CN106355513A - Analysis method for unit adjustable contribution area based on auxiliary machine state assessment of unit - Google Patents

Analysis method for unit adjustable contribution area based on auxiliary machine state assessment of unit Download PDF

Info

Publication number
CN106355513A
CN106355513A CN201610747699.7A CN201610747699A CN106355513A CN 106355513 A CN106355513 A CN 106355513A CN 201610747699 A CN201610747699 A CN 201610747699A CN 106355513 A CN106355513 A CN 106355513A
Authority
CN
China
Prior art keywords
auxiliary machinery
unit
set auxiliary
measuring point
exerting oneself
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610747699.7A
Other languages
Chinese (zh)
Inventor
孙栓柱
汪叶峰
周挺
徐春雷
杨梓俊
代家元
张友卫
王林
李�杰
周春蕾
王明
李春岩
杨晨琛
许国强
周志兴
佘国金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Jiangsu Fangtian Power Technology Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Jiangsu Fangtian Power Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Jiangsu Fangtian Power Technology Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610747699.7A priority Critical patent/CN106355513A/en
Publication of CN106355513A publication Critical patent/CN106355513A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Educational Administration (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses an analysis method for a unit adjustable contribution area based on auxiliary machine state assessment of a unit, comprising the following steps: 1) for multiple auxiliary machines in the unit, obtaining real-time running and monitoring data of the auxiliary machine of each unit, 2) confirming the operation state of the auxiliary machine of each unit; 3) outputting the unit adjustable contribution area under the operation state of the current auxiliary machine of the unit according to the control policy of unit DCS system. The analysis method for a unit adjustable contribution area based on auxiliary machine state assessment of a unit can analyze the influence of the operation state of the auxiliary machine on the unit contribution and power balance of the whole province so as to realize updating the adjustable contribution of the whole network timely;and the method is beneficial for the power dispatching operator to know about the change condition of the generation power of the unit and ensure the stable operation of the power grid.

Description

A kind of unit based on set auxiliary machinery state estimation is adjustable Novel Interval Methods of exerting oneself
Technical field
The present invention relates to a kind of unit output analysis method, more particularly to a kind of machine based on set auxiliary machinery state estimation Organize adjustable Novel Interval Methods of exerting oneself, belong to electric power unit control technology field.
Background technology
Carry forward vigorously extra-high voltage project construction with China, the extra-high voltage alternating current-direct current of " three friendships four are straight " will be built up in a lot of regions Serial-parallel power grid runs new frame, and it is always reached 30,000,000 kilowatts about so that a lot of region actually enters and " receives greatly by electric energy power End " electrical network, operation of power networks characteristic will occur to sexually revise at all.
For the operation of " big receiving end " electrical network, how soon the problem compeling highly necessary solution is exactly when extra-high voltage breaks down, Speed, be precisely controlled, realize quick regulation and the automatic synchronization of the resources such as load, generating.And two for extra-high voltage emergency disposal The customer charge of one of general orientation controls, and due to being related to the social people's livelihood, impact is often larger, therefore occurs in extra-high voltage fault When, first have to consideration is exactly the quick response of the local generation assets of other direction receiving end electrical network of emergency disposal, to keep away Exempt from the generation of power cuts to limit consumption.
Quick regulation for the local generation assets of receiving end electrical network is it is necessary first to assessment is each department, the combustion of the Ge Tai main force The scalable load setting of coal unit, i.e. adjustable the exerting oneself of the mutual disorder of internal organs of net source coordination.In extra-high voltage troubleshooting it is necessary first to Assessment is each unit schedulable load setting, and then determines to select which unit recovers balancing the load within the shortest time.
According to statistics, coal unit adjustable the exerting oneself that major pant item abnormal state leads to accounts for all factor proportions height limited by interval Reach 1/3, therefore, need badly and scientific and effective assessment is carried out to generating set major pant item state, and then quantify exert oneself adjustable to unit Influence degree.
Currently for major pant item running status, electric dispatching department relies on electricity power enterprise voluntarily to report it is impossible to real substantially When accurately understand its operation conditions.
Content of the invention
Present invention is primarily targeted at, overcome deficiency of the prior art, provide one kind to comment based on set auxiliary machinery state The adjustable Novel Interval Methods of exerting oneself of unit estimated, can analyze the impact to unit output for the subsidiary engine operation conditions and in real time to the whole province The impact of hair electric equilibrium, thus realize the whole network adjustable exert oneself upgrade in time, be conducive to power scheduling operations staff timely Solution unit generation capacity variation situation is it is ensured that the stable operation of electrical network.
In order to achieve the above object, the technical solution adopted in the present invention is:
A kind of unit based on set auxiliary machinery state estimation is adjustable Novel Interval Methods of exerting oneself, comprise the following steps:
1) if to the Ganlei's set auxiliary machinery in unit, obtaining the real time execution Monitoring Data of every class set auxiliary machinery;
2) determine the running status of set auxiliary machinery;
3) combine unit dcs system control strategy, export the adjustable area of exerting oneself of unit under current set auxiliary machinery running status Between.
The present invention is further arranged to: described set auxiliary machinery include the pressure fan of coal unit, air-introduced machine, primary air fan, Coal pulverizer and feed pump.
The present invention is further arranged to: described step 2) determine the running status of set auxiliary machinery, specifically,
2-1) select the crucial measuring point of set auxiliary machinery, obtain the Real-time Monitoring Data of crucial measuring point;
2-2) Real-time Monitoring Data of crucial measuring point is compared with controlling restriction, judge the real-time monitoring of crucial measuring point Whether data surmounts control limit;If surmounting control limit it is determined that the departure degree of set auxiliary machinery;
2-3) judge the running status of set auxiliary machinery.
The present invention is further arranged to: described key measuring point selection standard be, this measuring point belong to set auxiliary machinery body and The on-line monitoring measuring point of association motor and this measuring point is out-of-limit in dcs system control strategy that this set auxiliary machinery can be led to be in Equipment stoppage in transit state.
The present invention is further arranged to: described control limit comes really according to limit value tactful in unit dcs system control strategy Fixed, including alarm limits and tripping operation limit value.
The present invention is further arranged to: the departure degree of described set auxiliary machinery is determined according to calculation equation, its meter Calculating equation isWherein, δ is departure degree, sActualFor the actual operating data of crucial measuring point, sLimit valueFor closing The control limit of key measuring point, s0For crucial measuring point normal operation when meansigma methodss.
The present invention is further arranged to: the criterion of the running status of described set auxiliary machinery is,
If the crucial measuring point of monitoring belonging to set auxiliary machinery does not exist, and any warning is transfinited, trip out-of-limit situation, judging should Set auxiliary machinery stable and reliable operation, that is, be in steady operational status;
If belonging to set auxiliary machinery, the crucial measuring point of monitoring only exists warning transfiniting, there is not tripping operation overrun condition, then judging This set auxiliary machinery can maintain operation in the case of strengthening monitoring reluctantly, that is, be in maintenance running status;
If the crucial measuring point of monitoring belonging to set auxiliary machinery has tripping operation overrun condition, judge that this set auxiliary machinery has occurred bright Aobvious fault, and cannot recover in time in the short time, that is, it is in stoppage in transit state.
The present invention is further arranged to: described unit dcs system control strategy adopts the rb of unit dcs system to control plan Slightly.
Compared with prior art, the invention has the advantages that:
By to unit major pant item running state real-time monitoring and health degree assessment, analysis subsidiary engine operation conditions pair in real time The impact of unit output and the impact to the whole province's hair electric equilibrium, realize the whole network adjustable exert oneself upgrade in time, be conducive to electricity Power management and running personnel understand the whole province's unit generation capacity variation situation as early as possible it is ensured that the stable operation of electrical network.
The above is only the general introduction of technical solution of the present invention, in order to be better understood upon the technological means of the present invention, under Face combines accompanying drawing, and the invention will be further described.
Brief description
Fig. 1 is the flow chart of the embodiment of the present invention.
Specific embodiment
With reference to Figure of description, the present invention is further illustrated.
The present invention provides a kind of adjustable Novel Interval Methods of exerting oneself of unit based on set auxiliary machinery state estimation, as Fig. 1 institute Show, comprise the following steps:
1) if to the Ganlei's set auxiliary machinery in unit, obtaining the real time execution Monitoring Data of every class set auxiliary machinery;
Wherein, set auxiliary machinery includes pressure fan, air-introduced machine, primary air fan, coal pulverizer and feed pump of coal unit etc. 5 class Subsidiary engine equipment.
2) determine the running status of set auxiliary machinery, specifically,
2-1) select the crucial measuring point of set auxiliary machinery, obtain the Real-time Monitoring Data of crucial measuring point;
Wherein, the selection standard of crucial measuring point is, this measuring point belongs to set auxiliary machinery body and the online prison of association motor Survey measuring point and this measuring point is out-of-limit in dcs system control strategy that this set auxiliary machinery can be led to be in equipment stoppage in transit state.
2-2) Real-time Monitoring Data of crucial measuring point is compared with controlling restriction, judge the real-time monitoring of crucial measuring point Whether data surmounts control limit;If surmounting control limit it is determined that the departure degree of set auxiliary machinery;
Wherein, control limit to determine according to limit value tactful in unit dcs system control strategy, including alarm limits and jump Lock limit value;The departure degree of set auxiliary machinery is determined according to calculation equation, and its calculation equation is Wherein, δ is departure degree, sActualFor the actual operating data of crucial measuring point, sLimit valueFor the control limit of crucial measuring point, s0For key Meansigma methodss during the normal operation of measuring point.
2-3) judge the running status of set auxiliary machinery, criterion is,
If the crucial measuring point of monitoring belonging to set auxiliary machinery does not exist, and any warning is transfinited, trip out-of-limit situation, judging should Set auxiliary machinery stable and reliable operation, that is, be in steady operational status;
If belonging to set auxiliary machinery, the crucial measuring point of monitoring only exists warning transfiniting, there is not tripping operation overrun condition, then judging This set auxiliary machinery can maintain operation in the case of strengthening monitoring reluctantly, that is, be in maintenance running status;
If the crucial measuring point of monitoring belonging to set auxiliary machinery has tripping operation overrun condition, judge that this set auxiliary machinery has occurred bright Aobvious fault, and cannot recover in time in the short time, that is, it is in stoppage in transit state.
3) combine the rb control strategy of unit dcs system, the unit exporting under current set auxiliary machinery running status may bring up Power is interval.
, its major pant item operation conditions is carried out with real-time assessment taking certain 660mw grade unit as a example, carry out adjustable area of exerting oneself Between analyze.
This unit major pant item online monitoring data at a time is as shown in table 1 below:
Table 1
By entering with alarm limits, tripping operation limit value to the actual measurement Monitoring Data of the crucial measuring point of monitoring belonging to each major pant item Row compares, and calculates the irrelevance of each index, finally judges that each major pant item running status is as shown in table 2 below:
Table 2
The rb strategy of this unit dcs system design is as shown in table 3 below:
Table 3
In conjunction with each subsidiary engine running status and its rb control strategy it can be determined that this unit adjustable exert oneself interval for 330~ 660mw.
Ultimate principle, principal character and the advantage of the present invention have been shown and described above.The technical staff of the industry should Understand, the present invention is not restricted to the described embodiments, the simply explanation present invention's described in above-described embodiment and description is former Reason, without departing from the spirit and scope of the present invention, the present invention also has various changes and modifications, these changes and improvements Both fall within scope of the claimed invention.Claimed scope is by appending claims and its equivalent circle. Fixed.

Claims (8)

1. a kind of adjustable Novel Interval Methods of exerting oneself of unit based on set auxiliary machinery state estimation are it is characterised in that include following Step:
1) if to the Ganlei's set auxiliary machinery in unit, obtaining the real time execution Monitoring Data of every class set auxiliary machinery;
2) determine the running status of set auxiliary machinery;
3) combine unit dcs system control strategy, export the adjustable interval of exerting oneself of unit under current set auxiliary machinery running status.
2. the adjustable Novel Interval Methods of exerting oneself of a kind of unit based on set auxiliary machinery state estimation according to claim 1, It is characterized in that: described set auxiliary machinery includes pressure fan, air-introduced machine, primary air fan, coal pulverizer and the feed pump of coal unit.
3. the adjustable Novel Interval Methods of exerting oneself of a kind of unit based on set auxiliary machinery state estimation according to claim 1, It is characterized in that: described step 2) determine the running status of set auxiliary machinery, specifically,
2-1) select the crucial measuring point of set auxiliary machinery, obtain the Real-time Monitoring Data of crucial measuring point;
2-2) Real-time Monitoring Data of crucial measuring point is compared with controlling restriction, judge the Real-time Monitoring Data of crucial measuring point Whether surmount control limit;If surmounting control limit it is determined that the departure degree of set auxiliary machinery;
2-3) judge the running status of set auxiliary machinery.
4. the adjustable Novel Interval Methods of exerting oneself of a kind of unit based on set auxiliary machinery state estimation according to claim 3, It is characterized in that: the selection standard of described key measuring point is that this measuring point belongs to set auxiliary machinery body and associates the online of motor Monitoring measuring point and this measuring point is out-of-limit in dcs system control strategy that this set auxiliary machinery can be led to be in equipment stoppage in transit state.
5. the adjustable Novel Interval Methods of exerting oneself of a kind of unit based on set auxiliary machinery state estimation according to claim 3, It is characterized in that: described control limit to determine according to limit value tactful in unit dcs system control strategy, include alarm limits with Tripping operation limit value.
6. the adjustable Novel Interval Methods of exerting oneself of a kind of unit based on set auxiliary machinery state estimation according to claim 3, It is characterized in that: the departure degree of described set auxiliary machinery is determined according to calculation equation, and its calculation equation isWherein, δ is departure degree, sActualFor the actual operating data of crucial measuring point, sLimit valueControl for crucial measuring point Limit value processed, s0For crucial measuring point normal operation when meansigma methodss.
7. the adjustable Novel Interval Methods of exerting oneself of a kind of unit based on set auxiliary machinery state estimation according to claim 5, It is characterized in that: the criterion of the running status of described set auxiliary machinery is,
If the crucial measuring point of monitoring belonging to set auxiliary machinery does not exist, and any warning is transfinited, trip out-of-limit situation, judges this unit Subsidiary engine stable and reliable operation, that is, be in steady operational status;
If belonging to set auxiliary machinery, the crucial measuring point of monitoring only exists warning transfiniting, there is not tripping operation overrun condition, then judging this machine Group subsidiary engine can maintain operation in the case of strengthening monitoring reluctantly, that is, be in maintenance running status;
If the crucial measuring point of monitoring belonging to set auxiliary machinery has tripping operation overrun condition, judge that this set auxiliary machinery obvious event Barrier, and cannot recover in time in the short time, that is, it is in stoppage in transit state.
8. the adjustable Novel Interval Methods of exerting oneself of a kind of unit based on set auxiliary machinery state estimation according to claim 1, It is characterized in that: described unit dcs system control strategy adopts the rb control strategy of unit dcs system.
CN201610747699.7A 2016-08-29 2016-08-29 Analysis method for unit adjustable contribution area based on auxiliary machine state assessment of unit Pending CN106355513A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610747699.7A CN106355513A (en) 2016-08-29 2016-08-29 Analysis method for unit adjustable contribution area based on auxiliary machine state assessment of unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610747699.7A CN106355513A (en) 2016-08-29 2016-08-29 Analysis method for unit adjustable contribution area based on auxiliary machine state assessment of unit

Publications (1)

Publication Number Publication Date
CN106355513A true CN106355513A (en) 2017-01-25

Family

ID=57855296

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610747699.7A Pending CN106355513A (en) 2016-08-29 2016-08-29 Analysis method for unit adjustable contribution area based on auxiliary machine state assessment of unit

Country Status (1)

Country Link
CN (1) CN106355513A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114862085A (en) * 2021-12-31 2022-08-05 中国矿业大学 Subjective and objective classification combination weighting method for comprehensive evaluation of electric energy quality
CN116845887A (en) * 2023-09-01 2023-10-03 华北电力科学研究院有限责任公司 Fault processing method and device for single-side auxiliary machine configuration unit

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008069763A (en) * 2006-09-11 2008-03-27 Yoshio Sekine Load setter follow-up boiler-turbine parallel control runback control system
CN101526586A (en) * 2009-04-17 2009-09-09 上海电力学院 Embedded remote state monitoring system of generating unit
CN103616854A (en) * 2013-10-24 2014-03-05 上海迪吉特控制系统有限公司 A method for implementing hierarchical optimization of automatic plant start-up and shut-down control logic
CN104932310A (en) * 2015-06-05 2015-09-23 山东电力研究院 Self-adaptive coal quality adjustment system and method in RUNBACK (RB) process

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008069763A (en) * 2006-09-11 2008-03-27 Yoshio Sekine Load setter follow-up boiler-turbine parallel control runback control system
CN101526586A (en) * 2009-04-17 2009-09-09 上海电力学院 Embedded remote state monitoring system of generating unit
CN103616854A (en) * 2013-10-24 2014-03-05 上海迪吉特控制系统有限公司 A method for implementing hierarchical optimization of automatic plant start-up and shut-down control logic
CN104932310A (en) * 2015-06-05 2015-09-23 山东电力研究院 Self-adaptive coal quality adjustment system and method in RUNBACK (RB) process

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘清龙: "火电厂风机状态监测与故障诊断系统研究", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *
朱宏: "大型火电机组RunBack功能的分析与实现", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *
汤延令: "火电厂辅机状态监测及分析诊断探讨", 《福建电力与电工》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114862085A (en) * 2021-12-31 2022-08-05 中国矿业大学 Subjective and objective classification combination weighting method for comprehensive evaluation of electric energy quality
CN116845887A (en) * 2023-09-01 2023-10-03 华北电力科学研究院有限责任公司 Fault processing method and device for single-side auxiliary machine configuration unit
CN116845887B (en) * 2023-09-01 2023-11-10 华北电力科学研究院有限责任公司 Fault processing method and device for single-side auxiliary machine configuration unit

Similar Documents

Publication Publication Date Title
CN106291252B (en) A kind of 10kV line loss and low-voltage platform area line loss management analysis method
CN104537487B (en) A kind of appraisal procedure of power transmission and transforming equipment operation state risk
Li et al. Wide-area voltage monitoring and optimization
CN108336725A (en) The management of dispatching of power netwoks monitoring of tools and intelligent analysis system
CN103337043B (en) The method for early warning of electric power communication device running status and system
CN103647276A (en) Electric energy quality early warning system and method thereof
CN106385034A (en) Power grid dynamic partition calculating method based on N-1 security checking
CN105184521B (en) A kind of methods of risk assessment of grid operation mode, apparatus and system
CN104779608B (en) Safe stable on-line additional emergency control method of power system based on off-line strategy
CN102521672A (en) Safety risk automatic recognition method based on network-distribution production operation plan
CN105825315A (en) Electric energy quality early warning method
CN103310296A (en) Operation ticket security check method based on disturbance evaluation and trend analysis
CN105447657A (en) Risk-based operation and maintenance management system of 750KV power equipment
CN102830682A (en) Energy consumption police module for regional power generation corporation to run intelligent management and control system
CN110162555A (en) A kind of fired power generating unit start and stop and drop power output measure of supervision
CN107681780A (en) A kind of power network section monitors and turns to supply tactful intelligent generating system and method
CN110348637A (en) A kind of consideration field-net factor wind-powered electricity generation climbing event method for early warning
Hui et al. Analysis of" 8• 15" Blackout in Taiwan and the Improvement Method of Contingency Reserve Capacity Through Direct Load Control
CN106355513A (en) Analysis method for unit adjustable contribution area based on auxiliary machine state assessment of unit
CN109494757A (en) A kind of voltage power-less operation method for early warning and system
CN115603459A (en) Digital twin technology-based power distribution network key station monitoring method and system
CN110265998B (en) Method and device for checking strategy fixed value of stability control system
CN104050300A (en) Risk assessment method, device and system for power grid running method
CN109858768A (en) Consider the comprehensive energy electric-thermal net methods of risk assessment of comprehensive time-varying outage model
CN106451760B (en) A kind of 500kV substation centralized control system telemetry intelligence (TELINT) method for real-time monitoring

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170125