CN106245663A - A kind of make-up water pump house cofferdam preventing leaking water engineering construction method along the river - Google Patents

A kind of make-up water pump house cofferdam preventing leaking water engineering construction method along the river Download PDF

Info

Publication number
CN106245663A
CN106245663A CN201610737795.3A CN201610737795A CN106245663A CN 106245663 A CN106245663 A CN 106245663A CN 201610737795 A CN201610737795 A CN 201610737795A CN 106245663 A CN106245663 A CN 106245663A
Authority
CN
China
Prior art keywords
water
foundation ditch
river
cofferdam
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610737795.3A
Other languages
Chinese (zh)
Inventor
黄和伟
黄启江
陈贞南
蒋运良
李昭荣
农宝群
陈洪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baise Hundred Mine Power Generation Co Ltd
Original Assignee
Baise Hundred Mine Power Generation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baise Hundred Mine Power Generation Co Ltd filed Critical Baise Hundred Mine Power Generation Co Ltd
Priority to CN201610737795.3A priority Critical patent/CN106245663A/en
Publication of CN106245663A publication Critical patent/CN106245663A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits

Abstract

The present invention provides a kind of make-up water pump house cofferdam preventing leaking water engineering construction method along the river, belongs to Excavation Construction field.The method is to excavate foundation ditch at neighbouring riverside, construction make-up pump room base component and main part in foundation ditch, mainly include the cofferdam waterstop construction before foundation ditch excavation, use and slow down slope mode and excavate in foundation ditch and foundation ditch mining process the process present invention of infiltration and carry out cofferdam sealing by high-pressure rotary-spray concrete water-seal pile mode, use multi-stage platform to slow down slope mode and excavate foundation ditch, and employing arranges plash and bright for hydrops row extraction mode outside the venue carries out the process of hydrops in foundation ditch mining process, disclosure satisfy that the demand that make-up pump foundations hole is excavated along the river, sealing and dewatering effect are good, and it is short to have the duration, the advantage that engineering cost is low.

Description

A kind of make-up water pump house cofferdam preventing leaking water engineering construction method along the river
[technical field]
The present invention relates to Excavation Construction field, be specifically related to a kind of make-up water pump house cofferdam preventing leaking water engineering along the river Construction method.
[background technology]
When building make-up water pump house, possible addressing is just proximate to riverside or the river bank at water source, in this case, construction Time will increase the working procedure of cofferdam sealing.At present, the foundation ditch that neighbouring water source excavation pit uses drops, sealing construction mode master Want as follows:
1, first setting soil blocking pile part, its effect primarily serves the effect of retaining wall, and form has deposited reinforced concrete pile Or the stake of other form, there is certain space between stake and stake, but soil can be kept off;Then setting water-stop curtain part, its effect is Making the soil solidifying after retaining wall, block the water layer exchange inside and outside foundation ditch, form is probably cement mixing method or densification note Slurry;It is finally to support;Use the method the most long in time limit, and construction costs is high, makes cost bigger.
2, two-stage dewatering well is set between diaphram wall and water source, first uses the outer two-stage dewatering well of foundation ditch to reduce foundation ditch Level of ground water around, carries out construction of diaphragm wall the most again, finally carries out blood pressure lowering in precipitation, excavation of foundation pit, foundation ditch in foundation ditch. Adopting premise in this way is water source and foundation ditch has a certain distance to require (not to be suitable for water source and less deep of foundation ditch distance Base pit engineering), working procedure is more, and well-point pipe is arranged more, and cost is bigger.
Although above two method can meet the fall of deep foundation pit construction, sealing requirement, but, it is higher to construction requirement, Engineering cost is excessive, and the sealing ability of latter is more weak.
[summary of the invention]
The goal of the invention of the present invention is: for the problem of above-mentioned existence, it is provided that a kind of make-up water pump house cofferdam along the river is only Hydraulic Projects construction method, the method for the present invention can be greatly shortened the construction period, and significantly reduce construction cost.
To achieve these goals, the technical solution used in the present invention is as follows:
A kind of make-up water pump house cofferdam preventing leaking water engineering construction method along the river, is to excavate foundation ditch, at foundation ditch at neighbouring riverside Interior construction make-up pump room base component and main part, the cofferdam waterstop construction before excavating including foundation ditch, employing is slowed down Slope mode excavates the process of infiltration in foundation ditch and foundation ditch mining process, particularly as follows:
(1) high-pressure rotary-spray concrete water-seal pile mode is used to form a circle continuous print sealing curtain in the construction of region to be dug surrounding Curtain, the degree of depth of water-stop curtain extend into foundation ditch and presets below bottom excavation face;
(2) use stay the platform of more than two-stage slow down slope digging mode excavate foundation ditch, first in region to be excavated, from The ground of certain distance is not excavated along the river, as first order platform, at first order platform edges to regional center to be excavated Direction is slowed down slope and is excavated, and forms the first gentle slope;After first gentle slope has been excavated, carry out next stage platform successively and next delays Alternately excavating until reaching the bottom that foundation ditch is preset of slope;Wherein, the ratio of slope on each gentle slope is respectively less than 1:1;
(3), during foundation ditch excavates, when infiltration situation occurs, use and plash is set and extracts bright for hydrops row out field Outer mode processes.
More preferably, the stake footpath of described concrete water-seal pile is 500mm, and pile center's spacing is 0.35m, is formed between stake and stake The continuous water-stop curtain of engaged 150mm;Thus play the purpose that foundation pit construction region is carried out water proof.
More preferably, it is double that described concrete water-seal pile backfills part in side near a river and upstream and downstream, and its lap is single cloth Put.Arrange by carrying out high hydraulic pressure part reinforcing, the hydraulic pressure lateral pressure to side slope along the river can not only be reduced, prevent from excavating Deeply, form potential safety hazard, make also to have preferably antiseep effect.
More preferably, described water-stop curtain extend into foundation ditch and presets below bottom excavation face at least 0.5m, the top of water-stop curtain Portion and the vertical dimension at least 2.5 meters of river surface.
More preferably, the cement mortar making described concrete water-seal pile uses the portland cement of PO42.5 level, slurry water ash Ratio is 1:1, and Water glass content presses 3.43% admixture of cement consumption, and cement consumption is 455kg/m3.The cement mortar tool of this proportioning Having solidification fast, intensity is high, the advantage of good waterproof performance, meets the requirement of present invention construction.
More preferably, the width of second level platform is more than 2.5m, in practice of construction two grades of platforms may more than 4 meters, with The movement and the running that meet construction machinery are as the criterion, and the width of platform is the widest, can alleviate the lateral pressure reducing side slope, prevent out Dug deep, formed potential safety hazard, and it also had certain supporting role to water-stop curtain, reduced surrounding subsoil water and river to only The lateral pressure of water curtain.
More preferably, the width of first order platform is more than 2.0m, and principle is with second level platform.
More preferably, described high-pressure rotary-spray concrete water-seal pile uses three tube method churnings.Three tube method churnings are a kind of water, gas blowouts Penetrate, slurry filling stirring mixing jetting method.I.e. make high pressure water and air transverse injection simultaneously with triple injection pipe, and cut Foundation soil body, the climbing power by means of air is got rid of the soil being broken by earth's surface;Simultaneously, another nozzle is by cement mortar low pressure Power injection is injected in ground cut, that stir, makes cement mortar mix with soil and reaches to reinforce purpose.The three tube method suitabilitys are wide, May be used for any soil layer, and it is fast to have construction, the high advantage with low cost of mechanization degree.
In sum, owing to have employed technique scheme, the invention has the beneficial effects as follows: the present invention passes through high-pressure rotary-spray Concrete water-seal pile mode carries out cofferdam sealing, uses multi-stage platform to slow down slope mode and excavates foundation ditch, and at foundation ditch mining process Middle employing arranges plash and bright for hydrops row extraction mode outside the venue carries out the process of hydrops, it is possible to meet make-up pump along the river The demand that foundations hole is excavated, sealing and dewatering effect are good, and have the advantage that the duration is short, engineering cost is low.
[accompanying drawing explanation]
Fig. 1 is the engineering schematic diagram using the method for the present invention to carry out hundred ore deposit power plant for self-supply of group make-up water pump house construction.
Wherein 1-horizontal plane, 2-first order platform, 3-the first gentle slope, 4-second level platform, 5-the second gentle slope, the 6-third level Platform, 7-the 3rd gentle slope, 8-foundation ditch presets bottom, 9-water-seal pile.
[detailed description of the invention]
In order to more clearly express the present invention, below by way of specific embodiment, the invention will be further described.
The present invention provides a kind of make-up water pump house cofferdam preventing leaking water engineering construction method along the river, is to excavate base at neighbouring riverside Hole, construction make-up pump room base component and main part in foundation ditch, the cofferdam waterstop construction before excavating including foundation ditch, Employing is slowed down slope mode and is excavated the process of infiltration in foundation ditch and foundation ditch mining process, particularly as follows:
(1) high-pressure rotary-spray concrete water-seal pile mode is used to form a circle continuous print sealing curtain in the construction of region to be dug surrounding Curtain, the degree of depth of water-stop curtain extend into foundation ditch and presets below bottom excavation face;
(2) use stay the platform of more than two-stage slow down slope digging mode excavate foundation ditch, first in region to be excavated, from The ground of certain distance is not excavated along the river, as first order platform, at first order platform edges to regional center to be excavated Direction is slowed down slope and is excavated, and forms the first gentle slope;After first gentle slope has been excavated, carry out next stage platform and next stage successively Alternately excavating until reaching the bottom that foundation ditch is preset of gentle slope;Wherein, the ratio of slope on each gentle slope is respectively less than 1:1;
(3), during foundation ditch excavates, when infiltration situation occurs, use and plash is set and extracts bright for hydrops row out field Outer mode processes.
As some embodiments of the present invention, the stake footpath of concrete water-seal pile be 500mm or more than, pile center's spacing is 0.35m, forms the continuous water-stop curtain of engaged 150mm between stake and stake.
As some embodiments of the present invention, it is double that concrete water-seal pile backfills part in side near a river and upstream and downstream, its Lap is single layout.
As some embodiments of the present invention, described water-stop curtain extend into foundation ditch and presets below bottom excavation face at least 0.5m, the top of water-stop curtain and the vertical dimension of river surface at least 2.5 meters.
As some embodiments of the present invention, the cement mortar making described concrete water-seal pile uses the silicic acid of PO42.5 level Salt cement, slurry water gray scale is 1:1, and Water glass content presses 3.43% admixture of cement consumption, and cement consumption is 455kg/m3
As some embodiments of the present invention, the width of second level platform is more than 2.5m, two grades of platforms in practice of construction May be as the criterion with the movement and running meeting construction machinery, and the width of platform is the widest more than 4 meters, reduction limit can be alleviated The lateral pressure on slope, prevents from excavating deeply, forms potential safety hazard, and it also has certain supporting role to water-stop curtain, reduces four All subsoil water and the river lateral pressure to water-stop curtain.
As some embodiments of the present invention, the width of first order platform is more than 2.0m.
As some embodiments of the present invention, high-pressure rotary-spray concrete water-seal pile uses three tube method churnings.
Below as a example by the arrangement and method for construction of hundred ore deposit power plant for self-supply of group make-up water pump houses, the present invention is described in further detail Explanation.
Hundred ore deposit power plant for self-supply of group make-up water pump houses are positioned at the west side of power plant's coal yard, near river bank, the Youjiang River.As it is shown in figure 1, Original landforms nature elevation is 111.6m, and substrate absolute altitude is 94.7m, and design foundation ditch floor space is about 553, maximum cutting depth 16.9m, is 100m according to the water level elevation in on-the-spot right river, be equivalent to the substrate absolute altitude of make-up water pump house less than the river bank water surface- 5.3m, so the difficulty of construction of this engineering is the construction of water-retaining cofferdam sealing along the river, owing to soil property situation is drifting sand layer herein And sand pebble layer, subsoil water is abundanter, adds bigger difficulty to the construction of water-retaining cofferdam is invisible.
Embodiment 1
As this engineering uses conventional water-stop curtain way, the i.e. first step to be soil blocking pile parts, its effect primarily serves gear soil The effect of wall, form has the stake of deposited reinforced concrete pile or other form, has certain space, but can keep off between stake and stake Soil.Second step is water-stop curtain part, and its effect is the soil solidifying after retaining wall, blocks the water layer exchange inside and outside foundation ditch, Form is probably cement mixing method or compaction grouting.3rd step is to support.If implementing by this conventional scheme:
1, estimate and need to increase by 100Reinforced concrete revetment pile, the degree of depth about 12m, based on 800 yuan/m of unit price, This soil blocking pile engineering need to invest 960,000 yuan, and implementing this engineering needs the duration 30 days.
2, Part II is to do water-stop curtain, uses slope protection pile+spray mixing pile (high-pressure rotary jet grouting pile) to be collectively forming cut-pff wall Water-stop curtain mode, after arrangement is slope protection pile construction, arranges a spray mixing pile (high-pressure rotary-spray between each two slope protection pile Stake), stir spray spray stake engaged with slope protection pile, formation combination against seepage wall.This engineering estimates increase engineering cost about 1,000,000 Unit, implementing this engineering needs the duration 30 days.
3, earth excavation engineering: after carrying out soil blocking pile and water-stop curtain, can use the digging mode putting abrupt slope, puts the slope gradient By 1:0.6, reduce the excavated volume of the earthwork, the quantities of earth excavation about 20000m3, by 12 yuan/m of unit price3Meter, this engineering is thrown Rate with 240,000 yuan, 5 days durations.
4, earth excavation side slope shotcrete with steel bar nets close, quantities about 2500, by unit price 200 yuan/based on, this side slope is propped up Nurse's journey need to invest 500,000 yuan, 7 days construction periods.
By such scheme, the cofferdam preventing leaking water engineering accumulative investment about 2,700,000 yuan along the river of make-up water pump house, construction period need 72 My god.
Embodiment 2
1, triple-pipe high pressure jet grouting concrete water-seal pile mode is used to form a circle continuous print in the construction of region to be dug surrounding Water-stop curtain, quantities is 500Concrete-pile, pile length about 8.8 meters, pile center's spacing is 0.35m, formed stake with The continuous water-stop curtain of engaged 150mm between Zhuan;The degree of depth of water-stop curtain extend into foundation ditch and presets below bottom excavation face 0.5m, the top of water-stop curtain and the vertical dimension of river surface are 3 meters;Concrete water-seal pile backfills part in side near a river and upstream and downstream For double, its lap is single layout.The cement mortar making described concrete water-seal pile uses the portland cement of PO42.5 level, Slurry water gray scale is 1:1, and Water glass content presses 3.43% admixture of cement consumption, and cement consumption is 455kg/m3.This engineering Needing investment cost 1,000,000 yuan, the duration needs 45 days.
2 as it is shown in figure 1, use the digging mode staying Three-level Platform to slow down slope to excavate foundation ditch, first in region to be excavated Interior, the ground of limit, Lijiang River certain distance is not excavated, and as first order platform 2, the width of first order platform 2 is 2.5m, First order platform 2 edge slows down slope to regional center direction to be excavated and excavates, and forms the first gentle slope 3;First gentle slope 3 is excavated After completing, carry out the excavation of the excavation on second level platform the 4, second gentle slope 5, third level platform the 6, the 3rd gentle slope 7 successively;Finally reach Bottom 8 is preset to foundation ditch;Wherein, the ratio of slope on the first gentle slope 3 is 1:1.5, and the ratio of slope on the second gentle slope 5 and the 3rd gentle slope 7 is 1:1;The width of first order platform 2 is 2m, and the width of second level platform 4 is 3m, and the width of third level platform 6 is 2m.This work The volume of earthwork of journey excavation is about 30000m3, by 12 yuan/m of unit price3Meter, this engineering investment cost 360,000 yuan, the construction period 10 days.
3, during foundation ditch excavates, when infiltration situation occurs, use and plash is set and extracts bright for hydrops row out field Outer mode processes, and this expense is less than 10,000.
By the arrangement and method for construction of embodiment 2, the cofferdam preventing leaking water engineering accumulative investment about 1,370,000 yuan along the river of make-up water pump house, work 55 days phases.
Therefore, using the arrangement and method for construction of the present invention, engineering economy investment cost 1,330,000 yuan, the duration shortens 17 days, obtains bright Aobvious effect, prominent contribution is made in the completion on time for power plant for self-supply's water system.
Described above is the detailed description for the preferable possible embodiments of the present invention, but embodiment is not limited to this Bright patent claim, the equal change completed under the technical spirit suggested by all present invention or modification change, all should belong to In the contained the scope of the claims of the present invention.

Claims (8)

1. make-up water pump house cofferdam, a riverside preventing leaking water engineering construction method, is to excavate foundation ditch, in foundation ditch at neighbouring riverside Construction make-up pump room base component and main part, it is characterised in that include the cofferdam waterstop construction before foundation ditch excavation, Employing is slowed down slope mode and is excavated the process of infiltration in foundation ditch and foundation ditch mining process, particularly as follows:
(1) high-pressure rotary-spray concrete water-seal pile mode is used to form a circle continuous print water-stop curtain in the construction of region to be dug surrounding, The degree of depth of water-stop curtain extend into foundation ditch and presets below bottom excavation face;
(2) digging mode staying the platform of more than two-stage to slow down slope is used to excavate foundation ditch, first in region to be excavated, limit, the Lijiang River The ground of certain distance is not excavated, as first order platform, at first order platform edges to regional center direction to be excavated Slow down slope to excavate, form the first gentle slope;After first gentle slope has been excavated, carry out next stage platform and next gentle slope successively Alternately excavate until reaching the bottom that foundation ditch is preset;Wherein, the ratio of slope on each gentle slope is respectively less than 1:1;
(3), during foundation ditch excavates, when infiltration situation occurs, use and plash is set and bright for hydrops row is extracted out outside the venue Mode processes.
Cofferdam water-stopping method in neighbouring Excavation Process along the river the most according to claim 1, it is characterised in that: described The stake footpath of concrete water-seal pile is 500mm, and pile center's spacing is 0.35m.
Cofferdam water-stopping method in neighbouring Excavation Process along the river the most according to claim 1, it is characterised in that: described It is double that concrete water-seal pile backfills part in side near a river and upstream and downstream, and its lap is single layout.
Cofferdam water-stopping method in neighbouring Excavation Process along the river the most according to claim 1, it is characterised in that: described Water-stop curtain extend into foundation ditch and presets below bottom excavation face at least 0.5m, and the top of water-stop curtain is with the vertical dimension of river surface extremely Few 2.5 meters.
Cofferdam water-stopping method in neighbouring Excavation Process along the river the most according to claim 1, it is characterised in that: make The cement mortar of described concrete water-seal pile uses the portland cement of PO42.5 level, and slurry water gray scale is 1:1, and Water glass content is pressed 3.43% admixture of cement consumption, cement consumption is 455kg/m3
Cofferdam water-stopping method in neighbouring Excavation Process along the river the most according to claim 1, it is characterised in that: foundation ditch During excavation, the width of the second level platform dug is more than 2.5m.
Cofferdam water-stopping method in neighbouring Excavation Process along the river the most according to claim 1, it is characterised in that: first The width of level platform is more than 2.0m.
Cofferdam water-stopping method in neighbouring Excavation Process along the river the most according to claim 1, it is characterised in that: described High-pressure rotary-spray concrete water-seal pile uses three tube method churnings.
CN201610737795.3A 2016-08-26 2016-08-26 A kind of make-up water pump house cofferdam preventing leaking water engineering construction method along the river Pending CN106245663A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610737795.3A CN106245663A (en) 2016-08-26 2016-08-26 A kind of make-up water pump house cofferdam preventing leaking water engineering construction method along the river

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610737795.3A CN106245663A (en) 2016-08-26 2016-08-26 A kind of make-up water pump house cofferdam preventing leaking water engineering construction method along the river

Publications (1)

Publication Number Publication Date
CN106245663A true CN106245663A (en) 2016-12-21

Family

ID=57598361

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610737795.3A Pending CN106245663A (en) 2016-08-26 2016-08-26 A kind of make-up water pump house cofferdam preventing leaking water engineering construction method along the river

Country Status (1)

Country Link
CN (1) CN106245663A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000303467A (en) * 1999-04-19 2000-10-31 Takenaka Komuten Co Ltd Self-sustaining earth retaining wall and self-sustaining earth retaining wall construction method
CN101892668A (en) * 2010-07-30 2010-11-24 中铁四局集团第六工程有限公司 Combined support-excavated geologically solutional deep foundation pit and construction method thereof
CN102011404A (en) * 2010-11-24 2011-04-13 温州中城建设集团有限公司 Pit supporting structure and construction method thereof
CN102561362A (en) * 2011-12-31 2012-07-11 青建集团股份公司 Construction method for foundation pit supporting by dynamic compaction replacement of muddy soil
CN105544576A (en) * 2016-01-20 2016-05-04 山东科技大学 Foundation ditch dewatering and drainage excavation structure and application method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000303467A (en) * 1999-04-19 2000-10-31 Takenaka Komuten Co Ltd Self-sustaining earth retaining wall and self-sustaining earth retaining wall construction method
CN101892668A (en) * 2010-07-30 2010-11-24 中铁四局集团第六工程有限公司 Combined support-excavated geologically solutional deep foundation pit and construction method thereof
CN102011404A (en) * 2010-11-24 2011-04-13 温州中城建设集团有限公司 Pit supporting structure and construction method thereof
CN102561362A (en) * 2011-12-31 2012-07-11 青建集团股份公司 Construction method for foundation pit supporting by dynamic compaction replacement of muddy soil
CN105544576A (en) * 2016-01-20 2016-05-04 山东科技大学 Foundation ditch dewatering and drainage excavation structure and application method

Similar Documents

Publication Publication Date Title
CN107313431B (en) Close on not contour foundation pit method for synchronously constructing
CN103590425B (en) A kind of Peaty soft soil stratum subway station construction technology
CN104131575B (en) A kind of karst height grows the leak stopping water discharge method of the stratum dam foundation
CN102454167A (en) Construction method for large ultra-deep well
CN101914925A (en) Basement by using optimized composite prefabricated arch wall as external wall
CN114016513B (en) Time-sequence-sharing excavation method of complex foundation pit group supporting system
CN110359467A (en) A kind of construction method that base pit engineering high-pressure rotary jet grouting pile is reinforced
CN104674827A (en) Novel totally-closed water stopping system for water-rich stratum foundation pit and construction method of novel totally-closed water stopping system
CN101418569B (en) Optimization complex arch wall combining prefabricated arch leaf, support and major structure
CN110438999A (en) A kind of deep basal pit slope excavation construction method of rich groundwater
CN101775810A (en) Underground water control construction method in foundation pit dewatering project
CN103967504A (en) Supporting structure of tunnel opening of power plant circulating water system and construction method
CN108797618A (en) One kind being used for Urban Underground pipe gallery drainage of foundation pit structure and its construction method
CN102926392A (en) Foundation pit dewatering system and construction method thereof
CN102808627A (en) Underground excavation construction method of steel pipe shed
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN208934002U (en) A kind of barrier wall structure
CN112112657B (en) New construction method for digging and building inclined shaft of coal mine
CN109898556A (en) A kind of underground pipe gallery structure and sunk type construction method
CN109024609A (en) A kind of foundation pit supporting construction and its construction method based on old campshed
CN110185051A (en) Deep narrow excavation water discharge method
CN207828994U (en) It is a kind of draining and recharge constructing structure
CN202370539U (en) Front tunnel face excavated soil pre-reinforcing structure of tunnel
CN203925514U (en) A kind of supporting and protection structure of electric power plant circulating water system tunnel mouth
CN211421139U (en) Shield constructs well crown beam bearing structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161221