CN106401588A - 断层区内工作面开采期间冲击地压防控方法 - Google Patents

断层区内工作面开采期间冲击地压防控方法 Download PDF

Info

Publication number
CN106401588A
CN106401588A CN201610915920.5A CN201610915920A CN106401588A CN 106401588 A CN106401588 A CN 106401588A CN 201610915920 A CN201610915920 A CN 201610915920A CN 106401588 A CN106401588 A CN 106401588A
Authority
CN
China
Prior art keywords
fault
energy
working face
fault zone
energy release
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610915920.5A
Other languages
English (en)
Other versions
CN106401588B (zh
Inventor
潘立友
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University of Science and Technology
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN201610915920.5A priority Critical patent/CN106401588B/zh
Publication of CN106401588A publication Critical patent/CN106401588A/zh
Application granted granted Critical
Publication of CN106401588B publication Critical patent/CN106401588B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/18Methods of underground mining; Layouts therefor for brown or hard coal

Abstract

本发明公开了一种断层区内工作面开采期间冲击地压防控方法,首先在施工完采区巷道且工作面开采前,首先在采区巷道中的断层区域两侧,距离断层面100m的范围内,向煤层中施工一排能量释放孔;当工作面推进到能量释放孔开始位置时,如发现能量释放孔之间仍存在冲击危险时,应停止开采,再沿采区巷道向煤层中施工一排卸压爆破孔,起爆后重新释放能量,从而消除断层区的冲击地压危险性,使工作面可安全通过断层区域。本发明对于断层区、深部冲击地压矿井,能实现断层区域的安全开采。视情况分两步进行泄压,减少工作量,节约生产成本。

Description

断层区内工作面开采期间冲击地压防控方法
技术领域
本发明属于煤矿开采技术领域。
背景技术
冲击地压是我国煤矿重大灾害之一,冲击地压大多与地质条件密切相关,地质构造区域发生的冲击地压占总数的60%以上,一般发生在断层、褶曲等部位较多。随着开采深度的增加,断层区域的冲击地压时有发生,冲击强度随深度也增大,这种断层区域的冲击灾害已严重制约着我国煤矿的安全生产。实践证明,巷道掘进进入断层影响区或工作面推进到断层影响区时,由于断层区内岩层相对破碎和较软,巷道周围以破碎煤岩为主,应力分布复杂,而煤层冲击危险性强,在采掘工程扰动条件下会发生冲击地压,这种类型的冲击地压隐蔽性强,冲击地压发生时伴随顶板冒落等次生灾害,会造成煤岩突然跨落,防范难度极大,一旦煤岩突然跨落难支护。这种断层区域冲击地压的防控有别于常规方法,采用常规方法治理难以做到有效控制。由于断层带煤(岩)体由破碎到裂隙的差异性,巷道两帮煤层属于过渡型介质,采用常规措施很难实现有效防控。因此,需要发明一种适应断层区域的冲击地压防控方法。
发明内容
本发明的目的是提出一种适应断层区内工作面开采期间冲击地压防控方法。
为达到上述目的,本发明采取的技术方案是:
一种断层区内工作面开采期间冲击地压防控方法,其特征在于,步骤如下:
第一步、在施工完采区巷道且工作面开采前,首先在采区巷道中的断层区域两侧,距离断层面100m的范围内,沿采区巷道距离底板1.2m的高度,向煤层中施工一排能量释放导向钻孔,简称能量释放孔,能量释放孔直径110-150mm,孔深8-15m,间距由大到小,间距从3.0m开始,至靠近断层面时减到0.4-0.5m;该能量释放孔可将断层附近能量与煤层积聚能量随着工作面的开采提前得到耦合释放;
第二步、当工作面推进到能量释放孔开始位置时,如发现能量释放孔之间仍存在冲击危险时,说明能量释放不重分,应停止开采,再沿采区巷道距离底板1.2m的高度,向煤层中施工一排卸压爆破孔,卸压爆破孔的孔径42mm、间距5m、深度8.0--10.0m,装药量为孔深的1/3--1/2,起爆后重新释放能量,从而消除断层区的冲击地压危险性,使工作面可安全通过断层区域。
本发明的积极效果是:对于断层区、深部冲击地压矿井,能实现断层区域的安全开采。视情况分两步进行泄压,减少工作量,节约生产成本。
附图说明
下面结合附图说明本发明的实施。
图1是能量释放孔和卸压爆破孔布置示意图。
图中:1-采区巷道,2-距离断层面,3-卸压爆破孔,4-能量释放孔。
具体实施方式
如图1所示,一种断层区内工作面开采期间冲击地压防控方法,步骤如下:
一、在施工完采区巷道1且工作面开采前,首先在采区巷道1中的断层区域两侧,距离断层面2的d=100m的范围内,沿采区巷道1距离底板1.2m的高度,向煤层中施工一排能量释放导向钻孔,简称“能量释放孔4”,能量释放孔4直径110-150mm,孔深8-15m,间距由大到小,间距从b=3.0m开始,至靠近断层面2时减到c=0.4-0.5m;该能量释放孔4可将断层附近能量与煤层积聚能量随着工作面的开采提前得到耦合释放。
二、当工作面推进到能量释放孔4开始位置时,如发现能量释放孔4之间仍存在冲击危险时,说明能量释放不重分,应停止开采,再采区沿巷道1距离底板1.2m的高度,向煤层中施工一排卸压爆破孔3,卸压爆破孔3的孔径42mm、间距a=5m、深度8.0--10.0m,装药量为孔深的1/3--1/2,起爆后重分释放能量,从而消除断层区的冲击地压危险性,使工作面可安全通过断层区域。

Claims (1)

1.一种断层区内工作面开采期间冲击地压防控方法,其特征在于,步骤如下:
第一步、在施工完采区巷道且工作面开采前,首先在采区巷道中的断层区域两侧,距离断层面100m的范围内,沿采区巷道距离底板1.2m的高度,向煤层中施工一排能量释放导向钻孔,简称能量释放孔,能量释放孔直径110-150mm,孔深8-15m,间距由大到小,间距从3.0m开始,至靠近断层面时减到0.4-0.5m;该能量释放孔可将断层附近能量与煤层积聚能量随着工作面的开采提前得到耦合释放;
第二步、当工作面推进到能量释放孔开始位置时,如发现能量释放孔之间仍存在冲击危险时,说明能量释放不重分,应停止开采,再沿采区巷道距离底板1.2m的高度,向煤层中施工一排卸压爆破孔,卸压爆破孔的孔径42mm、间距5m、深度8.0--10.0m,装药量为孔深的1/3--1/2,起爆后重新释放能量,从而消除断层区的冲击地压危险性,使工作面可安全通过断层区域。
CN201610915920.5A 2016-10-20 2016-10-20 断层区内工作面开采期间冲击地压防控方法 Expired - Fee Related CN106401588B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610915920.5A CN106401588B (zh) 2016-10-20 2016-10-20 断层区内工作面开采期间冲击地压防控方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610915920.5A CN106401588B (zh) 2016-10-20 2016-10-20 断层区内工作面开采期间冲击地压防控方法

Publications (2)

Publication Number Publication Date
CN106401588A true CN106401588A (zh) 2017-02-15
CN106401588B CN106401588B (zh) 2019-05-17

Family

ID=58013248

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610915920.5A Expired - Fee Related CN106401588B (zh) 2016-10-20 2016-10-20 断层区内工作面开采期间冲击地压防控方法

Country Status (1)

Country Link
CN (1) CN106401588B (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109915142A (zh) * 2019-04-13 2019-06-21 山东科技大学 一种大断层边缘区域性冲击地压防治方法
CN109915143A (zh) * 2019-04-13 2019-06-21 山东科技大学 不等宽护巷煤柱工作面冲击地压的防治方法
CN110924945A (zh) * 2019-12-13 2020-03-27 山东科技大学 侧向悬顶冲击地压条件下的安全工作方法
CN111594183A (zh) * 2020-05-21 2020-08-28 陕西正通煤业有限责任公司 一种利用原卸压孔提升爆破效果的煤层深孔爆破泄压方法
CN113669062A (zh) * 2021-09-27 2021-11-19 重庆大学 一种基于地面承压爆破的断层活化型冲击地压控制方法
CN113847030A (zh) * 2021-08-21 2021-12-28 山西银锋科技有限公司 一种断层冲击地压防治系统及其防治方法
CN113847093A (zh) * 2021-10-22 2021-12-28 江苏徐矿能源股份有限公司张双楼煤矿 冲击地压防治方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101936162A (zh) * 2010-04-16 2011-01-05 兖州煤业股份有限公司 煤矿构造应力区层状巷道底板冲击地压防治方法
CN102518436A (zh) * 2011-11-14 2012-06-27 山东科技大学 煤矿巷道掘进时构造型冲击地压防治方法
CN104989405A (zh) * 2015-06-12 2015-10-21 北京科技大学 大倾角煤层开采冲击地压定向防治方法
CN105785471A (zh) * 2016-02-14 2016-07-20 辽宁工程技术大学 一种矿井预开采煤层的冲击危险性评价方法
CN105863638A (zh) * 2016-05-05 2016-08-17 山东唐口煤业有限公司 一种冲击地压倾向煤层瓦斯异常涌出治理方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101936162A (zh) * 2010-04-16 2011-01-05 兖州煤业股份有限公司 煤矿构造应力区层状巷道底板冲击地压防治方法
CN102518436A (zh) * 2011-11-14 2012-06-27 山东科技大学 煤矿巷道掘进时构造型冲击地压防治方法
CN104989405A (zh) * 2015-06-12 2015-10-21 北京科技大学 大倾角煤层开采冲击地压定向防治方法
CN105785471A (zh) * 2016-02-14 2016-07-20 辽宁工程技术大学 一种矿井预开采煤层的冲击危险性评价方法
CN105863638A (zh) * 2016-05-05 2016-08-17 山东唐口煤业有限公司 一种冲击地压倾向煤层瓦斯异常涌出治理方法

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109915142A (zh) * 2019-04-13 2019-06-21 山东科技大学 一种大断层边缘区域性冲击地压防治方法
CN109915143A (zh) * 2019-04-13 2019-06-21 山东科技大学 不等宽护巷煤柱工作面冲击地压的防治方法
CN110924945A (zh) * 2019-12-13 2020-03-27 山东科技大学 侧向悬顶冲击地压条件下的安全工作方法
CN111594183A (zh) * 2020-05-21 2020-08-28 陕西正通煤业有限责任公司 一种利用原卸压孔提升爆破效果的煤层深孔爆破泄压方法
CN113847030A (zh) * 2021-08-21 2021-12-28 山西银锋科技有限公司 一种断层冲击地压防治系统及其防治方法
CN113669062A (zh) * 2021-09-27 2021-11-19 重庆大学 一种基于地面承压爆破的断层活化型冲击地压控制方法
CN113669062B (zh) * 2021-09-27 2023-11-03 重庆大学 一种基于地面承压爆破的断层活化型冲击地压控制方法
CN113847093A (zh) * 2021-10-22 2021-12-28 江苏徐矿能源股份有限公司张双楼煤矿 冲击地压防治方法

Also Published As

Publication number Publication date
CN106401588B (zh) 2019-05-17

Similar Documents

Publication Publication Date Title
CN106401588A (zh) 断层区内工作面开采期间冲击地压防控方法
CN103161493B (zh) 气液固三相耦合爆破弱化冲击地压及增透方法
CN104989405B (zh) 大倾角煤层开采冲击地压定向防治方法
CN107764144B (zh) 一种隧道微差控制爆破方法
CN103821516B (zh) 二次卸压防治冲击地压的方法
CN102425416B (zh) 煤矿高应力区域巷道掘进工作面冲击地压防治方法
CN102606177B (zh) 一种用于液压支架系统的液压支柱
CN102678120B (zh) 冲击地压卸压解危方法
CN103061781B (zh) 人工调控巷道围岩支护消能减震特性防治冲击地压的方法
CN102296958A (zh) 人造空间缺陷体防治冲击地压方法
CN104790949B (zh) 巨厚坚硬顶板高瓦斯厚煤层顶板控制和提高瓦斯抽放效率的方法及钻孔机具
CN102518436B (zh) 煤矿巷道掘进时构造型冲击地压防治方法
CN104100266B (zh) 防治沿空巷道冲击地压的方法
CN105651127B (zh) 一种露天矿山超前破岩的装药系统
CN101864961B (zh) 一种岩爆的主动防治方法
CN107165638A (zh) 一种深部隧洞岩爆主动防控方法
CN102425418A (zh) 煤矿构造区域人造缺陷体防治冲击地压的方法
CN102296957B (zh) 冲击地压煤层巷道掘进时的一炮贯通卸压法
CN110645855B (zh) 一种露天矿中深孔抑尘爆破方法
CN102735124A (zh) 深孔爆破顶板弱化方法
CN110374599A (zh) 一种煤岩反复钻孔形成巷道防冲弱结构的方法
CN108661642A (zh) 一种深浅孔卸压爆破防治近直立煤层冲击地压的方法
CN102322267A (zh) 深井软岩型冲击地压防治方法
CN105627846A (zh) 一种深孔卸压爆破防治冲击地压的方法
CN111520183A (zh) 厚层砂岩下煤层群开采爆破切顶卸压增透瓦斯治理方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190517

Termination date: 20211020