CN106400805A - Construction method for pile bottom hole cleaning of pile foundation construction - Google Patents
Construction method for pile bottom hole cleaning of pile foundation construction Download PDFInfo
- Publication number
- CN106400805A CN106400805A CN201610804253.3A CN201610804253A CN106400805A CN 106400805 A CN106400805 A CN 106400805A CN 201610804253 A CN201610804253 A CN 201610804253A CN 106400805 A CN106400805 A CN 106400805A
- Authority
- CN
- China
- Prior art keywords
- outlet pipe
- water
- delivery device
- casing
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D13/00—Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
- E02D13/08—Removing obstacles
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Piles And Underground Anchors (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The invention relates to a construction method for pile bottom hole cleaning of pile foundation construction, in particular to a technology for removing silt and the like in a steel pipe pile through a gas lift hole cleaning device. The construction method comprises the following steps that the gas outlet end of a gas conveying pipe connected with a gas conveying device is connected with the bottom end of a water outlet pipe; the water outlet pipe is placed in an installed protection barrel; the water outlet end of a water conveying pipe connected with a water conveying device is placed in the protection barrel; and the gas conveying device and the water conveying device are started, and after no impurities exist in the protection barrel, the water conveying device stops working firstly, and finally the gas conveying device stops working. The construction method has the beneficial effects that the input is small, efficiency is high, and operation is easy. Compared with manual cleaning, safety is achieved, and a guarantee is provided for smooth implementation of pile driving construction.
Description
Technical field
The present invention relates to pile foundation construction stake bottom borehole cleaning technical field, utilize gaslift hole cleaning device to steel more particularly to a kind of
The method that silt in pile tube etc. is cleared up.
Background technology
Steel-pipe pile is a kind of building element being widely used in the building pile foundation such as bridge, harbour, house, in steel
During tube pile construction, inevitably, have the in the hole that silt or the entrance of other debris set, in order to ensure the suitable of construction
Profit, we have to clear out the debris of in the hole.
At present, in steel-pipe pile work progress, remove steel-pipe pile in debris, using by the way of be artificial borehole cleaning,
This borehole cleaning mode, high labor intensive, inefficiency, borehole cleaning effect is undesirable, and during borehole cleaning, there is safety hidden
Suffer from.
Content of the invention
It is an object of the invention to solving drawbacks described above that prior art exists it is proposed that a kind of pile foundation construction stake bottom borehole cleaning
Construction method, it has the characteristics that low cost, efficiency high, simple to operate.
The present invention is to be realized using following technical scheme:A kind of construction method of pile foundation construction stake bottom borehole cleaning, including
Following steps:
The bottom of the outlet side of the appendix being connected with air delivery device and outlet pipe is connected;
Outlet pipe is put in mounted casing;
The water side of the water-supply-pipe being connected with water delivery device is put in casing;
Start air delivery device and water delivery device, until after no-sundries in casing, first making water delivery device quit work, finally making
Air delivery device quits work.
Preferably, the step bag bottom of the outlet side of the appendix being connected with air delivery device and outlet pipe being connected
Include, the outlet side of appendix is put in outlet pipe from the bottom of outlet pipe;By appendix together with outlet pipe colligation it is ensured that
The outlet side of appendix will not be deviate from from outlet pipe.
Preferably, outlet pipe is put into the step in mounted casing to include, outlet pipe is connected with loop wheel machine;Behaviour
Make loop wheel machine to put into outlet pipe in casing.
Preferably, when operation loop wheel machine puts into outlet pipe in casing, outlet pipe is vertically placed.
Preferably, outlet pipe bottom is located above the debris within casing.
Preferably, the water side of water-supply-pipe is located above the debris within casing.
Preferably, after starting air delivery device, persistently rock outlet pipe, until the debris in casing are discharged.
Preferably, air delivery device is the air compressor machine being provided that gases at high pressure, and water delivery device is to be provided that highly pressurised liquid
Centrifugal pump.
The invention has the beneficial effects as follows:
The present invention has little, the efficiency high of input, feature simple to operate, with respect to labor cleaning, with more safety, is
The smooth enforcement of piling construction provides guarantee.
Brief description
Fig. 1 is the structural representation of hole cleaning device;
In figure:1 air compressor machine, 2 appendix, 3 centrifugal pump, 4 water-supply-pipe, 5 outlet pipe 6 casing.
Specific embodiment
With reference to specific embodiments and the drawings, the present invention will be further described.
As shown in figure 1, in steel-pipe pile installation, carrying out setting of casing 6 first, casing 6 sets takes vibration hammer
Constructed, stop when cannot sinking to casing 6, then carry out borehole cleaning operation.
The borehole cleaning operation of the present invention adopts the construction method of pile foundation construction stake bottom borehole cleaning, comprises the following steps, first will be defeated
Trachea 2 is connected with air delivery device, and the bottom of the outlet side of appendix 2 and outlet pipe 5 connects, specifically, by giving vent to anger of appendix 2
End puts in outlet pipe 5 from the bottom of outlet pipe 5;By appendix 2 it is ensured that the giving vent to anger of appendix 2 together with outlet pipe 5 colligation
End will not be deviate from from outlet pipe 5.
Then outlet pipe 5 is connected with loop wheel machine, outlet pipe 5 is vertically put in casing 6 by operation loop wheel machine, and outlet pipe
5 bottoms are located above the internal debris of casing 6, leave certain gap, to ensure that debris can smoothly enter casing 6 and then row
Go out.Again the water side of the water-supply-pipe 4 being connected with water delivery device is put in casing 6, make the water side of water-supply-pipe 4 be located at casing 6
Above internal debris, with hovel every a small distance, to ensure scouring effect.The device of so whole borehole cleaning just arranges
Become.Preferably, wherein air delivery device is the air compressor machine 1 being provided that gases at high pressure, water delivery device be provided that highly pressurised liquid from
Heart pump 3.
Finally start air compressor machine 1 and centrifugal pump 3, until after no-sundries in casing 6, that is, after the no obvious silt of casing 6, first
So that water delivery device is quit work, after the water in casing is all discharged, so that air delivery device is quit work, whole borehole cleaning work
Complete.It should be strongly noted that after startup air delivery device, will persistently rock outlet pipe 5, until the debris in casing 6 are discharged,
Such that borehole cleaning is in hgher efficiency, the effect of borehole cleaning is even more ideal.
After borehole cleaning finishes, take out whole hole cleaning device, then using vibration hammer, steel pile casting is extracted, then carry out staking out work
Industry.
The present invention reduces the blast of venthole by air compressor machine aerofluxuss, makes the mouth of pipe form the side of blowout by the pressure of water
Method realizes borehole cleaning.Centrifugal pump extracting seawater is introduced in casing by water-supply-pipe and forms high-pressure spray, silt is rushed, by water outlet
Bank of tubes goes out, and meanwhile, water-supply-pipe need to supplement casing maritime interior waters, keeps water-head.Air compressor machine air vent passes through hose connection high pressure steel
Pipe enters near mouth under sand discharge pipe (i.e. outlet pipe), forms powerful draught head, silt is along pipe in the pipe of sand discharge pipe and outside pipe
It is rushed out outside stake.
Certainly, the above is only presently preferred embodiments of the present invention it is impossible to be considered for limiting to inventive embodiment
Scope.The present invention is also not limited to the example above, and those skilled in the art are in the essential scope of the present invention
The impartial change made and improvement etc., all should belong to patent covering scope of the present invention.
Claims (8)
1. pile foundation construction stake bottom borehole cleaning construction method it is characterised in that:Comprise the following steps,
The bottom of the outlet side of the appendix being connected with air delivery device (2) and outlet pipe (5) is connected;
Outlet pipe (5) is put in mounted casing (6);
The water side of the water-supply-pipe being connected with water delivery device (4) is put in casing (6);
Start air delivery device and water delivery device, until after the interior no-sundries of casing (6), first making water delivery device quit work, finally making
Air delivery device quits work.
2. pile foundation construction stake bottom according to claim 1 borehole cleaning construction method it is characterised in that:Will with air delivery device even
The step that the bottom of the outlet side of appendix (2) that connects and outlet pipe (5) connects includes, by the outlet side of appendix (2) from going out
The bottom of water pipe (5) puts in outlet pipe (5);By appendix (2) it is ensured that appendix (2) together with outlet pipe (5) colligation
Outlet side will not be deviate from from outlet pipe (5).
3. pile foundation construction stake bottom according to claim 1 borehole cleaning construction method it is characterised in that:Outlet pipe (5) is put
The step entering in mounted casing (6) includes, and outlet pipe (5) is connected with loop wheel machine;Outlet pipe (5) is put into shield by operation loop wheel machine
In cylinder (6).
4. pile foundation construction stake bottom according to claim 3 borehole cleaning construction method it is characterised in that:Operation loop wheel machine is by water outlet
Pipe (5) put into casing (6) interior when, outlet pipe (5) is vertically placed.
5. pile foundation construction stake bottom according to claim 4 borehole cleaning construction method it is characterised in that:Outlet pipe (5) bottom
Above the internal debris of casing (6).
6. pile foundation construction stake bottom according to claim 1 borehole cleaning construction method it is characterised in that:The going out of water-supply-pipe (4)
Water end (W.E.) is located above the internal debris of casing (6).
7. pile foundation construction stake bottom according to claim 1 borehole cleaning construction method it is characterised in that:Start air delivery device
Afterwards, persistently rock outlet pipe (5), until the debris in casing (6) are discharged.
8. pile foundation construction stake bottom according to claim 1 borehole cleaning construction method it is characterised in that:Air delivery device is to carry
Air compressor machine (1) for gases at high pressure, water delivery device is the centrifugal pump (3) being provided that highly pressurised liquid.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610804253.3A CN106400805A (en) | 2016-09-06 | 2016-09-06 | Construction method for pile bottom hole cleaning of pile foundation construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610804253.3A CN106400805A (en) | 2016-09-06 | 2016-09-06 | Construction method for pile bottom hole cleaning of pile foundation construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106400805A true CN106400805A (en) | 2017-02-15 |
Family
ID=57998741
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610804253.3A Pending CN106400805A (en) | 2016-09-06 | 2016-09-06 | Construction method for pile bottom hole cleaning of pile foundation construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106400805A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108468520A (en) * | 2018-05-15 | 2018-08-31 | 张孝福 | Remove the device of motor-pumped well silt |
CN112252327A (en) * | 2020-10-30 | 2021-01-22 | 中铁大桥局集团第四工程有限公司 | Sand cleaning system and method for side pressure slurry tank of steel pipe pile |
CN112832236A (en) * | 2021-01-08 | 2021-05-25 | 中铁大桥局集团有限公司 | Pipe body structure and soil sampling device suitable for mud jacking tank soil sampling |
CN113202101A (en) * | 2021-03-28 | 2021-08-03 | 翟玉兰 | Fill out native device of clearance precast tubular pile stake core fast |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003088884A (en) * | 2001-09-17 | 2003-03-25 | Kotaro Koga | Sewage treating system using piles |
CN101109179A (en) * | 2007-06-21 | 2008-01-23 | 河北建设勘察研究院有限公司 | Gas lifting reverse circulation porus cleaning construction method for slurry bulkhead cast-in-situ bored pile |
CN202577409U (en) * | 2012-05-14 | 2012-12-05 | 中国石油化工股份有限公司 | Mud sand-rushing device for maintaining submarine pipeline |
CN102979469A (en) * | 2012-12-20 | 2013-03-20 | 广西建工集团第二建筑工程有限责任公司 | Secondary hole cleaning method for separating sediment of large-diameter ultra-deep punching pile by sucking slurry in inner air pipe |
CN103696417A (en) * | 2013-12-20 | 2014-04-02 | 中国一冶集团有限公司 | Secondary hole cleaning device and method of bottom of cast-in-situ bored pile |
-
2016
- 2016-09-06 CN CN201610804253.3A patent/CN106400805A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003088884A (en) * | 2001-09-17 | 2003-03-25 | Kotaro Koga | Sewage treating system using piles |
CN101109179A (en) * | 2007-06-21 | 2008-01-23 | 河北建设勘察研究院有限公司 | Gas lifting reverse circulation porus cleaning construction method for slurry bulkhead cast-in-situ bored pile |
CN202577409U (en) * | 2012-05-14 | 2012-12-05 | 中国石油化工股份有限公司 | Mud sand-rushing device for maintaining submarine pipeline |
CN102979469A (en) * | 2012-12-20 | 2013-03-20 | 广西建工集团第二建筑工程有限责任公司 | Secondary hole cleaning method for separating sediment of large-diameter ultra-deep punching pile by sucking slurry in inner air pipe |
CN103696417A (en) * | 2013-12-20 | 2014-04-02 | 中国一冶集团有限公司 | Secondary hole cleaning device and method of bottom of cast-in-situ bored pile |
Non-Patent Citations (1)
Title |
---|
李永升等: "桩基工程护筒气举清理法", 《港工技术》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108468520A (en) * | 2018-05-15 | 2018-08-31 | 张孝福 | Remove the device of motor-pumped well silt |
CN112252327A (en) * | 2020-10-30 | 2021-01-22 | 中铁大桥局集团第四工程有限公司 | Sand cleaning system and method for side pressure slurry tank of steel pipe pile |
CN112832236A (en) * | 2021-01-08 | 2021-05-25 | 中铁大桥局集团有限公司 | Pipe body structure and soil sampling device suitable for mud jacking tank soil sampling |
CN113202101A (en) * | 2021-03-28 | 2021-08-03 | 翟玉兰 | Fill out native device of clearance precast tubular pile stake core fast |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106400805A (en) | Construction method for pile bottom hole cleaning of pile foundation construction | |
CN102979469B (en) | Secondary hole cleaning method for separating sediment of large-diameter ultra-deep punching pile by sucking slurry in inner air pipe | |
CN101545366B (en) | Underwater mining method and device | |
WO2020030043A1 (en) | High-pressure air ramming device for oil well, and method | |
CN110284868A (en) | A kind of gas drainage pipeline air water coal separator | |
CN103507109A (en) | Underwater dry type cutting cabin and application method thereof | |
CN107939317B (en) | Hydrological hole cleaning device and using method | |
US4040486A (en) | Method and apparatus for air development and rejuvenation of water wells | |
JPH0979000A (en) | Mine drainage device | |
CN112281883B (en) | Precipitation system and operation method thereof | |
CN104294806B (en) | Excavation, diversion and drainage method for inter-pile water above water-resisting layer of deep foundation pit | |
CN210714529U (en) | Tunnel foundation pit dewatering well washing device | |
CN206617167U (en) | The ore lifting system and mining system exploited for metal nodule | |
CN210658408U (en) | Foundation pit dewatering well and plugging structure thereof | |
JP4476972B2 (en) | Water collecting pipe for well | |
CN103615014A (en) | Water-lowering device of soft-soil foundation pit and using method of water-lowering device | |
KR100719444B1 (en) | Level of underground water lowering method and deep well point system thereof | |
CN106195642A (en) | Ventilation type pipeline mud pressurizer | |
CN205823251U (en) | Comprehensive draining gas production system for low-voltage and low-yield well | |
CN210482341U (en) | Air-water mixed jet soil breaking and mud sucking device | |
CN213268257U (en) | Vacuum flushing system | |
CN204327009U (en) | A kind of ground precipitation deep-well well washing apparatus | |
JP4527158B2 (en) | Leakage recovery device in submersible construction method | |
CN87212716U (en) | Efflux type drainage system for well spots in construction engineering | |
CN113756831A (en) | Construction method for sand blowing and filling between main pipeline and sleeve |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170215 |