CN102296957B - 冲击地压煤层巷道掘进时的一炮贯通卸压法 - Google Patents

冲击地压煤层巷道掘进时的一炮贯通卸压法 Download PDF

Info

Publication number
CN102296957B
CN102296957B CN 201110216372 CN201110216372A CN102296957B CN 102296957 B CN102296957 B CN 102296957B CN 201110216372 CN201110216372 CN 201110216372 CN 201110216372 A CN201110216372 A CN 201110216372A CN 102296957 B CN102296957 B CN 102296957B
Authority
CN
China
Prior art keywords
boring
seam roadway
perforations
heading
rock burst
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201110216372
Other languages
English (en)
Other versions
CN102296957A (zh
Inventor
潘立友
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University of Science and Technology
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN 201110216372 priority Critical patent/CN102296957B/zh
Publication of CN102296957A publication Critical patent/CN102296957A/zh
Application granted granted Critical
Publication of CN102296957B publication Critical patent/CN102296957B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

本发明公开了一种冲击地压煤层巷道掘进时的一炮贯通卸压法,它首先在掘进的煤层巷道相距离贯通面15-18m时,停止掘进;在掘进迎头向贯通面打三个仰角3~5°的钻孔,钻孔布置在距煤层巷道底板1.0~1.3m的水平线上,中间的钻孔沿巷道中心线钻进,两侧的钻孔向斜前方钻进;然后向钻孔中装药卷,并均匀间隔布置3-5个雷管,每个孔中的雷管在孔外串联连线;将三个孔中的雷管一次起爆,然后采用现有掘进法使巷道贯通。本发明通过对煤层巷道煤体的强力爆破,改变了煤层巷道深部煤体的力学性质,使得具有冲击倾向的煤体转化为弱冲击倾向或没有冲击倾向,从根本上降低冲击危险性,为后续的巷道贯通提供了安全保障。

Description

冲击地压煤层巷道掘进时的一炮贯通卸压法
技术领域
本发明属于煤矿开采技术领域,尤其涉及煤层巷道掘进时的卸压法。
背景技术
在煤矿开采中,要在煤层中掘进巷道,往往遇到冲击地压的危害,尤其在巷道贯通时常有发生,冲击地压大都是由瓦斯突出造成的。高瓦斯冲击地压煤层巷道掘进贯通时常常伴随破坏性冲击地压(或瓦斯突出)。目前该类事故的防治与常规的防治方法基本相同,主要采取解危措施,包括钻孔爆破卸压、钻孔卸压等措施。与本发明有关的技术是钻孔爆破卸压法。
钻孔爆破卸压法是在巷道掘进贯通前,在巷道断面内钻5-6米深的卸压钻孔,爆破卸压,这种措施在具体实施过程中,由于没有考虑煤层巷道周围的环境应力场的突变特性,实施期间应力转移不到位,能量释放的程度不充分,容易造成贯通前局部应力集中,造成在掘进的扰动下能量突然释放,安全保障性没有把握。当煤层巷道处于沿空侧、埋深大时,实施常规的钻孔爆破和钻孔卸压时,钻进就很困难,解危效果较差。因此高应力、大埋深条件下煤层巷道贯通时的的冲击地压(瓦斯突出),到目前为止还没有从根本上达到完全控制的程度,所以掘进贯通时危险程度较大,很需要一种新的贯通方法。
发明内容
本发明的目的是针对目前煤层巷道掘进贯通时冲击地压的危害问题,提出一种一炮贯通卸压法。
本发明的技术方案是:
第一步:当掘进的煤层巷道相距离贯通面15-18m时,停止掘进;
第二步:在掘进迎头向贯通面打三个仰角3~5°的钻孔,钻孔布置在距煤层巷道底板1.0~1.3m的水平线上,钻孔间距1.0m、直径42mm,中间的钻孔沿巷道中心线钻进,两侧的钻孔以巷道轴线为基准外展30°角度向斜前方钻进,钻孔深度8.0-10.0m;
第三步:向钻孔中装药卷,装药长度4.0-5.0m,装药时均匀间隔布置3-5个雷管,每个孔中的雷管在孔外串联连线;
第四步:将三个孔中的雷管一次起爆,使煤层通过深孔爆破进行卸压;
第五步:采用现有掘进法使巷道贯通。
本发明的积极效果是:
1、通过对煤层巷道煤体的强力爆破,改变了煤层巷道深部煤体的力学性质,使从煤层巷道迎头到煤层巷道爆破范围的区域,煤体的强度减小,瓦斯压力和浓度降低,能量得到充分释放,从而使得具有冲击倾向的煤体转化为弱冲击倾向或没有冲击倾向,从根本上降低冲击危险性,为后续的巷道贯通提供了安全保障。
2、本发明采用斜孔向深度钻进,使得爆破区域的长度、宽度较大,能量释放范围广,对煤层巷道掘进起到防护作用,对煤层巷道内的工作人员起到保护作用。
附图说明
下面结合附图说明本发明的实施例;
图1是煤层巷道贯通前的平面图;
图2是钻孔布置俯视图;
图3是钻孔布置主视图;
图4是钻孔布置左视图。
图中:1-贯通面,2-巷道,3-钻孔,4-药卷。
具体实施方式
如图1-图4所示,本发明的一炮贯通卸压法步骤如下:
第一步:当掘进的煤层巷道2与贯通面1相距15-18m时,停止掘进(见图1);
第二步:在煤层巷道2的掘进迎头向贯通面1打三个仰角3~5°的钻孔3,钻孔3布置在距煤层巷道2底板1.0~1.3m的水平线上,钻孔3间距1.0m、直径42mm,中间的钻孔3沿煤层巷道2中心线钻进,两侧的钻孔3以巷道2轴线为基准外展30角度向斜前方钻进,钻孔深度8.0-10.0m(见图2、图3);
第三步:向钻孔3中装药卷4(见图4),药卷4长度4.0-5.0m,装药时均匀间隔布置3-5个雷管,每个钻孔3中的雷管在孔外串联连线;
第四步:将三个孔中的雷管一次起爆,使巷道2的煤层通过深孔爆破进行卸压;
第五步:采用现有掘进法使巷道贯通。

Claims (1)

1.一种冲击地压煤层巷道掘进时的一炮贯通卸压法,其特征在于,步骤如下:
第一步:当掘进的煤层巷道相距离贯通面15-18m时,停止掘进;
第二步:在掘进迎头向贯通面打三个仰角3~5°的钻孔,钻孔布置在距煤层巷道底板1.0~1.3m的水平线上,钻孔间距1.0m、直径42mm,中间的钻孔沿巷道中心线钻进,两侧的钻孔以巷道轴线为基准外展30°角度向斜前方钻进,钻孔深度8.0-10.0m;
第三步:向钻孔中装药卷,装药卷长度4.0-5.0m,装药时均匀间隔布置3-5个雷管,每个孔中的雷管在孔外串联连线;
第四步:将三个孔中的雷管一次起爆,使煤层通过深孔爆破进行卸压;
第五步:采用现有掘进法使巷道贯通。
CN 201110216372 2011-07-22 2011-07-22 冲击地压煤层巷道掘进时的一炮贯通卸压法 Expired - Fee Related CN102296957B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110216372 CN102296957B (zh) 2011-07-22 2011-07-22 冲击地压煤层巷道掘进时的一炮贯通卸压法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110216372 CN102296957B (zh) 2011-07-22 2011-07-22 冲击地压煤层巷道掘进时的一炮贯通卸压法

Publications (2)

Publication Number Publication Date
CN102296957A CN102296957A (zh) 2011-12-28
CN102296957B true CN102296957B (zh) 2013-07-17

Family

ID=45357612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110216372 Expired - Fee Related CN102296957B (zh) 2011-07-22 2011-07-22 冲击地压煤层巷道掘进时的一炮贯通卸压法

Country Status (1)

Country Link
CN (1) CN102296957B (zh)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105201510B (zh) * 2015-10-27 2018-02-06 山东科技大学 一种蠕变型冲击地压防控方法
CN106194186A (zh) * 2016-07-06 2016-12-07 中国矿业大学 长壁工作面回采巷道超前支护段变形的钻采卸压控制方法
CN108661642B (zh) * 2018-04-23 2019-08-06 北京科技大学 一种深浅孔卸压爆破防治近直立煤层冲击地压的方法
CN110005431A (zh) * 2019-04-13 2019-07-12 山东科技大学 一种不规则孤岛煤柱工作面冲击地压防治方法
CN109915140A (zh) * 2019-04-13 2019-06-21 山东科技大学 一种不规则孤岛煤柱巷道冲击地压防治方法
CN111270987B (zh) * 2020-01-20 2020-12-25 中国矿业大学 一种煤矿井下远程区域精准防控冲击地压方法
CN113914859B (zh) * 2021-09-07 2023-12-19 中煤科工开采研究院有限公司 一种煤矿掘进巷道过断层防治冲击地压的方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1664310A (zh) * 2005-02-28 2005-09-07 清华大学 煤矿孤岛煤柱冲击地压控制方法
CN101614134A (zh) * 2009-07-15 2009-12-30 中国矿业大学 钻、爆、抽三位一体卸压防突方法
CN101713290A (zh) * 2009-12-10 2010-05-26 天地科技股份有限公司 煤矿深部全煤巷道冲击地压解危方法
CN101936162A (zh) * 2010-04-16 2011-01-05 兖州煤业股份有限公司 煤矿构造应力区层状巷道底板冲击地压防治方法

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100557375C (zh) * 2007-07-28 2009-11-04 肖自立 横向松动爆破
CN101922902B (zh) * 2009-06-11 2012-12-12 淮南矿业(集团)有限责任公司 硬岩强度弱化方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1664310A (zh) * 2005-02-28 2005-09-07 清华大学 煤矿孤岛煤柱冲击地压控制方法
CN101614134A (zh) * 2009-07-15 2009-12-30 中国矿业大学 钻、爆、抽三位一体卸压防突方法
CN101713290A (zh) * 2009-12-10 2010-05-26 天地科技股份有限公司 煤矿深部全煤巷道冲击地压解危方法
CN101936162A (zh) * 2010-04-16 2011-01-05 兖州煤业股份有限公司 煤矿构造应力区层状巷道底板冲击地压防治方法

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
冲击地压防治技术在峻德煤矿的应用;赵雪林;《煤炭技术》;20110630;第30卷(第6期);全文 *
卸压钻孔在防治冲击地压区的实践;石长生;《能源技术与管理》;20070130(第1期);全文 *
徐仁桂等.深孔爆破在预防冲击地压中的应用.《煤矿安全》.2007,(第6期),
深孔爆破在预防冲击地压中的应用;徐仁桂等;《煤矿安全》;20070630(第6期);全文 *
石长生.卸压钻孔在防治冲击地压区的实践.《能源技术与管理》.2007,(第1期),
赵雪林.冲击地压防治技术在峻德煤矿的应用.《煤炭技术》.2011,第30卷(第6期),

Also Published As

Publication number Publication date
CN102296957A (zh) 2011-12-28

Similar Documents

Publication Publication Date Title
CN102296957B (zh) 冲击地压煤层巷道掘进时的一炮贯通卸压法
CN102425416B (zh) 煤矿高应力区域巷道掘进工作面冲击地压防治方法
CN102678120B (zh) 冲击地压卸压解危方法
CN101936162B (zh) 煤矿构造应力区层状巷道底板冲击地压防治方法
CN108661642B (zh) 一种深浅孔卸压爆破防治近直立煤层冲击地压的方法
CN104100266B (zh) 防治沿空巷道冲击地压的方法
CN102296958A (zh) 人造空间缺陷体防治冲击地压方法
CN110067557B (zh) 一种用于急倾斜煤层综放开采底煤的卸压方法
CN103161493B (zh) 气液固三相耦合爆破弱化冲击地压及增透方法
CN102518436B (zh) 煤矿巷道掘进时构造型冲击地压防治方法
CN106401588B (zh) 断层区内工作面开采期间冲击地压防控方法
CN105350965A (zh) 开采煤矿巷道冲击地压防治方法
CN102425418A (zh) 煤矿构造区域人造缺陷体防治冲击地压的方法
CN103939099A (zh) 一种强冲击危险煤层群冲击地压的防治方法
CN111335892A (zh) 一种强冲击煤层卸压防治方法
CN110067558A (zh) 一种急倾斜特厚煤层回采巷道联合卸压防治冲击矿压方法
CN102967191A (zh) 处理采空区的爆破方法
CN109915141A (zh) 不等宽护巷煤柱采场巷道冲击地压的防治方法
CN106247876A (zh) 大采高大切眼综采工作面坚硬顶板强制放顶的爆破方法
CN105627846A (zh) 一种深孔卸压爆破防治冲击地压的方法
CN108756881A (zh) 一种立体煤柱压煤区域的冲击地压防控方法
CN102322267A (zh) 深井软岩型冲击地压防治方法
CN104453898A (zh) 一种深孔爆破与静压注水相结合的煤层弱化方法
CN108548460A (zh) 一种爆破孔和大直径钻孔耦合卸压防治冲击地压的方法
CN106440981A (zh) 节理裂隙发育花岗岩矿山提高大块产率的深孔爆破方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130717

Termination date: 20210722

CF01 Termination of patent right due to non-payment of annual fee