CN106223304B - A kind of water delivery in navigation structure and energy-dissipating structure and its construction method - Google Patents

A kind of water delivery in navigation structure and energy-dissipating structure and its construction method Download PDF

Info

Publication number
CN106223304B
CN106223304B CN201610796783.8A CN201610796783A CN106223304B CN 106223304 B CN106223304 B CN 106223304B CN 201610796783 A CN201610796783 A CN 201610796783A CN 106223304 B CN106223304 B CN 106223304B
Authority
CN
China
Prior art keywords
lock head
curtain wall
energy
lock
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610796783.8A
Other languages
Chinese (zh)
Other versions
CN106223304A (en
Inventor
扈晓雯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina East China Engineering Zhengzhou Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201610796783.8A priority Critical patent/CN106223304B/en
Publication of CN106223304A publication Critical patent/CN106223304A/en
Application granted granted Critical
Publication of CN106223304B publication Critical patent/CN106223304B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02CSHIP-LIFTING DEVICES OR MECHANISMS
    • E02C1/00Locks or dry-docks; Shaft locks, i.e. locks of which one front side is formed by a solid wall with an opening in the lower part through which the ships pass
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02CSHIP-LIFTING DEVICES OR MECHANISMS
    • E02C1/00Locks or dry-docks; Shaft locks, i.e. locks of which one front side is formed by a solid wall with an opening in the lower part through which the ships pass
    • E02C1/08Arrangements for dissipating the energy of the water

Landscapes

  • Engineering & Computer Science (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The present invention relates to a kind of water delivery in navigation structure and energy-dissipating structure and its construction methods.It is an object of the invention to solve the technical problems such as medium lift lock water-carriage system infall clockwise slope, energy dissipater's arrangement, the simplification of ship lock structure.The technical scheme is that:The structure has shiplock head floor, lock head curtain wall and the lock head abutment pier positioned at lock head curtain wall both sides, the upstream side setting vertical inlet vertical shaft of lock head curtain wall simultaneously arranges the energy dissipating beam of different elevations in shaft wall, the interconnected annular culvert of the bottom of lock head curtain wall and lock head abutment pier setting, the annular culvert are connected with vertical inlet vertical shaft simultaneously;The downstream side of lock head curtain wall is provided with the water outlet being connected to annular culvert, is separated by baffle pier between adjacent two water outlet and buries the exhaust pipe towards air at the top of water outlet;The lock head curtain coping is equipped with convertible steel China's railway industry.The present invention is suitable for hydraulic and hydroelectric engineering, water transport traffic engineering.

Description

A kind of water delivery in navigation structure and energy-dissipating structure and its construction method
Technical field
The present invention relates to hydraulic and hydroelectric engineering, water transport traffic engineering, the water delivery and energy dissipating in especially a kind of navigation structure Structure and its construction method.
Background technology
The development in navigation structure has more than 2000 years history, at present nearly 4000 of the built ship lock in the whole world.China's ship The history of lock construction is very long, is completed nearly 800 of ship lock so far, accounts for about the 20% of whole world ship lock sum.Aided Locked Design Middle water-carriage system type selecting is good and bad, is one of the technology for ensureing ship lock highly effective and safe operation most critical.It is existing according to China's transportation industry Professional etiquette model, water-carriage system pattern mainly have collection to neutralize dispersed delivery system two major classes, and design selection is usually according to design head Judgement, then verified by hydraulic con-ceptual model.
In recent years, with the implementation of strategy to develop western regions, China's inland water transport cause is grown rapidly, and a batch is large-scale Ship lock is put into operation in succession.Such as:The largest Xijiang River Changzhou three of inland water transport hinge, four line ship lock in the world, Guiping two wires Ship lock, Changsha double lock, Jia Lingjiang River Cao Jie ship lock draw Jiang Jihan navigation locks, the overgrown with weeds Shen canal gulfs Yang Jia ship lock.On a large scale Ship lock construction, due to river difference, head is different, and apply mechanically type selecting according to specification merely does not adapt to ship lock construction requirements, right In the medium lift lock between centralization and decentralization water-carriage system, it is necessary to it breaks through specification and provides, research and innovation achievement, with Adapt to the service requirement of water head locks at different levels.
Invention content
The technical problem to be solved by the present invention is to:In view of the problems of the existing technology, it is proposed that navigation structure it is defeated Water and energy-dissipating structure and its construction method, it is preferred that emphasis is solve medium lift lock water-carriage system infall clockwise slope, energy dissipater's arrangement, The technical problems such as ship lock structure simplification.
The technical solution adopted in the present invention is:The water delivery in navigation structure and energy-dissipating structure have shiplock head floor, lock head Curtain wall and lock head abutment pier positioned at lock head curtain wall both sides, it is characterised in that vertical inlet is arranged in the upstream side of the lock head curtain wall Vertical shaft simultaneously arranges the energy dissipating beam of different elevations in shaft wall, the interconnected ring of the bottom setting of lock head curtain wall and lock head abutment pier Shape culvert, the annular culvert are connected with vertical inlet vertical shaft simultaneously;The downstream side of the lock head curtain wall be provided with The water outlet of annular culvert connection, separated by baffle pier between adjacent two water outlet and buried at the top of water outlet lead to it is big The exhaust pipe of gas;The lock head curtain coping is equipped with convertible steel China's railway industry.
Trash rack is arranged in the water inlet of the vertical inlet vertical shaft.
The middle part that the annular culvert is located at lock head abutment pier is equipped with maintenance valve and service valve.
The steel China's railway industry is installed by steel hinged-support at the top of the lock head curtain wall downstream side, is pacified on lock head abutment pier Dress makes the headstock gear cylinder support that steel China's railway industry opens and closes.
Cross dimensions of the annular culvert at the maintenance valve and service valve is 2.4m × 2.4m, annular The cross dimensions of the downstream side transverse direction gallery of culvert is 2.4m × 3.0m.
The water outlet downstream side is equipped with concrete river bottom protection.
The water delivery in navigation structure of the present invention and the construction method of energy-dissipating structure, steps are as follows:
1, lock head architecture basics excavation is carried out, shiplock head floor concrete is poured;
2, formwork erection construction vertical inlet vertical shaft, energy dissipating beam of constructing on shaft wall are installed in vertical inlet shaft top Trash rack;
3, lock head curtain wall concrete is poured;
4, the baffle pier in formwork erection construction lock head curtain wall downstream side is water outlet between two baffle piers, pre- at the top of water outlet Bury exhaust pipe;
5, lock head abutment pier concrete is poured;
6, the annular culvert of formwork erection construction, reserves maintenance valve gate slot and service valve gate slot;
7, the pre-buried steel twisted branch seat at the top of lock head curtain wall downstream side installs fixed steel China's railway industry, on lock head abutment pier Pre-buried connection opens and closes the bearing of Oil cylinder;
8, the concrete river bottom protection in construction water outlet downstream.
The beneficial effects of the invention are as follows:The technology of the present invention proposes a kind of water delivery and energy-dissipating structure and construction method.According to Hydraulics of shiplock requirement, for water-carriage system centralized arrangement at lock head position, this invention simplifies lock wall patterns, and it is disconnected to optimize lock wall Face reduces difficulty of construction, saves construction investment;Water-carriage system is verified through hydraulic model test, and water inlet flow-shape is good Good, high-velocity flow is by multiple energy dissipating, into lock chamber water flow stationary.The present invention is for solving the choosing of medium lift lock water-carriage system Type simplifies ship lock structure with apparent benefit.
Description of the drawings
Fig. 1 is the vertical view of the present invention.
Fig. 2 is the sectional view that Fig. 1 Parallel to the flow direction crosses center line.
Fig. 3 is sectional views of the Fig. 1 perpendicular to the water outlet of water (flow) direction.
Specific implementation mode
As shown in Figs. 1-3, the water delivery in the present embodiment navigation structure and energy-dissipating structure, including centralized arrangement is in lock head portion Shiplock head floor 5, lock head curtain wall 6 and the lock head abutment pier 9 positioned at lock head curtain wall both sides of position.
Using the space of lock head curtain wall 6 in upstream side setting vertical inlet vertical shaft 1, trash rack is set in the water inlet of vertical shaft 3, and arrange 2 energy dissipating of energy dissipating beam of different elevations in shaft wall.In the bottom of lock head curtain wall 6 and lock head abutment pier 9, setting is mutual The annular culvert 4 of connection, which is connected with vertical inlet vertical shaft 1 simultaneously, when water body vertically drops to Enter annular culvert 4 after lateral gallery first time energy dissipating.
The downstream side of the lock head curtain wall 6 is provided with the water outlet 14 being connected to annular culvert 4, adjacent two water outlet 14 Between separated by baffle pier 7, the top of water outlet 14 is embedded with the exhaust pipe 8 towards outside atmosphere.
Steel China's railway industry 10 is installed by steel hinged-support 11 at the top of 6 downstream side of lock head curtain wall, on lock head abutment pier 9 Headstock gear cylinder support is installed, steel China's railway industry 10 realizes folding by opening and closing Oil cylinder 12.When lock chamber is (under lock head curtain wall 6 Trip side) when being flushed with upstream water level, the unlatching of steel China's railway industry 10 is lain at the top of lock head curtain wall 6, and ship enters upstream for interior water level Approach channel is shown in Fig. 2.
The middle part Parallel to the flow direction of the annular culvert 4 (being located at lock head abutment pier 9) is equipped with maintenance valve and work successively Make valve.Cross dimensions of the annular culvert 4 at maintenance valve and service valve is 2.4m × 2.4m, annular culvert The cross dimensions of 4 downstream side transverse direction gallery is 2.4m × 3.0m, and water body is spread in the exit of culvert, two bursts of flows pair It is flowed out by the water outlet 14 between baffle pier after punching, into lock chamber or downstream.14 downstream side of the water outlet is equipped with concrete River bottom protection 13.
The construction procedure of the present embodiment is as follows:
1, lock head architecture basics excavation is carried out, 5 concrete of shiplock head floor is poured;
2, formwork erection construction vertical inlet vertical shaft 1, energy dissipating beam 2 of constructing on shaft wall, in 1 top peace of vertical inlet vertical shaft Fill trash rack 3;
3,6 concrete of lock head curtain wall is poured;
4, the baffle pier 7 in 6 downstream side of formwork erection construction lock head curtain wall is water outlet 14 between two adjacent two baffle piers, is being discharged Pre-buried exhaust pipe 8 at the top of mouthful;
5,9 concrete of lock head abutment pier is poured;
6, the annular culvert 4 of formwork erection construction reserves maintenance valve gate slot 4a and service valve gate slot 4b;
7, the pre-buried steel twisted branch seat 11 at the top of 6 downstream side of lock head curtain wall installs fixed steel China's railway industry 10, on lock head side Pre-buried connection opens and closes the bearing of Oil cylinder 12 on pier 9;
8, the concrete river bottom protection 13 in 14 downstream of construction water outlet.

Claims (7)

1. water delivery and the energy-dissipating structure in a kind of navigation structure have shiplock head floor (5), lock head curtain wall (6) and are located at lock head The lock head abutment pier (9) on curtain wall both sides, it is characterised in that:The upstream side setting vertical inlet vertical shaft (1) of the lock head curtain wall (6) is simultaneously Arrange that the energy dissipating beam (2) of different elevations, the bottom setting of lock head curtain wall (6) and lock head abutment pier (9) are interconnected in shaft wall Annular culvert (4), the annular culvert (4) while being connected with vertical inlet vertical shaft (1);The lock head curtain wall (6) downstream side is provided with the water outlet (14) being connected to annular culvert (4), by baffle pier between adjacent two water outlet (14) (7) it separates and buries the exhaust pipe (8) towards air at the top of water outlet (14);The top of the lock head curtain wall (6) is equipped with and turns over Rotatable steel China's railway industry (10).
2. water delivery and the energy-dissipating structure in navigation structure according to claim 1, it is characterised in that:The vertical inlet is perpendicular The water inlet setting trash rack (3) of well (1).
3. water delivery and the energy-dissipating structure in navigation structure according to claim 1 or 2, it is characterised in that:The annular is defeated The middle part that water gallery (4) is located at lock head abutment pier (9) is equipped with maintenance valve and service valve.
4. water delivery and the energy-dissipating structure in navigation structure according to claim 3, it is characterised in that:The lock head curtain wall (6) the steel China's railway industry (10) is installed by steel hinged-support (11) at the top of downstream side, being installed on lock head abutment pier (9) makes steel Keying Oil cylinder (12) bearing of matter China's railway industry (10) folding.
5. water delivery and the energy-dissipating structure in navigation structure according to claim 3, it is characterised in that:The annular water delivery corridor Cross dimensions of the road (4) at the maintenance valve and service valve is 2.4m × 2.4m, the downstream side of annular culvert (4) The cross dimensions of lateral gallery is 2.4m × 3.0m.
6. water delivery and the energy-dissipating structure in navigation structure according to claim 4, it is characterised in that:The water outlet (14) Downstream side is equipped with concrete river bottom protection (13).
7. a kind of water delivery in navigation structure as claimed in claim 6 and the construction method of energy-dissipating structure, it is characterised in that apply Steps are as follows for work:
7.1, lock head architecture basics excavation is carried out, shiplock head floor (5) concrete is poured;
7.2, formwork erection construction vertical inlet vertical shaft (1), energy dissipating beam (2) of constructing on shaft wall are pushed up in vertical inlet vertical shaft (1) Portion is installed by trash rack (3);
7.3, lock head curtain wall (6) concrete is poured;
7.4, the baffle pier (7) in formwork erection construction lock head curtain wall (6) downstream side, is water outlet (14) between two baffle piers, is being discharged Pre-buried exhaust pipe (8) at the top of mouthful;
7.5, lock head abutment pier (9) concrete is poured;
7.6, the annular culvert (4) of formwork erection construction, reserves maintenance valve gate slot (4a) and service valve gate slot (4b);
7.7, the pre-buried steel twisted branch seat (11) at the top of lock head curtain wall (6) downstream side installs fixed steel China's railway industry (10), in lock Pre-buried connection opens and closes the bearing of Oil cylinder (12) on first abutment pier (9);
7.8, the concrete river bottom protection (13) in construction water outlet (14) downstream.
CN201610796783.8A 2016-08-31 2016-08-31 A kind of water delivery in navigation structure and energy-dissipating structure and its construction method Active CN106223304B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610796783.8A CN106223304B (en) 2016-08-31 2016-08-31 A kind of water delivery in navigation structure and energy-dissipating structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610796783.8A CN106223304B (en) 2016-08-31 2016-08-31 A kind of water delivery in navigation structure and energy-dissipating structure and its construction method

Publications (2)

Publication Number Publication Date
CN106223304A CN106223304A (en) 2016-12-14
CN106223304B true CN106223304B (en) 2018-08-07

Family

ID=58073954

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610796783.8A Active CN106223304B (en) 2016-08-31 2016-08-31 A kind of water delivery in navigation structure and energy-dissipating structure and its construction method

Country Status (1)

Country Link
CN (1) CN106223304B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106677150A (en) * 2017-02-07 2017-05-17 中国电建集团华东勘测设计研究院有限公司 Under-sill water delivery energy dissipation structure and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2304660C1 (en) * 2006-04-28 2007-08-20 Общество с ограниченной ответственностью "СНПО Экогидротехника" Sluice
CN200978414Y (en) * 2006-12-09 2007-11-21 王成耀 Dam window type navigation lock
CN101525876A (en) * 2009-04-02 2009-09-09 水利部交通部电力工业部南京水利科学研究院 Ship lock concentration and dispersion delivery system without calm section
CN101608444A (en) * 2009-07-27 2009-12-23 中国水电顾问集团华东勘测设计研究院 A kind of water adding system of ship lock and job practices thereof
CN206157701U (en) * 2016-08-31 2017-05-10 中国电建集团华东勘测设计研究院有限公司 Navigation construction's water delivery and dissipation structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2304660C1 (en) * 2006-04-28 2007-08-20 Общество с ограниченной ответственностью "СНПО Экогидротехника" Sluice
CN200978414Y (en) * 2006-12-09 2007-11-21 王成耀 Dam window type navigation lock
CN101525876A (en) * 2009-04-02 2009-09-09 水利部交通部电力工业部南京水利科学研究院 Ship lock concentration and dispersion delivery system without calm section
CN101608444A (en) * 2009-07-27 2009-12-23 中国水电顾问集团华东勘测设计研究院 A kind of water adding system of ship lock and job practices thereof
CN206157701U (en) * 2016-08-31 2017-05-10 中国电建集团华东勘测设计研究院有限公司 Navigation construction's water delivery and dissipation structure

Also Published As

Publication number Publication date
CN106223304A (en) 2016-12-14

Similar Documents

Publication Publication Date Title
CN104563158B (en) Existing subway station realizes the construction method of transfer with new subway station platform layer
CN106968712A (en) Water rich strata tunnel bottom discharge structure and its construction method
CN105544575A (en) Underwater bottom sealing concrete construction method using steel truss for reinforcement
CN1963042A (en) Hydraulic sheeting and use method thereof
CN103469817A (en) Existing subway station main structure broadening construction method
CN108118690A (en) A kind of integral hoisting formula coercion underground continuous wall structure and its prefabricated and construction method
CN103806464A (en) Reverse construction method for vertical intersection between large high-speed rail station and subway
CN103276705A (en) Method for blocking diversion tunnel by cast-in-situ reinforced concrete without gate cutoff and blocking reinforcement cage
CN107178078B (en) Change to half intercept form block wall construction method of section in subway station
CN205035779U (en) Construction branch tunnel suitable for pressure regulating of water delivery tunnel and maintenance traffic
CN106223304B (en) A kind of water delivery in navigation structure and energy-dissipating structure and its construction method
CN206157701U (en) Navigation construction's water delivery and dissipation structure
CN105386464A (en) Inlet and outlet part for maintenance of intelligent urban underground comprehensive pipe gallery
CN202324058U (en) Double-layered pump and gate layout structure
CN105386460A (en) Intelligent urban underground comprehensive pipe gallery
CN110499740A (en) The safe method for blocking of diversion tunnel under a kind of hydroelectric project high water head unfavorable geological condition
CN112343654B (en) Maintainable drainage system for extremely water-rich stratum tunnel and tunnel
CN207093138U (en) A kind of Tunnel Second Lining water pressure control structure
CN110685256B (en) Structure using hydropower station pressure pipeline construction branch tunnel as maintenance channel and construction method
CN109183851A (en) A kind of underwater installation method of shell-type immersed tube
CN206408510U (en) Through tied arch bridge
CN206571490U (en) The drainage bucket of water burst is administered in a kind of vertical shaft for mine construction
TWI267575B (en) Method for constituting a vertical well in water, vertical well in water, method for connection of a vertical well and a horizontal well, and construction of a well
CN215715172U (en) Reconstruction and extension navigation building arrangement structure
CN206581242U (en) Water delivery energy-dissipating structure under a kind of sill

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201218

Address after: Floor 22, block B, Taihong International Plaza, 69 Shangding Road, Zhengdong New District, Zhengzhou City, Henan Province

Patentee after: China power construction east China Survey and Design Institute (Zhengzhou) Co.,Ltd.

Address before: 310014 No. 22 Chao Wang Road, Xiacheng District, Zhejiang, Hangzhou

Patentee before: PowerChina Huadong Engineering Corp.,Ltd.