CN106382055A - Wall protection assembly for building construction - Google Patents

Wall protection assembly for building construction Download PDF

Info

Publication number
CN106382055A
CN106382055A CN201610967872.4A CN201610967872A CN106382055A CN 106382055 A CN106382055 A CN 106382055A CN 201610967872 A CN201610967872 A CN 201610967872A CN 106382055 A CN106382055 A CN 106382055A
Authority
CN
China
Prior art keywords
wall body
body plate
ash wall
pillar
support rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610967872.4A
Other languages
Chinese (zh)
Other versions
CN106382055B (en
Inventor
叶丽琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Bejing Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610967872.4A priority Critical patent/CN106382055B/en
Publication of CN106382055A publication Critical patent/CN106382055A/en
Application granted granted Critical
Publication of CN106382055B publication Critical patent/CN106382055B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H17/00Fencing, e.g. fences, enclosures, corrals
    • E04H17/14Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H17/00Fencing, e.g. fences, enclosures, corrals
    • E04H17/14Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
    • E04H17/1413Post-and-rail fences, e.g. without vertical cross-members
    • E04H17/1417Post-and-rail fences, e.g. without vertical cross-members with vertical cross-members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H17/00Fencing, e.g. fences, enclosures, corrals
    • E04H17/14Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
    • E04H17/16Fences constructed of rigid elements, e.g. with additional wire fillings or with posts using prefabricated panel-like elements, e.g. wired frames
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H17/00Fencing, e.g. fences, enclosures, corrals
    • E04H17/14Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
    • E04H17/20Posts therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a wall protection assembly for building construction, which comprises a left pillar (10) and a right pillar (11), wherein a support cross rod (7) is connected between the left pillar (10) and the right pillar (11); the left end part of the support cross rod (7) penetrates through the left pillar (10) and extends to the left side of the left pillar (10); the right end part of the support cross rod (7) penetrates through the right pillar (11) and extends to the right side of the right pillar (11); the left end part of the support cross rod (7) and the right end part of the support cross rod (7) are respectively fixedly connected with the left pillar (10) and the right pillar (11) through locking nuts (9); external threads (8) matched with the locking nuts (9) are respectively arranged on the left end part of the support cross rod (7) and the right end part of the support cross rod (7); more than two wall plates (1) are sequentially arranged on the support cross rod (7).

Description

A kind of construction revetment assembly
Technical field
The present invention relates to a kind of construction revetment assembly.
Background technology
At present, in the periphery in construction building site, it is required for setting up enclosure wall, building site is completely cut off by enclosure wall, it is to avoid inoperative Personnel enter into the inside of construction site, also avoid non-working person to enter into the generation that the inside of construction site causes the accident, Also avoid construction material in construction site to be stolen, enclosure wall of the prior art mostly is masonry structure simultaneously, therefore building and Need larger manpower and materials during dismounting, so will result in larger quantities, and the enclosure wall of masonry structure is after dismounting Cannot reuse, larger waste in resource can be caused, input cost is larger.
Content of the invention
The technical problem to be solved in the present invention is to provide a kind of construction revetment assembly.
For solving the above problems, the present invention adopts the following technical scheme that:
A kind of construction revetment assembly of the present invention, including left pillar and right pillar, described left pillar and described right pillar Between be connected with support rail, the left part of described support rail passes through described left pillar and extends a left side for described left pillar Side, the right part of described support rail passes through described right pillar and extends the right side of described right pillar, described support rail Left part is fixedly connected with described left pillar and described right pillar by locking nut respectively with the right part of described support rail, The external screw thread coordinating described locking nut is provided with the right part of the left part of described support rail and described support rail, The ash wall body plate being provided with more than two pieces is arranged in order on described support rail, the left surface of described ash wall body plate is provided with insertion Groove, the right flank of described ash wall body plate is provided with coordinate the insertion of described insertion groove to protrude, the front end face of described ash wall body plate It is provided with hanging block at upper position, at the front end face upper position of described ash wall body plate, is provided with support strip, described support strip is led to Cross jointed shaft and be connected with the Liang Gen gimbal lever, two described gimbal levers are provided with conical head away from that one end of described jointed shaft, institute The bottom stating ash wall body plate is provided with insertion section in triangular shape, offers and the joining of described support rail cooperation in described hanging block Close groove, the inside of described cooperation groove is arc-shaped in order to convenient and described support rail cooperation, described hanging block later half It is provided with counterbore in portion, in the first half of described hanging block, is provided with intercommunicating pore, described counterbore is inserted into being combined with stop pin, institute State that counterbore is identical with the angle of inclination of described intercommunicating pore, described counterbore is identical with the diameter of described intercommunicating pore, and described stop pin is worn Cross described intercommunicating pore and extend in described counterbore, described stop pin in order to prevent described ash wall body plate depart from after being installed with described The fixation of support rail, is provided with positioning on the base of described left pillar and on the base of right pillar and protrudes, two described fixed Position protrusion is oppositely arranged and the tops of two described positioning protrusions are provided with U-type groove, and two described U-type groove are oppositely arranged, It is connected with locating rod, the trench bottom of described U-type groove is flushed with the top of described support strip, described in two described U-type groove Locating rod is located on described support strip and is conflicted with described support strip and described ash wall body plate, and described locating rod supports horizontal stroke with described Bar Relative vertical is arranged, and is provided with rotatable lamp on described left pillar and right pillar and near the side of described ash wall body plate Seat, described lamp socket is provided with LED spotlight, described LED spotlight is in order to use in night illumination.
Further, described counterbore and the angle of inclination of described intercommunicating pore are 45 degree.
Further, the bottom of described insertion section to described support strip distance be less than the described gimbal lever length.
Further, described left pillar and described right pillar are provided with the cross bar hole passing through for described support rail.
Further, described hanging block and described ash wall body plate are fixedly connected by welding, described support strip and described body of wall Plate is fixedly connected by welding.
Further, described insertion groove is identical with the size that described insertion is protruded, in two pieces of described ash wall body plate cooperations, its In the described insertion of one piece of described ash wall body plate protrude and coordinate to realize two pieces with the described insertion groove of other one piece of described ash wall body plate The tight fit of described ash wall body plate.
Further, the upper and lower ends that described insertion is protruded are provided with chamfering, and the setting of described chamfering is in order to convenient described Insertion protrusion is rapidly inserted into cooperation in described insertion groove.
Further, the height of described ash wall body plate is not less than 120cm, and the width of every piece of described ash wall body plate is 60cm-80cm.
Further, described ash wall body plate is solid construction, and described ash wall body plate is made up of PVC plastic.
The beneficial effect of construction revetment assembly of the present invention is:By support rail, more than two pieces of ash wall body plate is entered Row supports, and the insertion section of ash wall body plate is inserted into underground, and ash wall body plate is balanced support using the Liang Gen gimbal lever, increased wall Body plate stationarity after mounting, is connected between the ash wall body plate being made more than two pieces by the cooperation that insertion groove and insertion are protruded More firm, by the support coordinating in order to prevent ash wall body plate disengaging support rail of stop pin and counterbore, by locating rod pair Ash wall body plate carries out perpendicular positioning, prevents ash wall body plate from tilting to put, also increases wind resistance, the anti-pressure ability of ash wall body plate, when using, The base of left pillar and right pillar is cast and fixes on the ground, and one end that ash wall body plate is provided with hanging block is towards construction site Interior, other end is towards outside construction site, thus preventing ash wall body plate stolen, this device can be rapidly completed and build, and the later stage tears open Except being convenient to, also any part will be caused damage lead to use in demolishing process, save input cost, Its structure is simple, easy accessibility, and convenient transport is with low cost, is suitable for promoting the use of.
Brief description
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing Have technology description in required use accompanying drawing be briefly described it should be apparent that, drawings in the following description be only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, acceptable Other accompanying drawings are obtained according to these accompanying drawings.
Fig. 1 is the overall co-ordination structural representation of construction revetment assembly of the present invention;
Fig. 2 is the front view of ash wall body plate in Fig. 1;
Fig. 3 is the left view of ash wall body plate in Fig. 1;
Fig. 4 is the sectional view of hanging block in Fig. 2, and wherein, stop pin is not inserted in intercommunicating pore and counterbore.
Fig. 5 is the left view positioning protrusion in Fig. 1.
Fig. 6 is the top view of Fig. 5.
Specific embodiment
Below in conjunction with the accompanying drawings the preferred embodiments of the present invention are described in detail, so that advantages and features of the invention energy It is easier to be readily appreciated by one skilled in the art, thus protection scope of the present invention is made apparent clearly defining.
Refering to shown in Fig. 1-6, a kind of construction revetment assembly of the present invention, including left pillar 10 and right pillar 11, It is connected with support rail 7, the left part of described support rail 7 passes through a described left side between described left pillar 10 and described right pillar 11 Pillar 10 simultaneously extends the left side of described left pillar 10, and the right part of described support rail 7 passes through described right pillar 11 and extends Go out the right side of described right pillar 11, the left part of described support rail 7 and the right part of described support rail 7 pass through locking respectively Nut 9 is fixedly connected with described left pillar 10 and described right pillar 11, the left part of described support rail 7 and described support rail The external screw thread 8 coordinating described locking nut 9 is provided with 7 right part, described support rail 7 is arranged in order and is provided with More than two pieces of ash wall body plate 1, the left surface of described ash wall body plate 1 is provided with insertion groove 12, the right flank of described ash wall body plate 1 sets It is equipped with to coordinate the insertion of described insertion groove 12 to protrude 13, at the front end face upper position of described ash wall body plate 1, be provided with suspension Block 2, is provided with support strip 4 at the front end face upper position of described ash wall body plate 1, described support strip 4 is connected with two by jointed shaft 5 The root gimbal lever 6, two described gimbal levers 6 are provided with conical head 61 away from that one end of described jointed shaft 5, described ash wall body plate 1 Bottom is provided with the insertion section 3 in triangular shape, offers the cooperation groove with the cooperation of described support rail 7 in described hanging block 2 22, the inside of described cooperation groove 22 is that arc-shaped is coordinated with described support rail 7 in order to convenient, described hanging block 2 later half It is provided with counterbore 23 in portion, in the first half of described hanging block 2, is provided with intercommunicating pore 24, described counterbore 23 is inserted into being combined with lock Rationed marketing 25, described counterbore 23 is identical with the angle of inclination of described intercommunicating pore 24, the diameter of described counterbore 23 and described intercommunicating pore 24 Identical, described stop pin 25 extends in described counterbore 23 through described intercommunicating pore 24, and described stop pin 25 is described in order to prevent Ash wall body plate 1 departs from the fixation with described support rail 7 after being installed, the bottom with right pillar 11 on the base of described left pillar 10 It is provided with positioning protrusion 101, two described positioning are protruded 101 and are oppositely arranged and two described tops positioning protrusion 101 on Portion is provided with U-type groove 110, and two described U-type groove 110 are oppositely arranged, and it is fixed to be connected with two described U-type groove 110 Position bar 100, the trench bottom of described U-type groove 110 is flushed with the top of described support strip 4, and described locating rod 100 is located at described supporting Conflict on bar 4 and with described support strip 4 and described ash wall body plate 1, described locating rod 100 and described support rail 7 Relative vertical Setting, is provided with rotatable lamp socket 103 on described left pillar 10 and right pillar 11 and near the side of described ash wall body plate 1, LED spotlight 102 is provided with described lamp socket 103, described LED spotlight 102 is in order to use in night illumination, thus convenience is at night Described ash wall body plate 1 is installed, at night, described ash wall body plate 1 is stolen prevented also from illegal person.
Wherein, described counterbore 23 and the angle of inclination of described intercommunicating pore 24 are 45 degree.
Wherein, the bottom of described insertion section 3 to described support strip 4 distance be less than the described gimbal lever 6 length.
Wherein, described left pillar 10 and described right pillar 11 are provided with the cross bar hole passing through for described support rail 7.
Wherein, described hanging block 2 and described ash wall body plate 1 are fixedly connected by welding, described support strip 4 and described ash wall body plate 1 is fixedly connected by welding.
Wherein, described insertion groove 12 is identical with the size that described insertion protrudes 13, in two pieces of described ash wall body plate 1 cooperations, The described insertion of one of described ash wall body plate 1 protrude 13 with the described insertion groove 12 of other one piece of described ash wall body plate 1 coordinate with Realize the tight fit of two pieces of described ash wall body plate 1.
Wherein, the upper and lower ends of described insertion protrusion 13 are provided with chamfering 130, and the setting of described chamfering 130 is in order to convenient Described insertion is protruded 13 and is rapidly inserted into cooperation in described insertion groove 12.
Wherein, the height of described ash wall body plate 1 is not less than 120cm, and the width of every piece of described ash wall body plate 1 is 60cm-80cm.
Wherein, described ash wall body plate 1 is solid construction, and described ash wall body plate 1 is made up of PVC plastic.
The beneficial effect of construction revetment assembly of the present invention is:By support rail, more than two pieces of ash wall body plate is entered Row supports, and the insertion section of ash wall body plate is inserted into underground, and ash wall body plate is balanced support using the Liang Gen gimbal lever, increased wall Body plate stationarity after mounting, is connected between the ash wall body plate being made more than two pieces by the cooperation that insertion groove and insertion are protruded More firm, by the support coordinating in order to prevent ash wall body plate disengaging support rail of stop pin and counterbore, by locating rod pair Ash wall body plate carries out perpendicular positioning, prevents ash wall body plate from tilting to put, also increases wind resistance, the anti-pressure ability of ash wall body plate, when using, The base of left pillar and right pillar is cast and fixes on the ground, and one end that ash wall body plate is provided with hanging block is towards construction site Interior, other end is towards outside construction site, thus preventing ash wall body plate stolen, this device can be rapidly completed and build, and the later stage tears open Except being convenient to, also any part will be caused damage lead to use in demolishing process, save input cost, Its structure is simple, easy accessibility, and convenient transport is with low cost, is suitable for promoting the use of.
Ultimate principle, principal character and the advantages of the present invention of the present invention have been shown and described above.The technology of the industry , it should be appreciated that the present invention is not restricted to the described embodiments, the simply explanation described in above-described embodiment and description is originally for personnel Invention principle, without departing from the spirit and scope of the present invention the present invention also have various changes and modifications, these change Change and improvement both falls within scope of the claimed invention.Claimed scope by appending claims and its Equivalent defines.

Claims (9)

1. a kind of construction with revetment assembly it is characterised in that:Including left pillar(10)With right pillar(11), described left pillar (10)With described right pillar(11)Between be connected with support rail(7), described support rail(7)Left part pass through described left Post(10)And extend described left pillar(10)Left side, described support rail(7)Right part pass through described right pillar(11) And extend described right pillar(11)Right side, described support rail(7)Left part and described support rail(7)Right part Pass through locking nut respectively(9)With described left pillar(10)With described right pillar(11)It is fixedly connected, described support rail(7)'s Left part and described support rail(7)Right part on be provided with cooperation described locking nut(9)External screw thread(8), institute State support rail(7)On be arranged in order the ash wall body plate being provided with more than two pieces(1), described ash wall body plate(1)Left surface on arrange There is insertion groove(12), described ash wall body plate(1)Right flank on be provided with to coordinate described insertion groove(12)Insertion protrude (13), described ash wall body plate(1)Front end face upper position at be provided with hanging block(2), described ash wall body plate(1)Front end face on the lower It is provided with support strip at position(4), described support strip(4)By jointed shaft(5)It is connected with the Liang Gen gimbal lever(6), described in two The gimbal lever(6)Away from described jointed shaft(5)That one end be provided with conical head(61), described ash wall body plate(1)Bottom be provided with Insertion section in triangular shape(3), described hanging block(2)In offer and described support rail(7)The cooperation groove of cooperation (22), described cooperation groove(22)Inside be arc-shaped in order to convenient with described support rail(7)Cooperation, described hanging block (2)Latter half of in be provided with counterbore(23), described hanging block(2)First half in be provided with intercommunicating pore(24), described counterbore (23)It is inserted into being combined with stop pin(25), described counterbore(23)With described intercommunicating pore(24)Angle of inclination identical, described heavy Hole(23)With described intercommunicating pore(24)Diameter identical, described stop pin(25)Through described intercommunicating pore(24)It is described heavy to extend to Hole(23)Interior, described stop pin(25)In order to prevent described ash wall body plate(1)Depart from and described support rail after being installed(7)'s Fixing, described left pillar(10)Base on and right pillar(11)Base on be provided with positioning protrude(101), described in two Positioning is protruded(101)It is oppositely arranged and two described positioning are protruded(101)Top be provided with U-type groove(110), described in two U-type groove(110)It is oppositely arranged, in two described U-type groove(110)In be connected with locating rod(100), described U-type groove(110) Trench bottom and described support strip(4)Top flush, described locating rod(100)Positioned at described support strip(4)On and with institute State support strip(4)With described ash wall body plate(1)Conflict, described locating rod(100)With described support rail(7)Relative vertical is arranged, Described left pillar(10)With right pillar(11)Upper and close described ash wall body plate(1)Side be provided with rotatable lamp socket (103), described lamp socket(103)On be provided with LED spotlight(102), described LED spotlight(102)In order to use in night illumination.
2. construction according to claim 1 with revetment assembly it is characterised in that:Described counterbore(23)Connect with described Hole(24)Angle of inclination be 45 degree.
3. construction according to claim 1 with revetment assembly it is characterised in that:Described insertion section(3)Bottom arrive Described support strip(4)Distance be less than the described gimbal lever(6)Length.
4. construction according to claim 1 with revetment assembly it is characterised in that:Described left pillar(10)With the described right side Pillar(11)On be provided with for described support rail(7)The cross bar hole passing through.
5. construction according to claim 1 with revetment assembly it is characterised in that:Described hanging block(2)With described wall Body plate(1)It is fixedly connected by welding, described support strip(4)With described ash wall body plate(1)It is fixedly connected by welding.
6. construction according to claim 1 with revetment assembly it is characterised in that:Described insertion groove(12)Insert with described Enter to protrude(13)Size identical, in two pieces of described ash wall body plate(1)During cooperation, one of described ash wall body plate(1)Described insert Enter to protrude(13)With other one piece of described ash wall body plate(1)Described insertion groove(12)Cooperation is to realize two pieces of described ash wall body plate(1) Tight fit.
7. construction according to claim 6 with revetment assembly it is characterised in that:Described insertion is protruded(13)Upper and lower Two ends are provided with chamfering(130), described chamfering(130)Setting in order to facilitate described insertion protrude(13)It is rapidly inserted into described Insertion groove(12)Interior cooperation.
8. construction according to claim 1 with revetment assembly it is characterised in that:Described ash wall body plate(1)Height not Less than 120cm, every piece of described ash wall body plate(1)Width be 60cm-80cm.
9. construction according to claim 8 with revetment assembly it is characterised in that:Described ash wall body plate(1)For solid knot Structure, described ash wall body plate(1)It is made up of PVC plastic.
CN201610967872.4A 2016-11-04 2016-11-04 A kind of construction revetment component Active CN106382055B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610967872.4A CN106382055B (en) 2016-11-04 2016-11-04 A kind of construction revetment component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610967872.4A CN106382055B (en) 2016-11-04 2016-11-04 A kind of construction revetment component

Publications (2)

Publication Number Publication Date
CN106382055A true CN106382055A (en) 2017-02-08
CN106382055B CN106382055B (en) 2018-10-16

Family

ID=57956696

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610967872.4A Active CN106382055B (en) 2016-11-04 2016-11-04 A kind of construction revetment component

Country Status (1)

Country Link
CN (1) CN106382055B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104712175A (en) * 2015-03-20 2015-06-17 国家电网公司 General intelligent combined fence
CN204418796U (en) * 2015-01-20 2015-06-24 巫志丰 A kind of building site hoarding being easy to build
CN204436013U (en) * 2014-12-31 2015-07-01 浙江耀隆复合材料科技有限公司 A kind of fence
CN204511023U (en) * 2015-01-27 2015-07-29 浙江水利水电学院 A kind of river course security protection guardrail
JP2015190284A (en) * 2014-03-29 2015-11-02 積水樹脂株式会社 Breakable fence in emergency

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015190284A (en) * 2014-03-29 2015-11-02 積水樹脂株式会社 Breakable fence in emergency
CN204436013U (en) * 2014-12-31 2015-07-01 浙江耀隆复合材料科技有限公司 A kind of fence
CN204418796U (en) * 2015-01-20 2015-06-24 巫志丰 A kind of building site hoarding being easy to build
CN204511023U (en) * 2015-01-27 2015-07-29 浙江水利水电学院 A kind of river course security protection guardrail
CN104712175A (en) * 2015-03-20 2015-06-17 国家电网公司 General intelligent combined fence

Also Published As

Publication number Publication date
CN106382055B (en) 2018-10-16

Similar Documents

Publication Publication Date Title
CN207082227U (en) A kind of intelligent transportation guiding device of intelligent transportation system
CN108894237A (en) A kind of fixation device of mine slope supporting mesh
CN208615952U (en) A kind of screen door in rail transit column top mounting and adjusting structure
CN106382055A (en) Wall protection assembly for building construction
CN201650135U (en) Novel vertical telescopic derrick
CN202882393U (en) Pitch point connecting structure of inclined draw rod of scaffold
CN211037782U (en) Triangular support frame
CN205399241U (en) Public road bridge high strength windshield for roof beam
CN208899502U (en) A kind of fixation device of mine slope supporting mesh
CN106401281A (en) Novel revetment device used for building construction
CN107119899A (en) Scaffold for building with auto-lock function
CN107012811A (en) Safety barrier
CN106522652A (en) Parapet wall device used for building construction
CN206408561U (en) Safety barrier
CN205134930U (en) Novel scaffold connecting structure
CN210919157U (en) A interim plugging device for mine
CN211369496U (en) Triangular anti-shaking support piece for scaffold
CN204420911U (en) Portable street lamp post and street lamp
CN204960291U (en) Bracing piece of scaffold and fixed connection structure and scaffold between connecting rod
CN209260505U (en) A kind of concrete laying fixed frame
CN203336518U (en) Combined type metal halide lamp overhead support
CN211171715U (en) Height limiting alarm device for highway engineering
CN207905343U (en) A kind of fastener locking device for scaffold
CN207334530U (en) The Landscape Lamp of convenient installation
CN207878917U (en) A kind of construction scaffold

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20180829

Address after: 362321 Hou Hou Industrial Zone, Meishan Town, Nanan City, Quanzhou, Fujian

Applicant after: Fengshun, Quanzhou reaches metal product Co., Ltd

Address before: 362402 No. 50, Tu Lou, Peng Ge Village, Penglai Town, Anxi, Quanzhou, Fujian

Applicant before: Ye Liqin

GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191012

Address after: 362100 No. 236, Liang Liang village, Tu Tu Town, Huian County, Fujian, Quanzhou

Patentee after: Wang Pei Jie

Address before: 362321 Hou Hou Industrial Zone, Meishan Town, Nanan City, Quanzhou, Fujian

Patentee before: Fengshun, Quanzhou reaches metal product Co., Ltd

CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: No.102 Kaixuan Road, Fuxi street, Deqing County, Huzhou City, Zhejiang Province

Patentee after: Wang Peijie

Address before: 362100 No. 236, Liang Liang village, Tu Tu Town, Huian County, Fujian, Quanzhou

Patentee before: Wang Peijie

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200109

Address after: Xihongmen Town, Daxing District, Beijing 102600

Patentee after: China Railway 18th Bureau Group Beijing Engineering Co., Ltd

Address before: No.102 Kaixuan Road, Fuxi street, Deqing County, Huzhou City, Zhejiang Province

Patentee before: Wang Peijie