11-29 For processing the loop system and its operation method of steel band Active CN106424165B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611070673.XA CN106424165B (en) 2016-11-29 2016-11-29 For processing the loop system and its operation method of steel band

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611070673.XA CN106424165B (en) 2016-11-29 2016-11-29 For processing the loop system and its operation method of steel band

Publications (2)

Publication Number Publication Date
CN106424165A CN106424165A (en) 2017-02-22
CN106424165B true CN106424165B (en) 2018-12-11

Family

ID=58219297

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611070673.XA Active CN106424165B (en) 2016-11-29 2016-11-29 For processing the loop system and its operation method of steel band

Country Status (1)

Country Link
CN (1) CN106424165B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107971350A (en) * 2017-12-03 2018-05-01 哈尔滨广旺机电设备制造有限公司 The adiabatic guide and guard strainer in one kind outlet
CN115283463A (en) * 2022-08-25 2022-11-04 广东斗原精密技术有限公司 Steel belt buffering loop device occupying small space

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3960260A (en) * 1974-08-08 1976-06-01 Bridgestone Tire Company Limited Apparatus for and method of conveying and handling tire bead wires
CN201493322U (en) * 2009-08-24 2010-06-02 武汉钢铁(集团)公司 Detachable horizontal mobile sleeve swing door
CN102101128A (en) * 2011-01-31 2011-06-22 中冶赛迪工程技术股份有限公司 Novel two-way controllable looping system
CN206455005U (en) * 2016-11-29 2017-09-01 福建宏旺实业有限公司 Loop system for processing steel band

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3960260A (en) * 1974-08-08 1976-06-01 Bridgestone Tire Company Limited Apparatus for and method of conveying and handling tire bead wires
CN201493322U (en) * 2009-08-24 2010-06-02 武汉钢铁(集团)公司 Detachable horizontal mobile sleeve swing door
CN102101128A (en) * 2011-01-31 2011-06-22 中冶赛迪工程技术股份有限公司 Novel two-way controllable looping system
CN206455005U (en) * 2016-11-29 2017-09-01 福建宏旺实业有限公司 Loop system for processing steel band

Also Published As

Publication number Publication date
CN106424165A (en) 2017-02-22

Similar Documents

Publication Publication Date Title
CN106424164B (en) The operation method of loop system and loop system
US6390535B1 (en) Sliding door closure apparatus
CN105229251A (en) For opening and closing the device of car door
CN209591673U (en) Fire-resistant isinglass belt coating machine
CN106424165B (en) For processing the loop system and its operation method of steel band
CN102296901A (en) Device capable of automatically opening and closing cabin door in compact cabin body
CN110239871A (en) A kind of logistics carrying storage system
CN206088565U (en) Material system is received in automation of detonator extruder
CN201390575Y (en) Winding machine
CN206455004U (en) loop system
CN206455005U (en) Loop system for processing steel band
CN206308399U (en) For the swing arm door mechanism of loop system and loop system
CN208103460U (en) A kind of uncoiler of position-adjustable
CN205976880U (en) Storehouse is with electronic door that moves on whole
CN106367581A (en) Swing arm door mechanism for loop system and loop system
KR100898825B1 (en) An operating apparatus for a motor curtain
CN202500432U (en) Automatic on-off cabin door device inside compact cabin body
CN109466418A (en) A kind of automobile-used automatic covering lid cargo device of cargo transport
CN115246117A (en) Composite robot with openable and closable sealing door mechanism and control method thereof
CN107716598A (en) A kind of guiding mechanism of cable machine
CN110203126A (en) A kind of automobile-used covering cargo device of cargo transport
CN102241346A (en) Take-up and pay-off device for belt winding mechanism of belt conveyor
CN102619441B (en) Fully-automatic logistics dustproof door
CN2398154Y (en) Stringing machine for contact net of electrified railway
CN110773585A (en) Bidirectional operation controllable vertical loop

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Zhu Jiqiao

Inventor after: Hu Jun

Inventor after: Zhu Guorong

Inventor before: Zhu Jiqiao

Inventor before: Hu Jun

Inventor before: Zhu Guorong

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 355006 Wan Wu Zhen Shang Yang Cun, Fu'an City, Ningde City, Fujian Province

Patentee after: FUJIAN HONGWANG INDUSTRIAL Co.,Ltd.

Patentee after: Hongwang Holding Group Co.,Ltd.

Address before: 355006 Wan Wu Zhen Shang Yang Cun, Fu'an City, Ningde City, Fujian Province

Patentee before: FUJIAN HONGWANG INDUSTRIAL Co.,Ltd.

Patentee before: HONGWANG INVESTMENT GROUP Co.,Ltd.

CP01 Change in the name or title of a patent holder