CN106245652A - 一种临江深基坑土方开挖的施工方法 - Google Patents
一种临江深基坑土方开挖的施工方法 Download PDFInfo
- Publication number
- CN106245652A CN106245652A CN201610633134.6A CN201610633134A CN106245652A CN 106245652 A CN106245652 A CN 106245652A CN 201610633134 A CN201610633134 A CN 201610633134A CN 106245652 A CN106245652 A CN 106245652A
- Authority
- CN
- China
- Prior art keywords
- construction
- excavation
- hydraulicking
- foundation pit
- mechanical equivalent
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
Abstract
本发明公开一种临江深基坑土方开挖的施工方法,其特征是按以下步骤进行:在临江深基坑工程土方开挖施工过程中,根据深基坑施工现场实际情况,利用机械开挖施工基坑和水力冲挖施工基坑相结合,在采用传统机械开挖施工机械操作空间受限或土方运输车辆通行时间受限时,采用水力冲挖施工基坑,同时水力冲挖施工基坑将土方转化为泥浆,由江边泥浆船通过水路运输的方式将泥浆直接运走。对工程周边道路交通不造成任何影响,且没有运输时间限制。本发明的施工方法应用到建筑工程施工中,能有效提高深基坑工程土方开挖施工效率,且绿色环保,减少土方开挖噪音及扬尘污染,省时省工。
Description
技术领域:
本发明涉及一种临江深基坑土方开挖的施工方法。主要应用于建筑工程中,在临江深基坑土方开挖施工中应用水力冲挖及机械开挖组合技术进行土方开挖的施工方法。
背景技术:
在建筑工程领域中,进行深基坑土方开挖施工时,一般均采用大型土方开挖机械设备进行开挖施工,由土方车辆进行土方外运。但在部分工程施工中,因工程周边条件所限,具有如下不足之处:
1、土方运输车辆通行时间受到严格限制,运输效率低下;
2、深基坑工程基坑内支护形式复杂,土方开挖机械设备操作空间容易受到较大限制。
水力冲挖技术有高效、低成本、节能环保的特点,主要用于河道疏浚、填塘压浸、农田水利等工程,但由于受到土质及地域的影响,应用范围受到一定限制。
发明内容:
本发明针对深基坑土方开挖施工中上述两种施工方法的局限性,综合水力冲挖与机械开挖的长处,解决深基坑工程施工中采用单一土方开挖施工方法时遇到的施工条件受限,效率低下,进度缓慢的问题。而提供一种临江深基坑土方开挖的施工方法。
为实现上述目的,本发明实现的技术方案是:
一种临江深基坑土方开挖的施工方法,其特征是按以下步骤进行:在临江深基坑工程土方开挖施工过程中,根据深基坑施工现场实际情况,利用机械开挖施工基坑和水力冲挖施工基坑相结合,在采用传统机械开挖施工机械操作空间受限或土方运输车辆通行时间受限时,采用水力冲挖施工基坑,同时水力冲挖施工基坑将土方转化为泥浆,由江边泥浆船通过水路运输的方式将泥浆直接运走。
具体步骤为:根据深基坑施工现场实际情况,将便于机械开挖施工的中心区域划分为机械开挖区,不便于机械开挖施工的区域划分为水力冲挖区,机械开挖区与水力冲挖区之间设置缓冲区域,由机械开挖施工的机械开挖表层杂填土及旧有建筑基础,然后布置水力冲挖施工的机械,水力冲挖施工的机械开挖周边水力冲挖区,机械开挖施工的机械开挖区,机械开挖施工以1m为一层,始终保持土方机械开挖面高于土方水力冲挖面1m,若水力冲挖施工先达到预计标高,则机械开挖施工的机械白天将土方转运至水力冲挖区域出土,若机械开挖施工进度快于水力冲挖,则吊运备用泥浆泵及高压水枪至水力冲挖区域现场,增加水力冲挖施工机械,确保机械开挖施工与水力冲挖施工进度接近;在基坑开挖至离基底1m的标高时停止使用水力冲挖施工,全部使用机械开挖施工进行底层土方开挖,最后预留200mm深土方,通过人工清底完成。
本发明的机械开挖受限制的区域、危险系数大的区域等由水力冲挖完成,其余便于机械开挖的区域则由机械开挖完成。在机械开挖设备数量一定的条件下,通过计算机械开挖工作量及水力冲挖工作量,由机械开挖时间来确定水力冲挖时间,保证二者施工进度一致,进而确定水力冲挖设备布置数量。在基坑开挖至离基底1m的标高时停止使用水力冲挖,全部使用机械进行底层土方开挖,最后预留200mm深土方,通过人工清底完成。
本发明首先根据深基坑工程距离周边江河湖海的距离,确定预埋抽水及泥浆排放管道铺设长度。根据深基坑实际情况确定施工分区,将机械开挖施工布置在便于机械开挖操作区域,其余危险系数较大或不便于机械操作区域布置水力冲挖施工设备。水力冲挖始终领先机械开挖1m高度,施工过程中根据施工进度适当调整水力冲挖设备投入。
本发明将机械开挖及水力冲挖的长处结合起来,保证24小时不间断出土,提高了土方出土效率,同时可有效减少土方开挖期间扬尘污染,利于环境保护,减少对周边道路交通的影响,减少大型机械设备投入,对基坑施工中基坑本身及内支撑的安全起到了保护作用。
附图说明:
图1是本发明的临江深基坑土方开挖施工分区图。
图2是本发明的机械开挖表层杂填土及旧有建筑基础示意图。
图3是本发明的水力冲挖施工与机械开挖组合施工示意图。
图4是本发明的道路及路面下预埋泥浆排放管道及抽水管道示意图。
图5是本发明的泥浆船构造示意图。
具体实施方式:
下面结合附图对本发明进行详细说明:
如图1所示,根据深基坑施工现场实际情况,将便于机械开挖施工的中心区域划分为机械开挖区1,不便于机械开挖施工的区域划分为水力冲挖区2。根据基坑面积及开挖深度,计算机械开挖设备数量,布置施工机械,在机械开挖设备数量确定的条件下,通过计算机械开挖工作量及水力冲挖工作量,由机械开挖时间来确定水力冲挖时间,保证二者施工进度一致,进而确定水力冲挖设备布置数量。按图2所示,由机械开挖施工的机械3开挖表层杂填土及旧有建筑基础,然后布置水力冲挖施工的机械。如图3所示,水力冲挖施工的机械4开挖周边水力冲挖区,机械开挖施工的机械3开挖中心机械开挖区。机械开挖施工以1m为一层,始终保持土方机械开挖面高于土方水力冲挖面1m,若水力冲挖施工先达到预计标高,则机械开挖施工的机械白天将土方转运至水力冲挖区域出土,若机械开挖施工进度快于水力冲挖,则吊运备用泥浆泵及高压水枪至水力冲挖区域现场,增加水力冲挖施工机械,确保机械开挖施工与水力冲挖施工进度接近,在基坑开挖至离基底1m的标高时停止使用水力冲挖施工,全部使用机械开挖施工进行底层土方开挖,最后预留200mm深土方,通过人工清底完成。
如图4所示,水力冲挖施工前,应先在路面或地面下埋设管道,管道最上层为C30细石混凝土5,管道7之间铺垫钢板6,管道与钢板之间铺垫细砂8。管道两端分别接软管通至江边和基坑内。通过管道将清水抽至加压水箱加压,高压水枪喷出后开始水力冲挖施工。水泥冲挖产生的泥浆通过将泥浆泵抽取,将泥浆通过排泥管道由基坑内运输至江面上泥浆船中,泥浆船结构如图5,泥浆船由运沙船体12、两块钢板9、若干背楞钢板10、若干圆钢管11组成,在运沙船体12的货舱前后1/5处分别采用两块钢板9隔断,并与运沙船体的船舱焊接固定,保持两块钢板9间距为整个运沙船体货舱的3/5,在每块钢板9背部采用背楞钢板10按横竖间距1m加楞,对背楞钢板10横竖交接处采用圆钢管11支撑,且圆钢管11与运沙船体12的货舱前后侧壁焊接固定。所述的隔离钢板尺寸与运沙船体的货舱截面尺寸一致,根据运沙船体的货舱横截面场定制。所述的钢板的厚度为40mm。所述的背楞钢板厚40mm、宽400mm,所述的圆钢管壁厚8mm。
泥浆船满载运送泥浆至弃土码头,通过绑在泥浆泵上的高压水枪打散泥浆由泥浆泵抽取至岸边的泥浆池,自然风干后,形成可处理渣土。
Claims (2)
1.一种临江深基坑土方开挖的施工方法,其特征是按以下步骤进行:在临江深基坑工程土方开挖施工过程中,根据深基坑施工现场实际情况,利用机械开挖施工基坑和水力冲挖施工基坑相结合,在采用传统机械开挖施工机械操作空间受限或土方运输车辆通行时间受限时,采用水力冲挖施工基坑,同时水力冲挖施工基坑将土方转化为泥浆,由江边泥浆船通过水路运输的方式将泥浆直接运走。
2.根据权利要求1所述临江深基坑土方开挖的施工方法,其特征在于具体步骤为:根据深基坑施工现场实际情况,将便于机械开挖施工的中心区域划分为机械开挖区,不便于机械开挖施工的区域划分为水力冲挖区,机械开挖区与水力冲挖区之间设置缓冲区域,由机械开挖施工的机械开挖表层杂填土及旧有建筑基础,然后布置水力冲挖施工的机械,水力冲挖施工的机械开挖周边水力冲挖区,机械开挖施工的机械开挖区,机械开挖施工以1m为一层,始终保持土方机械开挖面高于土方水力冲挖面1m,若水力冲挖施工先达到预计标高,则机械开挖施工的机械白天将土方转运至水力冲挖区域出土,若机械开挖施工进度快于水力冲挖,则吊运备用泥浆泵及高压水枪至水力冲挖区域现场,增加水力冲挖施工机械,确保机械开挖施工与水力冲挖施工进度接近;在基坑开挖至离基底1m的标高时停止使用水力冲挖施工,全部使用机械开挖施工进行底层土方开挖,最后预留200mm深土方,通过人工清底完成。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610633134.6A CN106245652B (zh) | 2016-08-04 | 2016-08-04 | 一种临江深基坑土方开挖的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610633134.6A CN106245652B (zh) | 2016-08-04 | 2016-08-04 | 一种临江深基坑土方开挖的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106245652A true CN106245652A (zh) | 2016-12-21 |
CN106245652B CN106245652B (zh) | 2018-02-23 |
Family
ID=58077639
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610633134.6A Active CN106245652B (zh) | 2016-08-04 | 2016-08-04 | 一种临江深基坑土方开挖的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106245652B (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106988345A (zh) * | 2017-04-01 | 2017-07-28 | 武汉科技大学 | 一种逆作法施工基坑的开挖方法 |
CN107237331A (zh) * | 2017-06-14 | 2017-10-10 | 中铁第四勘察设计院集团有限公司 | 一种利用水压力支护的基坑修建方法 |
CN107254879A (zh) * | 2017-07-01 | 2017-10-17 | 温州振华建设有限公司 | 一种建筑施工地基开挖及施工方法 |
CN111125863A (zh) * | 2019-09-30 | 2020-05-08 | 南京吉欧地下空间科技有限公司 | 一种淤泥质土的水力冲挖制浆配比方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102605791A (zh) * | 2012-04-12 | 2012-07-25 | 中建三局第三建设工程有限责任公司 | 软土地基中土方开挖方法 |
CN103615010A (zh) * | 2013-12-03 | 2014-03-05 | 明业建设集团有限公司 | 一种利用水流冲刷挖运深基坑土方的施工方法 |
JP5868352B2 (ja) * | 2013-06-10 | 2016-02-24 | 旭化成ジオテック株式会社 | 法面に道路を敷設する方法 |
CN105804119A (zh) * | 2016-03-24 | 2016-07-27 | 张迈 | 一桩二用地下廊道结构及其施工方法 |
-
2016
- 2016-08-04 CN CN201610633134.6A patent/CN106245652B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102605791A (zh) * | 2012-04-12 | 2012-07-25 | 中建三局第三建设工程有限责任公司 | 软土地基中土方开挖方法 |
JP5868352B2 (ja) * | 2013-06-10 | 2016-02-24 | 旭化成ジオテック株式会社 | 法面に道路を敷設する方法 |
CN103615010A (zh) * | 2013-12-03 | 2014-03-05 | 明业建设集团有限公司 | 一种利用水流冲刷挖运深基坑土方的施工方法 |
CN105804119A (zh) * | 2016-03-24 | 2016-07-27 | 张迈 | 一桩二用地下廊道结构及其施工方法 |
Non-Patent Citations (1)
Title |
---|
张友春: "近海(地区)特大深基坑支护设计与施工方法研究", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106988345A (zh) * | 2017-04-01 | 2017-07-28 | 武汉科技大学 | 一种逆作法施工基坑的开挖方法 |
CN107237331A (zh) * | 2017-06-14 | 2017-10-10 | 中铁第四勘察设计院集团有限公司 | 一种利用水压力支护的基坑修建方法 |
CN107254879A (zh) * | 2017-07-01 | 2017-10-17 | 温州振华建设有限公司 | 一种建筑施工地基开挖及施工方法 |
CN111125863A (zh) * | 2019-09-30 | 2020-05-08 | 南京吉欧地下空间科技有限公司 | 一种淤泥质土的水力冲挖制浆配比方法 |
CN111125863B (zh) * | 2019-09-30 | 2023-07-14 | 南京吉欧地下空间科技有限公司 | 一种淤泥质土的水力冲挖制浆配比方法 |
Also Published As
Publication number | Publication date |
---|---|
CN106245652B (zh) | 2018-02-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101315139B (zh) | 一种过河管沉管施工工艺 | |
CN105672195B (zh) | 一种城市生态河道水下绞吸式清淤施工工法 | |
CN102535474B (zh) | 一种深基坑挖土的施工方法 | |
CN102720140B (zh) | 大跨度预应力砼连续梁深水桥墩施工工艺 | |
CN106245652B (zh) | 一种临江深基坑土方开挖的施工方法 | |
CN101775821B (zh) | 逆作法施工土方垂直运输装置及方法 | |
CN101225656B (zh) | 超软弱土浅表层快速加固方法 | |
CN111236957B (zh) | 机械顶管施工工艺 | |
CN109113020B (zh) | 一种海港防波堤结构及其施工方法 | |
CN103615010A (zh) | 一种利用水流冲刷挖运深基坑土方的施工方法 | |
CN109780325A (zh) | 一种水厂取水隧道水下管道安装方法 | |
CN104762982B (zh) | 一种富水红砂岩地质地下水位控制的施工方法 | |
CN108457277A (zh) | 一种大范围深厚淤泥开挖施工方法 | |
CN102561379A (zh) | 一种新型桥梁设置基础及其施工方法 | |
CN106381878B (zh) | 双层钢板桩土芯组合围堰环保拆除施工方法 | |
CN102561454B (zh) | 顶管垂直取水方法 | |
CN101509265B (zh) | 软弱地基场地牵引式推土机平整法及其牵引式推土机 | |
CN115823351A (zh) | 一种浅滩段海底管道安装方法及安装参数设计方法 | |
CN204510181U (zh) | 一种浅水区钻孔平台 | |
CN215715515U (zh) | 不良地质条件下市政管网施工支护一体化结构 | |
CN106988345A (zh) | 一种逆作法施工基坑的开挖方法 | |
CN110552360A (zh) | 一种双排钢管桩围堰施工方法 | |
CN2679245Y (zh) | 管道穿越河流水下挖沟装置 | |
Yavuz | Istanbul (Bosphorus) immersed tube tunnel and survey works | |
Usamaa et al. | Comparative Analysis of Underground & Underwater Tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |