CN106238465B - A kind of preparation method of PH stainless steel seamless steel pipe - Google Patents

A kind of preparation method of PH stainless steel seamless steel pipe Download PDF

Info

Publication number
CN106238465B
CN106238465B CN201610654968.5A CN201610654968A CN106238465B CN 106238465 B CN106238465 B CN 106238465B CN 201610654968 A CN201610654968 A CN 201610654968A CN 106238465 B CN106238465 B CN 106238465B
Authority
CN
China
Prior art keywords
stainless steel
preparation
pipe
steel pipe
rolling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610654968.5A
Other languages
Chinese (zh)
Other versions
CN106238465A (en
Inventor
鄢勇
尹人洁
张涛
童宗圣
王婀娜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pangang Group Chengdu Steel and Vanadium Co Ltd
Original Assignee
Pangang Group Chengdu Steel and Vanadium Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pangang Group Chengdu Steel and Vanadium Co Ltd filed Critical Pangang Group Chengdu Steel and Vanadium Co Ltd
Priority to CN201610654968.5A priority Critical patent/CN106238465B/en
Publication of CN106238465A publication Critical patent/CN106238465A/en
Application granted granted Critical
Publication of CN106238465B publication Critical patent/CN106238465B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B19/00Tube-rolling by rollers arranged outside the work and having their axes not perpendicular to the axis of the work
    • B21B19/02Tube-rolling by rollers arranged outside the work and having their axes not perpendicular to the axis of the work the axes of the rollers being arranged essentially diagonally to the axis of the work, e.g. "cross" tube-rolling ; Diescher mills, Stiefel disc piercers or Stiefel rotary piercers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21BROLLING OF METAL
    • B21B19/00Tube-rolling by rollers arranged outside the work and having their axes not perpendicular to the axis of the work
    • B21B19/02Tube-rolling by rollers arranged outside the work and having their axes not perpendicular to the axis of the work the axes of the rollers being arranged essentially diagonally to the axis of the work, e.g. "cross" tube-rolling ; Diescher mills, Stiefel disc piercers or Stiefel rotary piercers
    • B21B19/04Rolling basic material of solid, i.e. non-hollow, structure; Piercing, e.g. rotary piercing mills

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Heat Treatment Of Steel (AREA)

Abstract

The invention belongs to steel pipe rolling technical fields, and in particular to a kind of preparation method of PH stainless steel seamless steel pipe.Preparation method of the present invention, comprising the following steps: a, annular stove heating: heating temperature is 1140~1160 DEG C;B, punch is perforated: using micro- expanding form perforation;C, hot rolling: A-R precision Tube Rolling Train tube rolling is used;D, sizing to get.The present invention can also preferably share perforation with rolling load, guarantee that production process can be gone on smoothly;By parameter adjusting and optimizing, guarantee that product quality meets user's requirement;By sizing mill deformation distribution, final product quality is finally controlled, the lumber recovery of product is improved, reduces processing charges and process-cycle, saved production cost.

Description

A kind of preparation method of PH stainless steel seamless steel pipe
Technical field
The invention belongs to steel pipe rolling technical fields, and in particular to a kind of preparation of PH stainless steel seamless steel pipe Method.
Background technique
Gapless stainless steel tube abbreviation seamless pipe.Gapless stainless steel tube rough surface, length is without scale.Gapless stainless steel tube master It is used in the equipment such as boiler, central air-conditioning, steel construction, machining, pipe gas, fire-fighting.
For PH stainless steel seamless steel pipe, since its alloy content is higher, the perforation under high temperature is negative Lotus is much higher than plain C-Mn steel product, and the main production object of existing steel pipe's production equipment domestic at present be common carbon manganese or Middle-low alloy steel, hot rolling high-alloy steel and stainless steel have larger difficulty.In particular for the martensitic precipitation hardening type such as 17-4PH Stainless-steel seamless pipe, main production technology are " hot extrusion+cold rolling ", and main product is small-caliber seamless steel pipe.One As round billet carry out hot extrusion before, through-hole need to be drawn, then use hot extrusion, the pipe of specification close with fished pipe is made, most Final products are produced by the way of cold rolling eventually.In traditional handicraft, since process is many and diverse, the problems such as process flow is long, lead Cause production efficiency low, high production cost, and total lumber recovery is less than 70%.And the martensitic precipitation hardening type stainless steel such as 17-4PH Reasonable deformation temperature section be 1100~1180 DEG C, far below 1250 DEG C of plain C-Mn steel product.Therefore, martensitic precipitation There is the features such as deformation is difficult, and perforation load is big, and deformation temperature range is narrow, is also easy to produce defect in hardened stainless steel.
Application No. is " 200810039375.3 ", the entitled " system of seamless steel tubes made of martensite precipitation hardening stainless steel Preparation Method " discloses a kind of processing step are as follows: pipe → peeling → blanking → heating → hot piercing → cooling → finishing → pickling The preparation martensitic precipitation that → lubrication → cold rolling → degreasing → heat treatment → aligning → Pipe Cutting → pickling → is examined → is packed and stored The method of hardening stainless steel seamless steel pipe, the processing step is cumbersome, and process flow is long, at high cost, final pipe to finished product at Material rate can only achieve 51.31%, still not be able to satisfy at present to PH stainless steel seamless steel pipe high yield, low cost Deng requirement.
Therefore, in view of the deficiencies of the prior art, it is urgent to provide a kind of simple process, process are short, at low cost, finished product lumber recovery The preparation method of high PH stainless steel seamless steel pipe.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of simple process and low cost, high stainless of product lumber recovery The preparation method of steel seamless steel tube.
A kind of preparation method of PH stainless steel seamless steel pipe, comprising the following steps: annular stove heating → perforation Machine perforation → hot rolling → sizing → inspection, packaging;Specific step is as follows:
A, annular stove heating: in annular furnace, with the rate of heat addition of 150~200 DEG C/h by heating of pipe blank to 850 DEG C, then 1140~1160 DEG C are heated to the rate of heat addition of 250~300 DEG C/h, keeps the temperature 0.5~1.5h;
B, punch is perforated: being perforated using micro- expanding form to the pipe after the heating of a step;Wherein punch is worn Hole roller diameter is 1100~1300mm, and perforating roller length is 900~1100mm;Ovality >=1.05, roll off angle be -0.1 °~- 0.3 °, 300~380mm is come directly towards, the top amount of stretching is 200~250mm, 120 turns/min of revolving speed <;The outer diameter of the hollow billet obtained after perforation For 290~300mm, internal diameter is 260~270mm;
C, hot rolling: tube rolling is carried out to hollow billet using A-R precision Tube Rolling Train, obtains hot-rolled pipe;Wherein, rolling angle be 5 °~ 7 °, feed angle is 7 °~15 °, and rolling rate is 1~1.5m/s;Hot rolling pipe outside diameter be 280~290mm, internal diameter be 260~ 270mm;
D, to hot-rolled pipe carry out sizing to get.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method, wherein pipe heating temperature is 1150 DEG C in annular furnace in a step, soaking time 1h.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method, wherein b step middle punch machine diameter is 1200mm, and perforating roller length is 1000mm.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method, wherein ovality is 1.08 in b step, and roll off angle is -0.17 °, comes directly towards 35mm, and the top amount of stretching is 243mm, revolving speed 80 Turn/min.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method, the outer diameter of the hollow billet wherein obtained after b step middle punch are 298mm, internal diameter 268mm.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method, wherein rolling angle is 5.5 ° in step c, and feed angle is 14 °.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method, it is 1.2m/s that rate is wherein rolled in step c.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method, wherein hot rolling pipe outside diameter is 288mm, internal diameter 268mm in step c.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method wherein carries out sizing using three-roll sizing mill group in Step d.
The present invention uses on A-R precision pipe mill, passes through " annular stove heating → punch perforation → hot rolling → sizing " Technique, realize and directly produce the martensitic precipitation hardening type stainless steel jointless such as 17-4PH using an A-R precision Tube Rolling Train Steel pipe.The alternative martensitic precipitation hardening type stainless steel main production " hot extrusion+cold rolling ", while this hair at present of this technique It is bright also perforation preferably to be shared with rolling load, guarantee that production process can be gone on smoothly;By parameter adjusting and optimizing, Guarantee that product quality meets user's requirement;By sizing mill deformation distribution, finally control final product quality, improve product at Material rate, reduces processing charges and process-cycle, has saved production cost.
Specific embodiment
A kind of preparation method of PH stainless steel seamless steel pipe, comprising the following steps: annular stove heating → perforation Machine perforation → hot rolling → sizing → inspection, packaging;Specific step is as follows:
A, annular stove heating: in annular furnace, with the rate of heat addition of 150~200 DEG C/h by heating of pipe blank to 850 DEG C, then 1140~1160 DEG C are heated to the rate of heat addition of 250~300 DEG C/h, keeps the temperature 0.5~1.5h;
It is the thermal conductivity of the martensitic stain less steel (lower than 850 DEG C) because when temperature is lower using different heating rates heating Less than the 1/2 of ordinary carbon steel, temperature conduction speed is fast, if heating speed is too fast, easily causes hull-skin temperature higher, and interior table Face temperature is lower, and the biggish temperature difference generates great differences in expansion, and blank surface is caused to crack;And (it is higher than 850 in high temperature section DEG C) when, thermal conductivity difference is not obvious, and the rate of heat addition can be improved;
Wherein, the radius of the annular furnace is 4500mm;
B, punch is perforated: being perforated using micro- expanding form to the pipe after the heating of a step;Wherein punch is worn Hole roller diameter is 1100~1300mm, and perforating roller length is 900~1100mm;Ovality >=1.05, roll off angle be -0.1 °~- 0.3 °, 300~380mm is come directly towards, the top amount of stretching is 200~250mm, 120 turns/min of revolving speed <;The outer diameter of the hollow billet obtained after perforation For 290~300mm, internal diameter is 260~270mm;The present invention is perforated using two-roll piercer (i.e. cone mill);Its In, ovality=lead/roll spacing;If ovality is too small, load when perforation generally can be relatively high, and deformation is relatively difficult, Therefore present invention preferably employs ovality >=1.05;
In addition, top front reduction ratio can control by the control of the top amount of stretching, thus the load of one side influence of rolled, separately On the one hand it can improve the inner surface quality for the hollow billet produced;
C, hot rolling: tube rolling is carried out to hollow billet using A-R precision Tube Rolling Train (i.e. two rollers tiltedly prick machine), obtains hot-rolled pipe;;Its In, rolling angle is 5 °~7 °, and feed angle is 7 °~15 °, and rolling rate is 1~1.5m/s;The outer diameter of steel pipes obtained after rolling is 280~290mm, internal diameter are 260~270mm;On the one hand controlling the above parameter is the load for reducing production unit, it is steady to improve production It is qualitative;On the other hand it is to follow Deformation Theory principle by parameter setting, improves the quality of product;
D, to hot-rolled pipe carry out sizing to get.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method, wherein pipe heating temperature is 1150 DEG C in annular furnace in a step, soaking time 1h.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method, wherein b step middle punch machine diameter is 1200mm, and perforating roller length is 1000mm.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method, wherein ovality is 1.08 in b step, and roll off angle is -0.17 °, comes directly towards 35mm, and the top amount of stretching is 243mm, revolving speed 80 Turn/min.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method, the outer diameter of the hollow billet wherein obtained after b step middle punch are 298mm, internal diameter 268mm.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method, wherein rolling angle is 5.5 ° in step c, and feed angle is 14 °.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method, it is 1.2m/s that rate is wherein rolled in step c.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method, wherein hot rolling pipe outside diameter is 288mm, internal diameter 268mm in step c.
Further, technical solution more preferably, a kind of above-mentioned preparation of PH stainless steel seamless steel pipe Method wherein uses multi-frame sizing in Step d, it is preferred to use three-roll sizing mill group carries out sizing.
For PH stainless steel seamless steel pipe, since its alloy content is higher, the perforation under high temperature is negative Lotus is much higher than plain C-Mn steel product, and the main production object of existing steel pipe's production equipment domestic at present be common carbon manganese or Middle-low alloy steel, hot rolling high-alloy steel and stainless steel have larger difficulty.And the martensitic precipitation hardening type stainless steel such as 17-4PH Reasonable deformation temperature section is 1100~1180 DEG C, far below 1250 DEG C of plain C-Mn steel product.It is hard for martensitic precipitation The characteristics of deformation of change type stainless steel is difficult, and the big feature of perforation load, deformation temperature range is narrow, is also easy to produce defect, designs this hair Bright technique, is mainly characterized in that:
(1) perforation can effectively reduce perforation load using micro- expanding form perforation in this way.
(2) when perforating, using compared with product, smaller ovality and the bigger top amount of stretching can reduce steel pipe in this way and lack Sunken generation.
(3) by main deflection, finishing rolling mill process is concentrated on, deformation is concentrated, is precisely controlled.
(4) eventually by sizing process, fished pipe production is completed, finished product is formed.
The advantages of being designed in this way include:
(1) perforation can preferably be shared with rolling load, guarantees that production process can be gone on smoothly;
(2) by parameter adjusting and optimizing, guarantee that product quality meets user's requirement;
(3) by sizing mill deformation distribution, final product quality is finally controlled;
(4) present invention can shorten process flow, use with hot Dai Leng, reduce production process, improve product total lumber recovery, Reduce production cost.
A specific embodiment of the invention is further described below with reference to embodiment, is not therefore limited the present invention System is among the embodiment described range.
Embodiment 1
Stripped off the skin blank using 3 Φ 280mm, 17-4PH, boring 70mm through-hole, 159 unit punches as follows in Design technology is produced;
One, annular stove heating: in annular furnace, with the rate of heat addition of 150~200 DEG C/h by heating of pipe blank to 850 DEG C, then 1140~1160 DEG C are heated to the rate of heat addition of 250~300 DEG C/h, keeps the temperature 0.5~1.5h;Wherein, the half of the annular furnace Diameter is 4500mm;
Two, it is perforated using two-roll piercer (i.e. cone mill), wherein the perforation roller diameter of punch is 1200mm, perforating roller length are 1000mm;24s is about when entire perforation, perforation manufacturing parameter is as shown in table 1 below:
1 piercing process parameter of table
Three, after smoothly completing perforation, hollow billet is transported to A-R precision Tube Rolling Train and is rolled, rolling is using production Parameter is as shown in table 2 below:
2 hot-rolled process parameter of table
Group number Diameter of mandrel/mm Rolling angle/° Feed angle/° Tube rolling wall thickness/mm after rolling Roll rate/m/s
1 264 5.5 14 12 1.2
2 264 6 10 13 1.5
3 264 6.5 8 14 1
Four, sizing is carried out using three-roll sizing mill group, the tube rolling length obtained after sizing can reach 7500mm or more, mainly Lumber recovery loss cutting head amount for scaling loss and end to end, cutting head amount is about 300mm end to end, the stainless steel tube produced using present invention process Lumber recovery is up to 90% or more.

Claims (8)

1. a kind of preparation method of PH stainless steel seamless steel pipe, comprising the following steps: annular stove heating → punch Perforation → hot rolling → sizing → inspection, packaging;It is characterized by:
A, annular stove heating: in annular furnace, with the rate of heat addition of 150~200 DEG C/h by heating of pipe blank to 850 DEG C, then with 250 The rate of heat addition of~300 DEG C/h is heated to 1140~1160 DEG C, keeps the temperature 0.5~1.5h;
B, punch is perforated: being perforated using micro- expanding form to the pipe after the heating of a step;The wherein perforating roller of punch Diameter is 1100~1300mm, and perforating roller length is 900~1100mm;Ovality >=1.05, roll off angle are -0.1 °~-0.3 °, 300~380mm is come directly towards, the top amount of stretching is 200~250mm, 120 turns/min of revolving speed <;The outer diameter of the hollow billet obtained after perforation is 290 ~300mm, internal diameter are 260~270mm;
C, hot rolling: tube rolling is carried out to hollow billet using A-R precision Tube Rolling Train, obtains hot-rolled pipe;Wherein, roll off angle is 5 °~7 °, Feed angle is 7 °~15 °, and rolling rate is 1~1.5m/s;Hot rolling pipe outside diameter is 280~290mm, and internal diameter is 260~270mm;
D, to hot-rolled pipe carry out sizing to get;
Wherein, the PH stainless steel seamless steel pipe is martensitic precipitation hardening type stainless-steel seamless pipe.
2. a kind of preparation method of PH stainless steel seamless steel pipe according to claim 1, it is characterised in that: a step Pipe heating temperature is 1150 DEG C in annular furnace in rapid, soaking time 1h.
3. a kind of preparation method of PH stainless steel seamless steel pipe according to claim 1, it is characterised in that: b step The perforation roller diameter of rapid middle punch machine is 1200mm, and perforating roller length is 1000mm.
4. a kind of preparation method of PH stainless steel seamless steel pipe according to claim 1, it is characterised in that: b step The outer diameter of the hollow billet obtained after rapid middle punch is 298mm, internal diameter 268mm.
5. a kind of preparation method of PH stainless steel seamless steel pipe according to claim 1, it is characterised in that: c step Roll off angle is 5.5 ° in rapid, and feed angle is 14 °.
6. a kind of preparation method of PH stainless steel seamless steel pipe according to claim 1, it is characterised in that: c step Rolling rate is 1.2m/s in rapid.
7. a kind of preparation method of PH stainless steel seamless steel pipe according to claim 1, it is characterised in that: c step The outer diameter of hot-rolled pipe is 288mm, internal diameter 268mm in rapid.
8. a kind of preparation method of PH stainless steel seamless steel pipe according to claim 1, it is characterised in that: d step Sizing is carried out using three-roll sizing mill group in rapid.
CN201610654968.5A 2016-08-11 2016-08-11 A kind of preparation method of PH stainless steel seamless steel pipe Active CN106238465B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610654968.5A CN106238465B (en) 2016-08-11 2016-08-11 A kind of preparation method of PH stainless steel seamless steel pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610654968.5A CN106238465B (en) 2016-08-11 2016-08-11 A kind of preparation method of PH stainless steel seamless steel pipe

Publications (2)

Publication Number Publication Date
CN106238465A CN106238465A (en) 2016-12-21
CN106238465B true CN106238465B (en) 2019-02-05

Family

ID=58079138

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610654968.5A Active CN106238465B (en) 2016-08-11 2016-08-11 A kind of preparation method of PH stainless steel seamless steel pipe

Country Status (1)

Country Link
CN (1) CN106238465B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112893470B (en) * 2021-01-20 2022-11-08 杭州淳通新材料科技有限公司 Seamless steel tube forming process

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101612700A (en) * 2008-06-23 2009-12-30 宝山钢铁股份有限公司 The preparation method of seamless steel tubes made of martensite precipitation hardening stainless steel
CN101811149A (en) * 2010-04-14 2010-08-25 新兴铸管股份有限公司 Manufacturing method of high alloy seamless steel tube
JP2013094826A (en) * 2011-11-01 2013-05-20 Nippon Steel & Sumitomo Metal Corp Seamless-metal-pipe manufacturing method
CN104874606A (en) * 2015-06-16 2015-09-02 攀钢集团成都钢钒有限公司 Production method of high-chromium ferrite stainless steel seamless pipe
CN104907353A (en) * 2015-06-16 2015-09-16 攀钢集团成都钢钒有限公司 Production method of high-chromium ferrite stainless-steel seamless steel pipe blank

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101612700A (en) * 2008-06-23 2009-12-30 宝山钢铁股份有限公司 The preparation method of seamless steel tubes made of martensite precipitation hardening stainless steel
CN101811149A (en) * 2010-04-14 2010-08-25 新兴铸管股份有限公司 Manufacturing method of high alloy seamless steel tube
JP2013094826A (en) * 2011-11-01 2013-05-20 Nippon Steel & Sumitomo Metal Corp Seamless-metal-pipe manufacturing method
CN104874606A (en) * 2015-06-16 2015-09-02 攀钢集团成都钢钒有限公司 Production method of high-chromium ferrite stainless steel seamless pipe
CN104907353A (en) * 2015-06-16 2015-09-16 攀钢集团成都钢钒有限公司 Production method of high-chromium ferrite stainless-steel seamless steel pipe blank

Also Published As

Publication number Publication date
CN106238465A (en) 2016-12-21

Similar Documents

Publication Publication Date Title
CN107052076B (en) A kind of method of collet plug hot rolling heavy caliber titanium or titanium alloy thin-wall seamless pipe
CN102873512B (en) The manufacture method of thick-walled seamless steel pipes in used in nuclear power station heavy caliber
CN102039313B (en) Method for producing large-diameter seamless steel pipe for gas cylinder
CN103272845B (en) Hot rolling process of small-bore ultra-thin-wall seamless steel tube
CN107695102B (en) A method of block after preventing thick-walled pipe roll piercing
CN101439350B (en) Method for producing seamless steel pipe for producing gas cylinder with heavy caliber for hauled vehicle
CN101020190A (en) Hot rolling process of seamless steel pipe
CN105420651B (en) A kind of manufacture method of the seamless Zirconium tube of heavy caliber thick wall
CN105499920B (en) A kind of manufacturing method of heavy caliber thick wall seamless niobium tubing material
CN104907353B (en) The production method of high chromium content ferrite stainless steel seamless steel pipe blank
CN104874606A (en) Production method of high-chromium ferrite stainless steel seamless pipe
CN104259206A (en) Production method of titanium alloy seamless tubes used for tubing coupling
CN111589871A (en) Production line and production process of small-caliber thick-wall seamless steel pipe
CN109663831A (en) A method of producing small-bore Steel Pipe For Bearing
CN103128102A (en) Production method of titanium alloy oil well pipe
CN106345814A (en) A production method for spiral welded magnesium alloy seamless tube
CN102284486A (en) Process for manufacturing seamless steel tubes by hot rolling
CN106180195B (en) 508 millimeters of heavy caliber seamless steel pipe hot continuous rolling process
CN105568195A (en) Preparation method for high-accuracy and high-strength titanium alloy seamless tubes
CN104889163B (en) A kind of method of pure titanium seamless tubes roll piercing
CN105234200A (en) On-line tube-expanding production process of large-diameter seamless steel tubes
CN110170543A (en) A kind of titanium alloy seamless pipe short route processing method
CN113976629B (en) Seamless pipe and preparation method thereof
CN102873126B (en) Manufacturing method of large-aperture thin-walled seamless steel tube for nuclear power plant
CN106238465B (en) A kind of preparation method of PH stainless steel seamless steel pipe

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant