CN106320184B - A kind of unit construction bridge beam construction method - Google Patents
A kind of unit construction bridge beam construction method Download PDFInfo
- Publication number
- CN106320184B CN106320184B CN201610870798.4A CN201610870798A CN106320184B CN 106320184 B CN106320184 B CN 106320184B CN 201610870798 A CN201610870798 A CN 201610870798A CN 106320184 B CN106320184 B CN 106320184B
- Authority
- CN
- China
- Prior art keywords
- bridge
- prefabricated
- tower crane
- prefabricated bridge
- pier
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 42
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 57
- 239000010959 steel Substances 0.000 claims abstract description 57
- 239000004567 concrete Substances 0.000 claims description 13
- 239000011384 asphalt concrete Substances 0.000 claims description 10
- 230000003014 reinforcing effect Effects 0.000 claims description 9
- 238000003466 welding Methods 0.000 claims description 4
- 239000000565 sealant Substances 0.000 claims description 3
- 238000009408 flooring Methods 0.000 claims 4
- 230000015271 coagulation Effects 0.000 claims 1
- 238000005345 coagulation Methods 0.000 claims 1
- 238000007596 consolidation process Methods 0.000 claims 1
- 230000010485 coping Effects 0.000 claims 1
- 239000012530 fluid Substances 0.000 claims 1
- 238000011065 in-situ storage Methods 0.000 claims 1
- 239000000463 material Substances 0.000 claims 1
- 239000000203 mixture Substances 0.000 claims 1
- 238000010422 painting Methods 0.000 claims 1
- 238000000034 method Methods 0.000 abstract description 4
- 238000010586 diagram Methods 0.000 description 5
- 238000012423 maintenance Methods 0.000 description 3
- 239000002699 waste material Substances 0.000 description 3
- 238000009417 prefabrication Methods 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000001627 detrimental effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009440 infrastructure construction Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
发明提供一种装配式桥梁施工方法,解决现有技术中存在的运输困难、时间耗费量大等问题,保证了桥梁施工安全高效进行。采用预制装配式施工方法,施工速度快。相邻两块预制桥面板,采用钢板连接。保证了结构的完整性,更加安全可靠。施工过程中采用斜拉钢绞线连接预制桥面板和塔吊,保证了桥面板的稳定性,保障了施工人员在桥面板上操作的安全性。
The invention provides a prefabricated bridge construction method, which solves the problems in the prior art such as difficult transportation and large time consumption, and ensures safe and efficient bridge construction. The prefabricated construction method is adopted, and the construction speed is fast. Two adjacent prefabricated bridge decks are connected by steel plates. The integrity of the structure is guaranteed, making it safer and more reliable. During the construction process, cable-stayed steel strands are used to connect the prefabricated bridge deck and the tower crane, which ensures the stability of the bridge deck and the safety of construction personnel operating on the bridge deck.
Description
技术领域technical field
本发明涉及桥梁工程技术领域,特别涉及一种装配式桥梁施工方法。The invention relates to the technical field of bridge engineering, in particular to an assembly bridge construction method.
背景技术Background technique
我国正处于基础设施大力建设阶段,进入二十一世纪以来,我国公路和铁路每年建设的里程都以上万公里计量,根据“十二五”规划的要求,到2015年底,公里总里程将达到450万公里,铁路建设里程也将达到12万公里。而根据“十三五”规划的思想,完善中西部地区的交通网络将会成为重点,而对于中西部地区,地形地质条件相对复杂,丘壑纵横,为了缩短两地的通行时间以及保证行车的舒适度,需要建设大量的桥梁。Our country is in the stage of vigorous infrastructure construction. Since the beginning of the 21st century, the mileage of our country's roads and railways has been built more than 10,000 kilometers every year. According to the requirements of the "Twelfth Five-Year Plan", by the end of 2015, the total mileage will reach 450 kilometers. The mileage of railway construction will also reach 120,000 kilometers. According to the idea of the "Thirteenth Five-Year Plan", improving the transportation network in the central and western regions will become the focus. For the central and western regions, the terrain and geological conditions are relatively complex, with vertical and horizontal hills and valleys. In order to shorten the travel time between the two places and ensure the traffic safety Comfort requires the construction of a large number of bridges.
截止2013年,我国公路桥梁以达到71.34万座,为了控制造价,大部分桥梁均采用梁式桥和刚构桥的结构体系,对于这两种结构体系的桥梁施工,目前采用较多的为整体装配式或者挂篮式施工方法,如果采用整体装配式施工方法,需要大型机械运输大型桥面板至现场装配,而一般桥梁施工都在中西部山区进行,交通不便,所以运输很难实现;而对于挂篮式施工方法,通常是采用桥梁两端同时向前施工,然后在中部合拢。在推进过程中,浇筑的混凝土需要一定的时间来达到一定的强度以后,才能够继续向前推进,这样会浪费大量的时间,对于工期很紧的工程十分不利;另外由于先浇筑的混凝土已经具有一定的强度,因此会和后浇筑的混凝土在接触面处无法完全融合形成整体,进而对桥梁的承载能力不利,同时挂篮施工,相当于悬臂梁施工,会形成过大的挠度变形,这样在中部可能会由于挠度过大无法满足变形的要求,造成工程不安全因素。As of 2013, the number of highway bridges in my country has reached 713,400. In order to control the cost, most bridges adopt the structural system of beam bridge and rigid frame bridge. For the bridge construction of these two structural systems, the overall assembly type is currently used more Or the hanging basket construction method, if the overall assembly construction method is adopted, large-scale machinery is required to transport large bridge decks to the site for assembly, and the general bridge construction is carried out in the mountainous areas of the central and western regions, and the transportation is inconvenient, so transportation is difficult to achieve; and for hanging baskets The traditional construction method usually uses both ends of the bridge to be constructed forward at the same time, and then closed in the middle. During the advancing process, it takes a certain amount of time for the poured concrete to reach a certain strength before it can continue to advance, which will waste a lot of time and is very unfavorable for projects with a tight construction period; in addition, because the concrete poured earlier has already A certain strength, so it will not be completely integrated with the post-poured concrete at the contact surface to form a whole, which will be detrimental to the bearing capacity of the bridge. At the same time, the hanging basket construction, which is equivalent to the cantilever beam construction, will cause excessive deflection deformation. The middle part may be unable to meet the deformation requirements due to excessive deflection, resulting in engineering unsafe factors.
发明内容Contents of the invention
本发明的目的是提供一种装配式桥梁施工方法,解决现有技术中存在的运输困难、时间耗费量大等问题,保证桥梁施工安全高效进行。The purpose of the present invention is to provide a prefabricated bridge construction method, which solves the problems of difficult transportation and large time consumption in the prior art, and ensures safe and efficient bridge construction.
为实现本发明目的而采用的技术方案是这样的,一种装配式桥梁的施工方法,包括以下步骤:The technical scheme adopted for realizing the object of the present invention is such, a kind of construction method of prefabricated bridge, comprises the following steps:
1)勘察现场情况,确定桥梁的具体尺寸、路堤A的位置、路堤B的位置和两个桥墩的位置。1) Investigate the site situation, determine the specific size of the bridge, the location of embankment A, the location of embankment B and the location of two piers.
2)浇筑多块整体形状为长方体的预制桥面板,并按照规范要求对预制桥面板进行混凝土养护。2) Pour multiple prefabricated bridge decks whose overall shape is cuboid, and perform concrete curing on the prefabricated bridge decks according to the specification requirements.
其中:所述预制桥面板中预埋有钢筋。所述预制桥面板沿横向方向的两个面为侧面,沿纵向方向的两个面为端面。所述预制桥面板的横向长度等于桥面宽度,预制桥面板的纵向长度为2~5m。每块预制桥面板的顶面均预埋有若干个封闭拉钩。每块预制桥面板的两个侧面上靠近端面处均开有凹槽。两块预制桥面板的端面紧贴后,两个相邻凹槽形成与连接钢板配合的凹槽接口。Wherein: steel bars are pre-embedded in the prefabricated bridge deck. The two faces of the prefabricated bridge deck along the transverse direction are side faces, and the two faces along the longitudinal direction are end faces. The transverse length of the prefabricated bridge deck is equal to the width of the bridge deck, and the longitudinal length of the prefabricated bridge deck is 2-5m. The top surface of each prefabricated bridge deck is pre-embedded with several closed pull hooks. Both sides of each prefabricated bridge deck are provided with grooves close to the end faces. After the end faces of the two prefabricated bridge decks are closely attached, two adjacent grooves form a groove interface matched with the connecting steel plate.
3)根据设计要求现场浇筑两个桥墩,按设计分布将规定数量的钢筋的一端竖立预埋在桥墩中。3) According to the design requirements, two bridge piers are poured on site, and one end of the specified number of steel bars is erected and pre-buried in the bridge piers according to the design distribution.
4)按照规范规定要求对桥墩进行养护。4) Carry out maintenance on the pier according to the requirements of the specification.
5)对塔吊的塔吊标准节进行加固:塔吊标准节内焊接若干横杆和角钢。塔吊标准节沿桥纵向方向的两侧焊接多块抗拉钢板。5) Reinforce the tower crane standard section of the tower crane: Weld several cross bars and angle steels in the tower crane standard section. A number of tensile steel plates are welded on both sides of the tower crane standard section along the longitudinal direction of the bridge.
6)在桥墩顶部架设塔吊。所述塔吊和桥墩使用高强螺栓连接。步骤3)所述的钢筋穿过塔吊的底板。6) Erect the tower crane on the top of the pier. The tower crane and the pier are connected by high-strength bolts. Step 3) the steel bar passes through the bottom plate of the tower crane.
7)对塔吊底部进行进一步的加固处理。7) Carry out further reinforcement treatment on the bottom of the tower crane.
8)在路堤A和路堤B分别安装一个橡胶支座。8) Install a rubber bearing on embankment A and embankment B respectively.
9)运输预制桥面板到施工现场。9) Transport the prefabricated bridge deck to the construction site.
10)沿着桥梁纵向顺次铺设多块预制桥面板:使用塔吊把一块预制桥面板吊装至指定位置。使用斜拉钢绞线连接预制桥面板和塔吊的塔身。吊装下一块预制桥面板到达指定位置,使用斜拉钢绞线连接预制桥面板和塔吊的塔身。连接钢板采用高强螺栓和/或焊接方式将相邻的两块预制桥面板固定连接。同理继续放置预制桥面板直至达到设计数量。10) Lay multiple prefabricated bridge decks sequentially along the longitudinal direction of the bridge: Use a tower crane to hoist a prefabricated bridge deck to the designated position. Use cable-stayed steel strands to connect the prefabricated bridge deck and the tower body of the tower crane. Lift the next prefabricated bridge deck to the designated position, and use cable-stayed steel strands to connect the prefabricated bridge deck and the tower body of the tower crane. The connecting steel plates are fixedly connected to two adjacent prefabricated bridge decks by means of high-strength bolts and/or welding. In the same way, continue to place prefabricated bridge decks until the design quantity is reached.
其中:斜拉钢绞线一端焊接在抗拉钢板上,另一端穿过预制桥面板的封闭拉钩并进行锚固。相邻两块预制桥面板顶面平齐,端面紧贴在一起。连接钢板完全镶嵌在相邻两块预制桥面板的凹槽组成的凹槽接口中。Among them: one end of the cable-stayed steel strand is welded on the tensile steel plate, and the other end passes through the closed hook of the prefabricated bridge deck and is anchored. The top surfaces of two adjacent prefabricated bridge decks are flush, and the end surfaces are close together. The connecting steel plates are completely embedded in the groove interface formed by the grooves of two adjacent prefabricated bridge decks.
11)拆除塔吊至桥面高度。在剩余塔吊标准节所在位置浇筑与预制桥面板混凝土强度等级一致的普通混凝土。由此构成桥面的预制桥面板层。11) Remove the tower crane to the height of the bridge deck. Ordinary concrete with the same strength level as the prefabricated bridge deck concrete is poured at the position where the remaining tower crane standard sections are located. The prefabricated deck layers of the bridge deck are thus formed.
12)在预制桥面板层上部浇筑沥青混凝土层。12) Pour asphalt concrete layer on the upper part of the prefabricated bridge deck.
进一步,完成步骤12)之后,对桥面进行美化并回收废弃材料。Further, after completing step 12), the bridge deck is beautified and waste materials are recycled.
进一步,步骤3)所述的钢筋伸入桥墩长度不小于桥墩高度的三分之一,伸出桥墩顶部的长度为200~500mm。Further, the length of the reinforcing bar in step 3) extending into the bridge pier is not less than one-third of the height of the bridge pier, and the length extending out from the top of the bridge pier is 200-500 mm.
进一步,步骤3)所述的钢筋伸出桥墩顶部的一端攻有螺纹。在步骤6)中,所述钢筋穿过塔吊的底板后,高强螺母旋入这些钢筋端头的螺纹。Further, one end of the reinforcing bar protruding from the top of the pier in step 3) is threaded. In step 6), after the steel bars pass through the bottom plate of the tower crane, the high-strength nuts are screwed into the threads at the ends of these steel bars.
一种通过上述装配式桥梁的施工方法建成的装配式桥梁,包括桥面、两个桥墩和两个橡胶支座。A prefabricated bridge built by the above-mentioned construction method of the prefabricated bridge includes a bridge deck, two piers and two rubber bearings.
所述桥面架设在路堤A和路堤B之间。所述桥面与桥墩采用直穿钢筋连接。所述桥面与路堤之间安装有橡胶支座。The bridge deck is erected between embankment A and embankment B. The bridge deck and the bridge piers are connected by straight-through steel bars. A rubber bearing is installed between the bridge deck and the embankment.
所述桥面包括预制桥面板层和沥青混凝土层。所述沥青混凝土层铺设在预制桥面板层上,并与预制桥面板层紧密粘结。The bridge deck includes a prefabricated bridge deck layer and an asphalt concrete layer. The asphalt concrete layer is laid on the prefabricated bridge deck layer and tightly bonded with the prefabricated bridge deck layer.
所述预制桥面板层包括多块沿着桥梁纵向顺次铺设的预制桥面板。所述预制桥面板顶面平齐。所述预制桥面板层沿桥面宽度方向的两侧还具有若干凹槽接口。相邻预制桥面板通过连接钢板与凹槽接口的插装配合连接。所述连接钢板采用高强螺栓的形式将相邻预制桥面板固定为整体。The prefabricated bridge deck layer includes a plurality of prefabricated bridge decks laid sequentially along the longitudinal direction of the bridge. The top surfaces of the prefabricated bridge decks are flush. The prefabricated bridge deck layer also has several groove interfaces on both sides along the width direction of the bridge deck. Adjacent prefabricated bridge decks are connected by plug-in fit between connecting steel plates and groove interfaces. The connecting steel plates use high-strength bolts to fix the adjacent prefabricated bridge decks as a whole.
进一步,相邻预制桥面板的接缝形状为平缝、企口形或锯齿形。Further, the joint shape of adjacent prefabricated bridge decks is flat joint, tongue-and-groove or zigzag.
进一步,相邻预制桥面板的接缝中涂制有密封胶。Further, sealant is applied to the joints of adjacent prefabricated bridge decks.
本发明的技术效果是毋庸置疑的:Technical effect of the present invention is beyond doubt:
A)采用现场预制或工厂预制的方式预制桥面板,仅需要小型运输设备就可以实现构件运输,克服了偏远山区大型运输设备无法进场的难题;A) The bridge deck is prefabricated by on-site prefabrication or factory prefabrication, and only small transportation equipment is needed to realize component transportation, which overcomes the problem that large-scale transportation equipment cannot enter the site in remote mountainous areas;
B)采用预制装配式施工方法,施工速度快,不存在吊篮式施工的养护形成强度时间,可以缩短施工工期;B) The prefabricated assembly construction method is adopted, the construction speed is fast, and there is no maintenance and strength formation time for hanging basket construction, which can shorten the construction period;
C)采用钢板连接相邻两块预制桥面板,保证了结构的完整性,同时也不存在挂篮式施工中存在的现浇混凝土与后浇混凝土无法充分融和的情况,更加安全可靠;C) Steel plates are used to connect two adjacent prefabricated bridge decks to ensure the integrity of the structure. At the same time, there is no situation that the cast-in-place concrete and post-cast concrete cannot be fully integrated in the hanging basket construction, which is safer and more reliable;
D)施工过程中采用斜拉钢绞线连接预制桥面板和塔吊,保证了桥面板的稳定性,保障了施工人员在桥面板上操作的安全性;D) During the construction process, cable-stayed steel strands are used to connect the prefabricated bridge deck and the tower crane, which ensures the stability of the bridge deck and the safety of construction personnel operating on the bridge deck;
E)采用预制构件钢板连接,施工工期短,经济价值十分明显。E) Using prefabricated component steel plates to connect, the construction period is short and the economic value is very obvious.
附图说明Description of drawings
图1为装配式桥梁施工图;Figure 1 is the construction drawing of the fabricated bridge;
图2为预制桥面板结构示意图;Figure 2 is a schematic diagram of the structure of the prefabricated bridge deck;
图3为桥面板连接图;Figure 3 is a bridge deck connection diagram;
图4为塔吊标准节示意图;Figure 4 is a schematic diagram of a tower crane standard section;
图5为塔吊与桥墩连接图;Figure 5 is a connection diagram between the tower crane and the bridge pier;
图6为装配式桥梁结构示意图。Figure 6 is a schematic diagram of the fabricated bridge structure.
图中:橡胶支座1,桥墩2,钢筋201,连接钢板3,螺纹孔Ⅰ301,预制桥面板4,侧面401,端面402,凹槽403,螺纹孔Ⅱ4031,封闭拉钩404,凹槽接口405,斜拉钢绞线5,塔吊6,底板601,抗拉钢板602,沥青混凝土层7。In the figure: rubber bearing 1, pier 2, steel bar 201, connecting steel plate 3, threaded hole I301, prefabricated bridge deck 4, side 401, end face 402, groove 403, threaded hole II 4031, closed hook 404, groove interface 405, Cable-stayed steel strand 5, tower crane 6, bottom plate 601, tensile steel plate 602, asphalt concrete layer 7.
具体实施方式Detailed ways
下面结合实施例对本发明作进一步说明,但不应该理解为本发明上述主题范围仅限于下述实施例。在不脱离本发明上述技术思想的情况下,根据本领域普通技术知识和惯用手段,做出各种替换和变更,均应包括在本发明的保护范围内。The present invention will be further described below in conjunction with the examples, but it should not be understood that the scope of the subject of the present invention is limited to the following examples. Without departing from the above-mentioned technical ideas of the present invention, various replacements and changes made according to common technical knowledge and conventional means in this field shall be included in the protection scope of the present invention.
实施例1:Example 1:
本实施例公开一种装配式桥梁的施工方法,参见图1~图6,包括以下步骤:This embodiment discloses a construction method of a prefabricated bridge, referring to Fig. 1 to Fig. 6, including the following steps:
1)勘察现场情况,确定桥梁的具体尺寸、路堤A的位置、路堤B的位置和两个桥墩2的位置。1) Investigate the site conditions, determine the specific size of the bridge, the location of embankment A, the location of embankment B and the location of two piers 2.
2)浇筑多块整体形状为长方体的预制桥面板4,并按照规范要求对预制桥面板4进行混凝土养护。这些预制桥面板4中预埋有钢筋;2) Pour a plurality of prefabricated bridge decks 4 whose overall shape is a cuboid, and perform concrete curing on the prefabricated bridge decks 4 according to the specifications. These prefabricated bridge decks 4 are pre-embedded with steel bars;
其中:所述预制桥面板4沿横向方向的两个面为侧面401,沿纵向方向的两个面为端面402。所述预制桥面板4的横向长度等于桥面宽度,预制桥面板4的纵向长度为2~5m。每块预制桥面板4的顶面均预埋有2个封闭拉钩404。每块预制桥面板4的两个侧面401上靠近端面402处均开有凹槽403。两块预制桥面板4的端面402紧贴后,两个相邻凹槽403形成与连接钢板3配合的凹槽接口405。所述连接钢板3上开有4排螺纹孔Ⅰ301,每排8个。所述凹槽接口405对应位置上也开有螺纹孔Ⅱ4031。Wherein: the two faces of the prefabricated bridge deck 4 along the transverse direction are side faces 401 , and the two faces along the longitudinal direction are end faces 402 . The transverse length of the prefabricated bridge deck 4 is equal to the bridge deck width, and the longitudinal length of the prefabricated bridge deck 4 is 2-5m. Two closed hooks 404 are pre-embedded on the top surface of each prefabricated bridge deck 4 . Both sides 401 of each prefabricated bridge deck 4 are provided with grooves 403 near the end faces 402 . After the end surfaces 402 of the two prefabricated bridge decks 4 are closely attached, two adjacent grooves 403 form a groove interface 405 that cooperates with the connecting steel plate 3 . The connecting steel plate 3 is provided with 4 rows of threaded holes I301, 8 in each row. The corresponding position of the groove interface 405 is also provided with a threaded hole II 4031 .
3)根据设计要求现场浇筑两个桥墩2,按设计分布将规定数量的钢筋201的一端竖立预埋在桥墩2中。这些钢筋201伸出桥墩2顶部的一端攻有螺纹。这些钢筋201伸入桥墩长度不小于桥墩高度的三分之一,伸出桥墩顶部的长度为200~500mm。3) Two bridge piers 2 are poured on site according to the design requirements, and one end of a specified number of steel bars 201 is vertically pre-embedded in the bridge piers 2 according to the design distribution. One end of these steel bars 201 protruding from the top of the pier 2 is threaded. The length of these steel bars 201 extending into the pier is not less than one-third of the height of the pier, and the length extending from the top of the pier is 200-500 mm.
4)按照规范规定要求对桥墩2进行养护。4) Carry out maintenance on the pier 2 according to the requirements of the specification.
5)对塔吊6的塔吊标准节进行加固:塔吊标准节内焊接横杆和角钢。塔吊标准节沿桥纵向方向的两侧焊接多块抗拉钢板602。5) Reinforce the tower crane standard section of the tower crane 6: weld the cross bar and angle steel in the tower crane standard section. A plurality of tensile steel plates 602 are welded on both sides of the tower crane standard section along the longitudinal direction of the bridge.
6)在桥墩2顶部架设塔吊6。桥墩2和塔吊6通过高强螺栓固定连接在一起。步骤3)所述的钢筋201穿过塔吊6的底板601后,将高强螺母旋紧于钢筋201端头的螺纹上。6) Erect the tower crane 6 on the top of the pier 2. The pier 2 and the tower crane 6 are fixedly connected together by high-strength bolts. Step 3) After the steel bar 201 passes through the bottom plate 601 of the tower crane 6, tighten the high-strength nut on the thread at the end of the steel bar 201.
7)对塔吊底部即总高度的三分之一以下部分,焊接横杆和角钢进行进一步的加固处理以保证塔吊和桥墩形成整体工作。7) For the bottom part of the tower crane, which is less than one-third of the total height, the welded crossbar and angle steel are further reinforced to ensure that the tower crane and the pier form an integral work.
8)在路堤A和路堤B分别安装一个橡胶支座1。8) Install a rubber bearing 1 on embankment A and embankment B respectively.
9)运输预制桥面板4到施工现场。9) Transport the prefabricated bridge deck 4 to the construction site.
10)沿着桥梁纵向顺次铺设多块预制桥面板4:使用塔吊6把一块预制桥面板4吊装至指定位置。使用斜拉钢绞线5连接预制桥面板4和塔吊6的塔身。吊装下一块预制桥面板4到达指定位置,使用斜拉钢绞线5连接预制桥面板4和塔吊6的塔身。使用连接钢板3将相邻的两块预制桥面板4固定连接。同理继续放置预制桥面板4直至达到设计数量。10) Lay multiple pieces of prefabricated bridge decks 4 sequentially along the longitudinal direction of the bridge: use tower crane 6 to hoist a prefabricated bridge deck 4 to a designated position. A cable-stayed steel strand 5 is used to connect the prefabricated bridge deck 4 and the tower body of the tower crane 6 . The next prefabricated bridge deck 4 is hoisted to the designated position, and the cable-stayed steel strand 5 is used to connect the prefabricated bridge deck 4 and the tower body of the tower crane 6 . Two adjacent prefabricated bridge decks 4 are fixedly connected by connecting steel plates 3 . Similarly, continue to place the prefabricated bridge deck 4 until the design quantity is reached.
其中:斜拉钢绞线5一端焊接在抗拉钢板602上,另一端穿过预制桥面板4的封闭拉钩404并进行锚固。相邻两块预制桥面板4顶面平齐,端面402紧贴在一起。连接钢板3完全镶嵌在相邻两块预制桥面板4的凹槽403组成的凹槽接口405中。高强螺栓302依次穿入螺纹孔Ⅰ301和螺纹孔Ⅱ4031,将相邻两块预制桥面板4固定连接在一起。远离塔吊6的预制桥面板4与塔身顶部的标准节连接,靠近塔吊6的预制桥面板4与塔身底部的标准节连接。Wherein: one end of the cable-stayed steel strand 5 is welded on the tensile steel plate 602, and the other end passes through the closed hook 404 of the prefabricated bridge deck 4 and is anchored. The top surfaces of two adjacent prefabricated bridge decks 4 are flush, and the end surfaces 402 are close together. The connecting steel plates 3 are completely embedded in the groove interface 405 formed by the grooves 403 of two adjacent prefabricated bridge decks 4 . The high-strength bolts 302 penetrate through the threaded hole I301 and the threaded hole II4031 in sequence, and fix and connect two adjacent prefabricated bridge decks 4 together. The prefabricated bridge deck 4 far away from the tower crane 6 is connected with the standard joint at the top of the tower body, and the prefabricated bridge deck 4 close to the tower crane 6 is connected with the standard joint at the bottom of the tower body.
11)拆除塔吊6至桥面高度。在剩余塔吊标准节所在位置浇筑与预制桥面板4混凝土强度等级一致的普通混凝土。由此构成桥面的预制桥面板层。11) Remove the tower crane 6 to the height of the bridge deck. Pour ordinary concrete with the same strength level as the concrete of prefabricated bridge deck 4 at the position where the remaining tower crane standard sections are located. The prefabricated deck layers of the bridge deck are thus formed.
12)在预制桥面板层上部浇筑沥青混凝土层7。12) Pour the asphalt concrete layer 7 on the upper part of the prefabricated bridge deck.
13)对桥面进行美化并回收废弃材料。13) Beautify the bridge deck and recycle waste materials.
实施例2Example 2
本实施例公开一种通过实施例1所述装配式桥梁的施工方法建成的装配式桥梁,包括桥面、两个桥墩2和两个橡胶支座1。This embodiment discloses a prefabricated bridge built by the construction method of the prefabricated bridge described in Embodiment 1, including a bridge deck, two piers 2 and two rubber bearings 1 .
参见图6,所述桥面架设在路堤A和路堤B之间。所述桥面与桥墩2采用直穿钢筋连接。所述桥面与路堤之间安装有橡胶支座1。Referring to Fig. 6, the bridge deck is erected between embankment A and embankment B. The bridge deck and pier 2 are connected by straight through steel bars. A rubber bearing 1 is installed between the bridge deck and the embankment.
所述桥面1包括预制桥面板层和沥青混凝土层7。所述沥青混凝土层7铺设在预制桥面板层上,并与预制桥面板层紧密粘结。The bridge deck 1 includes a prefabricated bridge deck layer and an asphalt concrete layer 7 . The asphalt concrete layer 7 is laid on the prefabricated bridge deck layer and tightly bonded with the prefabricated bridge deck layer.
所述预制桥面板层包括多块沿着桥梁纵向顺次铺设的预制桥面板4。所述多块预制桥面板4顶面平齐。所述预制桥面板层沿桥面宽度方向的两侧还具有凹槽接口405。相邻预制桥面板4通过连接钢板3与凹槽接口405的插装配合连接。所述连接钢板3采用高强螺栓的形式将相邻预制桥面板4固定为整体。相邻预制桥面板4的接缝形状为平缝,且相邻预制桥面板4的接缝中涂制有密封胶。The prefabricated bridge deck layer includes a plurality of prefabricated bridge decks 4 sequentially laid along the longitudinal direction of the bridge. The top surfaces of the plurality of prefabricated bridge decks 4 are flush. The prefabricated bridge deck layer also has groove interfaces 405 on both sides along the width direction of the bridge deck. Adjacent prefabricated bridge decks 4 are connected by plug-in fitting between connecting steel plate 3 and groove interface 405 . The connecting steel plates 3 use high-strength bolts to fix the adjacent prefabricated bridge decks 4 as a whole. The joint shape of the adjacent prefabricated bridge decks 4 is a flat seam, and the joints of the adjacent prefabricated bridge decks 4 are coated with sealant.
Claims (7)
- A kind of 1. construction method of packaged type bridges, it is characterised in that:Comprise the following steps:1) field condition is reconnoitred, determines the specific size of bridge, the position of embankment A, the position of embankment B and two bridge piers (2) Position;2) pour polylith global shape be cuboid prefabricated bridge (4), and according to code requirement to prefabricated bridge (4) into Row concrete curing;Wherein:Reinforcing bar is embedded with the prefabricated bridge (4);Two faces of the prefabricated bridge (4) in transverse direction are Side (401), two faces along the longitudinal direction are end face (402);It is wide that the lateral length of the prefabricated bridge (4) is equal to bridge floor Degree, the longitudinal length of prefabricated bridge (4) is 2~5m;The top surface of every piece of prefabricated bridge (4) is embedded with several closings and draws Hook (404);On two sides (401) of every piece of prefabricated bridge (4) groove (403) is provided with by proximal end face (402) place;Two pieces After the end face (402) of prefabricated bridge (4) is close to, two adjacent grooves (403) form the groove coordinated with junction steel plate (3) and connect Mouth (405);3) according to two bridge piers (2) of design requirement cast in situs, one end of the reinforcing bar (201) of specified quantity is erected by design distribution It is vertical to be embedded in bridge pier (2);4) require to conserve bridge pier (2) according to specification regulation;5) standard section of tower crane of tower crane (6) is reinforced:Some cross bars of welding and angle steel in standard section of tower crane;Standard section of tower crane Along the both sides welding polylith tension steel plate (602) of bridge longitudinal direction;6) tower crane (6) is set up at the top of bridge pier (2);The tower crane (6) is connected with bridge pier (2) using high-strength bolt;Step 3) institute The reinforcing bar (201) stated passes through the bottom plate (601) of tower crane (6);7) further consolidation process is carried out to tower crane bottom;8) one rubber support (1) is installed respectively in embankment A and embankment B;9) transport prefabricated bridge (4) and arrive construction site;10) sequentially it is laid with polylith prefabricated bridge (4) along bridge longitudinal direction:One piece of prefabricated bridge (4) is hung using tower crane (6) It is filled to designated position;Use oblique pull steel strand wires (5) connection prefabricated bridge (4) and the tower body of tower crane (6);Lift next piece it is prefabricated Floorings (4) reach designated position, use oblique pull steel strand wires (5) connection prefabricated bridge (4) and the tower body of tower crane (6);Connection Two pieces of adjacent prefabricated bridges (4) are fixedly connected by steel plate (3) using high-strength bolt (302) and/or welding manner;Similarly after It is continuous to place prefabricated bridge (4) until reaching design quantity;Wherein:Oblique pull steel strand wires (5) one end is welded on tension steel plate (602), and the other end passes through the closing of prefabricated bridge (4) Drag hook (404) is simultaneously anchored;Adjacent two pieces of prefabricated bridges (4) either flush, end face (402) are close together;Connect steel Plate (3) is embedded in the groove interface (405) of groove (403) composition of adjacent two pieces of prefabricated bridges (4) completely;11) tower crane (6) is removed to bridge floor height;Poured in remaining standard section of tower crane position and prefabricated bridge (4) coagulation The consistent normal concrete of native strength grade;Thus the prefabricated bridge layer of bridge floor is formed;12) asphalt concrete layer (7) is poured on prefabricated bridge layer top.
- A kind of 2. construction method of packaged type bridges according to claim 1, it is characterised in that:After completing step 12), Bridge floor is beautified and recycles obsolete material.
- A kind of 3. construction method of packaged type bridges according to claim 1 or 2, it is characterised in that:Described in step 3) Reinforcing bar (201) stretches into 1/3rd that bridge pier length is not less than bridge pier height, and the length for stretching out pier coping portion is 200~500mm.
- A kind of 4. construction method of packaged type bridges according to claim 1 or 2, it is characterised in that:Described in step 3) One end that reinforcing bar (201) is stretched out at the top of bridge pier (2) is tapped;In step 6), the reinforcing bar (201) passes through tower crane (6) After bottom plate (601), high-strength nut screws in the screw thread of these reinforcing bar (201) terminations.
- A kind of 5. packaged type bridges that construction method by packaged type bridges described in claim 1 is built up, it is characterised in that:Bag Include bridge floor, two bridge piers (2) and two rubber supports (1);The bridge floor is erected between embankment A and embankment B;Rubber support (1) is installed between the bridge floor and embankment;The bridge Face uses direct puncture bar connecting with bridge pier (2);The bridge floor (1) includes prefabricated bridge layer and asphalt concrete layer (7);The asphalt concrete layer (7) is laid on pre- On bridge floor flaggy processed, and with prefabricated bridge layer tight bond;The prefabricated bridge layer includes the prefabricated bridge (4) that polylith is longitudinally sequentially laid with along bridge;The prefabricated bridge floor Plate (4) either flush;The prefabricated bridge layer also has some groove interfaces (405) along the both sides in bridge deck width direction;Phase Adjacent prefabricated bridge (4) is connected by the inserting of the junction steel plate (3) and groove interface (405);The junction steel plate (3) contiguous prefabricated floorings (4) are fixed as by entirety using the form of high-strength bolt.
- A kind of 6. packaged type bridges according to claim 5, it is characterised in that:The seam shape of contiguous prefabricated floorings (4) Shape is flush joint, rabbet-shaped or zigzag.
- A kind of 7. packaged type bridges according to claim 5 or 6, it is characterised in that:The seam of contiguous prefabricated floorings (4) Middle painting is formed with fluid sealant.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610870798.4A CN106320184B (en) | 2016-09-30 | 2016-09-30 | A kind of unit construction bridge beam construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610870798.4A CN106320184B (en) | 2016-09-30 | 2016-09-30 | A kind of unit construction bridge beam construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106320184A CN106320184A (en) | 2017-01-11 |
CN106320184B true CN106320184B (en) | 2018-05-08 |
Family
ID=57820546
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610870798.4A Active CN106320184B (en) | 2016-09-30 | 2016-09-30 | A kind of unit construction bridge beam construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106320184B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106968161B (en) * | 2017-05-18 | 2018-10-30 | 南京同力建设集团股份有限公司 | A kind of oblique pull foot bridge beam slab and building method |
CN108951430B (en) * | 2018-08-31 | 2021-02-26 | 张跃 | Road and bridge field installation structure and method and crane |
CN110886235B (en) * | 2019-12-21 | 2021-07-06 | 烟台仁晟工程设备有限公司 | Bridge construction method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008115628A (en) * | 2006-11-06 | 2008-05-22 | Ohbayashi Corp | Construction method for elevated structure |
CN201865037U (en) * | 2010-09-29 | 2011-06-15 | 郑州大学 | Assembly type hollow slab bridge transferring force by adopting bracket instead of ribbet |
CN102733299A (en) * | 2012-07-13 | 2012-10-17 | 福州大学 | Novel assembly type steel concrete simple supported slab bridge hinge joint and construction method thereof |
CN104074127A (en) * | 2014-06-30 | 2014-10-01 | 郑州大学 | Assembly type hollow slab bridge and construction method thereof |
CN205259049U (en) * | 2015-11-20 | 2016-05-25 | 中建交通建设集团有限公司 | A assembly type decking for landing stage construction |
-
2016
- 2016-09-30 CN CN201610870798.4A patent/CN106320184B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008115628A (en) * | 2006-11-06 | 2008-05-22 | Ohbayashi Corp | Construction method for elevated structure |
CN201865037U (en) * | 2010-09-29 | 2011-06-15 | 郑州大学 | Assembly type hollow slab bridge transferring force by adopting bracket instead of ribbet |
CN102733299A (en) * | 2012-07-13 | 2012-10-17 | 福州大学 | Novel assembly type steel concrete simple supported slab bridge hinge joint and construction method thereof |
CN104074127A (en) * | 2014-06-30 | 2014-10-01 | 郑州大学 | Assembly type hollow slab bridge and construction method thereof |
CN205259049U (en) * | 2015-11-20 | 2016-05-25 | 中建交通建设集团有限公司 | A assembly type decking for landing stage construction |
Also Published As
Publication number | Publication date |
---|---|
CN106320184A (en) | 2017-01-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104929034B (en) | A modular steel-concrete rapid construction small box girder bridge and its construction method | |
CN109082998A (en) | Integral prefabricated steel plate combination girder construction and construction method | |
CN103306189B (en) | Steel truss-prestressed concrete bridge deck combined bridge girder and construction method thereof | |
CN106337361B (en) | A kind of separate type FRP- concrete-steel combination beam bridge structure and construction method | |
CN107916617B (en) | A kind of spacial special-shaped oblique pull combined bridge of rapid construction three stride continuous and construction method | |
CN108060636B (en) | The construction method of overall assembled composite beam bridge | |
CN104294747A (en) | Double-tower hybrid beam cable-stayed bridge system and construction method thereof | |
CN104652242B (en) | Derrick connecting structure used for reinforcing PSC (Pre-stressed Concrete) continuous box girder bridge and construction method | |
CN105019357B (en) | The installation method of abnormity prefabricated bridge on a kind of arch bridge uncovered lattice girder steel | |
CN108867319A (en) | A kind of steel-UHPC combination beam and construction method for cable-stayed bridge | |
CN104695337A (en) | Self-lifting sliding and turnover construction system and construction method | |
CN106988201A (en) | A kind of double deck girder of suspension bridge structure | |
CN109811633A (en) | A corrugated steel and concrete composite double-curved arch bridge and its manufacturing method | |
CN106320184B (en) | A kind of unit construction bridge beam construction method | |
CN114892552A (en) | Box girder type bridge reconstruction construction method | |
CN103711067A (en) | Transversely assembled corrugated steel web combined box girder with small number of supports and construction method thereof | |
CN106978777A (en) | A kind of make-shift bridge device | |
CN103741577B (en) | A kind of T-shaped beam bridge and construction method thereof that bottom lateral bracing is set | |
CN107245953A (en) | The bent device and crossed construction method of a kind of multilayer bridge structure | |
CN113638304A (en) | Concrete beam type bridge hidden cover beam structure system and construction method thereof | |
CN110106772A (en) | A kind of highway clod wash U-shaped composite beam bridge and its construction method | |
CN102108675B (en) | Bridge deck expansion joint structure | |
CN205257790U (en) | Fixed high -low leg handle portal crane | |
CN107905084B (en) | RPC steel truss combined bridge deck and continuous beam bridge | |
CN103911948B (en) | Be applied to horizontal purlin formula steel work and the construction method thereof of wide concrete rib plate-girder |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |