CN106400805A
CN106400805A CN201610804253.3A CN201610804253A CN106400805A CN 106400805 A CN106400805 A CN 106400805A CN 201610804253 A CN201610804253 A CN 201610804253A CN 106400805 A CN106400805 A CN 106400805A
Authority
CN
China
Prior art keywords
outlet pipe
water
delivery device
casing
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610804253.3A
Other languages
Chinese (zh)
Inventor
刘德进
单国辉
徐善忠
李永升
孙合军
王为启
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN201610804253.3A priority Critical patent/CN106400805A/en
Publication of CN106400805A publication Critical patent/CN106400805A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/08Removing obstacles

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention relates to a construction method for pile bottom hole cleaning of pile foundation construction, in particular to a technology for removing silt and the like in a steel pipe pile through a gas lift hole cleaning device. The construction method comprises the following steps that the gas outlet end of a gas conveying pipe connected with a gas conveying device is connected with the bottom end of a water outlet pipe; the water outlet pipe is placed in an installed protection barrel; the water outlet end of a water conveying pipe connected with a water conveying device is placed in the protection barrel; and the gas conveying device and the water conveying device are started, and after no impurities exist in the protection barrel, the water conveying device stops working firstly, and finally the gas conveying device stops working. The construction method has the beneficial effects that the input is small, efficiency is high, and operation is easy. Compared with manual cleaning, safety is achieved, and a guarantee is provided for smooth implementation of pile driving construction.

Description

The construction method of pile foundation construction stake bottom borehole cleaning
Technical field
The present invention relates to pile foundation construction stake bottom borehole cleaning technical field, utilize gaslift hole cleaning device to steel more particularly to a kind of The method that silt in pile tube etc. is cleared up.
Background technology
Steel-pipe pile is a kind of building element being widely used in the building pile foundation such as bridge, harbour, house, in steel During tube pile construction, inevitably, have the in the hole that silt or the entrance of other debris set, in order to ensure the suitable of construction Profit, we have to clear out the debris of in the hole.
At present, in steel-pipe pile work progress, remove steel-pipe pile in debris, using by the way of be artificial borehole cleaning, This borehole cleaning mode, high labor intensive, inefficiency, borehole cleaning effect is undesirable, and during borehole cleaning, there is safety hidden Suffer from.
Content of the invention
It is an object of the invention to solving drawbacks described above that prior art exists it is proposed that a kind of pile foundation construction stake bottom borehole cleaning Construction method, it has the characteristics that low cost, efficiency high, simple to operate.
The present invention is to be realized using following technical scheme:A kind of construction method of pile foundation construction stake bottom borehole cleaning, including Following steps:
The bottom of the outlet side of the appendix being connected with air delivery device and outlet pipe is connected;
Outlet pipe is put in mounted casing;
The water side of the water-supply-pipe being connected with water delivery device is put in casing;
Start air delivery device and water delivery device, until after no-sundries in casing, first making water delivery device quit work, finally making Air delivery device quits work.
Preferably, the step bag bottom of the outlet side of the appendix being connected with air delivery device and outlet pipe being connected Include, the outlet side of appendix is put in outlet pipe from the bottom of outlet pipe;By appendix together with outlet pipe colligation it is ensured that The outlet side of appendix will not be deviate from from outlet pipe.
Preferably, outlet pipe is put into the step in mounted casing to include, outlet pipe is connected with loop wheel machine;Behaviour Make loop wheel machine to put into outlet pipe in casing.
Preferably, when operation loop wheel machine puts into outlet pipe in casing, outlet pipe is vertically placed.
Preferably, outlet pipe bottom is located above the debris within casing.
Preferably, the water side of water-supply-pipe is located above the debris within casing.
Preferably, after starting air delivery device, persistently rock outlet pipe, until the debris in casing are discharged.
Preferably, air delivery device is the air compressor machine being provided that gases at high pressure, and water delivery device is to be provided that highly pressurised liquid Centrifugal pump.
The invention has the beneficial effects as follows:
The present invention has little, the efficiency high of input, feature simple to operate, with respect to labor cleaning, with more safety, is The smooth enforcement of piling construction provides guarantee.
Brief description
Fig. 1 is the structural representation of hole cleaning device;
In figure:1 air compressor machine, 2 appendix, 3 centrifugal pump, 4 water-supply-pipe, 5 outlet pipe 6 casing.
Specific embodiment
With reference to specific embodiments and the drawings, the present invention will be further described.
As shown in figure 1, in steel-pipe pile installation, carrying out setting of casing 6 first, casing 6 sets takes vibration hammer Constructed, stop when cannot sinking to casing 6, then carry out borehole cleaning operation.
The borehole cleaning operation of the present invention adopts the construction method of pile foundation construction stake bottom borehole cleaning, comprises the following steps, first will be defeated Trachea 2 is connected with air delivery device, and the bottom of the outlet side of appendix 2 and outlet pipe 5 connects, specifically, by giving vent to anger of appendix 2 End puts in outlet pipe 5 from the bottom of outlet pipe 5;By appendix 2 it is ensured that the giving vent to anger of appendix 2 together with outlet pipe 5 colligation End will not be deviate from from outlet pipe 5.
Then outlet pipe 5 is connected with loop wheel machine, outlet pipe 5 is vertically put in casing 6 by operation loop wheel machine, and outlet pipe 5 bottoms are located above the internal debris of casing 6, leave certain gap, to ensure that debris can smoothly enter casing 6 and then row Go out.Again the water side of the water-supply-pipe 4 being connected with water delivery device is put in casing 6, make the water side of water-supply-pipe 4 be located at casing 6 Above internal debris, with hovel every a small distance, to ensure scouring effect.The device of so whole borehole cleaning just arranges Become.Preferably, wherein air delivery device is the air compressor machine 1 being provided that gases at high pressure, water delivery device be provided that highly pressurised liquid from Heart pump 3.
Finally start air compressor machine 1 and centrifugal pump 3, until after no-sundries in casing 6, that is, after the no obvious silt of casing 6, first So that water delivery device is quit work, after the water in casing is all discharged, so that air delivery device is quit work, whole borehole cleaning work Complete.It should be strongly noted that after startup air delivery device, will persistently rock outlet pipe 5, until the debris in casing 6 are discharged, Such that borehole cleaning is in hgher efficiency, the effect of borehole cleaning is even more ideal.
After borehole cleaning finishes, take out whole hole cleaning device, then using vibration hammer, steel pile casting is extracted, then carry out staking out work Industry.
The present invention reduces the blast of venthole by air compressor machine aerofluxuss, makes the mouth of pipe form the side of blowout by the pressure of water Method realizes borehole cleaning.Centrifugal pump extracting seawater is introduced in casing by water-supply-pipe and forms high-pressure spray, silt is rushed, by water outlet Bank of tubes goes out, and meanwhile, water-supply-pipe need to supplement casing maritime interior waters, keeps water-head.Air compressor machine air vent passes through hose connection high pressure steel Pipe enters near mouth under sand discharge pipe (i.e. outlet pipe), forms powerful draught head, silt is along pipe in the pipe of sand discharge pipe and outside pipe It is rushed out outside stake.
Certainly, the above is only presently preferred embodiments of the present invention it is impossible to be considered for limiting to inventive embodiment Scope.The present invention is also not limited to the example above, and those skilled in the art are in the essential scope of the present invention The impartial change made and improvement etc., all should belong to patent covering scope of the present invention.

Claims (8)

1. pile foundation construction stake bottom borehole cleaning construction method it is characterised in that:Comprise the following steps,
The bottom of the outlet side of the appendix being connected with air delivery device (2) and outlet pipe (5) is connected;
Outlet pipe (5) is put in mounted casing (6);
The water side of the water-supply-pipe being connected with water delivery device (4) is put in casing (6);
Start air delivery device and water delivery device, until after the interior no-sundries of casing (6), first making water delivery device quit work, finally making Air delivery device quits work.
2. pile foundation construction stake bottom according to claim 1 borehole cleaning construction method it is characterised in that:Will with air delivery device even The step that the bottom of the outlet side of appendix (2) that connects and outlet pipe (5) connects includes, by the outlet side of appendix (2) from going out The bottom of water pipe (5) puts in outlet pipe (5);By appendix (2) it is ensured that appendix (2) together with outlet pipe (5) colligation Outlet side will not be deviate from from outlet pipe (5).
3. pile foundation construction stake bottom according to claim 1 borehole cleaning construction method it is characterised in that:Outlet pipe (5) is put The step entering in mounted casing (6) includes, and outlet pipe (5) is connected with loop wheel machine;Outlet pipe (5) is put into shield by operation loop wheel machine In cylinder (6).
4. pile foundation construction stake bottom according to claim 3 borehole cleaning construction method it is characterised in that:Operation loop wheel machine is by water outlet Pipe (5) put into casing (6) interior when, outlet pipe (5) is vertically placed.
5. pile foundation construction stake bottom according to claim 4 borehole cleaning construction method it is characterised in that:Outlet pipe (5) bottom Above the internal debris of casing (6).
6. pile foundation construction stake bottom according to claim 1 borehole cleaning construction method it is characterised in that:The going out of water-supply-pipe (4) Water end (W.E.) is located above the internal debris of casing (6).
7. pile foundation construction stake bottom according to claim 1 borehole cleaning construction method it is characterised in that:Start air delivery device Afterwards, persistently rock outlet pipe (5), until the debris in casing (6) are discharged.
8. pile foundation construction stake bottom according to claim 1 borehole cleaning construction method it is characterised in that:Air delivery device is to carry Air compressor machine (1) for gases at high pressure, water delivery device is the centrifugal pump (3) being provided that highly pressurised liquid.
CN201610804253.3A 2016-09-06 2016-09-06 Construction method for pile bottom hole cleaning of pile foundation construction Pending CN106400805A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610804253.3A CN106400805A (en) 2016-09-06 2016-09-06 Construction method for pile bottom hole cleaning of pile foundation construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610804253.3A CN106400805A (en) 2016-09-06 2016-09-06 Construction method for pile bottom hole cleaning of pile foundation construction

Publications (1)

Publication Number Publication Date
CN106400805A true CN106400805A (en) 2017-02-15

Family

ID=57998741

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610804253.3A Pending CN106400805A (en) 2016-09-06 2016-09-06 Construction method for pile bottom hole cleaning of pile foundation construction

Country Status (1)

Country Link
CN (1) CN106400805A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108468520A (en) * 2018-05-15 2018-08-31 张孝福 Remove the device of motor-pumped well silt
CN112252327A (en) * 2020-10-30 2021-01-22 中铁大桥局集团第四工程有限公司 Sand cleaning system and method for side pressure slurry tank of steel pipe pile
CN112832236A (en) * 2021-01-08 2021-05-25 中铁大桥局集团有限公司 Pipe body structure and soil sampling device suitable for mud jacking tank soil sampling
CN113202101A (en) * 2021-03-28 2021-08-03 翟玉兰 Fill out native device of clearance precast tubular pile stake core fast

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003088884A (en) * 2001-09-17 2003-03-25 Kotaro Koga Sewage treating system using piles
CN101109179A (en) * 2007-06-21 2008-01-23 河北建设勘察研究院有限公司 Gas lifting reverse circulation porus cleaning construction method for slurry bulkhead cast-in-situ bored pile
CN202577409U (en) * 2012-05-14 2012-12-05 中国石油化工股份有限公司 Mud sand-rushing device for maintaining submarine pipeline
CN102979469A (en) * 2012-12-20 2013-03-20 广西建工集团第二建筑工程有限责任公司 Secondary hole cleaning method for separating sediment of large-diameter ultra-deep punching pile by sucking slurry in inner air pipe
CN103696417A (en) * 2013-12-20 2014-04-02 中国一冶集团有限公司 Secondary hole cleaning device and method of bottom of cast-in-situ bored pile

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003088884A (en) * 2001-09-17 2003-03-25 Kotaro Koga Sewage treating system using piles
CN101109179A (en) * 2007-06-21 2008-01-23 河北建设勘察研究院有限公司 Gas lifting reverse circulation porus cleaning construction method for slurry bulkhead cast-in-situ bored pile
CN202577409U (en) * 2012-05-14 2012-12-05 中国石油化工股份有限公司 Mud sand-rushing device for maintaining submarine pipeline
CN102979469A (en) * 2012-12-20 2013-03-20 广西建工集团第二建筑工程有限责任公司 Secondary hole cleaning method for separating sediment of large-diameter ultra-deep punching pile by sucking slurry in inner air pipe
CN103696417A (en) * 2013-12-20 2014-04-02 中国一冶集团有限公司 Secondary hole cleaning device and method of bottom of cast-in-situ bored pile

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李永升等: "桩基工程护筒气举清理法", 《港工技术》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108468520A (en) * 2018-05-15 2018-08-31 张孝福 Remove the device of motor-pumped well silt
CN112252327A (en) * 2020-10-30 2021-01-22 中铁大桥局集团第四工程有限公司 Sand cleaning system and method for side pressure slurry tank of steel pipe pile
CN112832236A (en) * 2021-01-08 2021-05-25 中铁大桥局集团有限公司 Pipe body structure and soil sampling device suitable for mud jacking tank soil sampling
CN113202101A (en) * 2021-03-28 2021-08-03 翟玉兰 Fill out native device of clearance precast tubular pile stake core fast

Similar Documents

Publication Publication Date Title
CN106400805A (en) Construction method for pile bottom hole cleaning of pile foundation construction
CN102979469B (en) Secondary hole cleaning method for separating sediment of large-diameter ultra-deep punching pile by sucking slurry in inner air pipe
CN101545366B (en) Underwater mining method and device
WO2020030043A1 (en) High-pressure air ramming device for oil well, and method
CN110284868A (en) A kind of gas drainage pipeline air water coal separator
CN103507109A (en) Underwater dry type cutting cabin and application method thereof
CN107939317B (en) Hydrological hole cleaning device and using method
US4040486A (en) Method and apparatus for air development and rejuvenation of water wells
JPH0979000A (en) Mine drainage device
CN112281883B (en) Precipitation system and operation method thereof
CN104294806B (en) Excavation, diversion and drainage method for inter-pile water above water-resisting layer of deep foundation pit
CN210714529U (en) Tunnel foundation pit dewatering well washing device
CN206617167U (en) The ore lifting system and mining system exploited for metal nodule
CN210658408U (en) Foundation pit dewatering well and plugging structure thereof
JP4476972B2 (en) Water collecting pipe for well
CN103615014A (en) Water-lowering device of soft-soil foundation pit and using method of water-lowering device
KR100719444B1 (en) Level of underground water lowering method and deep well point system thereof
CN106195642A (en) Ventilation type pipeline mud pressurizer
CN205823251U (en) Comprehensive draining gas production system for low-voltage and low-yield well
CN210482341U (en) Air-water mixed jet soil breaking and mud sucking device
CN213268257U (en) Vacuum flushing system
CN204327009U (en) A kind of ground precipitation deep-well well washing apparatus
JP4527158B2 (en) Leakage recovery device in submersible construction method
CN87212716U (en) Efflux type drainage system for well spots in construction engineering
CN113756831A (en) Construction method for sand blowing and filling between main pipeline and sleeve

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170215