CN2679245Y - 管道穿越河流水下挖沟装置 - Google Patents
管道穿越河流水下挖沟装置 Download PDFInfo
- Publication number
- CN2679245Y CN2679245Y CN 200420038212 CN200420038212U CN2679245Y CN 2679245 Y CN2679245 Y CN 2679245Y CN 200420038212 CN200420038212 CN 200420038212 CN 200420038212 U CN200420038212 U CN 200420038212U CN 2679245 Y CN2679245 Y CN 2679245Y
- Authority
- CN
- China
- Prior art keywords
- buoyancy tank
- river
- float tank
- pipeline
- under water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Revetment (AREA)
Abstract
本实用新型是一种管道穿越河流水下挖沟装置,属特殊用途的管沟挖掘机械。其特征是长臂单斗挖掘机稳固在浮箱上,挖掘机的履带轮底下有防滑板。四只地锚固定在河流的两岸上,每岸两只。四根钢丝绳的两端各有一端系在浮箱上,另一端系在地锚上。浮箱由四只小浮箱和20多个联接组件组装而成,联接组件均布在浮箱的上、下两面。每只小浮箱的内腔都焊上若干斜拉加强筋。浮箱的前后边沿各焊上两只用来穿系钢丝绳和绳鼻。该装置在西气东输管道工程穿越河流水下挖沟中试用效果良好,挖沟效率较高,水下管沟达到设计要求。搬迁、就位和拆装都比较方便,施工操作安全可靠。其浮箱还可用于驳载或水上运输施工设备、器材或钢管等。
Description
(一)技术领域
本实用新型涉及到特殊用途的挖掘机或疏浚机,具体而言是管道穿越河流水下挖沟装置。
(二)背景技术
铺设地下管道,特别是铺设大中口径地下油、气长输管道,在旱地上挖管沟已有多种专用设备。当管道穿越河流或水塘时,却没有水下挖沟专用设备。我公司施工的西气东输管道工程第26标段主干线68公里,直径1.016米,壁厚26.2毫米,工作压力10MPa,地处无锡、苏州江南水网区域,江河纵横,池塘密布,要穿越河流域90多条,其中通航河流8条,大小水塘102个,水下挖沟成为施工中的技术难题之一。我公司自行研制的“驳载式滩海管沟挖掘机”(专利号95110332.6)和“驳载托撬式滩海挖沟装置”(专利号96116100.0)只能用于宽阔的滩海区域。“江河挖泥船”(专利号98250388)只能用于江河挖泥清淤。都不能直接使用。
(三)发明内容
本实用新型的目的就在于借鉴上述己有技术的部分技术特点和施工应用经验,独辟蹊径,创新研制一种与众不同的管道穿越河流水下挖沟装置,解决水下挖沟技术难题。
上述目的是由下述技术方案实现的:
该水下挖沟装置包括浮箱、长臂单斗挖掘机、钢丝绳、地锚和防滑板。其特征是挖掘机稳固在浮箱上,挖掘机的履带轮底下有防滑板,四只地锚固定到河流的两岸上,每岸上两只,四根钢丝绳的两端各有一端系在浮箱上,另一端系在地锚上。浮箱由四只小浮箱和20多个联接组件组装而成,联接组件均布在浮箱的上、下两面。每只小浮箱的内腔都焊上若干斜拉加强筋,确保浮箱有足够的结构强度和刚性。浮箱的前、后上边沿各焊上两只用来穿系钢丝绳绳鼻。
上述水下挖沟装置中组成大浮箱的每个小浮箱尺寸为12×2.5×1.5(长×宽×高)米,用钢板焊成。其内腔的斜拉加强筋采用槽钢、角钢或钢管。大浮箱总载重量70吨以上。
上述水下挖沟装置中的浮箱联接组件由三块厚钢板和一根销轴组成。其中两块厚钢板焊接在同一只小浮箱边沿上,夹在两块厚钢板中间的一块厚钢板焊接在另一只小浮箱边沿上,销轴穿插在三块厚钢板中部的孔中。
上述水下挖沟装置中的钢丝绳可用漂浮缆替代,地锚可用重型施工设备替代。
本实用新型提供的水下挖沟装置,在西气东输管道工程江南水网地区河流穿越施工中试用效果很好,挖沟效率较高,水下管沟质量达到设计要求。搬迁、就位和拆装比较方便,施工操作安全可靠。其中的大浮箱还可用于驳载或水上运输施工设备、器材或钢管等。
(四)附图说明
附图1是本实用新型的组成及水下挖沟作业示意图。
附图2是其浮箱结构组装俯视图。
附图3是浮箱联接组件的结构组装俯视图。
(五)具体实施方式
结合附图说明一个实施例:
由图1所示,该水下挖沟装置包括浮箱1、长臂单斗挖掘机2、钢丝绳(或漂浮缆)3、地锚4和防滑板5。挖掘机2稳固在浮箱1上,挖机2的履带轮底下有防滑板5。四只地锚4固定在河流A的两岸B上。四根钢丝绳3的两端各有一端系在浮箱1上,另一端系在地锚4上。
由图2所示,浮箱1由四只小浮箱1.1~1.4和20多个联接组件6组装而成。联接组件6均布在浮箱1的上、下两面。四只小浮箱的内腔都焊上若干斜拉加强筋(图中未画出),以保证浮箱1有足够的结构强度和刚性。浮箱1的前、后上边沿各焊上两只用来穿系钢丝绳3的绳鼻7。
由图3所示,浮箱1的联接组件6由三块厚钢板6.2、6.3和销轴6.1组成。其中两块厚钢板6.3焊接在同一只小浮箱1.3的边沿上,夹在两块厚钢板1.3中间的厚钢板6.2焊接在另一只小浮箱1.2的边沿上。销轴6穿插在三块厚钢板中部的孔中。
该水下挖沟装置的操作过程是:先将四只小浮箱1.1~1.4运送到河流A中,按图2所示进行组装,成为一只大浮箱1,并靠近河岸B。搭上撬板,长臂单斗挖掘机2开到浮箱1上,并用防滑板5加以稳固。固定好两岸地锚4,系好钢丝绳3。从河流A的岸边开始,根据两岸已插好的标志旗,沿着管沟的中心线,利用浮箱1上的长臂单斗挖掘机2(臂长18米)开挖水下管沟。在同一个位置挖沟成形,由潜水员配合随时对管沟进行检验,其深度、宽度等达到设计要求后,再调整地锚4使钢丝绳3牵引浮箱1移动到下个位置,继续开挖水下管沟。依次类推,直到整条水下管沟挖成,并检验合格为止。挖出的河泥靠近两岸的直接放置在岸上,离岸较远时放在小形运泥船上运走,或随时撒布在离管沟较远处,但不能形成水下小丘影响航运。管沟回填时还要用岸上存放的河泥。
Claims (4)
1.一种管道穿越河流水下挖沟装置,包括浮箱、长臂单斗挖掘机、钢丝绳、地锚和防滑板,其特征是挖掘机(2)稳固在浮箱(1)上,挖掘机(2)的履带轮底下有防滑板(5),四只地锚(4)固定在河流(A)的两岸(B)上,每岸两只,四根钢丝绳3的两端各有一端系在浮箱(1)上,另一端系在地锚(4)上,浮箱(1)由四只小浮箱1.1~1.4和20多个联接组件(6)组装而成,联接组件(6)均布在浮箱(1)的上、下两面,每只小浮箱的内腔都焊上若干斜拉加强筋,浮箱(1)的前、后上边沿各焊上两只用来穿系钢丝绳(3)的绳鼻(7)。
2.根据权利要求1所述的管道穿越河流水下挖沟装置,其特征是组成大浮箱(1)的每个小浮箱1.1~1.4尺寸为12×2.5×1.5(长×宽×高)米,用钢板焊成,其内腔的斜拉加强筋采用槽钢、角钢或钢管,大浮箱(1)总载重量70吨以上。
3.根据权利要求1所述的管道穿越河流水下挖沟装置,其特征是浮箱联接组件(6)由三块厚钢板(6.2)、(6.3)和一根销轴(6.1)组成,其中两块厚钢板(6.3)焊接在同一只小浮箱(1.3)边沿上,夹在两块厚钢板(1.3)中间的一块厚钢板(1.2)焊接在另一只小浮箱(1.2)边沿上,销轴(6.1)穿插在三块厚钢板中部的孔中。
4.根据权利要求1所述的管道穿越河流水下挖沟装置,其特征是钢丝绳(3)可用漂浮缆替代,地锚(4)可用重型施工设备替代。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200420038212 CN2679245Y (zh) | 2004-01-30 | 2004-01-30 | 管道穿越河流水下挖沟装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200420038212 CN2679245Y (zh) | 2004-01-30 | 2004-01-30 | 管道穿越河流水下挖沟装置 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2679245Y true CN2679245Y (zh) | 2005-02-16 |
Family
ID=34583907
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 200420038212 Expired - Fee Related CN2679245Y (zh) | 2004-01-30 | 2004-01-30 | 管道穿越河流水下挖沟装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2679245Y (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102700686A (zh) * | 2012-05-24 | 2012-10-03 | 中铁十三局集团第五工程有限公司 | 一种用于过江施工的箱式浮船及其施工工艺 |
CN104843147A (zh) * | 2014-02-13 | 2015-08-19 | 黑龙江省水利科学研究院 | 钢索导向、定位抽砂船水下开挖系统构成 |
CN104988946A (zh) * | 2015-07-03 | 2015-10-21 | 中国十七冶集团有限公司 | 一种跨河水中桥墩基础施工平台操作方法 |
-
2004
- 2004-01-30 CN CN 200420038212 patent/CN2679245Y/zh not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102700686A (zh) * | 2012-05-24 | 2012-10-03 | 中铁十三局集团第五工程有限公司 | 一种用于过江施工的箱式浮船及其施工工艺 |
CN102700686B (zh) * | 2012-05-24 | 2015-09-30 | 中铁建大桥工程局集团第五工程有限公司 | 一种用于过江施工的箱式浮船及其施工工艺 |
CN104843147A (zh) * | 2014-02-13 | 2015-08-19 | 黑龙江省水利科学研究院 | 钢索导向、定位抽砂船水下开挖系统构成 |
CN104988946A (zh) * | 2015-07-03 | 2015-10-21 | 中国十七冶集团有限公司 | 一种跨河水中桥墩基础施工平台操作方法 |
CN104988946B (zh) * | 2015-07-03 | 2017-01-11 | 中国十七冶集团有限公司 | 一种跨河水中桥墩基础施工平台操作方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN1256531C (zh) | 管道穿越河流施工方法 | |
CN105672195B (zh) | 一种城市生态河道水下绞吸式清淤施工工法 | |
CN102605697A (zh) | 软土地基路堤吹填砂施工方法 | |
CN109137943B (zh) | 一种围填海的土方填筑施工工艺 | |
CN106245652B (zh) | 一种临江深基坑土方开挖的施工方法 | |
CN202969343U (zh) | 一种浓海水排海的扩散装置 | |
CN108532546B (zh) | 一种海港港池、航道逆序开挖的方法 | |
CN101929162B (zh) | 三栖式滩涂土方筑堤机施工方法 | |
CN112253847B (zh) | 一种砂地质水网地区管道施工方法 | |
CN2679245Y (zh) | 管道穿越河流水下挖沟装置 | |
CN201580547U (zh) | 适用于水面挖掘作业的浮箱 | |
CN102434719A (zh) | 一种分层开挖沉管施工工艺 | |
CN206143774U (zh) | 可拼装趸船水上作业平台 | |
CN201268856Y (zh) | 潜水挖沟机 | |
CN1262779C (zh) | 聚乙烯管道穿越滩涂与浅水河道的施工方法 | |
CN114960890B (zh) | 近海排水口的施工方法 | |
CN2911015Y (zh) | 潜水隧道 | |
Kurbonshoeva | Pipeline shore crossing approach in the arctic conditions | |
Grant et al. | Design of an outfall | |
Vercruysse et al. | Landfall and shore approach of the new Langeled pipeline at Easington, UK | |
Jin et al. | Zhoushan City Mainland Water Diversion Phase III Project Key Technologies of Cross-sea Pipeline Laying Construction | |
CN114923032A (zh) | 一种大直径长距离穿河管道整体安装的施工方法 | |
TW201903255A (zh) | 深層海洋水引水裝置、深層海洋水引水管道及其系統和建構之方法,以及藉由其汲取深層海洋水之引水方法 | |
TWM513231U (zh) | 深層海洋水引水隧道及其引水隧道系統、深層海洋水引水隧道與引水管道之混合系統、以及深層海洋水引水管道及其系統 | |
CN201686968U (zh) | 一种管型可调节式泄水口 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C19 | Lapse of patent right due to non-payment of the annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |