CN104907353B - The production method of high chromium content ferrite stainless steel seamless steel pipe blank - Google Patents

The production method of high chromium content ferrite stainless steel seamless steel pipe blank Download PDF

Info

Publication number
CN104907353B
CN104907353B CN201510334811.XA CN201510334811A CN104907353B CN 104907353 B CN104907353 B CN 104907353B CN 201510334811 A CN201510334811 A CN 201510334811A CN 104907353 B CN104907353 B CN 104907353B
Authority
CN
China
Prior art keywords
section
stainless steel
heating
chromium content
high chromium
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510334811.XA
Other languages
Chinese (zh)
Other versions
CN104907353A (en
Inventor
鄢勇
尹人洁
王婀娜
童宗圣
张涛
江健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pangang Group Chengdu Steel and Vanadium Co Ltd
Original Assignee
Pangang Group Chengdu Steel and Vanadium Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pangang Group Chengdu Steel and Vanadium Co Ltd filed Critical Pangang Group Chengdu Steel and Vanadium Co Ltd
Priority to CN201510334811.XA priority Critical patent/CN104907353B/en
Publication of CN104907353A publication Critical patent/CN104907353A/en
Application granted granted Critical
Publication of CN104907353B publication Critical patent/CN104907353B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21CMANUFACTURE OF METAL SHEETS, WIRE, RODS, TUBES OR PROFILES, OTHERWISE THAN BY ROLLING; AUXILIARY OPERATIONS USED IN CONNECTION WITH METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL
    • B21C37/00Manufacture of metal sheets, bars, wire, tubes or like semi-manufactured products, not otherwise provided for; Manufacture of tubes of special shape
    • B21C37/06Manufacture of metal sheets, bars, wire, tubes or like semi-manufactured products, not otherwise provided for; Manufacture of tubes of special shape of tubes or metal hoses; Combined procedures for making tubes, e.g. for making multi-wall tubes

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Forging (AREA)

Abstract

The invention belongs to metallurgical technology field, and in particular to a kind of production method of high chromium content ferrite stainless steel 2Cr25N seamless steel pipe blanks.The present invention provides a kind of production method of high chromium content ferrite stainless steel seamless steel pipe blank, and its technological process includes:Strip off the skin round billet → heating forging stock → perforation, wherein:Enter eleven punch 11 to round billet using punching machine and form hollow billet blank;In perforation process, overall diameter reduction ratio is 8~12%, top front reduction ratio≤4%, and ovality is 1.06~1.14.The method of the present invention has with short production cycle, the low feature of preparation cost;The Tube yield that gained blank is prepared is high.

Description

The production method of high chromium content ferrite stainless steel seamless steel pipe blank
Technical field
The invention belongs to metallurgical technology field, and in particular to a kind of high chromium content ferrite stainless steel 2Cr25N seamless steel pipe blanks Production method.
Background technology
High chromium content ferrite stainless steel 2Cr25N, height is measured containing Cr, and inoxidizability is better than the ferrite of Cr13 and Cr18 types not Rust steel, is particularly suitable for being used under conditions of the fierce fluctuation of temperature.Work various can be produced under more than 950 DEG C loading condictions Heat-resistant component.In traditional production technology, ferrite stainless steel pipe is mainly produced by the way of extrusion forming, specifically Technological process is:It is main to use " strip off the skin forging stock → bore hole → sensing heating → reaming → sensing heating → extruding ";It is therein " to take off Skin forging stock → bore hole → sensing heating → reaming " is its blank preparatory process, and this production process is relatively long, while bore hole, expansion Hole process, in addition to its operation processing charges, while there is larger lumber recovery to lose.
The content of the invention
For drawbacks described above, the present invention provides a kind of life of new chromium 2Cr25N ferritic stainless seamless steel tube blanks high Product method, the method for the present invention has with short production cycle, the low feature of preparation cost.
Technical scheme:
The present invention provides a kind of production method of high chromium content ferrite stainless steel seamless steel pipe blank, and its technological process includes: Strip off the skin round billet → heating forging stock → perforation, wherein:
Enter eleven punch 11 to round billet using punching machine and form hollow billet blank;In perforation process, overall diameter reduction ratio be 8~ 12%, top front reduction ratio is≤4%, and ovality is 1.06~1.14.
Further, rotary heating furnace, roller hearth type heating furnace or sensing heating are used in the heating forging stock operation.
In heating forging stock operation, using annular-heating stove heat, rotary heating furnace is followed successively by heat from charging end to discharge end Exhausting section, preheating section, bringing-up section, soaking zone;Wherein, heat-recovery section temperature (i.e. forging stock material charging temperature) is less than 800 DEG C, preheating Section temperature control at 1000~1030 DEG C, bringing-up section temperature≤1250 DEG C, soaking zone temperature control is at 1230 DEG C~1260 DEG C.One As, heat-recovery section is set at annular furnace charging aperture, heat-recovery section is using preheating section, bringing-up section, the soaking for setting behind The heat energy that the waste heat flue gas and high temperature section that the heat supply burner combustion of section is produced are brought is carried out to the pipe by heat-recovery section Preheating.
It is furthermore preferred that heating forging stock operation uses annular-heating stove heat, rotary heating furnace from charging end to discharge end according to Secondary is heat-recovery section, preheating section, bringing-up section, soaking zone;Bringing-up section is divided into 1 section of heating, 2 sections of heating, wherein, forging stock material is returned in heat Section, preheating section, 1 section of 5~7 hours heat time of (i.e. low-temperature zone) of heating are received, in 2 sections of heating, soaking zone (i.e. high temperature section) Heat time is less than 1.5~2 hours, so that overall heating-up temperature is uniform, forging stock intensity is suitable for the solid of perforation formation Blank.
Further, perforation is using two roller oblique milling bevel-type punches, cartridge type punch or cone mill.
Preferably, to blank endoporus nitrogen blowing and sandblasting before being rolled after perforation, to eliminate inner surface oxide skin and prevent Oxidation.
Specifically, the specification of the high chromium content ferrite stainless steel seamless steel pipe blank is 225 × 16.2mm of Ф, its technique stream Journey includes:Strip off the skin round billet → heating forging stock → perforation, wherein:
In perforation process, eleven punch 11 is entered using two-high cone shape piercing machine, penetrating parameter is:8.5 ° of feed angle, roll off angle 14 °, roll spacing 179.55mm, lead 202mm push up the amount of stretching 150mm, godet speed 1.5m/s, and mill speed 0.4~1.0 is (preferably 0.55m/s)m/s。
Heating forging stock operation in, using rotary heating furnace mode of heating, rotary heating furnace from charging end to discharge end successively It is heat-recovery section, preheating section, bringing-up section, soaking zone;Wherein, forging stock material charging temperature (i.e. heat-recovery section) is less than 800 DEG C;Preheating Section temperature control is 1230 DEG C~1260 DEG C in 1000~1030 DEG C, bringing-up section temperature≤1250 DEG C, soaking zone temperature control, is protected Card 2Cr25N blank heatings are uniform.
Beneficial effects of the present invention:
The present invention by suitable tool and mould and parameters adjusting, the technological innovation in production procedure, using " forging stock that strips off the skin → The mode of annular stove heat → punch perforation " carries out the preparation of its blank pipe, reaches raising lumber recovery, reduces blank cost Purpose.
Specific embodiment
The present invention provides a kind of production method of high chromium content ferrite stainless steel seamless steel pipe blank, and its technological process includes: Strip off the skin round billet → heating forging stock → perforation, wherein:
Enter eleven punch 11 to round billet using punching machine and form hollow billet blank;In perforation process, overall diameter reduction ratio be 8~ 12%, top front reduction ratio≤4%, ovality is 1.06~1.14;Wherein, blank is most in overall diameter reduction ratio=deformation process Minor diameter/original blank diameter × 100%;Top front reduction ratio=blank just contacts blank diameter/original blank during top Diameter × 100%;Ovality=lead/roll spacing;The high chromium content ferrite stainless steel is 2Cr25N steel.
The round billet that strips off the skin refer to outer surface is machined out or the treatment such as reconditioning circular blank.
Perforation principle is the rarefaction for being split using pipe center metal and not broken, top is placed in into puffs and is worn Hole, so as to obtain the optimal resultant effect of the mechanics of perforation procedure, kinematics and quality of hollow billet.The adjustment of piercing process parameter will The characteristics of from austenitic stainless steel, reach two purposes:One is to create good deformation condition, it is ensured that perforation procedure it is suitable Profit is carried out, and two is to prevent surfaces externally and internally defect.
Top front reduction ratio:When i.e. blank just contacts top, blank diameter and original blank diameter ratio.People's custom is used Top front reduction ratio come represent pipe formed vestibule degree of danger, and with this parameter as determination punch hole type design and top One of important evidence of position adjustment;Top front reduction ratio is too small, then cannot realize that the secondary of perforation is nipped;It is excessive, then easily formed Vestibule, causes infolding;The strength degree of steel is different with plasticity, and its critical compresibility is also different, at the same it is produced influence because Element is including macrostructure, mirco structure and heating quality etc.;But because blank is smaller, and high temperature hot deformation resistance is big, pipe During deformation, acutely, top front reduction ratio is difficult to set excessive for center rubbing.
Ovality:Ovality is the ratio of guidance disc distance and roll distance, and ovality influences quality of hollow billet, is nipped Condition, axial slip, punching rate, expanding amount, rolls card and hollow billet size Control etc.;More bright particularly is influenceed on quality of hollow billet During aobvious, ovality is bigger, increases metal transversely deforming, and axial deformation reduces, and metal transversely deforming increase can cause pipe The tension increase of heart district, promotes the formation of pipe center bore;Too small ovality can cause the pipe blank rotary that roll is formed It is short of power during offsetting its frictional force with top resistance with what is advanced, then can causes stall, roll card;It can be seen that, ovality sets Put various situations such as the quality, drag, unit capacity and the production specification that should be taken into account blank.Stainless steel spreads bigger than carbon steel, Therefore ovality selection is more slightly larger than carbon steel (generally 1.08).
Roll rotational speed:The speed of rolls of control punch machine is critically important to suppressing hollow billet heat, and punching rate is faster, hair The temperature of pipe, especially internal surface temperature are higher, cause the increase of defect in inner surface and the abrasion of rolling tool;Stainless steel tube is Perforation general speed is unsuitable too fast.
Further, rotary heating furnace, roller hearth type heating furnace or sensing heating are used in the heating forging stock operation.
In heating forging stock operation, using annular-heating stove heat, rotary heating furnace is followed successively by heat from charging end to discharge end Exhausting section, preheating section, bringing-up section, soaking zone;Wherein, heat-recovery section temperature (i.e. forging stock material charging temperature) is less than 800 DEG C, preheating Section temperature control at 1000~1030 DEG C, bringing-up section temperature≤1250 DEG C, soaking zone temperature control is at 1230 DEG C~1260 DEG C.One As, heat-recovery section is set at annular furnace charging aperture, heat-recovery section is using preheating section, bringing-up section, the soaking for setting behind The heat energy that the waste heat flue gas and high temperature section that the heat supply burner combustion of section is produced are brought is carried out to the pipe by heat-recovery section Preheating.
It is furthermore preferred that heating forging stock operation uses annular-heating stove heat, rotary heating furnace from charging end to discharge end according to Secondary is heat-recovery section, preheating section, bringing-up section, soaking zone;Bringing-up section is divided into 1 section of heating, 2 sections of heating, wherein, forging stock material is returned in heat Section, preheating section, 1 section of 5~7 hours heat time of (i.e. low-temperature zone) of heating are received, in 2 sections of heating, soaking zone (i.e. high temperature section) Heat time is less than 1.5~2 hours, so that overall heating-up temperature is uniform, forging stock intensity is suitable for the solid of perforation formation Blank.In the present invention, because pyroconductivity of the stainless steel in low temperature is only the 1/3~1/2 of ordinary carbon steel, routine is significantly less than The pyroconductivity of carbon steel, if heating is too fast, is easily caused blank bulk temperature inequality, is even ftractureed when serious;At 1000 DEG C or so High temperature when, the two pyroconductivity is roughly the same, and during high temperature of the Cr stainless steels high more than 1100 DEG C, is also easy to produce Cr segregations, Influence high temperature plastic, thus it is unsuitable long in the high temperature section time.
Specific embodiment of the invention is further described with reference to embodiment, is not therefore limited the present invention System is among described scope of embodiments.
Using 4 Φ 200mm, 2Cr25N forging stocks, in the case where heating-up temperature is 1230 DEG C~1260 DEG C controls, climbing The unit of Chengdu Gang Fan Co., Ltds of steel group 159, carries out production 89 × 5mm specification seamless steel pipes by the following method;Its blank Specific production technology it is as follows:
Heating requirements:Rotary heating furnace mode of heating is used in heating forging stock operation, rotary heating furnace is from charging end to going out Material end is followed successively by heat-recovery section, preheating section, bringing-up section, soaking zone;Wherein, forging stock material charging temperature (i.e. heat-recovery section) is less than 800℃;Preheating section temperature control is 1230 DEG C in 1000~1030 DEG C, bringing-up section temperature≤1250 DEG C, soaking zone temperature control ~1260 DEG C, it is ensured that the uniform each section of temperature of 2Cr25N blank heatings presses the control of 2Cr25N temperature requirements.After steel pipe goes out annular furnace, Enter eleven punch 11 in two-high cone shape piercing machine, penetrating parameter is as shown in table 1:
Table 1
By following formula measuring and calculating overall diameter reduction ratio, top front reduction ratio and ovality under the technological parameter:
The minimum diameter of blank/original blank diameter × 100% in overall diameter reduction ratio=deformation process;
Top front reduction ratio=blank just contacts blank diameter/original blank diameter × 100% during top;
Ovality=lead/roll spacing;It is 10% to calculate overall diameter reduction ratio, and top front reduction ratio is 1.7%, and ovality is 1.122, gained hollow billet specification is 225 × 16.2mm, and length is 2~8m.It is single steel pipe (i.e. hollow billet) to be produced using the inventive method Zhi Changdu is 2~8m, and main lumber recovery loss is scaling loss, and lumber recovery is up to more than 98%.

Claims (5)

1. the production method of high chromium content ferrite stainless steel seamless steel pipe blank, it is characterised in that its technological process includes:Strip off the skin circle Base → heating forging stock → perforation, wherein:
Enter eleven punch 11 to round billet using punching machine and form hollow billet blank;In perforation process, overall diameter reduction ratio is 8~12%, Top front reduction ratio is≤4%, and ovality is 1.06~1.14;The high chromium content ferrite stainless steel is 2Cr25N steel;
In heating forging stock operation, using annular-heating stove heat, rotary heating furnace is followed successively by recuperation of heat from charging end to discharge end Section, preheating section, bringing-up section, soaking zone;Wherein, heat-recovery section temperature is less than 800 DEG C, and preheating section temperature control is 1000~1030 DEG C, bringing-up section temperature≤1250 DEG C, soaking zone temperature control is at 1230 DEG C~1260 DEG C;Bringing-up section is divided into 1 section of heating, heating 2 Section, forging stock material in heat-recovery section, preheating section, 1 section of 5~7 hours heat times of heating, when 2 sections, the heating of soaking zone are heated Between be less than 1.5 hours.
2. the production method of high chromium content ferrite stainless steel seamless steel pipe blank according to claim 1, it is characterised in that wear Hole uses two roller oblique milling bevel-type punches, cartridge type punch or cone mill.
3. the production method of high chromium content ferrite stainless steel seamless steel pipe blank according to claim 1 and 2, its feature exists In to blank endoporus nitrogen blowing and sandblasting before being rolled after perforation, to eliminate inner surface oxide skin and anti-oxidation.
4. the production method of high chromium content ferrite stainless steel seamless steel pipe blank according to claim 2, it is characterised in that institute The specification of high chromium content ferrite stainless steel seamless steel pipe blank is stated for 225 × 16.2mm of Ф, in its technological process:
In perforation process, eleven punch 11 is entered using two roller oblique milling bevel-type punches, penetrating parameter is:8.5 ° of feed angle, roll off angle 14 °, roll spacing 179.55mm, lead 202mm push up the amount of stretching 150mm, godet speed 1.5m/s, 0.4~1.0m/s of mill speed.
5. the production method of high chromium content ferrite stainless steel seamless steel pipe blank according to claim 3, it is characterised in that institute The specification of high chromium content ferrite stainless steel seamless steel pipe blank is stated for 225 × 16.2mm of Ф, in its technological process:
In perforation process, eleven punch 11 is entered using two roller oblique milling bevel-type punches, penetrating parameter is:8.5 ° of feed angle, roll off angle 14 °, roll spacing 179.55mm, lead 202mm push up the amount of stretching 150mm, godet speed 1.5m/s, 0.4~1.0m/s of mill speed.
CN201510334811.XA 2015-06-16 2015-06-16 The production method of high chromium content ferrite stainless steel seamless steel pipe blank Active CN104907353B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510334811.XA CN104907353B (en) 2015-06-16 2015-06-16 The production method of high chromium content ferrite stainless steel seamless steel pipe blank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510334811.XA CN104907353B (en) 2015-06-16 2015-06-16 The production method of high chromium content ferrite stainless steel seamless steel pipe blank

Publications (2)

Publication Number Publication Date
CN104907353A CN104907353A (en) 2015-09-16
CN104907353B true CN104907353B (en) 2017-07-07

Family

ID=54077034

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510334811.XA Active CN104907353B (en) 2015-06-16 2015-06-16 The production method of high chromium content ferrite stainless steel seamless steel pipe blank

Country Status (1)

Country Link
CN (1) CN104907353B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106238465B (en) * 2016-08-11 2019-02-05 攀钢集团成都钢钒有限公司 A kind of preparation method of PH stainless steel seamless steel pipe
CN107774715B (en) * 2016-08-30 2019-11-05 林州凤宝管业有限公司 The double ruler production technology of 220 pipe of vehicle bridge pipe Φ
CN112570487A (en) * 2020-11-24 2021-03-30 江苏联峰能源装备有限公司 Molding process for producing X80 pipeline steel seamless steel tube by adopting phi 800 mm large round billet
CN112894276B (en) * 2021-01-18 2022-04-08 中国兵器工业第五九研究所 Deep blind hole cylindrical component and manufacturing method thereof
CN113441551B (en) * 2021-06-30 2022-07-01 北京科技大学 Thick-walled seamless steel pipe and preparation method thereof
CN113600637B (en) * 2021-06-30 2022-04-15 北京科技大学 Seamless steel pipe and preparation method thereof
CN113976628B (en) * 2021-11-08 2024-05-28 中冶东方工程技术有限公司 Production process and device of stainless steel seamless steel tube

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0925541A (en) * 1995-07-12 1997-01-28 Sumitomo Metal Ind Ltd Non-heat-treated hollow rolled bar steel having high strength and high toughness and its production
CN101020192A (en) * 2007-03-21 2007-08-22 中冶东方工程技术有限公司 Hot rolling process of seamless steel pipe
CN101337236A (en) * 2007-07-06 2009-01-07 中冶东方工程技术有限公司 Rolling mill technique of three-roller full-floating core rod tandem rolling tube
CN101327492A (en) * 2008-07-30 2008-12-24 郝建庚 Process and system for manufacturing hot-rolled seamless tube
CN103736734B (en) * 2013-12-30 2015-09-30 江苏常宝钢管股份有限公司 Hot rolling CPE unit prepares the technique of the super 13Cr seamless steel pipe of high-chromium alloy

Also Published As

Publication number Publication date
CN104907353A (en) 2015-09-16

Similar Documents

Publication Publication Date Title
CN104907353B (en) The production method of high chromium content ferrite stainless steel seamless steel pipe blank
CN104874606B (en) The production method of high chromium content ferrite stainless steel seamless steel pipe
CN107052076B (en) A kind of method of collet plug hot rolling heavy caliber titanium or titanium alloy thin-wall seamless pipe
CN108160709B (en) Titanium alloy hot-rolled seamless pipe production system and production process thereof
CN101020190A (en) Hot rolling process of seamless steel pipe
CN102039313B (en) Method for producing large-diameter seamless steel pipe for gas cylinder
CN104259206A (en) Production method of titanium alloy seamless tubes used for tubing coupling
WO2005068098A9 (en) Method for producing seamless pipe
CN107695102B (en) A method of block after preventing thick-walled pipe roll piercing
CN102069104A (en) Method for producing seamless steel tube for big-caliber long tube air bottle in hot rolling mode
RU2356675C1 (en) Manufacturing method of steel profile shell
CN101020191A (en) Hot rolling process of seamless steel pipe
CN104841720B (en) The method that heavy caliber thick wall Gr15 bushed bearings are produced with steel ingot
CN103157694A (en) Manufacturing method of steel tube provided with rack-shaped inner wall
CN104138905B (en) Seamless steel pipe continous way oblique milling new technology
CN104227344B (en) Production method of GH5188 square exhaust nozzle used for aircraft engine
CN1695839B (en) Roller trio skew rolling method for cold perforating and cold chambering ingot
CN103978038B (en) A kind of confession is cold rolling or the production method of the stainless-steel seamless pipe pipe of cold-drawn
CN107790493A (en) A kind of milling method of stud
CN106238465B (en) A kind of preparation method of PH stainless steel seamless steel pipe
CN104084430B (en) A kind of production control method of cutting die ribbon steel
CN1118582C (en) Forming process of heat-resisting Cr-Mn-Ni-N austenic steel rod
Morioka et al. Development of manufacturing technology for high alloy steel seamless pipe by Mannesmann process
JP3082678B2 (en) Manufacturing method of small diameter seamless metal pipe
JPS6035206B2 (en) Seamless steel pipe manufacturing method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant