CN106379704A - Push-pull translation steering construction system for large equipment - Google Patents
Push-pull translation steering construction system for large equipment Download PDFInfo
- Publication number
- CN106379704A CN106379704A CN201610936379.6A CN201610936379A CN106379704A CN 106379704 A CN106379704 A CN 106379704A CN 201610936379 A CN201610936379 A CN 201610936379A CN 106379704 A CN106379704 A CN 106379704A
- Authority
- CN
- China
- Prior art keywords
- hydraulic pusher
- equipment
- face
- auxiliary frame
- track
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G35/00—Mechanical conveyors not otherwise provided for
Abstract
The invention discloses a push-pull translation steering construction system for large equipment. The construction system comprises an auxiliary frame formed by assembling I-shaped steel, a rail and a hydraulic pusher. The auxiliary frame is arranged on the rail. The hydraulic pusher is installed in the auxiliary frame, one end of the hydraulic pusher is fixed to the rail through a rail clamp, the other end of the hydraulic pusher is movably connected with the auxiliary frame, and the face, connected with the hydraulic pusher, of the auxiliary frame is adjacent to the to-be-pushed equipment. The frame structure is a quadrangular prism structure with the section of a right trapezoid. The two parallel planes where the upper bottom and the lower bottom of the right trapezoid are located are perpendicular to the rail, and the plane where the hypotenuse of the right trapezoid is located is upward. The plane where the vertical side is located is placed on the rail. The hydraulic pusher is installed on the plane where the vertical side is located. The fixed end of the hydraulic pusher is located at the center position of the plane where the vertical side is located.
Description
Technical field
The invention discloses a kind of main equipment can push-and-pull translation turn to construction system.
Background technology
The volume of the large equipment of large nuclear-power and fired power generating unit is big, weight big, and the design space of Factory Building is often limited,
This results in large equipment after entering Factory Building it is impossible to be done directly lifting operation using large-scale crane, is typically lifted into
Neighbouring position, is completed the work such as the translation of equipment, steering, adjustment be in place using propulsion plant or is just dragged to using hoist engine
Position position, is then adjusted in place using jack.
When large equipment in place using conventional method, generally require the different directions arrangement hydraulic pressure translation dress in equipment
Put, due to installing space limit, possibly cannot arrange translating device, and if translating device lazy weight, need translating device
Repeatedly it is installed to different directions and carrys out adjusting device, take time and effort, and potential safety hazard is larger.
According to the same problem of hoist engine, if when hoist engine draws equipment in different directions, arrangement is complicated, workload
Larger;For example:As shown in Fig. 2 Haiyang AP1000 nuclear power first stage of the project, Integral Condenser lower module is divided into two pieces, in place
On the basis of position is in Factory Building sea water pond condenser, equipment turns to insufficient space, need to first will be in place first when lower module is in place
Good lower module, first pushes away on-station position, after the completion for the treatment of second piece of steering, then the propulsion plant of first piece of module is installed to
The opposite side of equipment, it is elapsed back again in place, and when two modules are assembled, also needs repeatedly to adjust lower module;Using
Prior art difficulty of construction is big, and construction is complicated.
Content of the invention
In order to solve the technical problem that background section is pointed out, the invention discloses a kind of turn for main equipment translation
To construction system, can be in the case of limited by construction space, equipment, only in the single direction cloth of equipment by this kind of construction system
Horizontalization moves instrument so that it may complete the translation of equipment, adjustment work.
The technical solution used in the present invention is as follows:
A kind of main equipment can push-and-pull translation turn to construction system, including the auxiliary frame being assembled by I-steel and rail
Road and hydraulic pusher, described auxiliary frame setting is in orbit;Described hydraulic pusher is arranged in auxiliary frame, and
Hydraulic pusher one end is fixed with track by rail clamping device, and the other end is flexibly connected with auxiliary frame, and auxiliary frame and hydraulic pressure
The face that propeller connects is adjacent with treating passage equipment, treats passage equipment for promoting.
Further, described frame structure is the quadrangular structure that a section is right-angled trapezium, and described right angle is terraced
In shape, bottom is vertical with track with the two of place of going to the bottom planes being parallel to each other, and right-angled trapezium hypotenuse be located face up, erect
The face that straight waist is located is placed in orbit;Described hydraulic pusher is arranged on the face that vertical waist is located.
Further, the fixing end of described hydraulic pusher is located at the center in the face that described vertical waist is located,
And vertically the length in face that waist is located and/or width are all higher than equal to length sum during two hydraulic pusher minimum stroke;
The length in face that vertically waist is located and/or width are respectively less than length sum during two hydraulic pusher ranges.
Further, described hydraulic pusher is that in-orbit weight elapses equipment, is a hydraulic jack.
Further, when hydraulic pusher only realizes the motion in former and later two directions, track only need to two parallel
Track, when hydraulic pusher will realize the motion of four direction all around, track then needs four sides all around
To all laying;In addition, the selection mode of track is also a lot, if the track having activity on band arc orbit, or track connects
Head (track for a train active joint), all can achieve the conversion direction of any direction.
The operation principle of the present invention is as follows:
When equipment needs to elapse forward, place propeller as shown in Figure 1, by propeller, equipment is put down forward
Move, if equipment needs to draw backward, to the left or to the right, directly can complete angle of rake movable end replacing direction after equipment
Draw work.
Beneficial effects of the present invention are as follows:
Push-and-pull translation can turn to construction system to carry out auxiliary equipment in place using the present invention, only with a set of translating device,
Achieve that the advance in a direction for the equipment or retrogressing, material-saving, equipment, artificial, shortening construction period.This patent is especially
It is applied to the in place of Integral Condenser lower module and the mounting condition main equipment similar with Integral Condenser is just
Install.
Brief description
Fig. 1 is can push-and-pull translation device structure chart;
Fig. 2 be large equipment can push-and-pull translation turn to construction system schematic diagram;
Fig. 3 Integral Condenser schematic diagram in place;
In figure:1. track, 2. propeller, 3. auxiliary frame, 4 equipment.
Specific embodiment
As shown in figure 1, the push-and-pull translation that the present invention is a kind of equipment turns to construction system, it does power using propeller,
After equipment is placed on track, arrange hydraulic pusher in the side of equipment, propeller is angle of rake with the fixing position of track
Fixing end, in equipment the same side auxiliary frame of being made by I-steel of arrangement, connect will in place equipment auxiliary frame with reliably
Connect, and auxiliary frame is in the propelling stroke of hydraulic pusher.
Specifically, it includes the auxiliary frame 3 being assembled by I-steel and track 1 and hydraulic pusher 2, described auxiliary frame
Frame setting is in orbit;Described hydraulic pusher is arranged in auxiliary frame 3, and hydraulic pusher one end pass through rail clamping device
Fix with track, the other end is flexibly connected with auxiliary frame, and the face that is connected with hydraulic pusher 2 of auxiliary frame 3 with wait to elapse
Equipment is adjacent, treats passage equipment 4 for promoting.
Further, described frame structure 3 is the quadrangular structure that a section is right-angled trapezium, and described right angle is terraced
In shape, bottom is vertical with track with the two of place of going to the bottom planes being parallel to each other, and right-angled trapezium hypotenuse be located face up, erect
The face that straight waist is located is placed in orbit;Described hydraulic pusher is arranged on the face that vertical waist is located.
Further, the fixing end of described hydraulic pusher 2 is located at the center in the face that described vertical waist is located,
And vertically the length in face that waist is located and/or width are all higher than equal to length sum during two hydraulic pusher minimum stroke;
The length in face that vertically waist is located and/or width are respectively less than length sum during two hydraulic pusher ranges.
When equipment needs to elapse forward, place propeller by shown in Fig. 1,2, by propeller, equipment is put down forward
Move, if equipment need to pull back, directly angle of rake movable end replacing direction can be completed the post-tensioning work of equipment.
The present invention large equipment in place during use hydraulic translation device, control and pipe be steadily reliable, especially
It is applied to the in place of precision equipment in place, can effectively ensure the installation quality of equipment.
This invention can complete the work in place of large equipment in the case of not using hoist engine, realize complicated big part and set
Standby delivery.
This invention can ensure can be only logical in the case of not carrying out other extra works in big part in place equipment in place
Cross the direction of change propeller movable end, the reciprocal translation of the equipment that completes.Easy construction of the present invention, labor intensive is few, saves
Material utensil, construction cost is few, short construction period.
When hydraulic pusher only realizes the motion in former and later two directions, track only needs to two parallel orbits,
When hydraulic pusher will realize the motion of four direction all around, track then needs four direction all around all to lay;
In addition, the selection mode of track is also a lot, if the rail joint (railway rail of activity is had on band arc orbit, or track
Road active joint), all can achieve the conversion direction of any direction.
Concrete application is as follows:
As shown in Figure 3:Integral Condenser lower component is divided into two pieces, when in place using Factory Building driving will wherein one put
Put on the track of the delivery platform of lower section and (to note controlling turning velocity it is ensured that assembly and mill building frame post in steering procedure
There is certain safe distance, steering procedure is slow and continuous).Then using equipment shown in the present invention, condenser lower component is elapsed
To on-station position, continuing translation condenser lower component, until stopping after meeting the revolution space of another of lower component, treating
Second assembly of condenser, to on-station position, is retracted on-station position using this device by second assembly movement, completes whole
Condenser lower module in place.In whole process, this push-and-pull translating device is only installed and once can be completed condenser lower module
In place;Secondly as this device selects hydraulic drive, translational speed is stable, in two assemblies in Integral Condenser bottom
Assembling construction is equally completed using this device.
Claims (2)
1. a kind of main equipment can push-and-pull translation turn to construction system it is characterised in that including the auxiliary being assembled by I-steel
Framework and track and hydraulic pusher, described auxiliary frame setting is in orbit;Described hydraulic pusher is arranged on auxiliary
In framework, and hydraulic pusher one end fixed with track by rail clamping device, the other end is flexibly connected with auxiliary frame, and assist
Framework is adjacent with treating passage equipment with the face that hydraulic pusher connects, and treats passage equipment for promoting;
Described frame structure is the quadrangular structure that a section is right-angled trapezium, bottom and the institute that goes to the bottom in described right-angled trapezium
Two planes being parallel to each other vertical with track, and facing up of being located of right-angled trapezium hypotenuse, the face that vertical waist is located is put
Put in orbit;Described hydraulic pusher is arranged on the face that vertical waist is located;
The center in the face that the fixing end of described hydraulic pusher is located positioned at described vertical waist, and vertical waist place
The length in face and/or width are all higher than equal to length sum during two hydraulic pusher minimum stroke;The face that vertically waist is located
Length and/or width be respectively less than two hydraulic pusher ranges when length sum.
2. main equipment as claimed in claim 1 push-and-pull translation can turn to construction system it is characterised in that described hydraulic pressure
Propeller is hydraulic jack.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610936379.6A CN106379704B (en) | 2016-11-01 | 2016-11-01 | A kind of translation that pushes and pulls of large scale equipment turns to construction system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610936379.6A CN106379704B (en) | 2016-11-01 | 2016-11-01 | A kind of translation that pushes and pulls of large scale equipment turns to construction system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106379704A true CN106379704A (en) | 2017-02-08 |
CN106379704B CN106379704B (en) | 2018-08-10 |
Family
ID=57957058
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610936379.6A Active CN106379704B (en) | 2016-11-01 | 2016-11-01 | A kind of translation that pushes and pulls of large scale equipment turns to construction system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106379704B (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0443214A2 (en) * | 1990-02-20 | 1991-08-28 | Harumoto Iron Works Co., Ltd. | Laying method of members |
CN101058372A (en) * | 2007-05-25 | 2007-10-24 | 中国舰船研究设计中心 | Large cargo translating device |
CN202321556U (en) * | 2011-11-25 | 2012-07-11 | 新疆华油技术服务股份有限公司 | Integral translation device for drilling machine |
CN203558470U (en) * | 2013-11-13 | 2014-04-23 | 北京英迈特矿山机械有限公司 | Intermittence push-pull moving device of hydraulic clamping rail |
CN103790154A (en) * | 2013-11-29 | 2014-05-14 | 中交第四航务工程局有限公司 | Reinforcement cage pushing system and reinforcement cage pushing method |
CN203807101U (en) * | 2014-04-18 | 2014-09-03 | 中国能源建设集团安徽电力建设第一工程公司 | Moving device for large-scale electrical equipment |
CN206187889U (en) * | 2016-11-01 | 2017-05-24 | 山东电力建设第一工程公司 | But push -and -pull translation of main equipment turns to construction system |
-
2016
- 2016-11-01 CN CN201610936379.6A patent/CN106379704B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0443214A2 (en) * | 1990-02-20 | 1991-08-28 | Harumoto Iron Works Co., Ltd. | Laying method of members |
CN101058372A (en) * | 2007-05-25 | 2007-10-24 | 中国舰船研究设计中心 | Large cargo translating device |
CN202321556U (en) * | 2011-11-25 | 2012-07-11 | 新疆华油技术服务股份有限公司 | Integral translation device for drilling machine |
CN203558470U (en) * | 2013-11-13 | 2014-04-23 | 北京英迈特矿山机械有限公司 | Intermittence push-pull moving device of hydraulic clamping rail |
CN103790154A (en) * | 2013-11-29 | 2014-05-14 | 中交第四航务工程局有限公司 | Reinforcement cage pushing system and reinforcement cage pushing method |
CN203807101U (en) * | 2014-04-18 | 2014-09-03 | 中国能源建设集团安徽电力建设第一工程公司 | Moving device for large-scale electrical equipment |
CN206187889U (en) * | 2016-11-01 | 2017-05-24 | 山东电力建设第一工程公司 | But push -and -pull translation of main equipment turns to construction system |
Also Published As
Publication number | Publication date |
---|---|
CN106379704B (en) | 2018-08-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101761032A (en) | Jack-in erection equipment for bridge | |
CN106245919B (en) | A kind of assembled architecture Automated assembly platform | |
CN105484514A (en) | Method for strengthening circular reinforced concrete pier column | |
CN105821773A (en) | Electric penetration device for hogging moment steel strands of prefabricated T-shaped beams | |
CN108608292A (en) | A kind of Construction of Civil Engineering metal sheet surface process equipment | |
CN216858783U (en) | Material increasing and decreasing mixed repairing device of water turbine mobile robot | |
CN103557011B (en) | A kind of side wall trolley | |
CN206187889U (en) | But push -and -pull translation of main equipment turns to construction system | |
CN106379704A (en) | Push-pull translation steering construction system for large equipment | |
CN103806374B (en) | The overall track erection supplying system of assembly type steel bridge on highway and erection push technique | |
CN104947804B (en) | A kind of steel bracket and the construction method that beam-column node structure is built using it | |
CN201908665U (en) | Movable variable-cross section lining trolley | |
CN205046480U (en) | Steel purlin girder segment point self -adaptation pushes away system in top in succession | |
CN106639337A (en) | Assembly type column-mounting auxiliary device | |
CN103835400A (en) | Prestress steel plate shear wall | |
CN217175828U (en) | Steel construction fixing device for construction | |
CN205205674U (en) | Top of tower hoist and mount system | |
CN205576922U (en) | A novel guider of assembled for construction of driven pile pile sinking | |
CN108457374A (en) | A kind of box beam and column are linked and packed formula node preparation process and its node | |
CN204326490U (en) | A kind of construction of lift well operating platform | |
CN205541966U (en) | Neutral beam injection ware supports and interfacing apparatus | |
CN110000922B (en) | Whole installation device of prefabricated T roof beam pterygoid lamina reinforcing bar of road bridge | |
CN108840234B (en) | Hoisting device for prefabricated section and hoisting method thereof | |
CN206220472U (en) | A kind of bracing means for improving bracing members stability of strutting system | |
CN106276603A (en) | Lifting device and using method thereof for cooling tower Construction of Steel Structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |