CN106351416B - A kind of dried hanging hang structure and its construction method for crossing apex stone material - Google Patents

A kind of dried hanging hang structure and its construction method for crossing apex stone material Download PDF

Info

Publication number
CN106351416B
CN106351416B CN201610748521.4A CN201610748521A CN106351416B CN 106351416 B CN106351416 B CN 106351416B CN 201610748521 A CN201610748521 A CN 201610748521A CN 106351416 B CN106351416 B CN 106351416B
Authority
CN
China
Prior art keywords
stone material
stone
angle steel
corner brace
material plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610748521.4A
Other languages
Chinese (zh)
Other versions
CN106351416A (en
Inventor
顾峰
顾一峰
沈菊芳
许锋
顾爱军
凌飞
王晓冬
姚翊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Jia Yang Hualian Building Decoration Ltd By Share Ltd
Original Assignee
Jiangsu Jia Yang Hualian Building Decoration Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Jia Yang Hualian Building Decoration Ltd By Share Ltd filed Critical Jiangsu Jia Yang Hualian Building Decoration Ltd By Share Ltd
Priority to CN201610748521.4A priority Critical patent/CN106351416B/en
Publication of CN106351416A publication Critical patent/CN106351416A/en
Application granted granted Critical
Publication of CN106351416B publication Critical patent/CN106351416B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0803Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
    • E04F13/081Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and covering elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/18Implements for finishing work on buildings for setting wall or ceiling slabs or plates
    • E04F21/1838Implements for finishing work on buildings for setting wall or ceiling slabs or plates for setting a plurality of similar elements
    • E04F21/1844Implements for finishing work on buildings for setting wall or ceiling slabs or plates for setting a plurality of similar elements by applying them one by one

Abstract

The invention discloses a kind of dried hanging hang structures and its construction method for crossing apex stone material, including structural beams, angle steel, stone facing and bindiny mechanism, the stone facing is assembled by muti-piece stone material plate, the angle steel and bindiny mechanism are set between structural beams and stone facing, by chemical anchor bolts or welded connecting between the angle steel and structural beams, connected between the angle steel and stone facing by bindiny mechanism;The bindiny mechanism includes:Angle steel corner brace and dry hanging article, one end of the angle steel corner brace are fixed by bolts in angle steel, and the other end of angle steel corner brace is fixed by bolt and dry hanging article, and the dry hanging article insertion, which is close in the stone material slot driller of splicing, hangs stone material, completely fill out structure glue in seam.The present invention can reduce bending deformation under stone material, increase the intensity of stone material at fluting, and it is safe to guarantee that apex stone used.

Description

A kind of dried hanging hang structure and its construction method for crossing apex stone material
Technical field
The present invention relates to building fields, more particularly to a kind of dried hanging hang structure and its construction method for crossing apex stone material.
Background technique
It is existing to cross apex stone material construction method:Angle steel is installed, is first hung on dry hanging article on angle steel with M8 stainless steel bolt.Pacifying Abrasive wheel cutting machine is used to fill structure glue in the groove at side surface of stone material, slot before filling stone material, it is then that the cladding slot of stone material plate is light It is buckled on dry hanging article.Accurate location is adjusted after installation is in place, tightens bolt.Remaining stone material plate is successively installed in order, is completed Joint filling gluing afterwards, it is solid wait be gelled.
It is insufficient that the prior art is primarily present following several points:
1, under gravity laod effect, stone material integrally by self gravity, generates bending, may cause stone plate fracture;
2, in pendant junction, because of fluting weakening plate section thickness, strength reduction at this, under gravity or wind load effect, It may cause the destruction of seam crossing stone material.
Summary of the invention
The invention mainly solves the technical problem of providing a kind of dried hanging hang structures and its construction method for crossing apex stone material, can Bending deformation under stone material is reduced, the intensity of stone material at fluting is increased, it is safe to guarantee that apex stone used.
In order to solve the above technical problems, one technical scheme adopted by the invention is that:There is provided it is a kind of cross apex stone material it is cladding Structure, including structural beams, angle steel, stone facing and bindiny mechanism, the stone facing is assembled by muti-piece stone material plate, institute State angle steel and bindiny mechanism be set between structural beams and stone facing, between the angle steel and structural beams by chemical anchor bolts or It is welded to connect, is connected between the angle steel and stone facing by bindiny mechanism;The bindiny mechanism includes:Angle steel corner brace and dry Pendant, one end of the angle steel corner brace are fixed by bolts in angle steel, and the other end of angle steel corner brace is solid by bolt and dry hanging article Fixed, the dry hanging article insertion, which is close in the stone material slot driller of splicing, hangs stone material, completely fills out structure glue in seam, hangs in dry hanging article It hangs the stone material plate back side at position and stone material reinforcing rib is set, the stone material reinforcing rib and stone material plate pass through structure glue, At the stone material plate back side close to stone material reinforcing rib, a dedicated corner brace, the dedicated corner brace bilateral symmetry are fixed with expansion bolt It is arranged and stone material plate is fixed in one end, the other end is fixed on angle steel corner brace.
Preferably, the dedicated corner brace is set as ladder-like, including:Riser, transverse slat and stepped plate, the one of the stepped plate End connection riser, the other end connect transverse slat, open up grooved hole in the middle part of the riser, offer circle in the middle part of the transverse slat Hole, the stone material reinforcing rib are set between the stepped plate of two pieces of symmetrical dedicated corner braces.
Preferably, the dedicated corner brace uses stainless steel material, and extexine is coated with zinc coat.
Preferably, structure glue is filled between the stone material reinforcing rib and dedicated corner brace.
Preferably, the stone facing is adhesive with layer of glass grid cloth close to the side of dedicated corner brace.
The present invention also provides a kind of construction methods of dried hanging hang structure for crossing apex stone material, mainly comprise the following steps:
One, surveying setting-out:According to construction drawing, unwrapping wire is measured, determines angle iron position;
Two, angle steel, concealment acceptance are installed;
Three, stone material plate examination row, positioning:According to stone material setting-out drawing, examination row, positioning are carried out to stone material plate;
Four, stone material plate is installed:
1, stone material plate is handled
1), according to stone material plate size cut fiberglass gridding cloth;
2), the stone material plate back side with glue special paste fiberglass gridding cloth;
3), stone material plate other plate faces do protective treatment;
4), at the fluting of the stone material plate back side with structure stone gluing reinforcing rib, it is the long 100-200mm of stone material reinforcing rib, wide about 60-80mm, thickness can be the same as stone material plate thickness.
5), dedicated corner brace side expansible plug connect with the stone material plate back side, dedicated corner brace and stone material reinforcing rib contact portion Position is closely knit with structure gluing knot.
6), stone material plate edge open cladding slot, groove width about 5mm between two parties with abrasive wheel cutting machine.
2, stone material plate is cladding
1), weatherproof structure glue is filled in cladding slot, dry hanging article is protruded into cladding slot, it is closely knit with weatherproof structure glue;
2), dedicated corner brace, stainless steel dry hanging article bolt and Bolted angle connection;
3), adjust stone material plate height by stainless steel dry hanging article and until decoration is finally completed face tightens bolt and fix;
4), remaining stone material plate is successively installed in this order;
Five, stone material partitioning slot is handled:Raked joint, gluing;
Six, stone surface is cleared up;
Seven, it checks and accepts.
The beneficial effects of the invention are as follows:
1, the stone material plate back side bonds fiberglass gridding cloth, improves the bending strength of stone material, reduces stone material in gravity Bending deformation under load action, avoids stone material from being broken;
2, stone material reinforcing rib is arranged in the cladding slot back side of stone material plate, increases the thickness of stone material plate at fluting, increases Shearing resistance section reduces stone material failure probability;
3, using dedicated corner brace, stone material plate, stone material reinforcing rib were both connected into an entirety, reaches dual reinforcing and makees With extending plate and fall immediately because it is directly connected to angle steel, and when can ensure that cladding position is destroyed, dry hanging article does not work Danger.
Detailed description of the invention
Fig. 1 is to cross apex stone material in a kind of one preferred embodiment of dried hanging hang structure and its construction method for crossing apex stone material of the present invention to do The structural schematic diagram of hanging hang structure;
Fig. 2 is part A partial enlargement diagram in Fig. 1;
Fig. 3 is the schematic perspective view of the dedicated corner brace;
The components in the drawings are labeled as follows:1, structural beams, 2, angle steel, 3, chemical anchor bolts, 4, bindiny mechanism, 5, stone material decorations Face, 6, bolt, 7, expansion bolt, 41, angle steel corner brace, 42, stone material reinforcing rib, 43, dedicated corner brace, 44, dry hanging article, 45, bolt, 431, riser, 432, stepped plate, 433, transverse slat, 434, slot, 435, circular hole.
Specific embodiment
The preferred embodiments of the present invention will be described in detail with reference to the accompanying drawing, so that advantages and features of the invention energy It is easier to be readily appreciated by one skilled in the art, so as to make a clearer definition of the protection scope of the present invention.
It please refers to Fig.1 to Fig.3, the embodiment of the present invention includes:
A kind of dried hanging hang structure for crossing apex stone material, including structural beams 1, angle steel 2, stone facing 5 and bindiny mechanism 4, the stone Material facing 5 is assembled by muti-piece stone material plate, the angle steel 2 and bindiny mechanism 4 be set to structural beams 1 and stone facing 5 it Between, by chemical anchor bolts 3 or welded connecting between the angle steel 2 and structural beams 1, pass through between the angle steel 2 and stone facing 5 Bindiny mechanism 4 connects;The bindiny mechanism 4 includes:One end of angle steel corner brace 41 and dry hanging article 44, the angle steel corner brace 41 passes through Bolt 6 is fixed on angle steel 2, and the other end of angle steel corner brace 41 is fixed by bolt 45 and dry hanging article 44, and the dry hanging article 44 is inserted into It is close in the stone material plate slot driller of splicing and hangs stone material plate, structure glue is completely filled out in seam, in 44 hanging position of dry hanging article Stone material reinforcing rib 42 is arranged in the stone material plate back side at place, and the stone material reinforcing rib 42 passes through structure glue with stone material plate, Close to the stone material plate back side of stone material reinforcing rib 42, a dedicated corner brace 43, the dedicated corner brace 43 or so are fixed with expansion bolt 7 It is symmetrical arranged and stone material plate is fixed in one end, the other end is fixed on angle steel corner brace 41.
Further, in order to increase the thickness of stone material plate at fluting, increase shearing resistance section, reduce stone material destroy it is general Rate is provided with stone material reinforcing rib 42 between the dedicated corner brace 43 and stone facing 5, as shown in figure 3, the dedicated corner brace 43 It is set as ladder-like, including:One end of riser 431, transverse slat 433 and stepped plate, 432 stepped plates 432 connects riser 431, The other end connects transverse slat 433, opens up grooved hole 434 at the middle part of the riser 431, offers at the middle part of the transverse slat 433 Circular hole 435, the stone material reinforcing rib 42 are set between the stepped plate 432 of the dedicated corner brace 43 of symmetrical two pieces.
Bolt in order to improve antirust ability, in the present invention(6,45,7)And dedicated corner brace 43, dry hanging article 44 are all made of not Rust steel material;The extexine of angle steel corner brace 41 and dedicated corner brace 43 is coated with zinc coat.
In order to ensure the reliability that stone material reinforcing rib 42 is connect with dedicated corner brace 43, in stone material reinforcing rib 42 and dedicated corner brace Structure glue is filled between 43.
The stone material plate back side bonds fiberglass gridding cloth, improves the bending strength of stone material, reduces stone material in gravity lotus Bending deformation under load effect, avoids stone material from being broken.
The embodiment of the invention also discloses a kind of construction method of dried hanging hang structure for crossing apex stone material, main includes following several Step:
One, surveying setting-out:According to construction drawing, unwrapping wire is measured, determines angle iron position;
Two, angle steel, concealment acceptance are installed;
Three, stone material plate examination row, positioning:According to stone material setting-out drawing, examination row, positioning are carried out to stone material plate;
Four, stone material plate is installed:
1, stone material plate is handled
1), according to stone material plate size cut fiberglass gridding cloth;
2), the stone material plate back side with glue special paste fiberglass gridding cloth;
3), stone material plate other plate faces do protective treatment;
4), at the fluting of the stone material plate back side with structure stone gluing reinforcing rib, it is the long 100-200mm of stone material reinforcing rib, wide about 60-80mm, thickness can be the same as stone material plate thickness.
5), dedicated corner brace side connect with M8 stainless steel hexagonal expansible plug with the stone material plate back side, dedicated corner brace and stone material Reinforcing rib contact site is closely knit with structure gluing knot.
6), stone material plate edge open cladding slot, groove width about 5mm between two parties with abrasive wheel cutting machine.
2, stone material plate is cladding
1), weatherproof structure glue is filled in cladding slot, dry hanging article is protruded into cladding slot, it is closely knit with weatherproof structure glue;
2), dedicated corner brace, stainless steel dry hanging article bolt and Bolted angle connection;
3), adjust stone material plate height by stainless steel dry hanging article and until decoration is finally completed face tightens bolt and fix;
4), remaining stone material plate is successively installed in this order;
Five, stone material partitioning slot is handled:Raked joint, gluing;
Six, stone surface is cleared up;
Seven, it checks and accepts.
The above description is only an embodiment of the present invention, is not intended to limit the scope of the invention, all to utilize this hair Equivalent structure or equivalent flow shift made by bright specification and accompanying drawing content is applied directly or indirectly in other relevant skills Art field, is included within the scope of the present invention.

Claims (1)

1. a kind of construction method for crossing apex stone material dried hanging hang structure, the apex stone material of crossing includes structural beams, angle steel, stone facing and company Connection mechanism, the stone facing is assembled by muti-piece stone material plate, and the angle steel and bindiny mechanism are set to structural beams and stone Between material facing, by chemical anchor bolts or welded connecting between the angle steel and structural beams, between the angle steel and stone facing It is connected by bindiny mechanism;The bindiny mechanism includes:One end of angle steel corner brace and dry hanging article, the angle steel corner brace passes through bolt It is fixed on angle steel, the other end of angle steel corner brace is fixed by bolt and dry hanging article, and the dry hanging article insertion is close to the stone material of splicing Stone material is hung in slot driller, completely fills out structure glue in seam, stone material is arranged in the stone material plate back side at dry hanging article hanging position Reinforcing rib, the stone material reinforcing rib and stone material plate are by structure glue, at the stone material plate back side close to stone material reinforcing rib, A dedicated corner brace is fixed with expansion bolt, the dedicated corner brace is symmetrical set and stone material plate, the other end are fixed in one end It is fixed on angle steel corner brace, the dedicated corner brace is set as ladder-like, including:Riser, transverse slat and stepped plate, the one of the stepped plate End connection riser, the other end connect transverse slat, open up grooved hole in the middle part of the riser, offer circle in the middle part of the transverse slat Hole, the stone material reinforcing rib are set between the stepped plate of two pieces of symmetrical dedicated corner braces, and the dedicated corner brace is not using Rust steel material, and extexine is coated with zinc coat, and structure glue is filled between the stone material reinforcing rib and dedicated corner brace, it is described Stone facing is adhesive with layer of glass grid cloth close to the side of dedicated corner brace,
It is characterized in that:Its construction method mainly comprises the following steps:
One, surveying setting-out:According to construction drawing, unwrapping wire is measured, determines angle iron position;
Two, angle steel, concealment acceptance are installed;
Three, stone material plate examination row, positioning:According to stone material setting-out drawing, examination row, positioning are carried out to stone material plate;
Four, stone material plate is installed:
1, stone material plate is handled
1), fiberglass gridding cloth is cut according to stone material plate size;
2), fiberglass gridding cloth is pasted with glue special at the stone material plate back side;
3), other plate faces of stone material plate do protective treatment;
4), with structure stone gluing reinforcing rib, the long 100-200mm of stone material reinforcing rib, width 60- at the fluting of the stone material plate back side 80mm, thickness are the same as stone material plate thickness;
5), dedicated corner brace side expansible plug is connect with the stone material plate back side, and dedicated corner brace and stone material reinforcing rib contact site are used Structure gluing knot is closely knit;
6), stone material plate edge opens cladding slot, groove width 5mm with abrasive wheel cutting machine between two parties;
2, stone material plate is cladding
1) weatherproof structure glue, is filled in cladding slot, and dry hanging article is protruded into cladding slot, it is closely knit with weatherproof structure glue;
2), dedicated corner brace, stainless steel dry hanging article bolt and Bolted angle connection;
3), stone material plate height is adjusted by stainless steel dry hanging article to tighten bolt until decoration is finally completed face and fix;
4), remaining stone material plate is successively installed in this order;
Five, stone material partitioning slot is handled:Raked joint, gluing;
Six, stone surface is cleared up;
Seven, it checks and accepts.
CN201610748521.4A 2016-08-30 2016-08-30 A kind of dried hanging hang structure and its construction method for crossing apex stone material Active CN106351416B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610748521.4A CN106351416B (en) 2016-08-30 2016-08-30 A kind of dried hanging hang structure and its construction method for crossing apex stone material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610748521.4A CN106351416B (en) 2016-08-30 2016-08-30 A kind of dried hanging hang structure and its construction method for crossing apex stone material

Publications (2)

Publication Number Publication Date
CN106351416A CN106351416A (en) 2017-01-25
CN106351416B true CN106351416B (en) 2018-11-23

Family

ID=57855415

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610748521.4A Active CN106351416B (en) 2016-08-30 2016-08-30 A kind of dried hanging hang structure and its construction method for crossing apex stone material

Country Status (1)

Country Link
CN (1) CN106351416B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107401234A (en) * 2017-08-15 2017-11-28 广东萨米特陶瓷有限公司 The big plate curtain wall dried hanging structure of architectural pottery and its construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0633570A (en) * 1992-07-13 1994-02-08 Ig Tech Res Inc Improved external wall structure
IL221317A (en) * 2012-08-06 2016-11-30 Yochanan Giat Ergonomic strategy and system for cast construction
CN202925824U (en) * 2012-08-14 2013-05-08 苏州苏明装饰股份有限公司 Dry hanging structure for stone door opening bottom plate
CN204676812U (en) * 2015-06-01 2015-09-30 深圳市茂华装饰工程有限公司 A kind of direct insertion dry hanging stone structure for decorated wall surface
CN106088514B (en) * 2016-08-25 2018-07-27 李彩斌 A kind of stone material dry suspending slabstone fixed structure with high anti-seismic function

Also Published As

Publication number Publication date
CN106351416A (en) 2017-01-25

Similar Documents

Publication Publication Date Title
CN105507539A (en) Light external wall point-hang heat-insulation and decorative plate combined anchoring system and method for constructing same
CN113323149B (en) Laminated wood prestressed casing bolt joint and construction method thereof
CN103556711A (en) Fabricated wood structure embedded steel bar joint and construction method thereof
CN103774789B (en) Structural thermal insulation integration pressure-bearing template and apply the construction techniques of this template
CN106639355A (en) Reinforced concrete beam structure
CN106351416B (en) A kind of dried hanging hang structure and its construction method for crossing apex stone material
CN106948343B (en) A kind of tonnage anchor cable of tension and compression combination bearing mode and peace method processed
CN207513219U (en) A kind of timber structure Tenon node with bracing reinforcement
CN108222289A (en) A kind of assembled bamboo wood beam-column joint connecting structure
CN104863285A (en) Heat-preservation decorative wall body and construction method of same
CN106382018A (en) Angle iron reinforcing structure capable of applying prestress to rectangular column and construction method of angle iron reinforcing structure
KR100995121B1 (en) Manufacturing method of improved embeded type channel for fixing fastener
CN105649241B (en) The installation method of restricted clearance Curtain Wall glass
CN209293228U (en) A kind of assembled foundation connecting node
CN203742066U (en) Structured heat preservation integrated pressure-bearing formwork
CN205063146U (en) Stiff and straight line furred ceiling turning structure of gypsum of preventing ftractureing
CN206784725U (en) Large span assembled open-type builds bottom plate I-beam erection support and mounting assembly
CN206427941U (en) Construction tower crane builds attachment temporarily
CN206769158U (en) A kind of cable-arch system lighting roof
CN208072791U (en) A kind of tile attachment device and tile roofing
CN209384102U (en) A kind of floorings ruggedized construction
CN207609196U (en) A kind of component of rapid reinforcement reinforced beam shear-carrying capacity
CN204266111U (en) Deep foundation ditch steel trestle
CN208899730U (en) Closed-section steel deck cast-in-situ floor elevator apparatus and ceiling structure
CN104879053A (en) Decorative louver

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant