CN106368705A - Method for controlling rock burst during roadway tunneling in fault fracture zone - Google Patents

Method for controlling rock burst during roadway tunneling in fault fracture zone Download PDF

Info

Publication number
CN106368705A
CN106368705A CN201610915674.3A CN201610915674A CN106368705A CN 106368705 A CN106368705 A CN 106368705A CN 201610915674 A CN201610915674 A CN 201610915674A CN 106368705 A CN106368705 A CN 106368705A
Authority
CN
China
Prior art keywords
chamber
concrete
anchor
grouting
fault
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610915674.3A
Other languages
Chinese (zh)
Inventor
潘立友
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University of Science and Technology
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN201610915674.3A priority Critical patent/CN106368705A/en
Publication of CN106368705A publication Critical patent/CN106368705A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/18Methods of underground mining; Layouts therefor for brown or hard coal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/003Machines for drilling anchor holes and setting anchor bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Inorganic Chemistry (AREA)
  • Chemical & Material Sciences (AREA)
  • Civil Engineering (AREA)
  • Remote Sensing (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a method for controlling rock burst during roadway tunneling in a fault fracture zone. The method comprises the steps that firstly, in the roadway tunneling process of a rock burst zone in the fault area, chambers are constructed to the two sides of a roadway at intervals, and temporary support through anchor rods is conducted; then, each chamber is filled with concrete through nogs; and finally, a roadway roof is subjected to grouting reinforcement. By implementing the three measures, in the roadway tunneling process in the high stress fault structure zone, the coupling effect of supporting, energy releasing and reinforcement can be achieved, the high stress fault structure zone can release energy stably for a long time, and the tendentiousness of the rock burst is reduced fundamentally.

Description

Controlling of Coal Outburst method during fault belt Nei Jue lane
Technical field
The invention belongs to Coal Mining Technology field.
Background technology
China's coal-mine bump is closely related with geological conditions, and geologicstructure area bump is susceptible to, and accounts for More than 60%.With the increase of coal mining depth, bump frequency and the intensity of structure realm are continuously increased, and occur disconnected The bump in layer region occupies construction bump larger specific gravity, and this fault belt impact disaster has seriously govern me The safety in production in state colliery.It was verified that tunnelling enters shear-zone, because fault belt rock stratum is relatively soft, and coal Layer has shock hazard by force, under the conditions of the Engineering Disturbance of driving, structure type bump, such impact can occur Ground pressure can cause coal petrography suddenly across falling, and takes precautions against difficulty greatly, and difficult supporting, difficult protection are disguised strong.This fault belt impact The preventing and treating of ground pressure is different from general type, is difficult to take precautions against using conventional measure.Because coal (rock) body produces mixing impact, routine Shield specific aim is difficult to hold, if being subject to the strong disturbance of work surface Dynamic stress field to act on again, easily occurs locality serious Bump.
The dangerous bump of shear-zone, deep mining, thump has very strong disguise, and often in tunnel, the way of escape is sent out Raw impact suddenly, is acted on motion with a large amount of rock fallings, and difficulty of afterwards resuming production is big.For the multi-fault zone of intersection Domain, tomography concentrate this danger of burst of pinching band abnormal serious, and these regions are mostly in deep and there is tectonic stress position, such as Synclinal shaft, basin region etc..China opens the old mine such as Luan mining area, southwest, northeast mining area, mountain energy mining area, mining depth Degree maximum reaches more than 1000m, and average mining depth is more than 800m.Therefore, for this fault belt, there is hidden spy The bump levied, needs to invent a kind of method adapting to high stress broken zone of rocks and energy prevention and control bump steady in a long-term, right Prevention and control construction rock blast hazard is significant.
Content of the invention
The purpose of the present invention is for the problems referred to above, proposes to adapt to that high stress broken zone of rocks releases energy steadily in the long term Plant Controlling of Coal Outburst method during fault belt Nei Jue lane.
For reaching above-mentioned purpose, the present invention adopts the technical scheme that:
A kind of Controlling of Coal Outburst method during fault belt Nei Jue lane is it is characterised in that include:
The first step, Chamber Construction
Exist in the section road tunneling process that bump occurs entering fault region, at interval of 15-20m, to lane Road both sides construction depth 5m, width 3m, the chamber of height 2-3m, chamber top board planarizing process, and carry out anchor pole gib; Using array pitch between 800*800 during anchor pole arrangement;
Grillage Concrete Filled in second step, chamber
First carry out grillage filling in the chamber of gib, then in grillage space filling concrete it is desirable to coagulation Native intensity is more than the intensity of chamber balkstone;For reducing the disturbance between adjacent chamber, fill order takes interval filling side Formula;
3rd step, back grouting and reinforcing
In there is the section road tunneling process that bump occurs, the strengthening supporting in driving, right first during supporting Back gunite concrete, concrete ejection thickness 50mm it is ensured that closing closely knit after, then perforating install grouting cable anchor, according to Conventional anchor cable grouting method carries out slip casting, grouting cable anchor length 6-7m, rope array pitch 1.6m, spacing 1.2m to back;Pass through Anchor rope grouting, crushed zone top board is consolidated into overall structure.
The positive effect of the present invention is: after being implemented using above-mentioned three kinds of measures, in heavily stressed fault belt Nei Jue lane Period, support will be played, release the coupling that can, reinforce, so that high stress broken zone of rocks is released energy steadily in the long term, fundamentally drop The tendentiousness of low bump.
Brief description
The enforcement of the present invention is described below in conjunction with the accompanying drawings.
Fig. 1 is chamber arrangement floor map of the present invention;
Fig. 2 is chamber anchor pole schematic diagram of the present invention;
Fig. 3 is chamber grillage Concrete Filled schematic diagram of the present invention;
Fig. 4 is back grouting and reinforcing schematic diagram of the present invention.
Specific embodiment
During the fault belt Nei Jue lane of the present invention, Controlling of Coal Outburst method and step is as follows:
First, high density supporting Chamber Construction
As shown in figure 1, moving towards with tunnel according to fault parameter, it is being susceptible to fault region bump section, interval 15-20m, construction depth 5m, width 3m, the chamber of height 2-3m, chamber top board planarizing process, and carry out anchor as shown in Figure 2 Bar gib;Using array pitch between 800mm*800mm during anchor pole arrangement.
2nd, grillage Concrete Filled
As shown in figure 3, first carrying out grillage filling in the chamber of gib, then filling coagulation in grillage space Soil is it is desirable to concrete strength is more than the intensity of chamber balkstone;For reducing the disturbance between adjacent chamber it is desirable to the filling time Every carry out.
3rd, back grouting and reinforcing
As shown in figure 4, in there is the section road tunneling process that bump occurs, the strengthening supporting in driving, First to back gunite concrete during shield, concrete ejection thickness 50mm it is ensured that closing closely knit after, then perforating install slip casting Anchor cable, carries out slip casting, grouting cable anchor length 6-7m, rope array pitch 1.6m, spacing according to conventional anchor cable grouting method to back 1.2m;By anchor rope grouting, crushed zone top board is consolidated into overall structure.

Claims (1)

1. one kind during fault belt Nei Jue lane Controlling of Coal Outburst method it is characterised in that step is as follows:
The first step, Chamber Construction
Exist in the section road tunneling process that bump occurs entering fault region, at interval of 15-20m, to tunnel two Other construction depth 5m, width 3m, the chamber of height 2-3m, chamber top board planarizing process, and carry out anchor pole gib;Anchor pole Array pitch between 800*800 is adopted during arrangement;
Grillage Concrete Filled in second step, chamber
First carry out grillage filling in the chamber of gib, then in grillage space filling concrete it is desirable to strong concrete Degree is more than the intensity of chamber balkstone;For reducing the disturbance between adjacent chamber, fill order takes interval filling mode;
3rd step, back grouting and reinforcing
In there is the section road tunneling process that bump occurs, the strengthening supporting in driving, first to tunnel during supporting Top board gunite concrete, concrete ejection thickness 50mm it is ensured that closing closely knit after, then perforating install grouting cable anchor, according to routine Anchor rope grouting method carries out slip casting, grouting cable anchor length 6-7m, rope array pitch 1.6m, spacing 1.2m to back;By anchor cable Slip casting, crushed zone top board is consolidated into overall structure.
CN201610915674.3A 2016-10-20 2016-10-20 Method for controlling rock burst during roadway tunneling in fault fracture zone Pending CN106368705A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610915674.3A CN106368705A (en) 2016-10-20 2016-10-20 Method for controlling rock burst during roadway tunneling in fault fracture zone

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610915674.3A CN106368705A (en) 2016-10-20 2016-10-20 Method for controlling rock burst during roadway tunneling in fault fracture zone

Publications (1)

Publication Number Publication Date
CN106368705A true CN106368705A (en) 2017-02-01

Family

ID=57895689

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610915674.3A Pending CN106368705A (en) 2016-10-20 2016-10-20 Method for controlling rock burst during roadway tunneling in fault fracture zone

Country Status (1)

Country Link
CN (1) CN106368705A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106837415A (en) * 2017-03-21 2017-06-13 辽宁工程技术大学 A kind of device and method of prevention coal mining working face bump
CN108708755A (en) * 2018-03-23 2018-10-26 武汉工程大学 A kind of underground rock-burst prevention method
CN109915142A (en) * 2019-04-13 2019-06-21 山东科技大学 A kind of major fault fringe region Controlling of Coal Outburst method
CN109915141A (en) * 2019-04-13 2019-06-21 山东科技大学 The control method of not wide protection pillar mining roadway bump
CN112483186A (en) * 2020-12-18 2021-03-12 山东科技大学 Method for judging impact risk of advanced broken roof coal seam by window intervention method
CN112483182A (en) * 2020-12-18 2021-03-12 山东科技大学 Method for judging impact risk of high-homogeneity coal seam by window intervention method
CN113107537A (en) * 2021-04-24 2021-07-13 淮北市平远软岩支护工程技术有限公司 Distributed grouting technology and method for rock burst confrontation type roadway
CN114000902A (en) * 2021-09-22 2022-02-01 中国矿业大学(北京) Method for maintaining broken top plate of negative coal pillar roadway by grouting reinforcement anchor rod suspension
CN114673508A (en) * 2022-04-14 2022-06-28 天地科技股份有限公司 Coal mine roadway area supporting method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2148171C1 (en) * 1998-07-06 2000-04-27 Дальневосточный государственный технический университет Method of mineral deposit mining
CN102296958A (en) * 2011-07-22 2011-12-28 山东科技大学 Method for preventing rock burst by artificial space defect body
CN102425418A (en) * 2011-11-14 2012-04-25 山东科技大学 Method for controlling rock burst in artificial defect body of coal mine structural area
CN102518471A (en) * 2011-11-14 2012-06-27 山东科技大学 Rock burst energy releasing method of roadway of high stress area in coal mine
CN102518436A (en) * 2011-11-14 2012-06-27 山东科技大学 Method for controlling tectonic rock burst in coal mine tunneling
CN105201510A (en) * 2015-10-27 2015-12-30 山东科技大学 Preventing and controlling method for creep-induced rock burst

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2148171C1 (en) * 1998-07-06 2000-04-27 Дальневосточный государственный технический университет Method of mineral deposit mining
CN102296958A (en) * 2011-07-22 2011-12-28 山东科技大学 Method for preventing rock burst by artificial space defect body
CN102425418A (en) * 2011-11-14 2012-04-25 山东科技大学 Method for controlling rock burst in artificial defect body of coal mine structural area
CN102518471A (en) * 2011-11-14 2012-06-27 山东科技大学 Rock burst energy releasing method of roadway of high stress area in coal mine
CN102518436A (en) * 2011-11-14 2012-06-27 山东科技大学 Method for controlling tectonic rock burst in coal mine tunneling
CN105201510A (en) * 2015-10-27 2015-12-30 山东科技大学 Preventing and controlling method for creep-induced rock burst

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106837415A (en) * 2017-03-21 2017-06-13 辽宁工程技术大学 A kind of device and method of prevention coal mining working face bump
CN108708755A (en) * 2018-03-23 2018-10-26 武汉工程大学 A kind of underground rock-burst prevention method
CN109915142A (en) * 2019-04-13 2019-06-21 山东科技大学 A kind of major fault fringe region Controlling of Coal Outburst method
CN109915141A (en) * 2019-04-13 2019-06-21 山东科技大学 The control method of not wide protection pillar mining roadway bump
CN112483186A (en) * 2020-12-18 2021-03-12 山东科技大学 Method for judging impact risk of advanced broken roof coal seam by window intervention method
CN112483182A (en) * 2020-12-18 2021-03-12 山东科技大学 Method for judging impact risk of high-homogeneity coal seam by window intervention method
CN113107537A (en) * 2021-04-24 2021-07-13 淮北市平远软岩支护工程技术有限公司 Distributed grouting technology and method for rock burst confrontation type roadway
CN113107537B (en) * 2021-04-24 2023-11-10 淮北市平远软岩支护工程技术有限公司 Distributed grouting technology and method for rock burst countermeasure type roadway
CN114000902A (en) * 2021-09-22 2022-02-01 中国矿业大学(北京) Method for maintaining broken top plate of negative coal pillar roadway by grouting reinforcement anchor rod suspension
CN114000902B (en) * 2021-09-22 2022-12-27 中国矿业大学(北京) Method for suspension maintenance of broken roof of negative coal pillar roadway by grouting reinforced anchor rod
CN114673508A (en) * 2022-04-14 2022-06-28 天地科技股份有限公司 Coal mine roadway area supporting method
CN114673508B (en) * 2022-04-14 2024-09-20 天地科技股份有限公司 Coal mine tunnel area supporting method

Similar Documents

Publication Publication Date Title
CN106368705A (en) Method for controlling rock burst during roadway tunneling in fault fracture zone
CN104832198B (en) Comprehensive treatment method for roadway surrounding rock deformation, impact mine pressure and coal and gas outburst
CN110206542B (en) Non-pillar self-entry mining method suitable for fully-mechanized top coal caving of thick coal seam
CN102518436B (en) Method for controlling tectonic rock burst in coal mine tunneling
CN105178981B (en) The closed depth coupling of broken soft rock roadway full-fracture-surfacanchoring-rod, which allows, presses bolt-grouting support method
CN105317459B (en) A kind of subregion placement method for being used to control tight roof large area caving disaster
CN111305876A (en) Deep roadway anchoring-splitting grouting-hydraulic fracturing pressure relief cooperative control method
CN103061781B (en) Method for preventing rock burst by manually regulating tunnel surrounding rock support energy dissipation damping characteristics
CN110318761B (en) Construction method for controlling roadway deformation
CN104533467B (en) A kind of high artesian, the method for protecting support in fault disruption zone tunnel
CN103557000B (en) Method for preventing gob-side entry rock burst through side-drawing filling
CN101603431A (en) A kind of method for reinforcing outburst-prone coal seam cross-cut coal uncovering
CN105019924B (en) Strong roof support pier column and method for protecting section coal pillar
CN110374600A (en) A kind of ultra close distance coal seam group stope drift active workings are error-free away from formula method for arranging
CN104594926A (en) Rapid composite roof roadway support method for high-stress water guiding karst cave group
CN103321677A (en) Method for actively controlling motion of coal mine critical layers by using strip filling walls
Xu et al. Control of floor heaves with steel pile in gob-side entry retaining
CN110130978B (en) Method for plugging broken coal side of thick coal seam in broken area of filling and re-mining small kiln
CN107387085A (en) A kind of tight roof and the porous controlled blasting softening method in coal seam
CN109763861A (en) One kind cutting intraocular fault belt treatment of roof collapse method
CN104453944A (en) Coal-pillar-impacting-preventing roadway protecting method
CN102383728A (en) Coal mine rockburst defect segmentation and control method
CN104533483A (en) Roadway total-space prestress truss, anchor cable and anchor rod coordinated supporting method
CN206205903U (en) A kind of base plate release ruggedized construction of control deep tunnel bottom distension
CN105781552A (en) Novel high-gas outburst coal seam stereoscopic punching crosscut coal uncovering method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170201

RJ01 Rejection of invention patent application after publication