CN106400937B - Floor drain protects structure - Google Patents

Floor drain protects structure Download PDF

Info

Publication number
CN106400937B
CN106400937B CN201610963838.XA CN201610963838A CN106400937B CN 106400937 B CN106400937 B CN 106400937B CN 201610963838 A CN201610963838 A CN 201610963838A CN 106400937 B CN106400937 B CN 106400937B
Authority
CN
China
Prior art keywords
external thread
supporting hinges
floor drain
thread rod
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610963838.XA
Other languages
Chinese (zh)
Other versions
CN106400937A (en
Inventor
骆文博
刘明友
冀艳刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 18th Metallurgical Construction Co., Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN201610963838.XA priority Critical patent/CN106400937B/en
Publication of CN106400937A publication Critical patent/CN106400937A/en
Application granted granted Critical
Publication of CN106400937B publication Critical patent/CN106400937B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/04Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
    • E03F5/0407Floor drains for indoor use
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/04Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
    • E03F5/041Accessories therefor

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Sink And Installation For Waste Water (AREA)

Abstract

The invention discloses a kind of floor drains to protect structure, including being placed on floor drain upper port and the protection cap with centre bore and locking mechanism for the protection cap to be lock onto floor drain upper port;The locking mechanism include the external thread rod being arranged in the centre bore, be threadedly engaged in external thread rod expose to the locking nut of the upper end of the protection cap, on external thread rod be located at protection cap under part expansion locking mechanism; it is fitted close for being expanded when screwing locking nut and moving up external thread rod with the inside pipe wall to leak down with ground, to generate frictional force with the inside pipe wall to fasten protection cap.Above-mentioned floor drain protects structure energy reliably protecting floor drain not to be destroyed, and reduces the probability that ground leaking drainage pipe is blocked by concrete mortar, while saving labour cost input by cleaning floor drain, the fee of material of secondary replacement floor drain consumption, labour cost.

Description

Floor drain protects structure
Technical field
Row is leaked into over the ground the present invention relates to construction and installation field is protected from the ground that floor drain and drainpipe are destroyed and block Leakage protection structure.
Background technique
There are a large amount of floor drains to install in every building building, floor drain is installed come into operation before have multiple working procedure construction, as Ground ball woll, masonry, plaster, do waterproof, is levelling, look for slope, insulating layer construction etc..These subsequent construction processes often destroy floor drain With cause floor drain and lower part to drain blockage.Before completion of works is checked and accepted and handed over, installation unit will spend a large amount of people Power and material re-replace, dredge floor drain and lower part sparge pipe, trap.And this part is replaced and dredges manually expense, material Material expense owner not approves, does not routinely also recognize this expense as the civil construction unit of general contracting unit.It causes to install Unit works hard but get little result, has hardship could not explain.
Summary of the invention
In view of the above shortcomings of the prior art, the technical problems to be solved by the present invention are: providing one kind can effectively protect Shield floor drain and lower bank of tubes are not blocked and do not destroy the floor drain protection structure of floor drain original structure in fastening.
In order to solve the above technical problems, one technical scheme adopted by the invention is that: a kind of floor drain protection structure, packet are provided It includes and is placed on floor drain upper port and has the protection cap of centre bore and the lock for the protection cap to be lock onto floor drain upper port Locking structure;
The locking mechanism includes the external thread rod being arranged in the centre bore, is threadedly engaged and exposes in external thread rod The locking nut of the upper end of the protection cap, on external thread rod be located at protection cap under part expansion locking mechanism, It is fitted close for being expanded when screwing locking nut and moving up external thread rod with the inside pipe wall to leak down with ground, thus Frictional force is generated with the inside pipe wall to fasten protection cap.
As optimization, the expansion locking mechanism includes the position limiting structure being located under protection cap, on external thread rod At least two groups supporting hinges component, at least two groups supporting hinges component is arranged along external thread rod length direction interval, each Group supporting hinges component includes at least two supporting hinges positioned at sustained height, the expansion locking mechanism further include with it is described At least two supporting hinges correspondingly cut with scissors with one group of support for being located at the top by least two expansion walls, the height of each expansion wall The distance of chain component to one group of supporting hinges component for being located at bottom matches;The first end of each supporting hinges with outer spiral shell Rasp bar is hinged, and can make and 0~90 degree of upper section external thread rod of the rotation positioned at hinge joint, Mei Yizhi in the hinge joint The second end of support hinge is articulated on corresponding expansion wall at corresponding to the position of the supporting hinges;The position limiting structure is for limiting The expansion wall is made to continue with external thread rod upwardly so that each supporting hinges of each group of supporting hinges component are in water It is flat-shaped, to make to expand wall and maximize to expand to be fitted close with floor drain lower end inside pipe wall.
As optimization, the supporting hinges component is two groups, and each group of supporting hinges component includes three supporting hinges, described Expanding wall is three pieces, the second end of three the first supporting hinges of first group of supporting hinges component being located above and three pieces of expansions The top of wall correspond it is hinged, the second end of three the second supporting hinges of underlying second group of supporting hinges component with The lower part of three pieces of expansion walls corresponds hinged.
As optimization, the angle between every adjacent two first supporting hinges is 120 degree, and three the second supporting hinges one are a pair of The underface of three the first supporting hinges should be located at.
As optimization, the expansion wall is that the arc to match with the inside pipe wall expands wall.
As optimization, the position limiting structure be fixed on protection cap lower end surface have be arranged in for external thread rod it is therein Cylindrical positive stop lug boss, the cylinder positive stop lug boss and external thread rod are concentric, and outer diameter matches with floor drain lower end bore.
As optimization, the position limiting structure includes the stroke for being arranged on external thread rod and being located above the first supporting hinges Limit conduit and with stroke limit conduit stroke limit disk connected vertically, the stroke limit conduit is not with outer spiral shell Rasp bar moves up, during the expansion wall is moved up with external thread rod, described in the upper end promotion of the expansion wall Stroke limit disk is move upwardly until that stroke limit conduit is butted on the lower end surface of the protection cap, the stroke limit disk resistance Only the expansion wall continues to move up, so that each supporting hinges move up and horizontal, band with external thread rod It moves the expansion wall and maximizes expansion.
As optimization, each supporting hinges include mounting structure and hinge arm, and the mounting structure includes outside being fixed on Threaded rod corresponding position and the sagging level guarantor of the perpendicular second end for preventing hinge arm hinged with corresponding expansion wall It holds portion, two installation side plates upwardly extended by the opposite two sides of horizontal maintaining part and crosses the pin set between two installation side plates Axis, the first end of the hinge arm are arranged on the pin shaft and can rotate around the pin shaft, and the horizontal maintaining part acts on hinge arm So that its maximum angle is 90 degree perpendicular with external thread rod and corresponding expansion wall.
As optimization, on the external thread rod be equipped with stroke limit chassis, the upper surface on the stroke limit chassis with The first end of second supporting hinges is in contact, and diameter and the floor drain lower end bore on the stroke limit chassis match.
As optimization, the expansion wall includes the rubber skin of steel plate and the outer surface for being attached to steel plate.
Floor drain of the invention protects structure, and compared with prior art, floor drain protection structure of the invention has the advantages that
1, effective protection floor drain and lower part drainpipe 3 are destroyed and block.
2, replacement, dredging floor drain and drainpipe 3 are omitted, a large amount of artificial and Master Costs are saved.
3, principle is simple and easy, by construction site tailing, can successfully realize the effective protection to floor drain.
4, the original structure of floor drain is not destroyed, guarantees that floor drain is intact.
Floor drain of the invention protects structure, and energy reliably protecting floor drain is not destroyed, and reduces ground leaking drainage pipe by concrete sand The probability of blocking is starched, while saving labour cost input by cleaning floor drain, it is the fee of material of secondary replacement floor drain consumption, artificial Take.Ground waterproof, ball woll when normal procedure floor drain construction look for the processes such as slope all not complete, and the construction of these processes is often floor drain It drains double-edged fine-toothed comb to destroy, a large amount of concrete slurries, cement mortar, sundries, stone etc. fall into floor drain and drainpipe, floor drain caused to be broken Bad, pipeline is blocked.It can effectively solve above-mentioned problem using the present invention and invention.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of floor drain protection structure first embodiment of the present invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Referring to Figure 1, floor drain of the invention protection structure includes the protection cap for being placed on 1 upper port of floor drain and having centre bore 20 and the locking mechanism for the protection cap 20 to be lock onto 1 upper port of floor drain;The locking mechanism includes being arranged in institute The external thread rod 21 in centre bore is stated, is threadedly engaged and exposes to the locking nut of the upper end of the protection cap 20 in external thread rod 21 22, it is located at the expansion locking mechanism of the part under protection cap 20 on external thread rod 21, screws locking nut 22 for working as Expand external thread rod 21 when moving up to be fitted close with the inside pipe wall under floor drain 1, to produce with the inside pipe wall Raw frictional force is to fasten protection cap 20.
In the embodiment, the expansion locking mechanism includes the position limiting structure 23 being located under protection cap 20, is set to external screw thread At least two groups supporting hinges component on bar 21, at least two groups supporting hinges component is along 21 length direction interval of external thread rod Setting, each group of supporting hinges component include at least two supporting hinges positioned at sustained height, and the expansion locking mechanism is also Including at least two supporting hinges at least two expansion wall 24 correspondingly, the height of each expansion wall 24 with positioned at most upper The distance of one group of supporting hinges component to the one group of supporting hinges component for being located at bottom of side matches;Each supporting hinges First end is hinged with external thread rod 21, and can make and the upper section external thread rod 21 0 positioned at hinge joint in the hinge joint ~90 degree of rotation, the second end of each supporting hinges are articulated with the position that the supporting hinges are corresponded on corresponding expansion wall 24 Place;The position limiting structure 23 is continued to move up for limiting the expansion wall 24 with external thread rod 21, so that each group of support When every supporting hinges of hinge component are gradually horizontal (vertical with external thread rod 21 and expansion wall 24), to make to expand wall 24 maximize expansion to be fitted close with 1 lower end inside pipe wall of floor drain.
Specifically in conjunction with attached drawing 1, the supporting hinges component in the present embodiment is two groups, and each group of supporting hinges component includes three Supporting hinges, the expansion wall 24 are three pieces, the spacing between the length and two groups of supporting hinges components of each piece of expansion wall 24 Match, each expansion wall 24 is in that the arc to match with 1 lower end inside pipe wall radian of floor drain expands wall 24, first be located above The second end of three the first supporting hinges 251 of group supporting hinges component 25 is corresponded with the top of three pieces of expansion walls 24 and is cut with scissors It connects, the second end and three pieces of expansion walls 24 of three the second supporting hinges 261 of underlying second group of supporting hinges component 26 Lower part correspond it is hinged.
In the present embodiment, the lower end pipe of floor drain 1 can be the lower end pipe of floor drain 1, be also possible to drainpipe 3, the present embodiment is Refer to drainpipe 3.The expansion wall 24 includes the rubber skin of steel plate and the outer surface for being attached to steel plate, in a kind of specific implementation In mode, 2mm thickness steel pipe sheet can be used and 2mm thickness rubber skin is riveted into one.
First group of supporting hinges component 25 is located at the middle part of external thread rod 21, and three of first group of supporting hinges component 25 In first supporting hinges 251, the angle between every two adjacent the first supporting hinges 251 is 120 degree, each first support The first end of hinge 251 is hinged with external thread rod 21, and the upper inside wall of second end and three pieces of expansion walls 24 corresponds hinged (in other embodiments can also be hinged with the other parts of expansion wall 24).
In the present embodiment, the second end of each the first supporting hinges 251 lets droop in order to prevent, and each first Support hinge 251 is using such as flowering structure: each first supporting hinges 251 includes the first mounting structure and the first hinge arm, institute Stating the first mounting structure includes being fixed on 21 corresponding position of external thread rod (middle section corresponding position) and perpendicular being used for The first level maintaining part (not shown go out) that prevents the second end of the first hinge arm sagging, by the opposite two sides of first level maintaining part While two first installation side plates (not shown go out) that upwardly extend and crossing the first pin shaft (figure set between two first installation side plates It is not shown), the first end of first hinge arm is arranged on first pin shaft and can rotate around first pin shaft, described first Horizontal maintaining part acts on the first hinge arm so that its maximum angle is perpendicular with external thread rod 21 and corresponding expansion wall 24 90 Degree.
Second group of supporting hinges component 26 is located at the bottom of external thread rod 21, and three of second group of supporting hinges component 26 Second supporting hinges 261 correspond the underface for being located at three the first supporting hinges 251.Each second supporting hinges 261 First end it is hinged with external thread rod 21, the lower inner wall of second end and three pieces of expansion walls 24 corresponds hinged (at other It can also be hinged with the other parts of expansion wall 24 in embodiment).
In the present embodiment, the second end of each the second supporting hinges 261 lets droop in order to prevent, and each second Support hinge 261 is using such as flowering structure: each second supporting hinges 261 includes the second mounting structure and the second hinge arm, institute Stating the second mounting structure includes being fixed on 21 corresponding position of external thread rod (bottom corresponding position) and perpendicular being used for The horizontal maintaining part of prevent the second end of the second hinge arm sagging second (not shown go out), by the opposite two sides of the second horizontal maintaining part While two second installation side plates (not shown go out) that upwardly extend and crossing the second pin shaft (figure set between two second installation side plates It is not shown), the first end of second hinge arm is arranged on second pin shaft and can rotate around second pin shaft, described second Horizontal maintaining part acts on the second hinge arm so that its maximum angle is perpendicular with external thread rod 21 and corresponding expansion wall 24 90 Degree.
When the angle of the first supporting hinges 251 and the second supporting hinges 261 and external thread rod 21 is 0 degree, the first support The second end of hinge 251 and the second supporting hinges 261 straight up, thus with external thread rod 21 and expansion wall 24 it is parallel, when When the angle of first supporting hinges 251 and the second supporting hinges 261 and external thread rod 21 is 90 degree, the first supporting hinges 251 and The second end of second supporting hinges 261 is horizontally outward with vertical with external thread rod 21 and expansion wall 24.
In the present embodiment, one stroke limit chassis 27, the stroke limit are additionally provided in the bottom face of external thread rod 21 The upper surface on chassis 27 is in contact with the first end of the second supporting hinges 261, the diameter and floor drain on the stroke limit chassis 27 Lower end bore matches.The trip limits the effect same level maintaining part on chassis 27, until being further ensured that supporting hinges water Flat effect.In other examples, the stroke limit chassis 27 can be set under the first supporting hinges 251, can also be with The position of second supporting hinges 261 is set on external thread rod 21, can also be in stroke limit chassis 27 and horizontal maintaining part Optional one.
Although being not limited to it should be understood that the present embodiment only lists two groups of supporting hinges up and down at other Three groups, four groups, five groups etc. are used in embodiment, according to three groups, then then setting gradually at least two on external thread rod 21 First supporting hinges 251, at least two second supporting hinges 261, at least two third supporting hinges ..., and so on, using two Supporting hinges more than group are protection scope of the present invention.
It is also understood that, in various embodiments, the structure for preventing the second end of supporting hinges sagging may be used also To there is different structures, just no longer repeated one by one herein.
In the present embodiment, the position limiting structure 23 includes being arranged on external thread rod 21 and being located at the first supporting hinges 251 top stroke limit conduit 230 and with the stroke limit conduit 230 stroke limit disk 232 connected vertically, institute It states stroke limit conduit 230 and stroke limit disk 232 is integrally formed.The stroke limit conduit 230 is not with external thread rod 21 It moves up, during the expansion wall 24 is moved up with external thread rod 21, the upper end of the expansion wall 24 pushes institute It states stroke limit disk 232 and is move upwardly until that row stroke limit conduit 230 is butted on the lower end surface of the protection cap 20, the row Degree circle of position disk 232 prevents the expansion wall 24 from continuing to move up so that each supporting hinges with external thread rod 21 to It is upper mobile and horizontal, drive the expansion wall 24 to maximize expansion.
In some embodiments, the position limiting structure 23 can also be to be fixed on having for 20 lower end surface of protection cap to supply outer spiral shell Rasp bar 21 is arranged in cylindrical positive stop lug boss therein, and the cylinder positive stop lug boss and external thread rod 21 are concentric, outer diameter and Floor drain lower end bore matches.The position limiting structure 23 can change accordingly according to demand in various embodiments, As long as expansion wall 24 can be limited when supporting hinges are in a horizontal state to continue to move up.
In the present embodiment, it is cased with protective case 28 on 20 locking nut 22 of floor drain protection cap, external screw thread during preventing Bar 21 gets rusty, pollutes and bad disassembly.In the case where no tool, the draining of floor drain protection cap 20, impurities removal object cannot be opened with hand.
The upper end of external thread rod 21 is pierced by protection cap 20, then locking nut 22 is twisted during installation by the embodiment of the present invention In exposed upper end, then by the lower end of external thread rod 21 by from floor drain 1 is penetrated, protection cap 20 is placed at 1 upper port of floor drain, this When expansion wall 24 be located in drainpipe 3, and due to not tightening locking nut 22, the upper end of position limiting structure 23 is not butted on protection cap 20 lower surface, the second end of each supporting hinges are in state upwardly and outwardly;Locking nut 22 is finally tightened, outer spiral shell is made Rasp bar 21 gradually moves up, and drives each group of supporting hinges component and expansion wall 24 to move up, until 23 upper end bottom of position limiting structure is in guarantor The lower end surface of protecting cover 20, lower end withstands expansion wall 24 and continues to move up, so that the second end of each supporting hinges is kept, And external thread rod 21 continues to move up with tightening for locking nut 22 at this time, continues to drive on each group of supporting hinges continue It moves, so that the first end of each supporting hinges continues to move up, hinge arm is gradually horizontal, and expansion wall 24 is expanded to Maximum (in different instances, corresponding tonicity is varied, and is determined according to example), outer diameter match with draining bore, produce Raw maximal friction (being determined according to different instances), tightening retaining nuts 22 pass through the frictional force and locking nut with inside pipe wall 22 cooperation, which reaches, lock onto protection cap 20 at 1 upper port of floor drain.
Compared with prior art, floor drain of the invention protection structure has the advantages that
1, effective protection floor drain and lower part drainpipe 3 are destroyed and block.
2, replacement, dredging floor drain and drainpipe 3 are omitted, a large amount of artificial and Master Costs are saved.
3, principle is simple and easy, by construction site tailing, can successfully realize the effective protection to floor drain.
4, the original structure of floor drain is not destroyed, guarantees that floor drain is intact.
Floor drain of the invention protects structure, and energy reliably protecting floor drain is not destroyed, and reduces ground leaking drainage pipe by concrete sand The probability of blocking is starched, while saving labour cost input by cleaning floor drain, it is the fee of material of secondary replacement floor drain consumption, artificial Take.Ground waterproof, ball woll when normal procedure floor drain construction look for the processes such as slope all not complete, and the construction of these processes is often floor drain It drains double-edged fine-toothed comb to destroy, a large amount of concrete slurries, cement mortar, sundries, stone etc. fall into floor drain and drainpipe, floor drain caused to be broken Bad, pipeline is blocked.It can effectively solve above-mentioned problem using the present invention and invention.
The above is only embodiments of the present invention, are not intended to limit the scope of the invention, all to utilize the present invention Equivalent structure or equivalent flow shift made by specification and accompanying drawing content is applied directly or indirectly in other relevant technologies Field is included within the scope of the present invention.

Claims (7)

1. a kind of floor drain protects structure, it is characterised in that: including be placed on floor drain upper port and protection cap with centre bore and For the protection cap to be lock onto the locking mechanism of floor drain upper port;
The locking mechanism include the external thread rod being arranged in the centre bore, be threadedly engaged exposed in external thread rod it is described The locking nut of the upper end of protection cap, on external thread rod be located at protection cap under part expansion locking mechanism, be used for It is expanded when screwing locking nut and moving up external thread rod and is fitted close with the inside pipe wall to leak down with ground, thus with institute It states inside pipe wall and generates frictional force to fasten protection cap;
The expansion locking mechanism includes the position limiting structure under protection cap, the support hinge of at least two groups on external thread rod Chain component, at least two groups supporting hinges component are arranged along external thread rod length direction interval, each group of supporting hinges component It include at least two supporting hinges positioned at sustained height, the expansion locking mechanism further includes and at least two supporting hinges One-to-one at least two expansions wall, the height of each expansion wall be located at one group of supporting hinges component of the top to being located at most The distance of one group of supporting hinges component of lower section matches;The first end of each supporting hinges is hinged with external thread rod, and Can the hinge joint make be located at hinge joint 0~90 degree of upper section external thread rod of rotation, the second of each supporting hinges End is articulated on corresponding expansion wall at corresponding to the position of the supporting hinges;The position limiting structure is for limiting the expansion wall Continue with external thread rod upwardly so that each supporting hinges of each group of supporting hinges component can be horizontal, thus It can make to expand wall and maximize to expand to be fitted close with floor drain lower end inside pipe wall;The position limiting structure is to be fixed under protection cap Having for end face is arranged in cylindrical positive stop lug boss therein for external thread rod, and the cylinder positive stop lug boss and external thread rod are same Axle center, outer diameter match with floor drain lower end bore;
The supporting hinges component is two groups, and each group of supporting hinges component includes three supporting hinges, and the expansion wall is three pieces, The top of the second ends of three the first supporting hinges of first group of supporting hinges component being located above and three pieces of expansion walls is one by one It is corresponding hinged, the second end of three the second supporting hinges of underlying second group of supporting hinges component and three pieces of expansion walls Lower part corresponds hinged;
Protective case is cased on the locking nut of protection cap.
2. floor drain as described in claim 1 protects structure, it is characterised in that: the angle between per adjacent two first supporting hinges It is 120 degree, three the second supporting hinges correspond the underface for being located at three the first supporting hinges.
3. floor drain as described in claim 1 protects structure, it is characterised in that: the expansion wall is to match with the inside pipe wall Arc expand wall.
4. floor drain as described in claim 1 protects structure, it is characterised in that: the position limiting structure includes being arranged in external thread rod It goes up and is located at the stroke limit conduit above the first supporting hinges and limited with stroke limit conduit stroke connected vertically Circle of position disk, the stroke limit conduit are not moved up with external thread rod, are moved up in the expansion wall with external thread rod In the process, the upper end of the expansion wall pushes the stroke limit disk to be move upwardly until that stroke limit conduit is butted on the guarantor The lower end surface of protecting cover, the stroke limit disk prevents the expansion wall from continuing to move up, so that each supporting hinges First end continue to move up and horizontal with external thread rod, drive the expansion wall to maximize and expand.
5. floor drain as described in claim 1 protects structure, it is characterised in that: each supporting hinges include mounting structure and hinge Arm, the mounting structure include being fixed on external thread rod corresponding position and perpendicular for preventing hinge arm from expanding with corresponding The sagging horizontal maintaining part of the hinged second end of wall, by two installation side plates that the opposite two sides of horizontal maintaining part upwardly extend with And the pin shaft set between two installation side plates is crossed, the first end of the hinge arm is arranged on the pin shaft and can turn around the pin shaft Dynamic, the horizontal maintaining part acts on hinge arm so that its maximum angle is perpendicular with external thread rod and corresponding expansion wall 90 Degree.
6. floor drain as described in claim 1 protects structure, it is characterised in that: be equipped with stroke limit bottom on the external thread rod The upper surface of disk, the stroke limit chassis is in contact with the first end of the second supporting hinges, the stroke limit chassis it is straight Diameter matches with floor drain lower end bore.
7. floor drain as described in claim 1 protects structure, it is characterised in that: the expansion wall includes steel plate and is attached to steel The rubber skin of the outer surface of plate.
CN201610963838.XA 2016-10-28 2016-10-28 Floor drain protects structure Active CN106400937B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610963838.XA CN106400937B (en) 2016-10-28 2016-10-28 Floor drain protects structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610963838.XA CN106400937B (en) 2016-10-28 2016-10-28 Floor drain protects structure

Publications (2)

Publication Number Publication Date
CN106400937A CN106400937A (en) 2017-02-15
CN106400937B true CN106400937B (en) 2019-02-05

Family

ID=58014272

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610963838.XA Active CN106400937B (en) 2016-10-28 2016-10-28 Floor drain protects structure

Country Status (1)

Country Link
CN (1) CN106400937B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107447843A (en) * 2017-03-01 2017-12-08 广州市双聚节能科技有限公司 A kind of odour-proof floor drain
CN108755910A (en) * 2018-06-01 2018-11-06 江北建设有限公司 A kind of floor drain protective device
CN109339208A (en) * 2018-11-27 2019-02-15 蔡海潮 Domestic environment-protection type is anti-error to tear floor drain open
CN112407159A (en) * 2020-10-27 2021-02-26 中船黄埔文冲船舶有限公司 Umbrella stand type floor drain assembly

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201428142Y (en) * 2009-06-24 2010-03-24 王鑫宇 Manhole cover
CN203834632U (en) * 2014-04-30 2014-09-17 浙江六通塑胶有限公司 Floor drain
CN203891468U (en) * 2014-04-23 2014-10-22 云南建工集团第十建筑有限公司 Fixing device for pouring building pipeline embedded part
CN205296358U (en) * 2015-11-30 2016-06-08 中国建筑第八工程局有限公司 Floor drain protection device
CN206128667U (en) * 2016-10-28 2017-04-26 中冶建工集团有限公司 Floor drain protection device

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5116990B1 (en) * 1970-08-17 1976-05-29

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201428142Y (en) * 2009-06-24 2010-03-24 王鑫宇 Manhole cover
CN203891468U (en) * 2014-04-23 2014-10-22 云南建工集团第十建筑有限公司 Fixing device for pouring building pipeline embedded part
CN203834632U (en) * 2014-04-30 2014-09-17 浙江六通塑胶有限公司 Floor drain
CN205296358U (en) * 2015-11-30 2016-06-08 中国建筑第八工程局有限公司 Floor drain protection device
CN206128667U (en) * 2016-10-28 2017-04-26 中冶建工集团有限公司 Floor drain protection device

Also Published As

Publication number Publication date
CN106400937A (en) 2017-02-15

Similar Documents

Publication Publication Date Title
CN106400937B (en) Floor drain protects structure
KR100910987B1 (en) Backfilling Apparatus for Wale
CN212865954U (en) Foundation pit supporting structure
CN206128667U (en) Floor drain protection device
CN207944730U (en) A kind of PC components supporting adn fixing device
CN210066837U (en) Advanced water stop structure of basement bottom plate
CN107100093A (en) A kind of cast in-situ piling pile reinforcement bridge pier structure and building method
CN111364479A (en) Inclined support threaded pile supporting structure for foundation pit enclosure and construction method thereof
CN111013699A (en) Building rubbish breaker for building engineering
CN108894255A (en) The water-stopping method of underground concrete structure deformation joint
KR101022463B1 (en) Connecting structure of vertical protection net for construction
CN209228051U (en) A kind of practical side wall fixture
CN210342669U (en) Anti-bank activity reinforcing apparatus of cast in situ concrete
KR102038370B1 (en) Underwater structure cofferdam frame and installation method using cofferdam
CN207988505U (en) A kind of connection structure between PC components
CN110094578B (en) Waterproof casing pipe and construction method thereof
CN208022571U (en) A kind of combined reinforced bar hanging ring for the lifting of side slope protection gutter channel prefabricated block
CN105971155A (en) Installation joint for outer wallboards
CN220686520U (en) Waterproof construction is exempted from to wear by roofing slag layer blast pipe
CN206034708U (en) Side fascia installation node
CN204592320U (en) Horizontal rotary closure gate
CN107816013B (en) The seam plugging device and method of impervious cement-earth wall and Hydro-concrete Structures
CN219158979U (en) Open caisson reserved hole anti-seepage structure
CN109138467A (en) One kind intercepts water component and its construction method
CN217899257U (en) Civil engineering construction equipment installation is pipeline protection anti-impact device for plumbing

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200716

Address after: No.8, Yejin Road, Shipingqiao, Jiulongpo District, Chongqing

Patentee after: China 18th Metallurgical Construction Co., Ltd

Address before: No. 1 West Road 400084 Dadukou District of Chongqing

Patentee before: CHINA METALLURGICAL CONSTRUCTION ENGINEERING GROUP Co.,Ltd.