CN106285005A - Constructional column top grout construction method - Google Patents

Constructional column top grout construction method Download PDF

Info

Publication number
CN106285005A
CN106285005A CN201610766812.6A CN201610766812A CN106285005A CN 106285005 A CN106285005 A CN 106285005A CN 201610766812 A CN201610766812 A CN 201610766812A CN 106285005 A CN106285005 A CN 106285005A
Authority
CN
China
Prior art keywords
constructional column
concrete
grouting
column top
constructional
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610766812.6A
Other languages
Chinese (zh)
Other versions
CN106285005B (en
Inventor
王新龙
韩俊
闫捷恒
任午文
王晓亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shanxi Sijian Group Co Ltd
Original Assignee
China Shanxi Sijian Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shanxi Sijian Group Co Ltd filed Critical China Shanxi Sijian Group Co Ltd
Priority to CN201610766812.6A priority Critical patent/CN106285005B/en
Publication of CN106285005A publication Critical patent/CN106285005A/en
Application granted granted Critical
Publication of CN106285005B publication Critical patent/CN106285005B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material

Abstract

The invention belongs to Constructional Col-umn Construction technical field for building, be specifically related to a kind of constructional column top grout construction method.In order to make to be completely embedded at the bottom of constructional column top and beam, give full play to the antihunt action of constructional column, the invention provides a kind of constructional column top grout construction method, it is after concrete beam plate reinforcing bar and model sheetinstallat, before concreting, position the pre-buried coating steel pipe through with constructional column top, constructional column concreting is to when occurring at the bottom of beams of concrete clogging closely knit, pre-buried coating steel pipe is utilized to be in the milk, ensure constructional column top be connected at the bottom of beam closely knit, improve stuffing wall construction quality, and original Constructional Col-umn Construction technological process will not be changed.And its pre-buried coating steel pipe is no less than two, while grouting, available embedded steel tube therein is as excessive slurry pipe, it is ensured that top grouting is fully.

Description

Constructional column top grout construction method
Technical field
The invention belongs to Constructional Col-umn Construction technical field for building, be specifically related to a kind of constructional column top grouting construction side Method.
Background technology
Constructional column is the predetermined portion at masonry house body of wall, by constructional reinforcement, and by placing concrete post after first building a wall The concrete column made of sequence of construction, constructional column, be primarily not and undertake vertical load, but resist shearing, the horizontal stroke such as antidetonation To load.During construction, constructional column will be with collar tie beam grade beam, foundation beam one-piece casting.But traditional constructional column top concrete is adopted Using horn mouth formwork erection, limited by technique, operating condition, top concrete is difficult to ensure that pouring is closely knit, forms sky at the bottom of beam Gap layer, reduces anti seismic efficiency.
Summary of the invention
The present invention, in order to make to be completely embedded at the bottom of constructional column top and beam, gives full play to the antihunt action of constructional column, Jin Erti Supply a kind of constructional column top grout construction method.
The present invention adopts the following technical scheme that
A kind of constructional column top grout construction method, technological process includes beam reinforced steel bar and model sheetinstallat, beam slab concrete successively Pour, constructional column formwork, pour constructional column concrete, it is characterised in that pouring constructional column concrete at the bottom of beams of concrete, going out Now cannot pour filling closely knit time, TOC the leakiness at the bottom of beams of concrete and between constructional column is carried out top filling Slurry, Specific construction process is as follows:
Pre-buried location: after beam reinforced steel bar with model sheetinstallat, before beam slab concreting, uses and executes picture location marking instrument The bed die of constructional column plane bed die diagonal positions smears two anchor points (a) of demarcation with red paint;
Reinforce pre-buried coating steel pipe: be fixed on red paint location by two by the zinc-plated embedded steel tube correspondence of adhesive tape closure upper end Fixing and reserved at some a and with reinforcing bar binding in beams of concrete, an embedded steel tube is Grouting Pipe, and another embedded steel tube is the slurry that overflows Pipe;
Dredging pre-buried pipeline: poured until beams of concrete, after form removable, the reinforcing bar sharp-pointed in one end, constructional column top is inserted Two coating steel pipes that rod dredging is pre-buried;
Being in the milk in top: constructional column formwork occurs and fill constructional column concreting at the bottom of beams of concrete, but cannot clog closely knit Time, carry out constructional column top formwork reinforcement and install, then with grouting equipment to the floor slip casting ipe grout at constructional column top, until The slurry pipe that overflows overflows underflow, and institute's grouting material is identical with the cement mortar ratio pouring constructional column concrete;
Cutting back exposes built-in pipe: cut the embedded steel tube that concrete back exposes, and completes top grouting.
Described picture location marking instrument of executing is bent into U-shaped making by reinforcing bar, and two opening terminations of U-shaped reinforcing bar are at structure The paint application point made on post plane bed die diagonal is anchor point, distance (the opening width of the most U-shaped reinforcing bar between two anchor points Degree) not less than the 1/3 of constructional column catercorner length, when width is less than 1/3, owing to the mobility of serosity limits, office may be caused Portion's grouting is not in place, uncompacted situation occurs.When constructional column cross section is bigger, anchor point (grouting point) quantity also can be set up, Ensure constructional column top be connected at the bottom of beam closely knit.
The described U-shaped bar diameter executing picture location marking instrument is 10 or 10mm.
The top of described zinc-plated embedded steel tube pours end face (upper surface of finished surface) more than 10cm beyond beams of concrete.
The present invention, by after concrete beam plate reinforcing bar and model sheetinstallat, before concreting, positions pre-buried and structure Making the coating steel pipe that capital end is through, constructional column concreting is to when occurring at the bottom of beams of concrete clogging closely knit, available Pre-buried coating steel pipe is in the milk, it is ensured that constructional column top be connected closely knit at the bottom of beam, do not improve stuffing wall construction quality, and not Original Constructional Col-umn Construction technological process can be changed.Its pre-buried coating steel pipe is no less than two, while grouting, can utilize it In embedded steel tube as excessive slurry pipe, it is ensured that top grouting is fully.Location marking instrument, grouting employed in work progress are logical Roads etc. all can be made up of the conventional steel pipe of job site, reinforcing bar, low cost, and manufacturing process is simple, is suitable for promoting the use of.
Accompanying drawing explanation
Fig. 1 is that constructional column built-in pipe positions floor map;
Fig. 2 is the structural representation executing picture location marking instrument;
Fig. 3 is A-A sectional view;
Fig. 4 is the structural representation of through hole mould;
In figure: 1-constructional column, 2-beams of concrete, 3-Grouting Pipe, 4-overflow and starch pipe, 5-constructional column top template, 6-concreting Face, 7-are in the milk position, a-anchor point.
Detailed description of the invention
In conjunction with accompanying drawing, the detailed description of the invention of the present invention is described further:
The technological principle of the present invention is complete at concrete beam plate reinforcing bar and model sheetinstallat, before concreting.Use Shi Huading Bit-identify instrument smears location with red paint on constructional column plane diagonal position bed die.Termination is blocked with adhesive tape again by two Coating steel pipe is fixed at red paint location, and fixes with reinforcing bar binding in beam and reserved.Treat that beam slab concreting completes, mould After plate is removed, the reinforcing bar sharp-pointed in one end, constructional column top is inserted rod and is inserted by pre-buried coating steel pipe.
Fill wall construction post concreting at the bottom of beam, it is impossible to when clogging closely knit, carry out constructional column top formwork reinforcement and prop up If.It is in the milk in one reserved hole of floor at constructional column top with grouting equipment, until another root built-in pipe overflows underflow, cuts Cut back and expose built-in pipe, it is ensured that constructional column top be connected at the bottom of beam closely knit, improve stuffing wall construction quality.
Technological process includes: beam reinforced steel bar and model sheetinstallat → measurements determine constructional column and pre-buried coating steel pipe position → in advance Bury and position → reinforce pre-buried coating steel pipe → beam slab concreting → dredge pre-buried pipeline → constructional column formwork → pour structure Post concrete → top back that is in the milk → cuts exposes built-in pipe.
1. grouting procedure node requirements
The construction node of pre-buried coating steel pipe operation is: concrete beam reinforcing and model sheetinstallat are complete, before concreting.
The construction node of grouting procedure is: constructional column concreting is to after at the bottom of beam.
2. template requirement
For ensureing quality, template should be cleaned out, must not have greasy dirt, the spot hindering paint brushing such as water stain, and beam bottom board Should be smooth.
3. measure and determine constructional column and pre-buried pvc pipe position
And suitably avoid reinforcement location on constructional column diagonal and determine pipe.
4. smear location with red paint at beam bottom board
According to the position determined, use and execute picture location marking instrument, the structure of this instrument as in figure 2 it is shown, long about 1.0m (also Length can be determined according to the actual requirements), when width is less not less than the 1/3(width of constructional column catercorner length, may go out Now grouting cannot be uniform, there is the uncompacted phenomenon in local), dip in appropriate red paint in termination, beam bottom board is smeared location, as Fig. 1.
The most pre-buried coating steel pipe
Two coating steel pipes (DN15 or DN20) beyond deck-molding 10cm are blocked termination, both sides with adhesive tape, the reddest in being inserted into beam Painting area and reinforcing bar fixation, as shown in Figure 3.
6. constructional column formwork, casting concrete are at the bottom of beam
Constructional column formwork, casting concrete are to using traditional handicraft at the bottom of beam.
7. coating steel pipe through hole
The most pre-buried coating steel pipe adhesive tape is blocked by the reinforcing bar (diameter 10 or 12mm) using one end as shown in Figure 4 sharp-pointed Termination punctures through hole.
8. coating steel pipe upper end grouting
It is in the milk (slurry is isostructure concrete proportioning mortar) with a grouting equipment coating steel pipe upper end from which, until from separately Slurry is overflowed in a piece coating steel pipe upper end.
9. cutting back exposes coating steel pipe
Coating steel pipe is exposed with cutting machine cutting back.

Claims (4)

1. a constructional column top grout construction method, technological process includes beam reinforced steel bar and model sheetinstallat, beam slab coagulation successively Soil pours, constructional column formwork, pour constructional column concrete, it is characterised in that pouring constructional column concrete at the bottom of beams of concrete, Appearance cannot pour when clogging closely knit, TOC the leakiness at the bottom of beams of concrete and between constructional column is carried out top Grouting, Specific construction process is as follows:
Pre-buried location: after beam reinforced steel bar with model sheetinstallat, before beam slab concreting, uses and executes picture location marking instrument Two anchor points (a) on the bed die of constructional column plane bed die diagonal positions;
Reinforce pre-buried coating steel pipe: two zinc-plated embedded steel tube correspondences that upper end blocks are fixed on anchor point (a) place and with In beams of concrete, reinforcing bar binding is fixed and reserved, and an embedded steel tube is Grouting Pipe (3), and another embedded steel tube is slurry pipe (4) that overflows;
Dredge pre-buried pipeline: poured until beams of concrete, after form removable, dredged pre-buried two piece coating steel pipe;
Being in the milk in top: constructional column formwork occurs and fill constructional column concreting at the bottom of beams of concrete, but cannot clog closely knit Time, carry out constructional column top formwork reinforcement and install, then be in the milk in the floor Grouting Pipe (3) at constructional column top with grouting equipment, Until overflowing, slurry pipe (4) overflows underflow, and institute's grouting material is identical with the cement mortar ratio pouring constructional column concrete;
Cutting back exposes built-in pipe: cut the embedded steel tube that concrete back exposes, and completes top grouting.
Constructional column top the most according to claim 1 grout construction method, it is characterised in that: described executes picture location mark Instrument is bent into U-shaped making by reinforcing bar, the two opening terminations of U-shaped reinforcing bar paint on constructional column plane bed die diagonal Smearing is some anchor point (a), and the distance between two anchor points (a) is not less than the 1/3 of constructional column catercorner length.
Constructional column top the most according to claim 2 grout construction method, it is characterised in that: described U-shaped picture location of executing is marked The bar diameter of knowledge instrument is 10 or 10mm.
Constructional column top the most according to claim 3 grout construction method, it is characterised in that: described zinc-plated embedded steel tube Top pours more than end face 10cm beyond beams of concrete.
CN201610766812.6A 2016-08-31 2016-08-31 Grout construction method at the top of constructional column Active CN106285005B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610766812.6A CN106285005B (en) 2016-08-31 2016-08-31 Grout construction method at the top of constructional column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610766812.6A CN106285005B (en) 2016-08-31 2016-08-31 Grout construction method at the top of constructional column

Publications (2)

Publication Number Publication Date
CN106285005A true CN106285005A (en) 2017-01-04
CN106285005B CN106285005B (en) 2018-08-21

Family

ID=57675184

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610766812.6A Active CN106285005B (en) 2016-08-31 2016-08-31 Grout construction method at the top of constructional column

Country Status (1)

Country Link
CN (1) CN106285005B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113356408A (en) * 2021-06-15 2021-09-07 浙江德为建材科技股份有限公司 Constructional column structure and pouring method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06146394A (en) * 1992-11-11 1994-05-27 Shimizu Corp Structure of reinforced concrete column and construction method thereof
JPH08105117A (en) * 1994-10-05 1996-04-23 Kumagai Gumi Co Ltd Precast concrete column member
JPH10204996A (en) * 1997-01-24 1998-08-04 Taisei Corp Concrete structure column with filled steel pipe and its method for construction
CN102535849A (en) * 2012-02-15 2012-07-04 中建三局第二建设工程有限责任公司 Constructional column top concreting method
CN103161313A (en) * 2013-03-14 2013-06-19 中国华冶科工集团有限公司 Connection method of main reinforcement of constructional column of infilled wall and framed girder
CN103255921A (en) * 2013-05-07 2013-08-21 中建八局第一建设有限公司青岛分公司 Top pouring method for concrete construction columns

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06146394A (en) * 1992-11-11 1994-05-27 Shimizu Corp Structure of reinforced concrete column and construction method thereof
JPH08105117A (en) * 1994-10-05 1996-04-23 Kumagai Gumi Co Ltd Precast concrete column member
JPH10204996A (en) * 1997-01-24 1998-08-04 Taisei Corp Concrete structure column with filled steel pipe and its method for construction
CN102535849A (en) * 2012-02-15 2012-07-04 中建三局第二建设工程有限责任公司 Constructional column top concreting method
CN103161313A (en) * 2013-03-14 2013-06-19 中国华冶科工集团有限公司 Connection method of main reinforcement of constructional column of infilled wall and framed girder
CN103255921A (en) * 2013-05-07 2013-08-21 中建八局第一建设有限公司青岛分公司 Top pouring method for concrete construction columns

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113356408A (en) * 2021-06-15 2021-09-07 浙江德为建材科技股份有限公司 Constructional column structure and pouring method

Also Published As

Publication number Publication date
CN106285005B (en) 2018-08-21

Similar Documents

Publication Publication Date Title
CN104895092B (en) The method that a kind of interim lattice column of inner support is used as permanent structure post
CN103410332B (en) A kind of concrete hollow block reinforcement wall construction technology
CN108166397B (en) Railway Frame Bridge construction method
CN102937027B (en) A kind of construction method of edge top arch and bottom arch of concrete pouring tunnel
CN103321257A (en) Anti-cracking seepage-proof construction method for ultra-long mass concrete structure basement
CN104060629B (en) The superimposed wall construction method in covered back-digging subway station and portable side wall formwork jumbo
CN109853832A (en) A kind of construction method of filling wall masonry and electrical pre-embedded pipe synchronous construction
CN102758456B (en) Construction method of basement waterproofing projects
CN106320706A (en) Masonry-wall line-pipe, line-groove and line-box burying construction method
CN101255692B (en) Heterotype squeezing-close bottom-enlarging filling pile construction method
CN106812219A (en) Filling wall top stuff up a crack construction method
CN109138215A (en) A kind of construction wall integral construction method
CN107083804B (en) A kind of wall structure column joint bar construction method
CN107447980A (en) A kind of building plastic formwork and its installation method for substituting brick fetal membrane
CN114809029A (en) High cutting slope anchor rod frame beam coupling construction method
CN110374630A (en) A kind of construction method of tunnel vault concrete vibrating
CN109113068A (en) A kind of inverse construction joint structure for building construction of deep basal pit
CN106285005B (en) Grout construction method at the top of constructional column
CN205677235U (en) A kind of prefabricated anti-bank constructing structure applied in toilet
CN108544655A (en) The curved beam prefabricated construction method of curved bridge
CN107905609A (en) Underground people's air defense construction method
CN107989049A (en) A kind of construction method of frame bank protection
CN107299640A (en) A kind of variable cross-section well shaft type ground continuous wall base and its construction method
CN103510537A (en) Construction method combining tower crane foundation and building basement floor
CN206815854U (en) A kind of Height marker for improving the smooth thickness construction first-time qualification rate of cast-in-situ floor

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Wang Xinlong

Inventor after: Hou Xiangdong

Inventor after: Han Jun

Inventor after: Yan Jieheng

Inventor after: Ren Wuwen

Inventor after: Wang Xiaoliang

Inventor before: Wang Xinlong

Inventor before: Han Jun

Inventor before: Yan Jieheng

Inventor before: Ren Wuwen

Inventor before: Wang Xiaoliang

GR01 Patent grant
GR01 Patent grant