CN109469262A CN201710807263.7A CN201710807263A CN109469262A CN 109469262 A CN109469262 A CN 109469262A CN 201710807263 A CN201710807263 A CN 201710807263A CN 109469262 A CN109469262 A CN 109469262A
Authority
CN
China
Prior art keywords
collet
sleeve
slot
conical surface
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710807263.7A
Other languages
Chinese (zh)
Inventor
沈金钟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710807263.7A priority Critical patent/CN109469262A/en
Publication of CN109469262A publication Critical patent/CN109469262A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements
    • E04C5/163Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction
    • E04C5/165Coaxial connection by means of sleeves
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • E04G21/122Machines for joining reinforcing bars

Abstract

A kind of rapid steel reinforcing bar butt joint, by sleeve, two collets in left and right in sleeve, the through slot and triangle wedge in sleeve middle section are constituted, the sleeve is hollow, sleeve conical surface section including sleeve middle section and the right and left, the all built-in collet of both sides sleeve conical surface section, the sleeve middle section has one to run through slot, the collet is bonded with sleeve lining and the band the bottom of the slope of collet is in through slot, the slot that runs through is the wedging for triangle wedge, the triangle wedge is chock metal construction, there are two can split pawl to what both sides were bent for one end, when triangle wedge wedges through slot, the band the bottom of the slope of two collets is squeezed simultaneously, four collets opening of collet, which is shunk, closes up, the clamping tooth of collet conical surface inner wall stings the end of the reinforcing bar tightly connected, the end docking of two reinforcing bars is got up.It is an advantage of the invention that it is low in cost, structure is simple, quickly reinforcing bar can be attached.

Description

A kind of rapid steel reinforcing bar butt joint
Technical field
The present invention relates to a kind of reinforcing bar fast junction apparatus.
Background technique
Straight screw sleeve now is usually used to the connection of reinforcing bar on building sites or electric welding machine welds.Straight screw sleeve It more often uses relatively, its connection method is exactly will be wait connect end reinforced longitudinal rib and cross rib screw-rolling machine using the method for cutting It peels a part off, is then directly rolled into common straight thread, connected with special straight screw sleeve, form the company of reinforcing bar It connects.This method is still a little complicated, and especially seem when interim small lot processes docking reinforcing bar trouble, if can have one kind Simpler method makes not need to carry bulky process equipment and goes to operate.
Summary of the invention
To achieve the above object, the present invention provides a kind of rapid steel reinforcing bar butt joints, and the butt joint is by sleeve 3, set Two collets 2 in left and right, the through slot in sleeve middle section and triangle wedge 1 are constituted in cylinder, and the sleeve 3 is hollow, including set The sleeve conical surface section 14 in cylinder middle section 15 and the right and left, all built-in collet of both sides sleeve conical surface section, the sleeve middle section 15 have one to run through slot;Through slot entrance 13 and outlet 12 be all on two collet directions of sleeve it is longer, in sleeve Section two sides are shorter;The sleeve middle section diameter is big, diametrically small outside sleeve conical surface section, the collet and place set Cylinder middle portion diameter is big, the collet conical surface 8 is diametrically small outside;The collet has band the bottom of the slope 7, the collet conical surface 8, among collet There is circular hollow 11 to be slightly larger than the size of clamped reinforcing bar, there are four collet opening 9,8 inner wall of the collet conical surface has the collet conical surface 8 Clamping tooth 10, collet is bonded with sleeve lining and the band the bottom of the slope 7 of collet is in through slot;It is above-mentioned through slot be into Mouth large outlet is small, and inside is the wedging for triangle wedge from large to small;The triangle wedge is chock metal small under upper width Construction, looks like a triangle from the side of connector when being inserted into through slot, there is a notch in the wide one end of triangle wedge 5, the other end is sharp-crested there are two that can split pawl 6 to what both sides were bent, this splits pawl for fixed triangle wedge in the position in slot It sets;When triangle wedge wedging through slot, while the band the bottom of the slope of two collets is squeezed, collet is made to be inconjunction with reinforcing bar all to sleeve Outer movement, four collets opening 9 of collet, which is shunk, closes up, and the clamping tooth of collet conical surface inner wall stings the reinforcing bar 4 tightly connected The end docking of two reinforcing bars is got up in end;It also includes using iron that the wedging method of the triangle wedge, which includes with clincher tool, Hammer.
It is an advantage of the invention that it is low in cost, structure is simple, can quickly be attached to reinforcing bar, do not need complicated work Tool and more operations, mitigate some unnecessary labor intensity.
Detailed description of the invention
Schematic diagram after Fig. 1 docking operation wedging triangle wedge of the present invention.
Schematic diagram before Fig. 2 docking operation wedging triangle wedge of the present invention.
Sleeve form schematic diagram Fig. 3 of the invention.
Triangular wedge state schematic diagram Fig. 4 of the invention.
Collet floor map Fig. 5 of the invention.
Collet schematic cross-sectional view Fig. 6 of the invention.
Collet clamping opening schematic diagram Fig. 7 of the invention.
Collet position view before triangle wedge Fig. 8 of the invention is wedged.
Clip position schematic diagram after triangle wedge wedging Fig. 9 of the invention.
Component mark in above-mentioned each attached drawing is respectively as follows: 1 --- triangle wedge, 2 --- collet, 3 --- sleeve, 4 --- The reinforcing bar, the 5 triangle wedge notches, 6 that are connected --- triangle wedge split pawl, 7 --- colleting the bottom of the slope, 8 --- collet conical surface, 9 --- --- collet clamping tooth, 11 are --- empty among collet, 12 --- through slot outlet, 13 --- run through slot for collet opening, 10 Entrance, 14 --- sleeve conical surface section, 15 --- sleeve middle section.
Specific embodiment
A kind of rapid steel reinforcing bar butt joint butt joint of the invention is by two collets 2 in left and right in sleeve 3, sleeve, in sleeve The through slot and triangle wedge 1 of section are constituted, and the construction has required enough robustnesses on material.
Sleeve is built-in with the collet for being close to sleeve lining, the docking that can be very easily used between two steel bar ends. Signified reinforcing bar refers to screw-thread steel in the present invention, but is also not excluded for using to plain bar, square reinforcing bar.As needed, reinforcing bar Size specification have it is several, so that it may be made into the butt joint of several specifications.
Butt joint of the present invention has a sleeve, and the sleeve is hollow, the set including sleeve middle section and the right and left Cylinder conical surface section, all built-in collet of both sides sleeve conical surface section, the sleeve middle section diameter is big, outside sleeve conical surface section diametrically It is small, the collet be also where sleeve middle portion diameter is big, diametrically small outside the collet conical surface.Butt joint sleeve middle section has One run through slot, for the wedging of triangle wedge, the band the bottom of the slope of collet is in through slot, when triangle wedge wedging through slot, Collet in sleeve is inconjunction with reinforcing bar and all moves to the outer of sleeve, and four collets of collet are open to be closed up to contract, collet The clamping tooth of inner wall wales the end for stinging tight connected reinforcing bar.
Mating operation process of the invention: as shown in Figure 1, the end of two reinforcing bars 4 docked is all inserted in collet 2 Empty position, two colleting the bottom of the slope in sleeve 3 can be protruded into through slot.
Again as shown in Fig. 2, the dedicated clincher tool of triangle wedge 1 is wedged through slot, triangle wedge 1 is oblique the band of collet 2 The edge of face bottom toward sleeve 3 pushes away, and just completes the work of this two sections of reinforcing bars 4 of docking.
Clincher tool can be a kind of one end and withstand triangle wedge notch, and one end can be split in pawl crack from triangle wedge to be protruded into simultaneously Toward butt joint both sides pressure a kind of strength pincers or a kind of compression formed punch, the present invention therefrom, can reach keeps triangle wedge complete Wedge the square groove tool just can be used as clincher tool come using.
Illustrate rapid steel reinforcing bar butt joint of the present invention in order to clearer, present embodiments provide structural exploded view, have Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7.
Fig. 3 is position and the sleeve that the hollow space about the sleeve in the present invention, in sleeve includes the collets of left and right two The through slot in middle section.
Butt joint of the present invention includes symmetrical sleeve conical surface section 14, and sleeve middle section 15 is relatively large in diameter, sleeve conical surface section It is diametrically smaller outside 14, it is in the conical surface.Sleeve 3 as shown in the figure at colleting the bottom of the slope can completely through, but in reality In can also not exclusively penetrate through, still there is metal to connect together with sleeve middle section 15 at the inclined-plane of colleting the bottom of the slope, this Sample is unlikely to that sleeve middle section 15 is too thin, can reinforce the intensity of butt joint itself.Two collets penetrate through in following butt joints There is sufficiently large hole that can communicate on groove location, the band the bottom of the slope of collet is just in through slot.
Sleeve middle section 15 has one through slot, preferably square groove, it is also preferred that all through the entrance 13 of slot and outlet 12 It is longer on two collet directions of sleeve, length and width relationship through slot inside each position in shorter in sleeve middle section two sides It is also such.Through slot can also be other shapes.
It is that entrance large outlet is small through slot, inside is that gradually small Form-space exports small, the wedging for triangle wedge.
As shown in figure 4, the wedging of triangle wedge 1 is to withstand the notch 5 of triangle wedge on one side with a special clincher tool, Triangle wedge is split pawl 6 on one side to press toward opposite both sides, when triangle wedge wedging through slot, the band the bottom of the slope of collet is squeezed, makes to press from both sides Head is inconjunction with reinforcing bar and all moves to the outer of sleeve, and four collets opening of collet, which is shunk, closes up, the clamping of collet conical surface inner wall Tooth is waled together with the conical surface section of the end for stinging tight reinforcing bar, reinforcing bar and collet and sleeve.This tool is long handle pliers type, people Work operation, it is fairly simple.When not having to aforementioned clincher tool, is squeezed into triangle wedge with the common iron hammer in building site and pounded and split pawl into triangle wedge 6 is also possible.
Triangle wedge in Fig. 4, the triangle wedge is chock metal construction small under upper width, in insertion through slot Shi Conglian The side of connector looks like a triangle.Triangle wedge wedge body can be flat, and triangle wedge splits the length on pawl top with slightly Length less than through slot is advisable, and it is gradually small from top to bottom that triangle wedge splits pawl top.There is a notch 5 in the wide one end of triangle wedge, should Notch circle is preferably circular, and the notch of other shapes is also possible, as long as helping to maintain clincher tool in triangle wedge Between point on do not shift.The other end of triangle wedge is sharp-crested, and there are two that can make, there are two the pressures that can split to both sides at sharp-crested end Curved splits pawl 6.It can be split with clincher tool and divide curved, compression, triangle wedge can also be squeezed into iron hammer.Triangle wedge splits pawl 6 and is used for Ensure presence of the triangle wedge in through slot and does not generate displacement.
Following about collet of the invention, collet is the cylindrical shape for having opening, and collet is used to clamp the reinforcing bar to be docked End.Collet needs most be described in detail in the present invention, present embodiments provides Fig. 5, Fig. 6, Fig. 7 thus and specially says The floor map of bright collet, collet cross-sectional view, clamping opening schematic diagram.
A following collets 2 is all placed in sleeve, collet is used to clamp reinforcing bar.Preferably, sleeve is circular, accordingly Collet be also rectangular.
Outside collet as shown in Figure 5, the collet 2 in the present invention is that have one section of position on bottom be columnar, side Another section of edge is the cone that becomes smaller toward on edge direction, with sleeve correspondingly, collet and collet sleeve middle portion is straight Diameter is larger, the collet conical surface 8 is diametrically smaller outside, is bonded with sleeve lining.The hollow part of collet is a substantially inside and outside sample ruler It is very little, can be larger with edge, facilitate insertion steel bar end when this is to dock.
Collet has band the bottom of the slope 7, the collet conical surface 8, collet opening 9, and the opening of clamping opening is deeper, and the size of opening has centainly Size Control, collet when closing up is shunk with opening can most clamp reinforcing bar and be advisable.
Empty schematic diagram among collet as shown in Figure 7, as shown, have circular hollow 11 among collet, circular hollow 11 Diameter dimension be subject to the size for being slightly wider than the reinforcing bar to be applicable in.There are four orderly aligned openings 9 on the collet conical surface 8.Four A opening is fixed one of the mode of convenient gathering, had both maintained clamping dynamics, and had also guaranteed the intensity of collet itself, certainly It is also possible to open three or five openings.
Cross-sectional view as shown in FIG. 6,8 inner wall of the collet conical surface have clamping tooth 10, the striped in the clamping tooth preferred levels direction Shape is also possible to the shape in the direction of lines on reinforcing bar.Clamping tooth has enough bite forces after being clamped with reinforcing bar Keep two sections of reinforcing bars of docking not separated, and is the more to draw the more tight.Colleting the bottom of the slope 7 is can to extend into through slot in figure 's.
From the foregoing, the mode of action of collet of the present invention and the effect of setscrew are on the contrary, setscrew is that bottom is swollen Distending, and designed by the present invention it is the clamping tooth and the threaded engagement of the reinforcing bar pressed from both sides of the collet conical surface inner wall.It can use Attached drawing 8 and attached drawing 9 show the variation of rapid abutting joint head ontology docking of the present invention front and back respectively.Before docking, two collets 2 are all covering The penetralia of cylinder 3 can protrude into reinforcing bar in collet, wedge aforementioned triangle wedge, and after docking, collet 2 is extruded to the edge of sleeve 3, Collet, which is locked, bites reinforcing bar.After riveting triangle wedge fitting butt joint two sides can with butt joint one integrated mass, as far as possible Do not generate corner angle and tartar, this can have benefited from the applicability of clincher tool.
Stress smaller part is preferably arranged in steel reinforcement abutting joints head position of the invention, and same Reinforcement should not be arranged two Or more than two connectors.Connector end to reinforcing bar bends up several times that distance a little is no less than bar diameter.
Present invention is mainly used on construction site, bigger efficiency is provided for construction, it helps promotion needs to connect The bonding strength of the reinforcing bar of lengthening.

Claims (2)

1. a kind of rapid steel reinforcing bar butt joint, it is characterized in that: the butt joint is by two collets (2) in left and right, set in sleeve (3), sleeve Cylinder middle section through slot and triangle wedge (1) constitute, the sleeve (3) be it is hollow, including sleeve middle section 15 and left and right two The sleeve conical surface section 14 on side, all built-in collet of both sides sleeve conical surface section;The sleeve middle section 15 has one through slot, passes through The entrance (13) of wears groove and outlet (12) are all longer on two collet directions of sleeve, institutes shorter in sleeve middle section two sides The sleeve middle section diameter stated is big, diametrically small outside sleeve conical surface section;The collet and place sleeve middle portion diameter Greatly, the collet conical surface (8) is diametrically small outside, and the collet has band the bottom of the slope (7), the collet conical surface (8), has circle among collet Hollow (11) are slightly larger than the size of clamped reinforcing bar, and there are four collet opening (9), the collet conical surface (8) inner walls for the collet conical surface (8) Have clamping tooth (10), collet is bonded with sleeve lining and the band the bottom of the slope (7) of collet is in through slot;It is above-mentioned to run through Slot is that entrance large outlet is small, and inside is the wedging for triangle wedge from large to small;The triangle wedge is wedge small under upper width Sub- metal construction, looks like a triangle from the side of connector when being inserted into through slot, and the wide one end of triangle wedge has one A notch (5), the other end are sharp-cresteds there are two that can split pawl (6) to what both sides were bent, this splits pawl and is passing through for fixed triangle wedge Position in wears groove;When triangle wedge wedging through slot, while the band the bottom of the slope of two collets is squeezed, collet is made to be inconjunction with reinforcing bar It is all moved to the outer of sleeve, four collets opening (9) of collet, which is shunk, closes up, and the clamping tooth of collet conical surface inner wall stings company, tight institute The end docking of two reinforcing bars is got up in the end for connecing reinforcing bar (4).
2. a kind of rapid steel reinforcing bar butt joint according to claim 1, it is characterized in that: the wedging method packet of the triangle wedge Including with clincher tool also includes using iron hammer.
CN201710807263.7A 2017-09-08 2017-09-08 A kind of rapid steel reinforcing bar butt joint Pending CN109469262A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710807263.7A CN109469262A (en) 2017-09-08 2017-09-08 A kind of rapid steel reinforcing bar butt joint

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710807263.7A CN109469262A (en) 2017-09-08 2017-09-08 A kind of rapid steel reinforcing bar butt joint

Publications (1)

Publication Number Publication Date
CN109469262A true CN109469262A (en) 2019-03-15

Family

ID=65658172

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710807263.7A Pending CN109469262A (en) 2017-09-08 2017-09-08 A kind of rapid steel reinforcing bar butt joint

Country Status (1)

Country Link
CN (1) CN109469262A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113818633A (en) * 2021-09-22 2021-12-21 湖北垚尚科技有限公司 Connecting method and connecting device for materials with different diameters
EP4180588A1 (en) * 2021-11-11 2023-05-17 Hilti Aktiengesellschaft Rebar coupler with bias pusher

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113818633A (en) * 2021-09-22 2021-12-21 湖北垚尚科技有限公司 Connecting method and connecting device for materials with different diameters
EP4180588A1 (en) * 2021-11-11 2023-05-17 Hilti Aktiengesellschaft Rebar coupler with bias pusher

Similar Documents

Publication Publication Date Title
US3033600A (en) Connectors for jointing wires, rods and the like
KR101102531B1 (en) One touch type quick coupler for reinforcement bar connection
KR100791619B1 (en) Reinforcing bar coupler
KR101720515B1 (en) Coupler for Thread Bar
KR200409526Y1 (en) Threaded sleeve for coupling the threaded deformed reinforcing bars
KR20070054417A (en) Threaded sleeve for coupling the threaded deformed reinforcing bars
CN107023120B (en) Self-locking clamping type steel bar direct-plugging connector
CN109424807B (en) Tongue-and-groove joint
CN109469262A (en) A kind of rapid steel reinforcing bar butt joint
CN103758926A (en) Quick connector for cables
KR101806073B1 (en) One-Touch Type Coupler
KR101541243B1 (en) Reinforcing bar coupler
JP7026362B2 (en) Deformed reinforcing bar connecting metal fittings
CN105350530A (en) Pipe pile connecting method
KR101498662B1 (en) Reinforced seams coupling
CN104019092B (en) A kind of plate quick-connect machanism
US10378687B2 (en) Apparatus and method for coupling
JP2000234333A (en) Vertically connecting device for steel pipe sheet pile
CN106677435A (en) Self-locking clamping pipe type steel bar direct insertion connector
CN204001439U (en) A kind of indented bars connector
KR101676320B1 (en) Structure of pipe connector
HU217512B (en) Fastening plug
CN203702993U (en) Quick connector for cable
CN214604103U (en) Pipe connecting tool
KR102183364B1 (en) Coupling for Reinforcement

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190315