CN106195445A - A kind of for administering the sand throwing method that submarine pipeline is unsettled - Google Patents

A kind of for administering the sand throwing method that submarine pipeline is unsettled Download PDF

Info

Publication number
CN106195445A
CN106195445A CN201610833235.8A CN201610833235A CN106195445A CN 106195445 A CN106195445 A CN 106195445A CN 201610833235 A CN201610833235 A CN 201610833235A CN 106195445 A CN106195445 A CN 106195445A
Authority
CN
China
Prior art keywords
spacer sleeve
main body
unsettled
sandbag
self
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610833235.8A
Other languages
Chinese (zh)
Inventor
刘华东
王继耕
刘轩
冯嘉
李辉
周金刚
王悦文
李友龙
张超
韩伟
韩羽
李志强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Offshore Oil Corp CNOOC
CNOOC Energy Technology and Services Ltd
CNOOC Energy Development of Equipment and Technology Co Ltd
Original Assignee
China National Offshore Oil Corp CNOOC
CNOOC Energy Technology and Services Ltd
CNOOC Energy Development of Equipment and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Offshore Oil Corp CNOOC, CNOOC Energy Technology and Services Ltd, CNOOC Energy Development of Equipment and Technology Co Ltd filed Critical China National Offshore Oil Corp CNOOC
Priority to CN201610833235.8A priority Critical patent/CN106195445A/en
Publication of CN106195445A publication Critical patent/CN106195445A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/12Laying or reclaiming pipes on or under water
    • F16L1/16Laying or reclaiming pipes on or under water on the bottom
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/12Laying or reclaiming pipes on or under water
    • F16L1/20Accessories therefor, e.g. floats, weights
    • F16L1/202Accessories therefor, e.g. floats, weights fixed on or to vessels
    • F16L1/207Pipe handling apparatus

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Pipe Accessories (AREA)

Abstract

The invention discloses a kind of for administering the sand throwing method that submarine pipeline is unsettled, employing following steps: one) after the position of unsettled seabed pipe determines, it is directed to rope from ramming ship to discharging under water, and the lower end of described guide rope is fixed at described unsettled seabed pipe;Two) sandbag is hung under water on automatic decoupling device, the employing shackle of described automatic decoupling device under water is hung on described guide rope;Three) described in, automatic decoupling device is carried at the described sandbag described unsettled seabed pipe of arrival by described guide rope under water, pulls the described rope that breaks off relations to discharge described sandbag.The present invention uses automatic decoupling device under water to carry sandbag, use guide rope to guide and arrive construction area, by pulling unhook rope release sandbag, the sandbag loss caused because of flow action during greatly reducing sand throwing, decrease labor intensity and time of staying under water of diver, add the accuracy of sand throwing.

Description

A kind of for administering the sand throwing method that submarine pipeline is unsettled
Technical field
The present invention relates to the unsettled Treatment process of submarine pipeline, particularly relate to a kind of for administering the throwing that submarine pipeline is unsettled Method for determining sand.
Background technology
Submarine pipeline is an important component part in offshore oilfield production system, safeguards that the safety of submarine pipeline is to protect Card safety in production and the important step protected the marine environment.If finding after early stage route survey that most of submarine pipeline occurs not With the unsettled situation of degree, after professional assesses, find the most unsettled safe operation having had a strong impact on pipeline, with Time also threaten the safety of the marine eco-environment, it is necessary to administer.The unsettled administering method of existing submarine pipeline mainly has: sandbag covers Gai Fa, mechanical support method, paving imitative sod culture and jackstone landfill method etc., currently mainly use sandbag cladding process, material predominantly sea The sandbag that husky and cement is filled after mixing by a certain percentage.Directly sandbag is thrown in water when construction, due to the effect of current, Part sandbag can be caused to drift out construction area, in turn result in diver and arrange the workload of sandbag under water relatively greatly, the time of staying Longer.In sum, existing sand throwing mode not only results in the wasting of resources, also add the underwater workload of diver and stops Stay the time.
Summary of the invention
The present invention solves technical problem present in known technology and provide a kind of unsettled for administering submarine pipeline Sand throwing method, the method sand throwing is accurate, and can greatly reduce the loss of sandbag, reduces diver's labor intensity and stops under water Stay the time.
The present invention solves that technical problem is adopted the technical scheme that present in known technology: one is used for administering sea The sand throwing method that bottom pipeline is unsettled, employing following steps:
One), after the position at unsettled seabed pipe determines, it is directed to rope from ramming ship to discharging under water, and leads described It is fixed at described unsettled seabed pipe to the lower end of rope;Two) sandbag is hung under water on automatic decoupling device, by described under water from Dynamic detacher uses shackle to hang on described guide rope;Described automatic decoupling device under water includes a master being connected with described shackle Body, a rotation blocking arm and a rotation suspension hook;Described main body includes two pieces of spaced side shields of symmetry, two pieces of described sides Baffle plate is fixed together by self-locking screw III, self-locking screw IV and self-locking screw V, and described self-locking screw III is installed on main body In spacer sleeve I, described self-locking screw IV is installed in main body spacer sleeve II, and described self-locking screw V is installed on main body spacer sleeve III In, described main body spacer sleeve I, described main body spacer sleeve II and described main body spacer sleeve III be all fixed in two pieces of described side shields it Between, described main body spacer sleeve II uses elastomeric material to make;It is provided with on the top of described main body and to be connected with described shackle Lifting hole(eyelet);Described rotation blocking arm includes that two pivoted arms being fixed together, two described pivoted arms are symmetrically arranged the two of described main body Side is the most hinged with described main body by described self-locking screw III;The free end of two described pivoted arms is connected to by self-locking screw I Together, being provided with the blocking arm spacer sleeve I affixed with it on described self-locking screw I, self-locking spiral shell is passed through in the bottom of two described pivoted arms Bolt II links together, and is provided with the blocking arm spacer sleeve II being rotationally connected with it on described self-locking screw II, and described blocking arm is spaced Set II and described blocking arm spacer sleeve I are arranged between two described pivoted arms, are to be connected to break off relations on described blocking arm spacer sleeve I Rope;The connection end of described rotation suspension hook is arranged between two pieces of described side shields and by described main body spacer sleeve III and described master Body is hinged, is provided with and the draw-in groove of described blocking arm spacer sleeve II adaptation on described rotation suspension hook, when described rotation suspension hook locks, Described rotation suspension hook vertically fixes on described blocking arm spacer sleeve II, and described main body spacer sleeve II is pressed on described rotation suspension hook On;Described sandbag hangs on described rotation suspension hook;Three) described in, automatic decoupling device carries described sandbag by described guide rope under water Arrive at described unsettled seabed pipe, pull the described rope that breaks off relations to discharge described sandbag.
The interval obturator being positioned at described body top it is provided with between two pieces of described side shields.
Described rotation suspension hook uses L-type structure, and the angle of described L-type structure is 115~125 °
Described side shield uses blade type structure.
The present invention has the advantage that with good effect:
1) use automatic decoupling device under water to carry sandbag, use guide rope to guide and arrive construction area, by pulling unhook Rope release sandbag, the sandbag loss caused because of flow action during greatly reducing sand throwing, the work decreasing diver is strong Degree and the under water time of staying, add the accuracy of sand throwing.
2) when rotating suspension hook locking, use elastic body spacer sleeve II to compress and rotate suspension hook, rotate suspension hook and use draw-in groove Vertically is on blocking arm spacer sleeve II, it is possible to effectively prevents rotating suspension hook and gets loose when hanging sandbag, can effectively protect simultaneously Card breaks off relations when sandbag discharges and is not affected by wave stream.
3) blocking arm spacer sleeve II uses rotation connection structure, it is possible to reduces resistance and realizes easily breaking off relations.
4) use of self-locking screw is prevented from bolt and gets loose under water, it is ensured that sand throwing operation can the entering of highly effective and safe OK.
5) revolving meber and connector etc. all use high-grade stainless steel material, and the structure rotating suspension hook and rotation blocking arm is all examined Consider the impact of underwater construction apoplexy, wave, stream, be suitable for underwater performance.
6) by adjusting the length of break off relations rope and guide rope, release under water and the unhook of different depth can be met.
7) use L-type to rotate suspension hook and can bear the weight of multiple sandbag, and the not hook sandbag when release.
8) present configuration is simple, and parts used are convenient to be obtained, easy to make.
Accompanying drawing explanation
Fig. 1 is the structural representation that the present invention applies;
Fig. 2 is the front view that automatic decoupling device under water of the present invention is in the lock state;
Fig. 3 is the right view of Fig. 2;
Fig. 4 is the front view that automatic decoupling device under water of the present invention is in release conditions.
In figure: 1, unsettled seabed pipe, 2, sandbag, 3, under water automatic decoupling device, 31, main body, 311, side shield, 312, from Lock bolt III, 313, self-locking screw IV, 314, self-locking screw V, 315 main body spacer sleeves I, 316, main body spacer sleeve II, 317, main Body spacer sleeve III, 318, interval obturator, 319, lifting hole(eyelet);32, rotate blocking arm, 321, self-locking screw I, 322, self-locking screw II, 323, blocking arm spacer sleeve I, 324, blocking arm spacer sleeve II, 325, pivoted arm;33, suspension hook is rotated;4, shackle, 5, break off relations rope, 6, guide Rope, 7, ramming ship.
Detailed description of the invention
For the summary of the invention of the present invention, feature and effect can be further appreciated that, hereby enumerate following example, and coordinate accompanying drawing Describe in detail as follows:
Refer to Fig. 1~Fig. 4, a kind of for administering the sand throwing method that submarine pipeline is unsettled, employing following steps:
One) after the position at unsettled seabed pipe 1 determines, be directed to restrict 6 from ramming ship 7 to discharging under water, and by institute The lower end stating guide rope 6 is fixed at described unsettled seabed pipe 1.
Two) sandbag 2 is hung under water on automatic decoupling device 3, use shackle 4 to hang over institute described automatic decoupling device under water 3 State on guide rope 6.
Described automatic decoupling device under water 3 includes that a main body being connected with described shackle 4 31, rotates blocking arm 32 and Individual rotation suspension hook 33.
Described main body 31 includes two pieces of spaced side shields of symmetry 311, and two pieces of described side shields 311 are by self-locking spiral shell Bolt III 312, self-locking screw IV 313 and self-locking screw V 314 are fixed together, and described self-locking screw III 312 is installed between main body In spacer I 315, described self-locking screw IV 313 is installed in main body spacer sleeve II 316, and described self-locking screw V 314 is installed on master In body spacer sleeve III 317, described main body spacer sleeve I 315, described main body spacer sleeve II 316 and described main body spacer sleeve III 317 are equal Being fixed between two pieces of described side shields 311, described main body spacer sleeve II 316 uses elastomeric material to make, preferably bullet The elastomer material that property is higher;The lifting hole(eyelet) 319 being connected with described shackle 4 it is provided with on the top of described main body 31.
Described rotation blocking arm 32 includes that two pivoted arms being fixed together, two described pivoted arms are symmetrically arranged described main body The both sides of 31 are the most hinged with described main body 31 by described self-locking screw III 312;The free end of two described pivoted arms 32 is by certainly Lock bolt I 321 links together, and is provided with the blocking arm spacer sleeve I 323 affixed with it, two institutes on described self-locking screw I 321 The bottom stating pivoted arm 32 is linked together by self-locking screw II 322, is provided with company of rotation with it on described self-locking screw II 322 The blocking arm spacer sleeve II 324 connect, described blocking arm spacer sleeve II 324 and described blocking arm spacer sleeve I 323 are arranged at described in two turning Between arm 32, described blocking arm spacer sleeve I 323 is to be connected to unhook rope 5.
The connection end of described rotation suspension hook 33 is arranged between two pieces of described side shields 311 and by described main body spacer sleeve III 317 is hinged with described main body 31, is provided with and the draw-in groove of described blocking arm spacer sleeve II 324 adaptation on described rotation suspension hook 33, When described rotation suspension hook 33 locks, described rotation suspension hook 33 vertically fixes on described blocking arm spacer sleeve II 324, described main body Spacer sleeve II 316 is pressed on described rotation suspension hook 33.
Described sandbag 2 hangs on described rotation suspension hook 33.
Three) described in, automatic decoupling device 3 carries described sandbag 2 by described guide rope 6 and arrives described unsettled Submarine Pipeline under water At section 1, pull the described rope 5 described sandbag 2 of release that breaks off relations.
In the present embodiment, above-mentioned main parts size structure, form and act on:
Described main body 31 is for being connected with guide rope 6, including two pieces of described side shields 311 being fixed together, described side Baffle plate 311 uses blade type structure, to facilitate unhook.Use the main body spacer sleeve II 316 that elastomer material is made for hanging sandbag 2 Time auto lock rotate suspension hook 32, prevent rotate suspension hook 32 hang sandbag 2 time get loose.In the present embodiment, the most automatically take off Hook device 3 and guide rope 6 use U-shaped shackle to be connected, for prevent guide rope 6 enter the described side shield 311 of main body 31 two pieces it Between crack and strengthen agent structure, be provided with between two pieces of described side shields 311 be positioned at described main body 31 top interval fill Body 318.Breaking off relations for convenience, described rotation suspension hook 33 uses the L-type structure, the angle of described L-type structure with 115~125 ° to be Preferably, in the present embodiment, the angle of L-type structure is 120 °.Described rotation blocking arm 32 rotates suspension hook 33 for locking or release.Institute State rotation suspension hook 33 to be made up of one block of L-type steel plate, be used for hanging or discharge sandbag 2.When breaking off relations, blocking arm spacer sleeve II 324 exists Rotate under the effect of frictional force, it is possible to reduce resistance and realize easily breaking off relations.The present invention uses the self-locking screw can be in use process In prevent bolt from getting loose under water;Rotate the draw-in groove on suspension hook 33, it is possible to prevent rotating suspension hook 33 and get loose.
Although the preferred embodiments of the present invention being described above in conjunction with accompanying drawing, but the invention is not limited in The detailed description of the invention stated, above-mentioned detailed description of the invention is only schematically, is not restrictive, this area common Technical staff, under the enlightenment of the present invention, in the case of without departing from present inventive concept and scope of the claimed protection, also may be used To make a lot of form, within these belong to protection scope of the present invention.

Claims (4)

1. one kind is used for administering the sand throwing method that submarine pipeline is unsettled, it is characterised in that employing following steps:
One), after the position at unsettled seabed pipe determines, it is directed to rope from ramming ship to discharging under water, and by described guide rope Lower end be fixed at described unsettled seabed pipe;
Two) sandbag is hung under water on automatic decoupling device, the employing shackle of described automatic decoupling device under water is hung over described guide rope On;
Described automatic decoupling device under water includes that a main body being connected with described shackle, a rotation blocking arm and a rotation are hung Hook;
Described main body includes two pieces of spaced side shields of symmetry, and two pieces of described side shields are by self-locking screw III, self-locking spiral shell Bolt IV and self-locking screw V are fixed together, and described self-locking screw III is installed in main body spacer sleeve I, and described self-locking screw IV is worn Being contained in main body spacer sleeve II, described self-locking screw V is installed in main body spacer sleeve III, described main body spacer sleeve I, described master Body spacer sleeve II and described main body spacer sleeve III are all fixed between two pieces of described side shields, and described main body spacer sleeve II is to use Elastomeric material is made;The lifting hole(eyelet) being connected with described shackle it is provided with on the top of described main body;
Described rotation blocking arm includes two pivoted arms being fixed together, and two described pivoted arms are symmetrically arranged the both sides of described main body And it is hinged with described main body by described self-locking screw III;The free end of two described pivoted arms is connected to one by self-locking screw I Rising, be provided with the blocking arm spacer sleeve I affixed with it on described self-locking screw I, self-locking screw is passed through in the bottom of two described pivoted arms II links together, and is provided with the blocking arm spacer sleeve II being rotationally connected with it, described blocking arm spacer sleeve on described self-locking screw II II and described blocking arm spacer sleeve I be arranged between two described pivoted arms, described blocking arm spacer sleeve I is be connected to break off relations rope;
The connection end of described rotation suspension hook is arranged between two pieces of described side shields and by described main body spacer sleeve III with described Main body is hinged, is provided with and the draw-in groove of described blocking arm spacer sleeve II adaptation on described rotation suspension hook, when described rotation suspension hook locks Time, described rotation suspension hook vertically fixes on described blocking arm spacer sleeve II, and described main body spacer sleeve II is pressed on described rotation and hangs On hook;
Described sandbag hangs on described rotation suspension hook;
Three) described in, automatic decoupling device is carried at the described sandbag described unsettled seabed pipe of arrival by described guide rope under water, draws The dynamic described rope that breaks off relations discharges described sandbag.
The most according to claim 1 for administering the sand throwing method that submarine pipeline is unsettled, it is characterised in that described in two pieces The interval obturator being positioned at described body top it is provided with between side shield.
The most according to claim 1 for administering the sand throwing method that submarine pipeline is unsettled, it is characterised in that described rotation is hung Hook uses L-type structure, and the angle of described L-type structure is 115~125 °.
The most according to claim 1 for administering the sand throwing method that submarine pipeline is unsettled, it is characterised in that described side shield Use blade type structure.
CN201610833235.8A 2016-09-19 2016-09-19 A kind of for administering the sand throwing method that submarine pipeline is unsettled Pending CN106195445A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610833235.8A CN106195445A (en) 2016-09-19 2016-09-19 A kind of for administering the sand throwing method that submarine pipeline is unsettled

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610833235.8A CN106195445A (en) 2016-09-19 2016-09-19 A kind of for administering the sand throwing method that submarine pipeline is unsettled

Publications (1)

Publication Number Publication Date
CN106195445A true CN106195445A (en) 2016-12-07

Family

ID=58067288

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610833235.8A Pending CN106195445A (en) 2016-09-19 2016-09-19 A kind of for administering the sand throwing method that submarine pipeline is unsettled

Country Status (1)

Country Link
CN (1) CN106195445A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105626963A (en) * 2016-04-11 2016-06-01 中国石油大学(华东) Channel-type hanging submarine pipeline slinging treatment device and construction method thereof
CN109237124A (en) * 2018-09-26 2019-01-18 中国石油大学(华东) Aerial Submarine Pipeline improvement piles up constructing device with sand pocket
CN112500054A (en) * 2020-11-18 2021-03-16 中海油能源发展股份有限公司 Submarine pipe cable protective pad, content of submarine pipe cable protective pad and content preparation method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4329086A (en) * 1979-06-20 1982-05-11 Saipem S.P.A. Method for laying an underwater pipe to straddle an already laid pipe, and the relative devices
CN2712855Y (en) * 2004-07-09 2005-07-27 长兴欧德申机械有限公司 Automatic unhooking device for hanging transfer chain
CN202953385U (en) * 2012-11-12 2013-05-29 中国石油化工股份有限公司 Seabed guide cage for oriented throwing of sand pocket
CN203095409U (en) * 2012-12-26 2013-07-31 胜利油田龙玺石油工程服务有限责任公司 Maritime sand-cast bottoming-type automatic tripping gear
CN203247009U (en) * 2013-05-03 2013-10-23 中国葛洲坝集团股份有限公司 Automatic detacher of under water hanging object
CN204737574U (en) * 2015-06-03 2015-11-04 武汉二航路桥特种工程有限责任公司 Automatic unhooking device under water who fills out is thrown in pier protection
CN105626963A (en) * 2016-04-11 2016-06-01 中国石油大学(华东) Channel-type hanging submarine pipeline slinging treatment device and construction method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4329086A (en) * 1979-06-20 1982-05-11 Saipem S.P.A. Method for laying an underwater pipe to straddle an already laid pipe, and the relative devices
CN2712855Y (en) * 2004-07-09 2005-07-27 长兴欧德申机械有限公司 Automatic unhooking device for hanging transfer chain
CN202953385U (en) * 2012-11-12 2013-05-29 中国石油化工股份有限公司 Seabed guide cage for oriented throwing of sand pocket
CN203095409U (en) * 2012-12-26 2013-07-31 胜利油田龙玺石油工程服务有限责任公司 Maritime sand-cast bottoming-type automatic tripping gear
CN203247009U (en) * 2013-05-03 2013-10-23 中国葛洲坝集团股份有限公司 Automatic detacher of under water hanging object
CN204737574U (en) * 2015-06-03 2015-11-04 武汉二航路桥特种工程有限责任公司 Automatic unhooking device under water who fills out is thrown in pier protection
CN105626963A (en) * 2016-04-11 2016-06-01 中国石油大学(华东) Channel-type hanging submarine pipeline slinging treatment device and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105626963A (en) * 2016-04-11 2016-06-01 中国石油大学(华东) Channel-type hanging submarine pipeline slinging treatment device and construction method thereof
CN105626963B (en) * 2016-04-11 2017-09-01 中国石油大学(华东) Channel-type Aerial Submarine Pipeline ramming controlling device and construction method
CN109237124A (en) * 2018-09-26 2019-01-18 中国石油大学(华东) Aerial Submarine Pipeline improvement piles up constructing device with sand pocket
CN109237124B (en) * 2018-09-26 2020-05-12 中国石油大学(华东) Sand bag piling construction device for seabed suspended pipeline treatment
CN112500054A (en) * 2020-11-18 2021-03-16 中海油能源发展股份有限公司 Submarine pipe cable protective pad, content of submarine pipe cable protective pad and content preparation method

Similar Documents

Publication Publication Date Title
CN107060794B (en) Hobboing cutter serrated knife exchanges process under a kind of compound stratum shield normal pressure
CN106195445A (en) A kind of for administering the sand throwing method that submarine pipeline is unsettled
CN101881148B (en) Jacket riser mounting method and special riser component thereof
CN110300700A (en) The system being used together with the crane on above water craft
CN104686412A (en) Marine fish release ship
CN109322285A (en) Breach plugging system and method for blocking
CN104719193A (en) Large yellow croaker release device
CN206173968U (en) Automatically unhook ware under water
KR20140053072A (en) A hydraulic laver bed hoisting system
CN210238548U (en) Installation device of well pipe for deep foundation pit
CN103556626B (en) Hanging structure for hoisting large-diameter hole drilling filling pile steel bar cage
CN206956785U (en) A kind of self-locking type manhole cover
CN103490327B (en) Integration deep sea cable salvages diced system and method
KR20130042414A (en) A device for sampling ocean deposits with a hanging type nosecone
CN208603620U (en) A kind of positive well excavation steady rope device of cage of vertical shaft
CN205872379U (en) Boats and ships are with grabbing anchor
CN204551494U (en) Construction equipment is transferred in a kind of steel sheet-pile cofferdam inner support superposition
CN207985116U (en) A kind of ship anchor being applicable in sand mud geology
CN205895163U (en) Guard aperture pipe device that can rise automatically
CN208102273U (en) Stinger installation and fixed system
CN207372016U (en) Retired pipeline cement mortar crams stirring system
CN209412888U (en) A kind of riverbed sludge strand suction ship
CN210530782U (en) Lifting and hanging joint for installing drilling sleeve
CN205872373U (en) Anchor storage device
CN109632373A (en) A kind of gravity type sampler of additional spiral paddle pod

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161207