CN106326583A - Stacking method for engineering materials based on BIM - Google Patents

Stacking method for engineering materials based on BIM Download PDF

Info

Publication number
CN106326583A
CN106326583A CN201610760439.3A CN201610760439A CN106326583A CN 106326583 A CN106326583 A CN 106326583A CN 201610760439 A CN201610760439 A CN 201610760439A CN 106326583 A CN106326583 A CN 106326583A
Authority
CN
China
Prior art keywords
construction
bim
information data
building materials
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610760439.3A
Other languages
Chinese (zh)
Inventor
张凤勇
代凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Ershiye Construction Co Ltd
Original Assignee
Shanghai Ershiye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Ershiye Construction Co Ltd filed Critical Shanghai Ershiye Construction Co Ltd
Priority to CN201610760439.3A priority Critical patent/CN106326583A/en
Publication of CN106326583A publication Critical patent/CN106326583A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • General Physics & Mathematics (AREA)
  • Geometry (AREA)
  • Strategic Management (AREA)
  • Computer Hardware Design (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Primary Health Care (AREA)
  • Mathematical Analysis (AREA)
  • General Health & Medical Sciences (AREA)
  • Structural Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Pure & Applied Mathematics (AREA)
  • Civil Engineering (AREA)
  • Computational Mathematics (AREA)
  • Architecture (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Mathematical Optimization (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

Provided in particular is a stacking method for engineering materials based on BIM; the method is characterized by collecting planning programming drawings; inputting the drawings into a BIM system and conducting 3D modeling; conducting operation of decomposition of materials to classify building materials to form building materials information data; inputting the building materials information data into the BIM system and conducting simulating operation of stacking and transporting; outputting the building materials information data and form text after the successful simulating. According to the method, buildings, roads and sites in the construction region are taken into consideration when simulated modeling is conducted, and amounts, types, service condition are calculated in advance and in real time and matched with the dynamic data in actual construction operation, allocation for the building materials is simulated, announced and carried By doing so, even in a construction site of high density, building materials can also be allocated and regulated reasonably, accurately, and in time so as to improve the efficiency of the construction operation.

Description

Engineering material stacking method based on BIM
Technical field
The present invention relates to large-scale engineering construction field, a kind of engineering material stacking method based on BIM.
Background technology
General in high density groups of building engineering construction, owing to construction material or other material have enormous amount, model is complicated, Placing of material has a strong impact on construction speed, affects construction management.
Summary of the invention
It is an object of the invention to, it is provided that a kind of engineering material stacking method based on BIM software, it has stacking efficiency Feature high, easily allotment.
In order to achieve the above object, the present invention is achieved in that
A kind of engineering material stacking method based on BIM, including
The design planning of all roads in the design planning drawing of each building, collection construction area in step 1, collection construction area Drawing;
Step 2, by sheet template BIM system described in step 1 and carry out three-dimensional modeling;
Step 3, carry out material apportioned effort, construction material is classified, the categorical data of statistics construction material, statistics building The time of marching into the arena of material, the use unit of statistics construction material and use time;All construction materials are carried out by profile, effect Classify and plan stowed location, stowed location is carried out coordinate demarcation;It is thusly-formed construction material information data;
Step 4, the dry run that windrow of going forward side by side in construction material information data input BIM system described in step 3 is put, transported; Guarantee that the dry run stacked and transport is unobstructed, fluent;
After step 5, step 4 dry run success, construction material information data is exported and forms text.
Described engineering material stacking method based on BIM, step 4 also includes: the three-dimensional modeling of construction material, to difference Region is stacked in the permission of material, zones of different placing of material is controlled the size and added up;Run simulation and include any floor or portion The quantities output of position, the simulation of material stockyard capacity and automatically distributing;Form graphics according to simulation conclusion and export.
This stacking method is simulated modeling to the building of construction area, road, place, and by the quantity of construction material, Classification, service condition are carried out in advance, real-time statistics, then coordinate the tune to construction material of the dynamic data in practice of construction operation Join simulation and carry out.So, even if in highdensity construction place, also can rationally, accurately and timely to building Build material allocate and regulate and control, and then improve the efficiency of construction operation.
Detailed description of the invention
The present invention is further illustrated below by way of specific embodiment.
A kind of engineering material stacking method based on BIM, including
The design planning of all roads in the design planning drawing of each building, collection construction area in step 1, collection construction area Drawing;
Step 2, by sheet template BIM system described in step 1 and carry out three-dimensional modeling;
Step 3, carry out material apportioned effort, construction material is classified, the categorical data of statistics construction material, statistics building The time of marching into the arena of material, the use unit of statistics construction material and use time;All construction materials are carried out by profile, effect Classify and plan stowed location, stowed location is carried out coordinate demarcation;It is thusly-formed construction material information data;
Step 4, the dry run that windrow of going forward side by side in construction material information data input BIM system described in step 3 is put, transported; Guarantee that the dry run stacked and transport is unobstructed, fluent;
After step 5, step 4 dry run success, construction material information data is exported and forms text.
Described engineering material stacking method based on BIM, step 4 also includes: the three-dimensional modeling of construction material, to difference Region is stacked in the permission of material, zones of different placing of material is controlled the size and added up;Run simulation and include any floor or portion The quantities output of position, the simulation of material stockyard capacity and automatically distributing;Form graphics according to simulation conclusion and export.
This stacking method is simulated modeling to the building of construction area, road, place, and by the quantity of construction material, Classification, service condition are carried out in advance, real-time statistics, then coordinate the tune to construction material of the dynamic data in practice of construction operation Join simulation and carry out.So, even if in highdensity construction place, also can rationally, accurately and timely to building Build material allocate and regulate and control, and then improve the efficiency of construction operation.

Claims (2)

1. an engineering material stacking method based on BIM, is characterized in that, including
The design planning of all roads in the design planning drawing of each building, collection construction area in step 1, collection construction area Drawing;
Step 2, by sheet template BIM system described in step 1 and carry out three-dimensional modeling;
Step 3, carry out material apportioned effort, construction material is classified, the categorical data of statistics construction material, statistics building The time of marching into the arena of material, the use unit of statistics construction material and use time;All construction materials are carried out by profile, effect Classify and plan stowed location, stowed location is carried out coordinate demarcation;It is thusly-formed construction material information data;
Step 4, the dry run that windrow of going forward side by side in construction material information data input BIM system described in step 3 is put, transported; Guarantee that the dry run stacked and transport is unobstructed, fluent;
After step 5, step 4 dry run success, construction material information data is exported and forms text.
Engineering material stacking method based on BIM the most according to claim 1, is characterized in that, step 4 also includes: building The three-dimensional modeling of material, permission stacking region, zones of different placing of material to different materials are controlled the size and are added up;Run Simulation includes the quantities output at any floor or position, the simulation of material stockyard capacity and automatically distributes;According to simulation conclusion Form graphics and export.
CN201610760439.3A 2016-08-30 2016-08-30 Stacking method for engineering materials based on BIM Pending CN106326583A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610760439.3A CN106326583A (en) 2016-08-30 2016-08-30 Stacking method for engineering materials based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610760439.3A CN106326583A (en) 2016-08-30 2016-08-30 Stacking method for engineering materials based on BIM

Publications (1)

Publication Number Publication Date
CN106326583A true CN106326583A (en) 2017-01-11

Family

ID=57789135

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610760439.3A Pending CN106326583A (en) 2016-08-30 2016-08-30 Stacking method for engineering materials based on BIM

Country Status (1)

Country Link
CN (1) CN106326583A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107292538A (en) * 2017-07-25 2017-10-24 浙江精工钢结构集团有限公司 A kind of live material visual intelligent management system of Construction of Steel Structure
CN108427787A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of assembled stockyard layout management method and system based on BIM
CN108427790A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 The component logistics management emulation mode and device of erecting yard based on BIM
CN109403630A (en) * 2018-11-05 2019-03-01 江苏东保装饰集团有限公司 A kind of public building interior decoration engineering sample construction method
CN109872110A (en) * 2019-03-05 2019-06-11 深圳市国晨工程造价咨询有限公司 A kind of project materials purchasing management system
CN110580574A (en) * 2019-08-26 2019-12-17 交通运输部水运科学研究所 method, system, device, medium and computing equipment for acquiring container stacking risk
CN113326963A (en) * 2020-02-28 2021-08-31 天津大学 Storage yard optimization method based on prefabricated part transportation tracking and real-time progress

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104680321A (en) * 2015-02-13 2015-06-03 上海同筑信息科技有限公司 BIM technology-based visual material control system and method
CN105868502A (en) * 2016-04-22 2016-08-17 广州硕品物联网科技有限公司 BIM (building information modeling) based material management system and control method thereof

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104680321A (en) * 2015-02-13 2015-06-03 上海同筑信息科技有限公司 BIM technology-based visual material control system and method
CN105868502A (en) * 2016-04-22 2016-08-17 广州硕品物联网科技有限公司 BIM (building information modeling) based material management system and control method thereof

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107292538A (en) * 2017-07-25 2017-10-24 浙江精工钢结构集团有限公司 A kind of live material visual intelligent management system of Construction of Steel Structure
CN108427787A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of assembled stockyard layout management method and system based on BIM
CN108427790A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 The component logistics management emulation mode and device of erecting yard based on BIM
CN109403630A (en) * 2018-11-05 2019-03-01 江苏东保装饰集团有限公司 A kind of public building interior decoration engineering sample construction method
CN109872110A (en) * 2019-03-05 2019-06-11 深圳市国晨工程造价咨询有限公司 A kind of project materials purchasing management system
CN110580574A (en) * 2019-08-26 2019-12-17 交通运输部水运科学研究所 method, system, device, medium and computing equipment for acquiring container stacking risk
CN110580574B (en) * 2019-08-26 2024-02-20 交通运输部水运科学研究所 Method, system, device, medium and computing equipment for acquiring container stacking risk
CN113326963A (en) * 2020-02-28 2021-08-31 天津大学 Storage yard optimization method based on prefabricated part transportation tracking and real-time progress
CN113326963B (en) * 2020-02-28 2022-12-20 天津大学 Storage yard optimization method based on prefabricated part transportation tracking and real-time progress

Similar Documents

Publication Publication Date Title
CN106326583A (en) Stacking method for engineering materials based on BIM
CN105868502A (en) BIM (building information modeling) based material management system and control method thereof
CN107967399A (en) A kind of assembled architecture Deepen Design method based on BIM softwares
CN108428194A (en) A kind of management method and device of the building material processing dispatching based on BIM
CN106326536A (en) Standardized construction method for hydraulic prefabricated member based on BIM (Building Information Modeling)
Yu et al. A BIM-based dynamic model for site material supply
CN105427064A (en) Steel coil stock control method based on crane positioning system
CN101814174A (en) Optimization method of agricultural material chain operation logistics center site selection
CN103606124A (en) Microscopic simulation method of handling traffic system layout and traffic organization of container terminal
CN105243453A (en) Dynamic ore matching optimization method for mined ore
CN106773686A (en) With piler scheduling path model method for building up under the double car operational modes of rail
CN104680352A (en) Fresh agricultural product cold-chain logistics system network layout optimization method
Straka et al. Simulation of homogeneous production processes
Sakhaii et al. A robust model for a dynamic cellular manufacturing system with production planning
CN113190885A (en) Layout planning method for industrial assembly line workshop
Huka et al. Log yard logistics
CN106203716A (en) A kind of analysis method and apparatus of the dual resource distribution of production unit
CN104392344A (en) Reverse logistics network configuration method based on multi-population PSO (Particle Swarm Optimization)
Huang et al. Estimation of construction waste generation and management in Taiwan
Baek et al. An Earthwork Districting Model for Large Construction Projects
CN109117571A (en) A kind of interconnection cooperative motion autocontrol method for unmanned plane cluster
CN108268962A (en) Construction supply chain management method and apparatus based on 4D BIM and GIS
Malé‐Alemany et al. Soft tolerance: an approach for additive construction on site
Askari-Nasab et al. Simulation optimisation of mine operational plans
Le et al. Complex simulation of stockyard mining operations

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170111