CN106312279A - Flash butt welding twisted steel butt joint device - Google Patents
Flash butt welding twisted steel butt joint device Download PDFInfo
- Publication number
- CN106312279A CN106312279A CN201610968410.4A CN201610968410A CN106312279A CN 106312279 A CN106312279 A CN 106312279A CN 201610968410 A CN201610968410 A CN 201610968410A CN 106312279 A CN106312279 A CN 106312279A
- Authority
- CN
- China
- Prior art keywords
- branch sleeve
- splice
- flash butt
- clamp
- reinforcing bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K11/00—Resistance welding; Severing by resistance heating
- B23K11/04—Flash butt welding
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K11/00—Resistance welding; Severing by resistance heating
- B23K11/36—Auxiliary equipment
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K37/00—Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
- B23K37/04—Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work
- B23K37/0426—Fixtures for other work
- B23K37/0435—Clamps
- B23K37/0443—Jigs
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Optics & Photonics (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
The invention relates to a flash butt welding twisted steel butt joint device which is mainly used for steel bar butt joint in the field of constructional engineering. The flash butt welding twisted steel butt joint device has reliability in butt joint firmness, is simple in process and has low requirements for workers' skills. The flash butt welding twisted steel butt joint device is mainly composed of a connecting sleeve 1, a pair of fixed pliers 5 and a pair of movable pliers 6, a working table 8 and a flash butt welder. The main working principle of the flash butt welding twisted steel butt joint device is that first a clamp A5 is used to clamp a steel bar on the left side, a steel bar connector on the left side is inserted into a through hole 3 in the left side of the connecting sleeve 1, the left end of the connecting sleeve 1 abuts against the right end of the clamp A5, a steel bar on the right side is inserted into the through hole 3 in the right side of the connecting sleeve 1, a clamp B6 is used to clamp the steel bar on the right side, at the same time, the distance between the left end of the pair of movable pliers 6 and the right end of the connecting sleeve 1 is a value L, the flash butt welder is started, a low-voltage high current of the flash butt welder heats the steel bar connector into a plastic state, and then the pair of movable pliers 6 is pushed, so that the left end of the pair of movable pliers 6 abuts against the right end of the connecting sleeve 1 to finish steel bar butt joint.
Description
Technical field
Present invention is mainly used for building engineering field steel reinforcement abutting joints to use.
Background technology
The connected mode of commonly used flash butt welding, this connected mode is docked at present at building engineering field spiral
Strict to operation technological requirement, the operating technology of workman is required height, it is easy to produce lack of joint penetration, slag inclusion, weld metal
The mass defects such as burning, joint area crackle, these mass defects never allow for main steel bar stress, this steel
Muscle docking mode is the most gradually eliminated in China much areas.
Summary of the invention
Instant invention overcomes drawbacks described above, its docking is solid and reliable, and technique is simple, requires low to the technology of workman;This
Bright mainly it is made up of branch sleeve (1), fixation clamps (5), mobile pincers (6), workbench (8), flash butt welder;Branch sleeve (1)
There is enlarged cavity (2) centre, and both sides have through hole (3), the periphery of through hole (3) to have multiple air discharge duct (7);Fixation clamps (5) and workbench
(8) fixing, fixation clamps (5) and mobile pincers (6) all have wire (9), wire (9) to be connected with the both positive and negative polarity of flash butt welder, fixing
Bar clamp can be handled by pincers (5) and mobile pincers (6);The main operational principle of the present invention is: first by fixation clamps (5) by the left side
Bar clamp handles, then is inserted at the splice on the left side by the left side through hole (3) of branch sleeve (1) and make branch sleeve (1)
Left end withstands the right-hand member of fixation clamps (5), in then the reinforcing bar on the right inserts the through hole (3) on branch sleeve (1) the right and with moving
It is L-value that the bar clamp on the right is handled the distance of the left end simultaneously making mobile pincers (6) right-hand member away from branch sleeve (1) by dynamic pincers (6),
Starting flash butt welder, splice is heated to mecystasis by the low-voltage and high-current of flash butt welder, now heats reinforcing bar
Steam and flue gas that joint produces will be discharged from multiple air discharge ducts (7), then promote mobile pincers (6), make the left end top of mobile pincers (6)
Living the right-hand member of branch sleeve (1), steel reinforcement abutting joints completes;After reinforcing bar is heated to form plasticity, the thrusting action of mobile pincers (6), will mould
The splice pushing tow of sexual state to branch sleeve (1) enlarged cavity (2) in and be crowded with enlarged cavity (2), the splice on both sides
Forming enlarged footing in branch sleeve (1), the reinforcing bar deformed also is crowded with and is made the reinforcing bar on both sides connect by the through hole (3) on both sides simultaneously
Head position is connected sleeve (1) and clamps firmly, no matter at splice axially or radial direction, splice all without
Loosen;The volume assuming enlarged cavity (2) is V, and the radius of reinforcing bar is R, then reinforcing bar is pressed into length L=that enlarged cavity (2) shortens afterwards
V÷∏R2;Reinforcing bar by during action of pulling stress mainly by branch sleeve (1) stress, two splice faces can not be considered
Stressing conditions, accordingly even when there is mass defect and also do not interfere with the joint quality of whole banjo fixing butt jointing in two splice faces;
Need explanation: the left end of mobile pincers (6) is provided with rule;Branch sleeve (1) need to be according to different bar diameter customizations;Adapter sleeve
The medial surface of cylinder (1) scribbles fire-proof insulation paint.
Accompanying drawing explanation
Description of reference numerals: 1-branch sleeve, 2-enlarged cavity, 3-through hole, 4-reinforcing bar, 5-fixation clamps, 6-moves pincers, and 7-arranges
Air drain, 8-workbench, 9-wire.
Fig. 1 is the facade section of the present invention.
Fig. 2 is the facade section after steel reinforcement abutting joints of the present invention.
Fig. 3 is the B-B profile of the present invention.
Fig. 4 is the A-A profile of the present invention.
Fig. 5 is the longitudinal sectional drawing of branch sleeve of the present invention (1).
Detailed description of the invention
Summary of the invention has been described in detail the detailed description of the invention of the present invention, is not repeated herein;Need explanation: see Fig. 3,
The enlarged cavity 2 of branch sleeve 1 refers to the cavity volume beyond through hole 3;The volume of the enlarged cavity 2 of the branch sleeve 1 of different-diameter
Being known, can calculate L-value required during the steel reinforcement abutting joints of different-diameter, L-value is exactly that the left end of mobile pincers 6 is away from connection
The distance of the right-hand member of sleeve 1, can be fabricated to label by the L-value needed for different bar diameter docking and installs in real work
On mobile pincers 6, compare label during operative it is known that L-value;By the medial surface brushing fire-proof insulation of branch sleeve 1
Paint is to make branch sleeve 1 remain in the event of high temperatures with charged splice keep insulation, makes the splice can be just
Often it is heated to mecystasis;Splice is simply heated to mecystasis by the present invention, therefore wants flash butt welding acc power
Ask low.
Claims (1)
1. a twisted steel butt-joint device for flash butt welding, is characterized in that: it mainly by branch sleeve (1), fixation clamps (5),
Mobile pincers (6), workbench (8), flash butt welder composition;Having enlarged cavity (2) in the middle of branch sleeve (1), there is through hole (3) on both sides,
The periphery of through hole (3) has multiple air discharge duct (7);Fixation clamps (5) is fixed with workbench (8), and fixation clamps (5) and mobile pincers (6) are equal
Having wire (9), wire (9) to be connected with the both positive and negative polarity of flash butt welder, reinforcing bar can be clamped by fixation clamps (5) and mobile pincers (6)
Live;The main operational principle of the present invention is: first handled by the bar clamp on the left side by fixation clamps (5), then the left side by branch sleeve (1)
Limit through hole (3) inserts at the splice on the left side and makes the left end of branch sleeve (1) withstand the right-hand member of fixation clamps (5), then will
Clamp (6) and the bar clamp on the right handled make simultaneously in the reinforcing bar on the right inserts the through hole (3) on branch sleeve (1) the right and with moving
The distance of the left end of mobile pincers (6) right-hand member away from branch sleeve (1) is L-value, starts flash butt welder, the low electricity of flash butt welder
Pressing big electric current that splice is heated to mecystasis, steam and flue gas that now heating splice produces will be from multiple aerofluxuss
Groove (7) is discharged, then promotes mobile pincers (6), makes the left end of mobile pincers (6) withstand the right-hand member of branch sleeve (1), and steel reinforcement abutting joints is complete
Become;After reinforcing bar is heated to form plasticity, the thrusting action of mobile pincers (6), by the splice pushing tow of mecystasis to branch sleeve
(1) enlarged cavity (2) is interior and is crowded with enlarged cavity (2), and the splice on both sides forms enlarged footing in branch sleeve (1), simultaneously
The reinforcing bar deformed also is crowded with and is made the splice position on both sides be connected sleeve (1) to clamp firmly by the through hole (3) on both sides
Live, no matter at splice axially or radially, splice is all without loosening;The volume assuming enlarged cavity (2) is V,
The radius of reinforcing bar is R, then reinforcing bar is pressed into the length L=V ÷ ∏ R that enlarged cavity (2) shortens afterwards2;Reinforcing bar is by action of pulling stress
Time mainly by branch sleeve (1) stress, the stressing conditions in two splice faces can not be considered, accordingly even when two reinforcing bars connect
There is mass defect and also do not interfere with the joint quality of whole banjo fixing butt jointing in head;Need explanation: the left end of mobile pincers (6) is provided with
Rule;Branch sleeve (1) need to be according to different bar diameter customizations;The medial surface of branch sleeve (1) scribbles fire-proof insulation paint.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610968410.4A CN106312279A (en) | 2016-11-06 | 2016-11-06 | Flash butt welding twisted steel butt joint device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610968410.4A CN106312279A (en) | 2016-11-06 | 2016-11-06 | Flash butt welding twisted steel butt joint device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106312279A true CN106312279A (en) | 2017-01-11 |
Family
ID=57816694
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610968410.4A Pending CN106312279A (en) | 2016-11-06 | 2016-11-06 | Flash butt welding twisted steel butt joint device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106312279A (en) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000265618A (en) * | 1999-03-12 | 2000-09-26 | Nishimatsu Constr Co Ltd | Molding method for anchoring part of reinforcement, reinforcement, and reinforcement construction method |
CN2618714Y (en) * | 2003-04-28 | 2004-06-02 | 梁满堂 | Auxiliary connector for screw-thread steel welding |
CN1548263A (en) * | 2003-05-15 | 2004-11-24 | 梁满堂 | Gas-protected special steel bar welding method and fixture |
CN201598779U (en) * | 2010-02-05 | 2010-10-06 | 上海建研钢筋连接技术有限公司 | Bar reinforcement connection structure |
JP4589898B2 (en) * | 2006-07-26 | 2010-12-01 | 新日本製鐵株式会社 | Steel strip butt welder |
JP5659965B2 (en) * | 2010-10-14 | 2015-01-28 | 新日鐵住金株式会社 | Flash butt welding method for rail steel |
CN105178517A (en) * | 2015-10-27 | 2015-12-23 | 周桂香 | Upset-head type sleeve mechanical connector for high-strength steel bars and implementation method thereof |
CN105397363A (en) * | 2015-11-26 | 2016-03-16 | 重庆亨尔通冶金新技术股份有限公司 | Butt welding clamp |
CN205271125U (en) * | 2015-09-24 | 2016-06-01 | 嘉善偌德传动设备有限公司 | Reinforcing bar flash butt welding machine |
-
2016
- 2016-11-06 CN CN201610968410.4A patent/CN106312279A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000265618A (en) * | 1999-03-12 | 2000-09-26 | Nishimatsu Constr Co Ltd | Molding method for anchoring part of reinforcement, reinforcement, and reinforcement construction method |
CN2618714Y (en) * | 2003-04-28 | 2004-06-02 | 梁满堂 | Auxiliary connector for screw-thread steel welding |
CN1548263A (en) * | 2003-05-15 | 2004-11-24 | 梁满堂 | Gas-protected special steel bar welding method and fixture |
JP4589898B2 (en) * | 2006-07-26 | 2010-12-01 | 新日本製鐵株式会社 | Steel strip butt welder |
CN201598779U (en) * | 2010-02-05 | 2010-10-06 | 上海建研钢筋连接技术有限公司 | Bar reinforcement connection structure |
JP5659965B2 (en) * | 2010-10-14 | 2015-01-28 | 新日鐵住金株式会社 | Flash butt welding method for rail steel |
CN205271125U (en) * | 2015-09-24 | 2016-06-01 | 嘉善偌德传动设备有限公司 | Reinforcing bar flash butt welding machine |
CN105178517A (en) * | 2015-10-27 | 2015-12-23 | 周桂香 | Upset-head type sleeve mechanical connector for high-strength steel bars and implementation method thereof |
CN105397363A (en) * | 2015-11-26 | 2016-03-16 | 重庆亨尔通冶金新技术股份有限公司 | Butt welding clamp |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20180219345A1 (en) | Sonotrode, device and method for producing a join | |
CN106312279A (en) | Flash butt welding twisted steel butt joint device | |
CN105945507A (en) | Pipeline fixing welding method in building construction | |
CN107081535B (en) | A kind of steel pipe grafting connector improving structural strength | |
CN106181209A (en) | In a kind of construction, movable pipeline fixes welding method | |
CN218798294U (en) | Novel stainless steel product production design device | |
CN106499122A (en) | A kind of spiral pier nose docking facilities | |
ATE557232T1 (en) | PLUG APPARATUS AND METHOD | |
KR101878601B1 (en) | Pipe joint, apparatus for producing the same and method for constructing piping system using the same | |
CN109469262A (en) | A kind of rapid steel reinforcing bar butt joint | |
US2016795A (en) | Device for flaring pipe | |
CN111001976A (en) | Opening aligning device for large-diameter thin-wall pipeline and using method thereof | |
JP5808588B2 (en) | Temporary compression tool for indirect hot wire method | |
KR101060481B1 (en) | A method for manufacturing wedge type pipe joint with metal pipe | |
CN210976345U (en) | Reinforcing steel bar butt joint assembly | |
CN204343454U (en) | A kind of interfacing part of axial cross shape annulus plate docking steel pipe | |
CN204312481U (en) | The interfacing part of a kind of use axial Y shape annulus plate docking steel pipe | |
CN108067578B (en) | Pliers for upsetting bar | |
CN214604103U (en) | Pipe connecting tool | |
CN212105062U (en) | Foot hand tool for building roasting furnace | |
CN110725480B (en) | Reinforcing steel bar butt joint method and reinforcing steel bar butt joint assembly | |
KR102158530B1 (en) | Coupler for repairing PVC pipes and the PVC pipe repairing method using this | |
CN204344595U (en) | The interfacing part of a kind of use axial meter-shape annulus plate docking steel pipe | |
JP7282641B2 (en) | Pressure welding jig for rebar | |
CN214958504U (en) | Chlorinated polyvinyl chloride cable sheath pipe convenient to connect |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170111 |
|
RJ01 | Rejection of invention patent application after publication |