CN106297462A - A kind of for transformer station's dynamic simulation system - Google Patents
A kind of for transformer station's dynamic simulation system Download PDFInfo
- Publication number
- CN106297462A CN106297462A CN201610606748.5A CN201610606748A CN106297462A CN 106297462 A CN106297462 A CN 106297462A CN 201610606748 A CN201610606748 A CN 201610606748A CN 106297462 A CN106297462 A CN 106297462A
- Authority
- CN
- China
- Prior art keywords
- model
- simulation
- transformer station
- main frame
- system model
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G09—EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
- G09B—EDUCATIONAL OR DEMONSTRATION APPLIANCES; APPLIANCES FOR TEACHING, OR COMMUNICATING WITH, THE BLIND, DEAF OR MUTE; MODELS; PLANETARIA; GLOBES; MAPS; DIAGRAMS
- G09B9/00—Simulators for teaching or training purposes
Abstract
The invention discloses a kind of for transformer station's dynamic simulation system, including main frame, main frame is provided with primary system model, electrical secondary system model and motion graphics module, primary system model artwork storehouse integration mode, including substation simulation model, substation simulation model includes the secondary side current model of CT, the secondary side voltage model of PT and on off state model and load tap changer position model, its data leave in real-time data base in real time, electrical secondary system model uses secondary artwork storehouse mode, electrical secondary system model variable data carry out data exchange with the exchange of data in real-time data base by motion graphics module, main frame is connected to actual physical simulator by interface box.The present invention can monitor in time and put in place and monitor accurately, it is achieved that in-circuit emulation, and attended operation personnel carry out Breakdown Maintenance exactly, efficiency is greatly improved, safeguarding that mistake is substantially reduced, the present invention can also realize off-line simulation, has simulating realistic, the more preferable feature of simulated effect.
Description
Technical field
The present invention relates to a kind of for transformer station's dynamic simulation system, belong to transformer station's technical field.
Background technology
The monitoring of existing substation fault and Breakdown Maintenance are difficult to carry out, because of attended operation personnel's professional skill and prison simultaneously
The monitoring accuracy of control equipment is low, and causing trouble Monitoring Data is unreliable, and attended operation personnel's maintenance efficiency is low, safeguards and easily sends out
Raw mistake, causes whole operation of power networks to produce impact.
Summary of the invention
The technical problem to be solved in the present invention is: provides one for transformer station's dynamic simulation system, is imitated by graph model
Genuine pattern, it is possible to Real Time Data of Substation is corresponding, can monitor in time when breaking down and put in place and monitor accurately, safeguard
Operator complete Breakdown Maintenance under monitoring is instructed like clockwork, and efficiency is greatly improved, and safeguards that mistake is substantially reduced, to solve
Certainly problems of the prior art.
The technical scheme that the present invention takes is: a kind of for transformer station's dynamic simulation system, including main frame, arranges in main frame
Once system model, electrical secondary system model and motion graphics module, primary system model artwork storehouse integration mode, including
Substation simulation model, for Simulation Substation ruuning situation, substation simulation model includes the secondary side current model of CT, PT
Secondary side voltage model and on off state model and load tap changer position model, its data leave number in real time in real time in
According in storehouse, electrical secondary system model uses secondary artwork storehouse mode, for the simulation run of each transformer station of Centralized Monitoring, secondary system
System model variable data carry out data exchange with the exchange of data in real-time data base by motion graphics module, and main frame is also connected with
There is interface box, be connected to actual physical simulator or five-preventing system by interface box.
Preferably, above-mentioned interface box includes analog quantity channel, output switch parameter passage and On-off signal passage.
Preferably, above-mentioned main frame is also associated with database server, stores data and include artwork storehouse in database server
Module, artwork library module reads for the figure of primary system model and electrical secondary system model construction.
Preferably, above-mentioned electrical secondary system is also associated with floppy disk platform, is communicated by mailslot agreement.
Preferably, above-mentioned primary system model also includes system model, geographic model and supervision model, system model,
Reason model and supervision model are respectively adopted system diagram, geographical map and watch circle and realize emulation.
Preferably, being additionally provided with electrical network examination emulation module in above-mentioned main frame, and connection has multiple invigilator's terminal, monitoring is eventually
End connects the identity recognizer and recognition of face device logged in for examinee, and identity recognizer is used for identifying that identity card, electrical network are examined
Examination emulation module uses semi-physical simulation device to realize, and it includes Substation Training emulation module, concentrator station Simulated training module
And electrical network Simulated training module.
Beneficial effects of the present invention: compared with prior art, the analogue system of present invention phantom based on artwork storehouse
It is connected to the actual physical simulator of multiple transformer station, the pattern emulated by graph model, it is possible to by Real Time Data of Substation
Corresponding, can monitor in time when breaking down and put in place and monitor accurately, it is achieved that in-circuit emulation, attended operation personnel are in monitoring
Completing Breakdown Maintenance under guidance like clockwork, efficiency is greatly improved, and safeguards that mistake is substantially reduced, the present invention can also realize from
Line emulates, and has simulating realistic, the more preferable feature of simulated effect.
Accompanying drawing explanation
Fig. 1 is the control attachment structure schematic diagram of the present invention.
Detailed description of the invention
Below in conjunction with the accompanying drawings and the present invention is described further by specific embodiment.
Embodiment 1: as it is shown in figure 1, a kind of for transformer station's dynamic simulation system, including main frame, main frame is provided with one
Subsystem model, electrical secondary system model and motion graphics module, primary system model artwork storehouse integration mode, including power transformation
Stand phantom, for Simulation Substation ruuning situation, substation simulation model include the secondary side current model of CT, the two of PT
Secondary side voltage model and on off state model and load tap changer position model, its data leave real-time data base in real time in
In, electrical secondary system model uses secondary artwork storehouse mode, for the simulation run of each transformer station of Centralized Monitoring, electrical secondary system mould
Type variable data carries out data exchange with the exchange of data in real-time data base by motion graphics module, and main frame is also associated with connecing
Mouth case, is connected to actual physical simulator or five-preventing system by interface box.
Preferably, above-mentioned interface box includes analog quantity channel, output switch parameter passage and On-off signal passage, it is possible to real
The fast and reliable transmission of existing Various types of data.
Preferably, above-mentioned main frame is also associated with database server, stores data and include artwork storehouse in database server
Module, artwork library module is read for the figure of primary system model and electrical secondary system model construction, is taken by independent data base
Business device can allow data transmission relatively reliable and quick, and system is run more stable.
Preferably, above-mentioned electrical secondary system is also associated with floppy disk platform, is communicated by mailslot agreement, and floppy disk platform is for whole
The monitoring of individual system.
Preferably, above-mentioned primary system model also includes system model, geographic model and supervision model, system model,
Reason model and supervision model are respectively adopted system diagram, geographical map and watch circle and realize emulation, it is possible to monitoring of environmental and system in real time
Environment.
Preferably, being additionally provided with electrical network examination emulation module in above-mentioned main frame, and connection has multiple invigilator's terminal, monitoring is eventually
End connects the identity recognizer and recognition of face device logged in for examinee, and identity recognizer is used for identifying identity card, it is possible to rise
Taking an examination to examinee's automated log on and prevent the generation impersonated, reducing the cost examining business personnel, electrical network examination emulation module uses
Semi-physical simulation device realizes, and it includes that Substation Training emulation module, concentrator station Simulated training module and electrical network training are imitative
True module, examination emulation is more true, and has certain practical advice, takes an examination significant.
The above, the only detailed description of the invention of the present invention, but protection scope of the present invention is not limited thereto, and any
Those familiar with the art, in the technical scope that the invention discloses, can readily occur in change or replace, should contain
Covering within protection scope of the present invention, therefore, protection scope of the present invention should be as the criterion with described scope of the claims.
Claims (6)
1. one kind is used for transformer station's dynamic simulation system, it is characterised in that: include main frame, main frame is provided with primary system mould
Type, electrical secondary system model and motion graphics module, primary system model artwork storehouse integration mode, including substation simulation mould
Type, for Simulation Substation ruuning situation, substation simulation model includes the secondary side voltage of the secondary side current model of CT, PT
Model and on off state model and load tap changer position model, its data leave in real-time data base in real time, secondary
System model uses secondary artwork storehouse mode, for the simulation run of each transformer station of Centralized Monitoring, electrical secondary system model variable
Data carry out data exchange with the exchange of data in real-time data base by motion graphics module, and main frame is also associated with interface box,
It is connected to actual physical simulator or five-preventing system by interface box.
One the most according to claim 1 is used for transformer station's dynamic simulation system, it is characterised in that: interface box includes simulation
Amount passage, output switch parameter passage and On-off signal passage.
One the most according to claim 1 is used for transformer station's dynamic simulation system, it is characterised in that: main frame is also associated with number
According to storehouse server, database server stores data and includes artwork library module, artwork library module for primary system model and
The figure of electrical secondary system model construction reads.
One the most according to claim 1 is used for transformer station's dynamic simulation system, it is characterised in that electrical secondary system is also connected with
There is floppy disk platform, communicated by mailslot agreement.
One the most according to claim 1 is used for transformer station's dynamic simulation system, it is characterised in that: primary system model is also
Including system model, geographic model and supervision model, system model, geographic model and supervision model be respectively adopted system diagram,
Reason figure and watch circle realize emulation.
One the most according to claim 1 is used for transformer station's dynamic simulation system, it is characterised in that: main frame is additionally provided with
Electrical network examination emulation module, and connect and have multiple invigilator's terminal, monitor terminal connects the identity recognizer logged in for examinee
With recognition of face device, identity recognizer is used for identifying that identity card, electrical network examination emulation module use semi-physical simulation device to realize,
It includes Substation Training emulation module, concentrator station Simulated training module and electrical network Simulated training module.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610606748.5A CN106297462A (en) | 2016-07-29 | 2016-07-29 | A kind of for transformer station's dynamic simulation system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610606748.5A CN106297462A (en) | 2016-07-29 | 2016-07-29 | A kind of for transformer station's dynamic simulation system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106297462A true CN106297462A (en) | 2017-01-04 |
Family
ID=57662780
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610606748.5A Pending CN106297462A (en) | 2016-07-29 | 2016-07-29 | A kind of for transformer station's dynamic simulation system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106297462A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107132772A (en) * | 2017-04-21 | 2017-09-05 | 南方电网科学研究院有限责任公司 | The real-time emulation system and method for alternating current-direct current power network |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05316652A (en) * | 1992-05-07 | 1993-11-26 | Toshiba Corp | Training simulator for electric power system |
CN102663912A (en) * | 2012-03-14 | 2012-09-12 | 福建省电力有限公司培训中心 | Computer simulation systems for integrated dispatching and monitoring of regional power network |
CN103324911A (en) * | 2013-05-30 | 2013-09-25 | 苏州福丰科技有限公司 | Anti-cheating system based on face recognition |
CN103366312A (en) * | 2013-07-15 | 2013-10-23 | 国家电网公司 | Intelligent transformer substation cloud system |
CN103680238A (en) * | 2013-11-04 | 2014-03-26 | 国家电网公司 | Intelligent transformer station mixing simulation training system |
CN105321397A (en) * | 2014-08-05 | 2016-02-10 | 国家电网公司 | Simulation method, device and system |
CN105373655A (en) * | 2015-11-04 | 2016-03-02 | 国网电力科学研究院武汉南瑞有限责任公司 | Method for organically correlating primary and secondary system connection diagrams of intelligent substation |
CN205354423U (en) * | 2015-11-17 | 2016-06-29 | 广州供电局有限公司 | Intelligent substation emulation training system |
-
2016
- 2016-07-29 CN CN201610606748.5A patent/CN106297462A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05316652A (en) * | 1992-05-07 | 1993-11-26 | Toshiba Corp | Training simulator for electric power system |
CN102663912A (en) * | 2012-03-14 | 2012-09-12 | 福建省电力有限公司培训中心 | Computer simulation systems for integrated dispatching and monitoring of regional power network |
CN103324911A (en) * | 2013-05-30 | 2013-09-25 | 苏州福丰科技有限公司 | Anti-cheating system based on face recognition |
CN103366312A (en) * | 2013-07-15 | 2013-10-23 | 国家电网公司 | Intelligent transformer substation cloud system |
CN103680238A (en) * | 2013-11-04 | 2014-03-26 | 国家电网公司 | Intelligent transformer station mixing simulation training system |
CN105321397A (en) * | 2014-08-05 | 2016-02-10 | 国家电网公司 | Simulation method, device and system |
CN105373655A (en) * | 2015-11-04 | 2016-03-02 | 国网电力科学研究院武汉南瑞有限责任公司 | Method for organically correlating primary and secondary system connection diagrams of intelligent substation |
CN205354423U (en) * | 2015-11-17 | 2016-06-29 | 广州供电局有限公司 | Intelligent substation emulation training system |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107132772A (en) * | 2017-04-21 | 2017-09-05 | 南方电网科学研究院有限责任公司 | The real-time emulation system and method for alternating current-direct current power network |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106971663B (en) | A kind of wind power plant analogue system and method | |
CN107369347A (en) | A kind of universal power station Three-dimensional Simulation System | |
CN102054377B (en) | Remote simulation training system for electrical tests of transformer | |
CN103617760B (en) | A kind of power distribution network DTS analogue system and emulation mode thereof | |
CN105894887B (en) | A kind of power distribution network simulation training system and method | |
CN103123758B (en) | A kind of dispatching automation numeral physical mixed simulation training system | |
CN102663912B (en) | Computer simulation systems for integrated dispatching and monitoring of regional power network | |
CN106935089B (en) | Power information acquisition terminal installation training system and method | |
CN103559822A (en) | Substation simulation training system | |
CN108257439A (en) | A kind of distribution automation Training Methodology and analogue system for adapting to various modes | |
CN102831792B (en) | Distribution Network Failure analogue system and emulation mode thereof | |
CN105139714A (en) | Visualized simulation training system and method for electrified railway traction substation | |
CN102831798A (en) | Electrical test training and examination simulation system | |
CN103544857A (en) | Integrated power transformation operation and maintenance training system | |
CN106251033A (en) | A kind of intelligent substation operation management system | |
CN109697903A (en) | A kind of substation relay protection safety practical training method based on VR | |
CN202795855U (en) | Electrical test training and checking simulation system | |
CN202221628U (en) | Simulation system for power grid of hybrid transformer substation | |
CN104091514A (en) | Power grid dispatching personnel training simulation system | |
CN109003500A (en) | A kind of intelligent electrician's practical operation checking system | |
CN107481598A (en) | A kind of emulation training platform of intelligent substation | |
CN104064065A (en) | Distribution network fault simulation analysis training system implementation method | |
CN110930807A (en) | Simulation training system of electric power system | |
CN112216167A (en) | Booster station simulation operation automatic scoring system, method and equipment | |
CN110942698B (en) | Simulation real operation control platform for distribution network uninterrupted operation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170104 |
|
RJ01 | Rejection of invention patent application after publication |